You are on page 1of 8

OTC 13991

Development and Implementation of a Top-Tensioned Riser for Drilling, Completion


and Producing Operations
K.M. Craik, SIEP Inc., G.T. Ju, SIEP Inc., J.L. Peterson, SEPCo Inc., B.R. James, SIEP Inc., K.D. Castleman, SEPCo Inc.

Copyright 2002, Offshore Technology Conference


addition to documenting these hazards and the risk mitigation
This paper was prepared for presentation at the 2002 Offshore Technology Conference held in strategies, this paper also addresses design considerations,
Houston, Texas U.S.A., 6–9 May 2002.
potential benefits, and limitations of this concept.
This paper was selected for presentation by the OTC Program Committee following review of
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Offshore Technology Conference and are subject to Introduction
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Offshore Technology Conference or its officers. Electronic reproduction, Brutus is a Tension Leg Platform (TLP) installed in 2985’ of
distribution, or storage of any part of this paper for commercial purposes without the written
consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print
water on the Green Canyon 158 block in the Gulf of Mexico,
is restricted to an abstract of not more than 300 words; illustrations may not be copied. The approximately 165 miles southwest of New Orleans (Figure
abstract must contain conspicuous acknowledgment of where and by whom the paper was
presented. 1). Gross recoverable reserves are in excess of 250 million
bbls of oil equivalent. Owned 100 percent by Shell
Exploration and Production Company (SEPCo), the hub class
Abstract
TLP is designed to accommodate eight platform wells and has
For the Brutus tension-leg-platform (TLP), a total of eight
payload and deck space for up to five future subsea
wells were required for field development. Five were pre-
development tie-ins. The dual train facilities can process up
drilled to total depth before the TLP was installed at the site.
to 130 MBOPD and 165 MMCFD. The oil (20”) and gas (20”)
These wells are referred to as “pre-drilled” wells, and they will
pipelines tie into existing pipeline infrastructure 23-25
be completed and produced through 10-¾” production risers.
miles away.
The remaining three wells, referred to as “batch-set” wells,
were pre-drilled to an intermediate depth, and their 13-5/8”
Initial design work on the project began in 1997 during a
casing strings were set. Final drilling for these three wells will
period of severely depressed oil and gas prices. In order to
be performed by the TLP rig.
meet minimum acceptable profitability hurdles the project
focussed on three objectives: Reducing project equipment
In a departure from Company practice on the Auger, Mars,
costs, time to first oil, and well drilling and completion costs.
Ram/Powell, and Ursa TLPs, drilling to total depth on these
The use of Combo Risers helped permit the project to meet all
three batch-set wells will not be performed through a 21”
three objectives.
drilling riser system. Instead, a new concept was developed
and approved for this project. 13-¾” top-tensioned risers will
Conventional Drilling/Completion Program
be used to drill, complete, and produce these wells. This
The well plans for the Brutus wells were based on experiences
combination or “Combo Riser” results in significant project
from the discovery well and two appraisal wells. The site
cost savings by removing the need for a purpose-built drilling
selected for the TLP, close to the first appraisal well, was not
riser system. Furthermore, the rig time requirement for
expected to have severe shallow water flows. However, 16”
drilling and completion of the three batch-set wells from the
casing was set across the potential water flow sands to isolate
TLP is reduced, since there is no drilling riser to install
them from the rest of the well intervals. The initial casing
and remove.
program (Figure 2) permitted a 4 ½” or 5” completion in 8-
5/8” production tieback casing. The 10-¾” production
Since the Combo Riser is used for all TLP drilling,
risers were designed to contain shut-in casing pressures
completion, and producing operations, the risk of riser damage
(SICP) equivalent to the design pressure for the 13-5/8”
resulting from normal drilling operations and potential drilling
protective casing.
hazards is greater than for typical production risers. Thorough
studies were therefore conducted in order to identify the
The wells were designed to be drilled in two stages. The
hazards associated with this concept, and mitigation strategies
initial intervals through the 16” casing were to be batch-drilled
were formulated and implemented to minimize risk. In
by a semi-submersible rig. Batch drilling would optimize the
2 K. M. CRAIK, G. T. JU, J. L. PETERSON, B. R. JAMES, K. D. CASTLEMAN OTC 13991

