Professional Documents
Culture Documents
Final Report Volume Iii Design Manual: For Internal Use Only
Final Report Volume Iii Design Manual: For Internal Use Only
CHAPTER I GENERAL
CHAPTER 2 CONSTRUCTION PLAN
CHAPTER 3 OST ESTIMATE
CHAPTER I GENERAL
CHAPTER 2 SEQUENCE OF
OPERATION DISPLAYS
CHAPTER 3 LISTS OF INPUT DATA
The design manual was prepared for an aim of In Division IV : Operational Manual for
technology transfer to the JKR engineers who Computer-Aided Design Programme and
are to undertake design of the standard bridges Division V Operational Manual for Computer-
that were established in the Study on the Aided Drawing Programme, both explain on
Standardization of Bridge Design in Malaysia respective data files, input operation and basics
implemented by JICA (Japan International for key operation for input. They also present
Cooperation Agency). the sequence of operation displays and the list
of input data for design programme and draw-
The manual consists of three major subjects, ing programme respectively.
namely, bridge planning, bridge design and
bridge construction and cost estimates, and it Generally, the manuals cover all fundamentals
also includes two operational manuals for com- needed for the JKR engineers to carry out the
puter aided design and drawing programme. design work from planning stage up to cost
estimate and also they include practical opera-
In Division I : Manual for Bridge Planning, tional guidelines for computer aided design and
although it is difficult to systematize all of the drawing programmes.
bridge planning procedures, it will provide
mainly with the procedures for structural side Each of the divisions can be used independent-
of bridge planning for the engineers who are ly of the other but is actually inter-related with
not always well experienced. Particularly, the each other in the process of design work.
provisions for the waterway crossing require-
ments, which is the extraction of the Japan's It is hoped that the manuals are useful for the
river management ordinance, will be a good JKR engineers not only to carry out design
help to understand how to take hydrological work, but also to improve the knowledge of
condition into the bridge planning to cross bridge engineering.
rivers.
In the above cycle, the steps (1) to (4) are 2.2 Demand for Bridge
defined as the planning stage, and which are Construction
the very process to be discussed in this manual.
Bridges are constructed for various purposes to
The steps (5) and (6) are recognized as the support roads and highways at strategic points
design stage to cover the activities from struc- along their routes. Bridge structures are
tural analysis up to preparation of drawings and required to cross over rivers and valleys, or for
specifications normally including construction grade-separation with other roads and railways.
contract documents. The step (5) - preliminary
design is generally performed with less accura- Bridges are generally classified and separately
cy than that of detailed design to obtain outline called by purpose as follows:
of the project and clarify problems, which
enable the authority to take early actions and (1) Road or highway bridge
corrections before detailed design sets in. General name for any bridge on roads
and highways.
Bridge plan is materialized through the detailed
design and construction. Completed bridge will (2) Railway bridge
be used over a long period as a public facility General name for any bridge on
receiving maintenance and when it becomes railways.
decrepit, the demand for new bridge construc-
tion arises again. (3) Flyover or overpass bridge
Bridges for grade-separation with other
CHAPTER 2 roads, highways, or railways at
intersections.
PROCESS OF BRIDGE
PLANNING (4) Viaduct
Bridges to support elevated roads,
2.1 General highways, or railways, which are built
mainly at where ground space is limited
The work of bridge planning is begun upon in urban area or embankment is difficult
seizing the demand for bridge construction and for ground is soft.
takes the steps as explained in the bridge life
cycle toward implementation. However, the 2.3 Definition of Requirements and
process of bridge planning explained in this Conditions
manual is not always applicable as it is to every
case. By cases, different planning process will 2.3.1 General
be taken: some bridges can be planned more
simply but some may need another or addition- Upon receiving a demand of bridge construc-
al consideration. Practically, the experienced tion plan, it is the first step to clarify all the
bridge designers tend to perform bridge plan- information attending the proposed bridge plan
ning by taking into account various conditions including both of requirements and conditions.
simultaneously. Requirements mean functions and capacities
intended to the planned bridge. Conditions
This chapter of bridge planning process will be mean natural environment and surroundings
useful for less experienced engineer as a check- where the bridge is to be constructed.
list not to miss the essentials of planning and
for advanced engineers to prepare lucid expla- 2.3.2 Requirements
nation and report for their planning.
