Calc no NCWI-R-C-0090
Project title Rang Dong Field Development Proj no 350/00376
Client Japan Vietnam Petroleum Company Limited Phase/CTR 353120
Calculation title Black-start fuel gas(off N1) cooling Page 1 of 5
Calculation objective
Preface: The black start fuel gas on NCWI is anticipated to be made available from N1 test separator at a operating
conditions (P=400 psig, T=95°C). As part of conditioning of the fuel gas, the N1 gas is required to be cooled down to as low
as 45°C. Given the distance between N1 and NCWI to be 40 m, it is contemplated to make use of 40 m long unwarranted-
travelling of the gas in the cooling service, such that the massive air-cooler which is otherwise required could be eliminated.
Objective: With the above background and intention, the objectives of this calculation are as follows:
1) To estimate the overall heat transfer coefficient between the gas flow in the pipe and ambient air.
2) To estimate the cooling duty and coressponding heat transfer area.
3) To estimate the long fin pipe to meet the required heat transfer area.
If air cooling via single (3") long fin-pipe comes out to be insufficient from the calculation, then further two options will be
studied to meet the required cooling duty; A) flow splitting in parallel fin-pipes, B) dipping the fin-pipe in the sea.
Calculation method :
1) Evaluation of individual film heat transfer coefficients; ambient air side and gas side.
2) Determination of overall heat transfer coefficient.
3) Estimation of LMTD and required cooling duty.
4) Estimation of required heat transfer area.
5) Estimation of available heat transfer area for fin pipes.
Assumptions
1) Normal air velocity 10 m/s. Given 1 minute mean air velocity 20.6 m/s (per BOD wind data). Conservative assumption.
2) Max. air temperature 35°C (per BOD max. temp. 35°C). Conservative assumption.
3) Distance between N1 and NCWI to be 40 m. Conservative assumption.
References
1) Fin tube data from 'Brown Fintube' as attached.
2) Basis of Design, as attached only the relevant sheets.
3) GPC Vol.2, page 120; for the estimation of ambient air side film HT Coefficient, as attached.
4) N1 gas properties; Hysys printout sheet as attached from calc: CPC-NCWI-R-C-0084 (Fuel gas).
Conclusions
2
HT area required to cool gas from 95°C to 45°C 102 m
HT area available in 40m x 3" Fin-pipe 96 m2
509422688.xls ems/project_execution/pefm10b.xls
Rev 19a
Calculation Checklist
Calc no NCWI-R-C-0090
Project title Rang Dong Field Development Proj no 350/00376
Client Japan Vietnam Petroleum Company Limited Phase/CTR 353120
Calculation title Black-start fuel gas(off N1) cooling Page 2 of 5
Please check boxes for all applicable items checked or delete if not appropriate:
Calculations:
✘
Calculation number assigned and registered (usual format is Proj No-CAL-Discipline code-Seq No eg XXXX-CAL-E-
001, but format may be varied by Project Manager).
✘ Project title shown.
✘ Calculation title shown.
✘ Revision history box complete and signed.
Index.
✘ Appropriate stamp for preliminary issues.
✘ Calculation objectives (aims) stated.
✘ Calculation method defined or described (including formulae if relevant).
✘
Reference made to text, standard or code. Check version/edition with that required for project.
✘ Source of input data stated (with revision number and date if relevant).
✘ Assumptions stated.
✘ Summary of results or conclusions if appropriate.
✘ For software based calculations, reference to software verification if available.
✘ Method clear and easy to follow.
✘ Input data correct.
✘
Calculation arithmetically correct OR software previously verified and reference to verification checked.
509422688.xls ems/project_execution/pefm10b.xls
Rev 19a
Calculation Sheet
A 21-Aug SK
1 Estimation of air side film coefficient of heat transfer (Ref. GCP Vol.2)
0 .6
Av g
Using the formula ha =
d0 .3
2 o
Air side film coefficient of heat transfer ha 190 kJ /h . m . C
2 Estimation of gas side film coefficient of heat transfer (By Dittus Boelter Eqn.)
0. 3
hi d dv ρ 0. 8 cP μ
k
=0 . 023
μ ( )( ) k
2 o
Gas side film coefficient of heat transfer hi 3008 kJ /h . m . C
1 1 1
3 Estimation of overall heat transfer coefficient = +
U h a hi U 179 kJ /h . m2 . o C
ems/project_execution/pefm10b.xls
509422688.xls
Rev 19a
Calculation Sheet
A 21-Aug SK
4 Estimation of LMTD
ΔT 1− ΔT 2
The LMTD
ΔT LMTD=
[( )]
ln
ΔT 1
ΔT 2
27.91 °C
5 Estimation of heat duty required to cool the gas from 95°C to 45°C
Temperature at inlet t1 95 °C
Temperature at outlet t2 40 °C
Temperature difference Δt 55 °C
142.02 kW
6 Estimation of heat transfer area
ems/project_execution/pefm10b.xls
509422688.xls
Rev 19a
Calculation Sheet
A 21-Aug SK
7 Estimation of Finned-Pipe
2.4085366 sq.m/m
ems/project_execution/pefm10b.xls
509422688.xls
Rev 19a
Calculation Sheet
A 21-Aug SK
688051 lb/h
Q total ### kW
Q ### ### kW
8729061 Btu/h
Ux 2
t1 air temperature 97
Del Tn 22.65
DT1 65
DT2 63.00
LMTD 64
Ax 74819 ft2
Assume rows 6