large-hole drilling and casing operations and minimize the versus a lower cost TLP rig, and the additional cost of a
capital invested should the platform location need to be larger-than-required production riser system.
abandoned because of shallow water flow problems. One or
two wells would be pre-drilled to total depth by the semi- 13-5/8” Combo Riser
submersible rig to gain additional geologic information and 1. Skid TLP Rig
accelerate first oil. 2. Run 13-5/8” Combo Riser
3. Nipple Up 13-5/8” BOPs
After the TLP was installed, and the initial wells 4. Drill to 11-¾” Casing Point
completed, the intervals on the remaining wells would be 5. Run & Cement 11-¾” Liner
drilled by a contract TLP rig using surface BOPs, a 21” 6. Drill to TD
drilling riser and a 13-5/8” high-pressure inner riser. The 7. Run & Cement 7-5/8” or 8 5/8” Production Liner
critical time steps involved in drilling and completing the 8. Run Production Casing Tie Back & Cement
wells are noted in Table 1. 9. Complete Well
Table 2. Combo Riser Critical Path Steps
Conventional Dual Drilling Riser
1. Skid TLP Rig Analysis of Risk Associated with Combo Riser
2. Run 21” Marine Riser A risk analysis of the Brutus Combo Riser was completed in
3. Nipple Up 20-¾” Blowout Preventers (BOPs) order to understand the economic risk associated with using it
4. Drill to 13-5/8” Casing Point and to determine whether it was economically justifiable
5. Run & Cement 13-5/8” Casing to Mud Line compared to a traditional dual drilling riser. While the Combo
6. Run 13-5/8” Inner Riser Riser has benefits from reduced costs, accelerated production
and reduced risk from a riser drop, it has an increased risk
7. Nipple Down 20-¾” BOPs
from blowouts because of its single barrier compared to the
8. Nipple Up 13-5/8” BOPs
dual barrier of the traditional TLP riser.
9. Drill to 11-¾” Casing Point
10. Run & Cement 11-¾” Liner One of the major challenges was to carry out an effective
11. Drill to TD analysis despite a lack of quantitative information. Therefore
12. Run & Cement 7-5/8” or 8 5/8” Production Liner the approach was to keep the quantitative analysis relatively
13. TA Well simple, while examining the problem from as wide a
14. Nipple Down 13-5/8” BOPs viewpoint as possible. This approach was chosen for a
15. Retrieve 13-5/8” Inner Riser number of reasons:
16. Run 13-5/8” x 10-¾” Casing Hanger Profile
17. Displace & Retrieve 21” Marine Riser 1. A simpler approach is more transparent to decision
18. Run 10-¾” Production Riser makers than a complex one.
19. Nipple Up 13-5/8” BOPs 2. A detailed quantitative risk analysis would have been
20. Clean Out TA Plug difficult to carry out because of the complexity of the
21. Run Production Casing Tie Back & Cement. problem and the lack of information.
22. Complete Well 3. A detailed quantitative risk analysis should not be relied
Table 1. Conventional Dual Drilling Riser Critical Path Steps on solely for low-probability, high-consequence events
(Theofanus, 1999), such as a catastrophic blowout.
Combo Riser Drilling/Completion Program
Upon review of the drilling and completion scope of work and Sources of information used in the analysis included
the well program, several cost and time reduction numerous Company technical staff, external experts, existing
opportunities were identified. It was noted that the 13-5/8” quantitative risk analysis studies of single production risers,
casing interval was quite short and if drilled during the batch dropped object studies, historical blowout data, and past
setting operations, would eliminate the need to purchase a experience with riser wear. The study relied most heavily on
large-bore drilling riser, high-pressure inner riser, and drilling historical data since it was felt that historical data was the
riser tensioner and rent a 20-¾” BOP. It would also remove most reliable.
the time to drill that interval from the well’s critical path to
production. It was furthermore noted that if a single riser was The decision tree used in the analysis is shown in Figure
used to drill, complete and produce, the critical path steps 3. The tree was kept large enough to capture major elements
could be reduced from twenty-two to nine, (Table 2) saving of risk, but small enough to be able to intuitively understand
additional critical path time. what was happening. Capturing every uncertainty would
result in a decision tree so large that it could not be practically
Offsetting these savings would be the additional cost to visualized in a meaningful way.
drill the interval with a more expensive semi-submersible rig
DEVELOPMENT AND IMPLEMENTATION OF A TOP-TENSIONED RISER FOR
OTC 13991 DRILLING, COMPLETION AND PRODUCING OPERATIONS 3