For the planning of road and highway bridges,
Approximate location and size of bridge The requests of affixing public utilities
are initially defined in the vertical and should be confirmed to each utility agency
horizontal alignments of planned road. The and taken into account in bridge planning
road alignment of the proposed bridge if requested. The accommodation space for
section and its vicinity will be sometimes utilities shall be secured in the bridge
modified if that is not favorable for bridge crosssectional profile and their additional
planning, for example to avoid steep grade, weights including that of affixing devices
sharp skew, curbed alignment, etc. In case be taken into bridge loading. Utilities are
of bridge replacement, the new bridge is usually accommodated under bridge deck
generally planned in parallel with the old, and between beams to be concealed from
and approach roads are required to connect the external view. Affixing of electric lines
with the existing road. needs insulated covering against electric
shock risk. Affixing of water main pipes
(2) Cross-section of road sometimes makes the bridge structural lay
out difficult especially in case that water
The cross-sectional profile of bridge pipe is too large to be accommodated
generally conforms to the standard cross- between beams.
section of road design. Same traffic lane
widths as that of the road section are The cost of affixing public utilities is
normally applied to the bridge section, too. generally beared by the utility agencies in
As regards shoulder and sidewalk, different the proportion of the utility weight to the
designs are sometimes adopted according total bridge design loads.
to the situation of the proposed bridge for
example reducing or adding such widths 2.3.3 Conditions
from economical reason.
Bridges are so planned as not only to meet
(3) Design vehicle loads the prescribed requirements but also to be
Design vehicle loads to be imposed on compatible with the surrounding
bridge must conform to the JKR environment and other site conditions.
specification for bridge live load. Over Normally, the following conditions are
loading provision may be considered involved:
according to the classification of road and
the design traffic volume especially of (1) Topography
heavy commercial vehicles ratio.
Bridge structure is planned so as to fit
(4) Affixed public utilities in surrounding topography. Normally,
Bridge, although its major function is to topographic map and profile elevations
support traffic loads, is often requested to are prepared by the plane and levelling
affix the following public utilities: surveys, and on which bridge structure
is planned mainly for determining
- Tele-communication cables location, length, and spans.
- Electric cables
For the bridges planned with minimum Irrespective of the above economic
height on the high water level, the study, the limit of the safe embankment
abutment location is generally so height will be an decisive factor to
decided, according to the crossing decide the abutment location where the
conditions, as to minimize the bridge ground cannot support high fills. After
length from economic reason. Crossing all such studies, abutment is generally
conditions are detailed later in Chapter planned of its height ranging from
3.3. around 4 to 15m.
(2) Pier location, span, and bridge type construction cost for each case
including all the superstructure and
After defining the bridge location substructure costs and compare them
and length, the next is to select pier to find the most economical span
location and spans as well as appli arrangement and bridge type.
cable bridge types (of
superstruture) by studying the 3)In order to hold the accuracy of
ground (topographical and the cost comparison, bride type
geological) and crossing (of should be selected appropriate for
waterway, road, or railway) the proposed span and be practicable
conditions on the base map. As in construction. The superstructure
spans are decided, the choice of type is comparatively quick to be
bridge types will be narrowed down, looked up from the standard design
that is, span is generally selected compared to the substructure which
within the applicable range for each is usually not easy and owes much
bridge type. The reference of bridge to the engineer's experience and the
types and suitable span range is past similar designs. Simplified
given later in Tables 1.5 and 1.6 of stability calculation is sometimes
Chapter 3.4.2. required to define the size of sub
structure especially the size and
For the bridges where pier location number of piles which affect the
is restricted by crossing conditions, substructure cost significantly.
it is so selected, according to the
recommendations detailed in 4) In conclusion, the economy of
Chapter 3.3 - Crossing Conditions, selecting span and bridge type is
as to minimize the interference with understood as the cost balance
the crossing river, road, or railway. between superstructure and sub
structure. That is, the cost of super
However, for the bridges where pier structure is generally much the
location is discretionary, it is higher as the longer span is. On the
selected economically by comparing other hand, the cost of substructure
the costs for several span depends more on ground condition
alternatives. This study holds true than span and bridge type.
more for longer bridges. A sample Therefore, for such bridges as the
of the cost comparison is substructure cost is small because,
demonstrated as follows: for instance, no pile is required
owing to shallow bearing stratum,
1) Propose minimum three the choice of shorter span with
alternatives of different span many piers is economical, and vice
arrangements and their versa.
corresponding bridge types for a
certain bridge length. For example,
suppose the following three
arrangement cases as shown in Fig.
1.4 - Economical Span
Arrangement.