Riser drop was considered one of the major risks 4. Perform a risk ranking of the hazard.
associated with the traditional dual riser. Each time a riser is 5. Recommend mitigation alternatives.
installed or removed there is an inherent potential risk of it 6. Assign project team members to follow up each item.
being dropped. If the riser is dropped, the consequences are 7. Record the results.
assumed to be either minimal or extreme. Studies have shown 8. Repeat the process for all key guidewords.
that as a riser drops, it will deform into a jumbled mass. In
the extreme case as it falls it can hit other risers causing them Each identified risk was categorized as high, medium, or
also to fail. The potential cost can be in the hundreds of low, based on likelihood of occurrence and severity of
millions of dollars. consequence. A broad mitigation approach was assigned to
each category, as shown in the table below.
If the riser does not drop, there is a blowout risk, which
can be extreme, major, or limited. The extreme risk Risk Category Description and Mitigation Process
consequence represents a major spill as well as the total loss of Items that fall in this high-risk category
the facility. The total cost of this event is in the billions of should be mitigated. Sufficient risk
dollars. The major risk consequence represents a smaller spill mitigation measures should be
with major damage to the facility. The limited risk implemented to lower the risk to a
consequence represents a blowout with minor damage and a tolerable level. The Company
small to negligible oil spill. High
Management Team should be made aware
of the presence of each risk in this
The risks associated with the Combo Riser are identical to category. Approvals from the Company
those associated with the dual riser. However, the probability Mamagement Team are required for any
of the riser dropping is only one third of that of the dual riser operations that fall in this category.
because only one riser run is involved in employing the Items in this category should be mitigated
Combo Riser whereas three riser runs are used for the dual on a cost/benefit basis. Recommended
riser. With regard to blowout risk, the risk has been divided mitigation actions should be implemented
into two components, normal blowout risk and the incremental only if determined cost-effective. The
risk brought on by using the single riser. Medium
Company Management Team should be
informed whenever non-mitigated
The results from the analysis indicated that the risk- acceptance of an item in this category is
discounted cost of the Combo Riser was less than that of the being proposed.
dual riser. The Combo Riser’s overall risk was lower that that Items in this category represent areas
of the dual riser system because the increased risk from where the level of risk is acceptable
blowouts, was more than offset by the reduction in riser Low without mitigation. No Company
drop risk. Management Team review or
concurrence is necessary.
HAZOP Issues Table 3. Mitigation Requirements for HAZOP-Identified Risks
Once the economic benefit of the concept was demonstrated, a
rigorous Hazard and Operability (HAZOP) review was From the HAZOP review of the concept, thirty-four scenarios
conducted in order to determine operability issues and identify were identified that might pose unacceptable risks to the
potential safety and environmental risks associated with the project. Most of these scenarios fell in the “High” and
Brutus Combo Riser system. In addition to the Brutus well “Medium” risk categories, and can be further categorized
system team, a group of Company experts in drilling, as follows:
completion, production, offshore installation, materials
science, and QA/QC was also assembled to participate in the Quality Assurance / Quality Control (QA/QC): Several
HAZOP workshop. The workshop agenda was designed to concerns from the HAZOP review were related to QA/QC of
provide a systematic analysis of potential risk and system critical riser equipment such as the wellhead tie-back
operability issues followed by an opportunity to identify connector, stress joints, girth welding of riser joints, riser
candidate mitigation strategies for each issue. The basic connectors, and tensioner joints, since the concept is based on
approach was: the premise that no catastrophic failures of riser equipment can
be tolerated during operation. Examples of catastrophic
1. Describe the system. failures due to poor QA/QC of riser equipment range from
2. Go through a list of key risk guidewords until a relevant tieback connector failure due to poor metallurgy to parting of
hazard is identified. the riser pipe body due to fatigue cracks emanating from
3. Describe the hazard scenario and consequences, and surface flaws.
identify any safeguards currently in place to mitigate
the risk.
4 K. M. CRAIK, G. T. JU, J. L. PETERSON, B. R. JAMES, K. D. CASTLEMAN OTC 13991