2.5 Evaluation and Selection but the problem is to select the type
and size of piles. Several options will
2.5.1 General be suggested with advantages and
disadvantages. For instance, PC spun
Chapter 2.4 explained how to draft a piles may be the cheapest but
bridge plan to meet the requirements in uncertain in execution for the depth
the given conditions. As a matter of of bearing stratum and the existence
course, drafting work is always per of intermediate sand layers. Steel
formed to seek better plan and through pile piles are reliable in construction
this process various judgments and but may be the most expensive.
reasonings as well as selections will Bored cast-insitu concrete piles will
have been developed. However, such be another possibility reliable in
developed information will not have execution and advantageous for less
been logically compiled yet. For the noise if the site is in residential area,
final conclusion of bridge plan, the but the site work will be complex for
process of evaluation is required to arge facilities and skilled techniques
justify it objectively. re required. Thus, even taking the
problem of piles which is only a part
The work of evaluation should start with of a bridge, evaluation is required to
making clear the objects of evaluation, select the best.
be followed by the comparison of
advantages and disadvantages, and be In bridge planning, the followings
concluded by rating. are the most common objects of
partial evaluation:
2.5.2 Objects of Evaluation
1) To select location, length, and
Bridge is a composite figure made of spans
many components which are roughly
divided into superstructure and - Abutment location by cost
substructure including foundation. To comparison between bridge
select such a composite figure, and earthfills, and maximum
evaluation is required in both ways, safe earth-fill.
partially and totally. 1-15
The criteria for safety of structures is (6) Traffic safety and comfort
generally given by design
specifications or codes, which is a The traffic safety and comfort on
necessary condition in bridge design bridges depend not only on the road
but not a sufficient. To harmonize geometries and alignment but also on
safety and economy in bridge the existence of structures on the
planning, it requires the profound bridge surface. In view of that, the
knowledges of an experienced following measures are
engineer. However, the drawing or recommended:
the completed bridge given due such
consideration will convince the 1) Adopt deck type bridge rather
people's eye that the structure is than through type except the
functional, and safe, too. cases that the under-bridge
Longitudinal and lateral profiles are This is a visual survey to judge the
preferably prepared by the leveling subsoil conditions from the outcrops
surveying along the road center line. of rocks and strata. The survey is
Alternatively, profile can be also carried out by walking along the
prepared from the contours of the existing roads and rivers in the
topographic map and that may be survey area while observing the
usable considering less accuracy. outcrops to make a field
reconnaissance map.
3.2.2 Geological Survey Landslide traces, obstacles, terrain
and ground condition which seem to
(1) Survey method be troubles for construction, will be
also surveyed in this occasion.
The geological survey for bridge
planning is performed putting stress (4) Soil boring
on obtaining the general subsoil
information of bridge site rather than 1) General
detailed soil tests. The survey is
normally carried out from data Boring survey is the most popular
collection and field reconnaissance, soil investigation method to
and followed by boring, test-pit obtain the underground
digging, or geophysical exploration stratification and the engineering
if considered necessary. characteristics of strata. The
method bores a hole into ground
(2) Data collection by boring machine, collects
samples and carries out in-situ
This is performed at early stage of tests through the hole. Soil boring
the survey to collect the existing generally performs the following
geological data around the site. surveys:
Major data sources are the geological - Discrimination of
map issued by the National Geology stratification
Office and the previous boring or - Observation of cored soils
geophysical data of the vicinity. If - Sampling and laboratory soil
such existing data is available, the test
general geological condition of site - Water level in bore
can be often supposed from those - In-situ test in bore: standard
data and so special field survey may penetration test, vane shear
not be required. Thus, the execution test, lateral loading test, pore
of field survey depends on the data water pressure test,
collection. geophysical exploration, etc.
The result of standard penetration test “ N-value” is the most important information widely
used for the design of foundations. Many design factors shown in Table 1.2 can be from N-
value.
The Meyerhof’s suggested relations of N-value to relative density and internal frictional
angle is given in Table 1.3 and the Terzaghi-Pecks’s of N-value to consistency and uniaxial
compression strength in Table 1.4.
For selecting the bearing stratum for bridge foundation according to N-value, although there
are many exceptions to design and site condition, the fllowing values are generally suggested
as a standard
Sandy Soil : N>40
Clayey Soil : N>30
construction should not become any occurred more at the curved reaches
obstruction to the river improvement than the straight. Although small
plan. meanderings occur even in straight
reaches by the movement of sand
3.3 Crossing Conditions bars, it is far better to select bridge
site at the straight reach compared to
3.3.1 General the curved. Further, it is important to
investigate the historical change of
Bridges are constructed to cross existing river course and bridge site should be
land space, most are public spaces such selected at where the change of river
as rivers, roads, railways, etc. and where course is small.
the bridge structures must exist long
time after being constructed. Therefore, 2) Cross river in perpendicular to its
bridge plan is required to have due flow.
consultations with the competent
authorities of such space for approval. The bridges crossing rivers with
skew direction often cause erosions
The crossing conditions required to and scourings at around bridges.
bridge plans are different depending on Skew bridge will produce
their planned location and purpose, and asymmetric turbulence in river flow
governed by various regulations relevant and that makes the bank protection
to land use. against erosion very difficult.
Although it varies depending on water depth, the design discharge and the required waterway
width have a general relation as follow :
300 40 - 60
500 60 - 80
1000 90 - 120
2000 160 - 220
5000 350 - 450
The freeboard between HWL and the top of dike for the rivers having compound cross-
sections, shall be not less than the following values:
For the rivers having single cross length in relation to the design
sections, the freeboard is discharge is generally given by the
recommended to take at least 0.6 m. following formula.
3) Pier location close to bank The pier width shall be measured in per
pendicular to flow direction at high
Pier should not be laid on the slope water level, and the waterway width
of bank nor at the foot of bank slope. shall be the width of high water level.
It is recommended for the piers
planned close by bank to take at
least the following distance from the
toe of bank slope.
i) Low water channel and the part of high More than 2m below the river bed of low
water channel within 20m from the top water channel
of the slope of low water channel:
ii) High water channel beyond 20m from the More than 1m below the river bed of high
top of the slope of low water channel : water channel.
1 Superstructure
- Pavement surface area (m²)
(include curbs and rails)
- Expansion Joints size and length (m)
- Main beams
(include erection work and diaphragms)
PC precast beam type,size and number of beams from standard
design (pieces)
PC box girder concrete volume per bridge surface area from
previous project data (m³/m²)
Steel girder steel weight per bridge surface area from
previous project data (ton/m²)
- Deck Slab concrete volume (m³)
- Bearing shoes capacity and number of shoes (pieces)
2 Substructure
- Abutments and piers concrete volume (m³)
- Excavation and temporary cofferdam excavation volume (m³)
- Foundation
Spread footing be included in abutment and pier concrete
volume
- Piles type, size,depth, and number of piles
(total pile length : m)
3 Approach road
- Road earth -fills earth volume (m³)
- Pavement surface area (m²)
4 Other works
- Temporary staging surface area (m²)
- Traffic detour - way length or surface area (m or m²)
- Bank protection surface area (m²)
The unit costs used in this method are considered to include all direct, indirect, and corporate indirect
costs. With this method,accuracy is expected to be within 10-20 percent range.
Significant error may occur if unususal construction techniques and temporary facilities are involved
and are not properly compensated for in the unit costs applied. This is a reason why the preliminary
cost is sometimes far below the contractor’s bid cost.
Government Project Administrative A project overview from identification of Outline Entire Month Low
department director planning need through feasibility study, Project Project
FOR INTERNAL USE ONLY
Clients
Project Project Co-ordination Design period, documentation, letting Outline and Project Week Low/medium
manager manager of design and contracts, and construction period. broad details design and
construction construction
Contractor Staff Tender plan All activities within construction period in Construction Construction Week Medium
sufficient detail to enable contractor to programme period
prepare the tender
Contractor's or Staff Resource Every activity, major items of plant, dates Short-term Months Day Medium/high
Managers
Engineer's planning of key material deliveries and site movement programme.
Representatives
Foreman Staff Disposition of Every operation with the actual plant, Weekly Weeks Half-day High
plant manpower and supervisors employed. programme
and manpower
Page 17
Final Report Volume III Design Manual
FOR INTERNAL USE ONLY Final Report Volume III Design Manual
Primary impacts are generally easier to benefit from view; (3) bridges or
analyze and measure, while secondary elevated highway out of scale with
impacts are usually more difficult to adjacent urban development; (4)
measure. Secondary impacts may, in visual distraction and displeasing
fact, be more significant than primary glare visible in recreational and
impacts. residential areas; and (5) unattractive
contrast between existing vegetation
3.6.2 Impacts of Highway and Bridge and revegetated or landscaped areas,
Project between natural landforms and
engineering features, and between
(1) General urban or existing development
patterns and highway features.