QA/QC of riser equipment has been a key issue in all of Personnel Training: Special operation procedures were
Company’s previous TLP projects. In the past, the operation developed to help insure the success of this concept. Since
philosophy has been to use dual-barrier protection while several of these procedures are unique to the Combo Riser
drilling through hydrocarbon bearing sands and for well concept, there is concern over whether operators will receive
completion with the reasoning that simultaneous catastrophic adequate training to operate the system, given its unique
failure of two mechanical components is not considered to be requirements. Continuity of personnel who will be operating
a credible scenario. The Combo Riser concept departs from the equipment is another concern.
this philosophy by drilling into pay sands with a single barrier.
Therefore, poor QA/QC leading to possible equipment failure All the areas of concern and each of the action items for
poses a major threat to the project. mitigating the risks that were identified in the HAZOP review
workshop have been systematically resolved and documented.
Drilling Wear and Riser Damage: Historically, drilling wear The resulting document was delivered to the Brutus Well
is accounted for in drilling riser and casing design and is Systems project team, which had the responsibility for all
permitted, provided the pressure capacity of the tubular is action items. Furthermore, the team was responsible for
maintained above demand by a suitable safety factor. Pressure reporting risk mitigation progress to the Brutus HAZOP
capacity for these tubulars can be determined through testing management team in order to ensure that all action items were
after any operation, and drilling riser joints can always be properly resolved.
inspected before they are used. The Combo Riser, however,
remains in place for the life of the well, functioning as the Risk Mitigation
production riser after being exposed to drilling and completion In order to mitigate the risks mentioned above, several novel
operations. Since any drilling wear incurred by the riser will design approaches were taken for this riser, as summarized
not only lower the pressure rating of the riser but also reduce below:
its fatigue resistance, the Combo Riser concept has an
exposure to risk that is more significant than the exposure for Pressure Rating of the Riser System: The design was
conventional production risers. Furthermore, detection of reviewed and verified to meet and/or exceed all Company and
minor drilling wear while the riser is in place can be difficult. regulatory requirements.
Uncertainty in the contour of the worn surface makes it
impractical to attempt to predict the remaining riser fatigue Fatigue Resistance Enhancement of Lower Riser Section:
life once wear occurs. For these reasons, drilling wear was Typically, fatigue life of production risers is designed to be 10
identified as one of the most critical areas of concern. times the service life. Due to criticality to the concept and the
uncertainty of potential drilling wear, the lower section of the
Another area of concern is riser damage induced by riser near the stress joint was designed with enhanced fatigue
running casing through the combination riser. Several TLP resistance greater than the above requirement.
drilling risers have had indications of impact damage to lower
drilling riser sections due to casing installation through the Damage Protection: It is well known that fatigue resistance
riser. This damage is typically caused by sharp edges of the of the riser can be significantly reduced if the riser inner or
casing connections coming into contact with the riser during outer surfaces are gouged. As a result, impact damage and
casing installation. Furthermore, most instances of this type of drilling wear must be avoided in critical sections of the riser
damage have occurred with the TLP at a large offset because such as the stress joint. Unfortunately, it has been determined
of weather conditions. Since the Combo Risers will be used that operational damage cannot be totally eliminated without
as permanent production risers, it is critical to avoid this type seriously reducing the allowable weather window for
of impact damage. operations. In order to maintain a reasonable operation
weather window, the Brutus Well System project team
Damage Caused by Operational Errors adopted the idea of using a damage sleeve inside the stress
Operational error is another major category of concern. One joint to protect it from potential damage induced by drilling.
of the most prominent examples is an insufficient riser tension This allowed drilling operations to continue in most sea
setting caused by operational errors during drilling. If the riser conditions.
tension is insufficient, significant doglegs can form in the riser
section, and serious drilling wear can occur if this happens Operational Guidelines: In order to reduce the risk of
during drilling. potential riser damage from drilling operations and operational
errors, strict adherence to the following critical drilling
Well Control: There is concern over whether a well can be guidelines was required.
secured in the presence of small riser leaks that may develop
during operations. As a result, the ability to kill the well in the 1. Use non-rotating drill pipe protectors (NRDPs) while
presence of small riser leaks was identified as a critical area drilling through the Combo Riser.
of concern. 2. Insure correct riser tension at all times by frequent
inspection and/or alarms.
DEVELOPMENT AND IMPLEMENTATION OF A TOP-TENSIONED RISER FOR
OTC 13991 DRILLING, COMPLETION AND PRODUCING OPERATIONS 5