Bridges are a part of highway,
accordingly the environmental (3) Air quality impacts
impacts of the bridge construction
should be discussed in the Air quality impacts include: (1) dust
environmental problem of the and/or particulate matter on
highway construction. vegetation and structures
surrounding the construction site or
Highway construction has impacts in along roads: (2) tire and exhaust
a number of areas, the most particles coating roadside vegetation
noteworthy of which are aesthetics, and structures; (3) increase in
air quality, circulation and traffic severity of existing smog conditions
patterns, noise, socioeconomics, due to an increase in automobiles
water quality, and wildlife. Highway traveling through the area; and (4)
may stimulate or induce other generation of vehicle fumes and
actions (secondary impacts), such as odors (such as from exhaust
more rapid land development or emissions, or tire and brake rubber).
changed patterns of social and
economic activities. Impacts (4) Noise impacts
associated with secondary action
may often be even more substantial Noise impacts generally involve the
than the primary impacts associated area within sound of the traffic such
with construction. For example, the as:
effect on population and area growth (1) disturbance of surrounding
associated with the construction of passive recreational activities
new highways may be among the requiring quiet and serene conditions
more significant impacts. for their enjoyment; (2) disturbance
of educational, health care, and
(2) Aesthetics impacts cultural activities or institutions
particularly sensitive to noise, such
Of general concern relative to as schools, churches, hospitals,
aesthetics are such impacts as: (1) sanitariums, auditoriums, and
blocking viewlines along visual theaters; (3) disturbance to operation
corridors (such as valleys, stream or patronage of commercial activities
courses, and streets); (2) blocking requiring or benefiting from quiet
viewlines to landmarks in the surroundings; and (4) disturbance to
community from residential, surrounding residential development.
recreation, and commercial areas that
transit routes; (2) dividing single land proportions, clean lines, interesting
uses or resource areas such as but not fancy forms. The bridge
agricultural operations, recreation areas, designer should never forget the
wildlife ranges or habitats; (3) projected 100-year life for his
increasing truck and construction structure. If he wants his critics of
equipment traffic on public roads during eight or ten decades hence to
construction: (4) providing new or admire his work, he had better make
improved access to previously it a basically excellent design. He
inaccessible or relatively inaccessible must walk the fine line between
public and private lands; (5) providing uninteresting starkness and overdone
or improving access to relatively decoration.
undeveloped areas outside urban
centers, thus inducing commercial and High fills have blocked the view of
industrial operations to locate outside many attractive canyons, when the
urban centers; and (6) increasing traffic beauty of many deep canyons would
traveling through the area and thus be enhanced by the slim framework
causing an increased demand for travel of a welldesigned bridge. Fills and
related services. culverts have their place when they
will not destroy natural beauty. But,
3.6.3 Aesthetic Consideration where there is such beauty, consider
a bridge rather than a culvert and fill.
(1) General As a practical matter, the apparent
economy of a culvert at the base of a
A bridge should never usurp its role huge fill may prove false if debris
as a part of the highway. It should plugs the culvert and the water backs
always look as though it thoroughly up and floods the country above the
belonged to the rest of the highway. road. Such shortsighted economy can
It should be completely compatible generate law suits.
with its surroundings. The bridge
belongs in that location. (2) Aesthetics of structures
The analysis system is shown in the (4) BS 8110 - Structural use of concrete
Fig.2.l, 2.2 and 2.3 on the following pages.
A full automatic design system, with Part 1 : 1985 - Code of Practice for
personal computer, is applied for design and construction
superstructure, whereas a partially Part 2 : 1985 - Code of Practice for
computerized system is used for special circumstances
substructure design.
In addition, the following Japanese
"Bridge Structural Analysis" is the standards are also adopted in instances
techniques required to assess the adequacy whereby it is impossible to comply with
of the structural strength or resistance of the above mentioned standards.
the bridge under the reasonably conceived
severe loads. The analysis techniques are - Specifications for Highway Bridges
entirely based on the theories and formulas ( Japan Road Association)
stipulated in the authorized publications.
Part I : 1994 - General Specifications
Part II : 1994 - Specifications for
Concrete Bridges
Part III : 1994 - Specifications for data. That is, effects of the design loads
Substructure in various forms such as overturning
moments, displacemnts, stresses,
1.4 How to Use the Manual strength, etc.
CHECK
CHECK
YES
Drawing Program System
STOP STOP
Drawing Program System
1
Page 29
Final Report Volume III Design Manual