3. Implement programs for initial inspection, riser testing, the rate of mud loss through the hole (or slot) was measured.
and wear monitoring. Tests were performed using both clean 13.5 ppg mud and the
4. Develop procedures to prevent all down-hole tools, same mud with one percent Oklahoma No. 1 sand added. One
casing, and operating procedures from damaging the riser. percent was selected because it represents a maximum likely
5. Develop well control procedures for the scenario of a concentration of sand. Typically the concentration observed is
leaking riser, and provide training for operations a trace.
personnel and drilling crews that will enable them to
manage such a situation. In all of the tests, the initial loss rate through the hole was
over 18 barrels per hour (BPH), which is above the loss rate
The Company Management Team must approve any and that is expected to be easily detected in normal rig operations.
all operational deviations from these guidelines. In addition, the loss rate did not change significantly over the
course of the tests which all lasted over 16 hours. In fact, the
The Brutus Well Systems Team also included a special data plotted as a straight line. Therefore, based on these
chapter in the operation manual for Combo Riser operations. tests the erosion does not appear to be as dramatic as may
Procedures associated with the above guidelines are clearly be expected for drill pipe operating at a higher
documented and have been communicated to field operators differential pressure.
through this document..
Riser Hole Plugging
Several training sessions were held to expose the rig At the conclusion of the above erosion tests, plugging tests
crews to the Combo Riser procedures as early as practical in were conducted using a more-or-less conventional coarse lost
order for them to gain a basic understanding of how the circulation material (LCM) pill. It was concluded that LCM
Combo Riser effects daily operations (use of NRDPs, no would plug and seal over 1,000 psi differential pressure for
shallow testing of MWDs, etc.) and expose them to the holes 0.25” and smaller but would not seal 0.500” holes.
planned contingency operations in order to give them Subsequent tests using conventional ball sealers found (as
confidence in the safety of the system. expected) that a single ball would seal a hole that was slightly
smaller than the ball. However, it was not possible to achieve
QA/QC of Riser Equipment: Strict QA/QC programs were a “wedging effect” with more than one ball trying to exit a
developed for critical riser components in order to reduce the hole at the same time, initiating a bridge to be further plugged
potential for gross component failure due to poor with LCM.
manufacturing quality. The resulting inspection procedures
and requirements were clearly communicated to field Well Control
inspectors, and the Brutus Project Leadership Team audited all The above tests established that there should be time to deal
quality programs with no significant negative findings. with a small hole in the riser; the problem was to determine
the best method(s) of well control for all practical cases.
Well Control Issues These methods or procedures were developed by a team
During the development of the Combo Riser system, it was composed of drilling operations staff that could be expected to
obvious that a gross failure of the riser with no subsea BOPs be on-site if a problem occurred and drilling engineering staff.
could not be tolerated. The absence of any pressure drop The recommendations were reviewed by experienced
across a hole in the riser and only a seawater gradient from engineering, operations, and management personnel and found
that depth up would likely make well control impossible. The acceptable. It is important to note that the primary premise in
methods employed to substantially eliminate the chance of these operations is to SAVE THE ASSET – DON’T WORRY
gross riser failure are as discussed above. However, the ABOUT SAVING THE WELL!! The conclusions are
question remained, how would a “small leak” in the riser as follows:
system be handled.
Hole in Riser That was Not Initiated by a Well Kick: The
Riser Erosion Tendency following cases were considered:
A fundamental well control question is at what rate will a
small hole in a tubular enlarge. That is, from the time that a 1. Pipe out of the hole
leak is first detected, how much reaction time is available 2. Drilling or tripping
before it has gotten totally out of hand. To answer this 3. Wire line operations
question, a series of tests were performed using a 10-¾” test 4. Cementing a liner
chamber manufactured from riser material. To simulate a 5. Running a liner
small hole, erosion tests were conducted starting with a 0.125”
drilled hole and also with a slot measuring about 0.07” by
0.30”. Water based drilling fluid was pumped at a constant
800 psi (the anticipated maximum pressure differential) and
6 K. M. CRAIK, G. T. JU, J. L. PETERSON, B. R. JAMES, K. D. CASTLEMAN OTC 13991

After extensive review and discussion the following to get it into place. The formation can then be isolated with a
fundamental plan was formulated for use any time there is lost combination of cement and mechanical devices.
circulation:
Field Implementation
1. Keep the hole full of the original mud weight (do not fill A well thought-out plan for the specific well location, casing
the hole with seawater). program, etc. is required in order to implement the
2. Jump the ROV and inspect the riser for a leak. Assuming contingency procedures. It should not be expected that one
that a leak is found, method will meet all requirements, but the above logic should
3. Continue to keep the hole full of the original mud weight be a start. Training of all key persons in the process is
while the formation is isolated, typically by setting a essential and all have to buy into the plan up front. During a
bridge plug and a retrievable test tool as deep as possible well problem is not the time to expect to be able to correctly
below the mud line. Two tools are required to provide a think out other alternatives. A flow chart is suggested for the
dual barrier and a method to test to ensure that they are basic well control plan. However, detailed procedures are
holding. When running or cementing a liner, the logic is necessary for the specific pieces of equipment to be used and
similar but the sequence of the steps is different these pieces of equipment must be on board and ready to run
depending on where you are in the process and the use of in the event of a well problem. This would also include
liner isolation packers or retrievable test tools. specifics on mud for bull-heading operations and the possible
4. Spot a riser margin kill mud. but undesirable option of using seawater (to fill the annulus)
combined with surface pressure in lieu of the original weight
The above logic was adopted because it was relatively mud. The age-old rule to “keep the hole full” is one of the
simple and consistent. The “flow chart” method was adopted basic tools. Therefore, the importance of the “trip tank hand”
to work the alternatives after much time was spent with the should not be underestimated. That person needs to pay
“detailed prognosis” method. The “flow chart” was also attention to detail and must be left alone to do their job and not
adopted for training and field procedures because it was easier be called off station to do something else when there is open
to define the well control stages and processes for a variety hole in the well!
of situations.
Benefits and Limitations of Combo Risers to Brutus
It is important to note that cement is not used except as it The use of a Combo Riser for three wells at Brutus permitted
would normally be used for the liner cementing. Emotionally, the project to achieve its objectives of reducing the project
cement is typically a first thought, however, considering the equipment costs, reducing time to first oil and full production,
difficulty of cementing a liner top or setting side track plugs, and reducing the well drilling and completion costs. The
cement is not believed to be as reliable a method (by itself) for savings from reduction in project equipment costs resulting
positive isolation as a packer type tool. from the elimination of the drilling riser system was $10
million, which includes the increased costs of the 13-¾”
Hole in Riser Initiated by a Well Kick: Well control of a Combo Riser system versus the 10-¾” production riser
kick should include the assumption that there is a hole in the system. The acceleration to production for the three wells
riser. As noted above, this is done by inspection of the riser due to pre-drilling the additional hole section was 12 days.
with the ROV throughout the well control operation. In some The reduction in time for the three wells resulting from the
applications it can also be done by pressuring up on the riser elimination of the 21” riser and 13-5/8” inner riser installation
and observing the response. The following procedures were and retrieval operations was an additional 12 days.
developed to maintain/reestablish well control if a hole was
discovered during the course of a well control event. Benefits to future projects
Some of the benefits that future projects may accrue using a
If a hole in the riser is determined when the primary well Combo Riser program, include the following:
control is nearly completed (i.e. heavy mud almost in place to 1. Reduction in risk of dropping riser. Once the production
keep the formation static) then finish the displacement and platform is installed, only one riser run per well is
continue similar procedures as in the above case of drilling or required as opposed to three runs with a dual casing
tripping to isolate the formation. drilling riser and production riser.
2. Possible reduction in the size of the floating structure.
If the hole in the riser is located when the primary well Area and buoyancy do not have to be built into the
control is not as far along, then bullhead the maximum mud structure to store a dedicated drilling riser and inner riser.
weight that can be easily mixed on the rig, with sufficient 3. Reduction in rig requirements. In deeper water it may be
volume to have the hydrostatic pressure slightly above the leak possible to use a smaller rig because the rig will not be
off pressure at the casing shoe. The strategy is to keep the required to retrieve and support a large-bore drilling riser
mud moving down, not up, while tripping to pick up a and inner riser.
retrievable bridge plug. Since the well may or may not be
static, a retrievable bridge plug is used, as it will take less time
DEVELOPMENT AND IMPLEMENTATION OF A TOP-TENSIONED RISER FOR
OTC 13991 DRILLING, COMPLETION AND PRODUCING OPERATIONS 7

Limitations to Future Projects Exploration and Production Company Inc. for their permission
Although the Combo Riser system resulted in savings to to publish this paper. Special recognition is owed to the
Brutus and appears to have applications for other deepwater following individuals for their significant contributions toward
developments, it has some limitations as noted below. the development of the Combo Riser: J. D. Smith, R.
1. A well program requiring a deep intermediate casing Gopalkrishnan, V. S. Kim, C. M. Maryan, R. D. Hounsel,
interval to be drilled by the more expensive semi- Shell International Exploration and Production Inc., J. L.
submersible rig will adversely impact economics. Duran and M. B. Whitaker, H. L. Shores, Shell Exploration
2. Geologic uncertainty may preclude committing to an and Production Company Inc., and L. M. Todd, Shell Expro.
intermediate casing shoe location during batch
setting operations. Nomenclature
3. Long intervals to be drilled through the Combo Riser TLP, Tension Leg Platform
increase the possibility of riser damage. TD, Total Depth
4. For large well counts the additional weight of the Combo BOP, Blowout Preventers
Risers, if larger than the conventional risers, may require TA, Temporarily Abandon
upsizing of the structure or may limit future facility HAZOP, Hazard and Operability Review
expansion possibilities. QA/QC, Quality Assurance/Quality Control
NRDP, Non-Rotating Drillpipe Protectors
Complacency with time and failure to adhere to the LCM, Lost Circulation Material
safeguards to avoid riser failures can be costly. BPH, Barrels per Hour

Conclusion References
The use of Combo Risers permitted the Brutus project to Theofanus, T. (1998) Personal Communication, Director of
achieve three important objectives: reduce project equipment Center of Risk Studies and Safety, University at California at
costs, accelerate first oil, and reduce well drilling and Santa Barbara.
completion costs. In order to utilize this system, a departure
from previous riser systems, a thorough risk analysis and Metric Conversion Factors
HAZOP was undertaken. A series of operational guidelines 1 foot = 0.3048 meters
and detailed well control procedures were developed to ensure 1 inch = 2.54 centimeters
safe implementation and operation. 1 psi = 0.07031 kg/sq cm
1 barrel = 159.6 l
Acknowledgements 1 ppg = 119.82 kg/m^3
The authors wish to express their thanks to the management of
Shell International Exploration and Production Inc. and Shell

Figures

Figure 1. Location Map of the Brutus TLP


8 K. M. CRAIK, G. T. JU, J. L. PETERSON, B. R. JAMES, K. D. CASTLEMAN OTC 13991

Figure 2. Brutus TLP Well Casing Program

Figure 3. Combo Riser Decision Tree

You might also like