DATUM ARCHITECTURE - PT MANDALABHAKTI SENTOSA

Drawing Register/Transmital
BUIN BATU SCHOOL - WEST SUMBAWA
Day 23 18 15 05 28 10 24 30 18 7 14 15 22 25 28 5 11 18 22
ARCHITECTURE DRAWINGS Month 01 03 07 09 09 11 11 11 12 01 01 01 01 01 01 02 02 02 02
Year 20 20 20 20 20 20 20 20 20 21 21 21 21 21 21 21 21 21 21
Drawing Tittle PT AMNT Dwg.No Arch. Dwg. No.
1 Cover A00.00 A A B C
2 Drawing List A00.01 A A B C
3 Siteplan A00.02 A A B C D E
4 Blockplan A00.03 A A B C D E

5 1st Floorplan A10.01 A A B C D E


6 2nd Floorplan A10.02 A A B C D E
7 3rd Floorplan A10.03 A A B C D E
8 Roof Plan A10.04 A A B C D E

9 1st Floorplan Admin Block A10.05 A A B C E


10 2nd Floorplan Admin Block A10.06 A A B C E
11 3rd Floorplan Admin Block A10.07 A A B C E
12 Roof Plan Admin Block A10.08 A A B C E

13 1st Floorplan Gym A10.09 A A B C E


14 2nd Floorplan Gym A10.10 A A B C E
15 Roof Plan Gym A10.11 A A B C E

16 Floorplan - Kindergarten 1st & 2nd Floor A10.12 A A B C E


17 Floorplan - Kindergarten Roof A10.13 A A B C E
18 Floorplan - Primary School 1st & 2nd Floor A10.14 A A B C E
19 Floorplan - Primary School Roof A10.15 A A B C E
20 Floorplan -Middle School 1st Floor A10.16 A A B C E
21 Floorplan - Middle School 2nd Floor A10.17 A A B C E
22 Floorplan - Middle School Roof A10.18 A A B C E
23 Floorplan - High School 1st & 2nd Floor A10.19 A A B C E
24 Floorplan - High School Roof A10.20 A A B C E

25 Floorplan - Pooldeck Plan A10.21 E


26 Floorplan - Pooldeck Roof A10.22 E
27 Floorplan - Drop Off & Parking A10.23 A

28 Elevation - Kindergarten A20.01 A B


29 Elevation - Primary School A20.02 A B
30 Elevation - Middle School A20.03 A B
31 Elevation - High School A20.04 A B
32 Elevation - Admin, Theatre, Library A20.05 A B
33 Elevation - Gym A20.06 A

34 Site Section A-A, B-B, C-C, I-I A30.01 A


35 Site Section J-J, K-K A30.02 A

36 Section - Kindergarten Section A-A, B-B A31.01 A B C


37 Section - Primary School Section A-A, B-B, C-C A31.02 A B C
38 Section - Primary School Section D-D, E-E A31.02A B C
38 Section - Middle School Section A-A, B-B, C-C, D-D, E-E A31.03 A B C
39 Section - High School Section A-A, B-B, C-C, D-D A31.04 A B C
40 Section - Admin, Theatre, Library Section A-A, B-B, C-C A31.05 A P2 B C
41 Section - Admin, Theatre, Library Section D-D, E-E A31.05A P2 B C
42 Section - Gym Section A-A, B-B, C-C A31.06 A B C
43 Section - Musholla, Walkway A31.07 A B

44 Finishing plan - Kindergarten - 1st Floor & AC Space A50.01 A B


45 Finishing plan - Primary School - 1st & 2nd Floor A50.02 A B
46 Finishing plan - Primary School - Roof Deck A50.03 A B
47 Finishing plan - Middle School - 1st Floor A50.04 A B
48 Finishing plan - Middle School - 2nd Floor A50.05 A B
49 Finishing plan - Middle School- Roof Deck A50.06 A B
50 Finishing plan - High School - 1st & 2nd Floor A50.07 A B
51 Finishing plan - Admin - 1st Floor A50.08 A B
52 Finishing plan - Admin - 2nd Floor A50.09 A B
53 Finishing plan - Admin - 3rd Floor A50.10 A B
54 Finishing Plan - Admin & Gym Roof Deck A50.11 A B
55 Finishing Plan - Gym - 1st Floor A50.12 A B
56 Finishing Plan - Gym - 2nd Floor A50.13 A B
57 Finishing Plan - Pool Deck A50.14 A B
58 Finishing Plan - Drop Off & Parking A50.15 B

59 RCP - Kindergarten - 1st Floor A60.01 A B


60 RCP - Primary School - 1st & 2nd Floor A60.02 A B
61 RCP - Middle School - 1st Floor A60.03 A B
62 RCP - Middle School - 2nd Floor A60.04 A B
63 RCP - High School - 1st & 2nd Floor A60.05 A B
64 RCP - Admin - 1st Floor A60.06 A B
65 RCP - Admin - 2nd Floor A60.07 A B
66 RCP - Admin - 3rd Floor A60.08 A B
67 RCP - Gym - 1st Floor A60.09 A B
68 RCP - Gym - 2nd Floor A60.10 A B
69 RCP - Pool Deck A60.11 A
70 RCP - Walkway & Pergola A60.12 A

71 Electrical Plan - Kindergarten - 1st Floor & AC Space A61.01 A


72 Electrical Plan - Primary School - 1st & 2nd Floor A61.02 A
73 Electrical Plan - Primary & Middle School - Roof Deck A61.03 A
74 Electrical Plan - Middle School - 1st Floor A61.04 A
75 Electrical Plan - Middle School - 2nd Floor A61.05 A
76 Electrical Plan - High School - 1st & 2nd Floor A61.06 A
77 Electrical Plan - Admin - 1st Floor A61.07 A
78 Electrical Plan - Admin - 2nd Floor A61.08 A
79 Electrical Plan - Admin - 3rd Floor A61.09 A
80 Electrical Plan - Admin & Gym - Roof Deck A60.10 A
81 Electrical Plan - Gym - 1st Floor A61.11 A
82 Electrical Plan - Gym - 2nd Floor A61.12 A
83 Electrical Plan - Pool - Deck A61.13 A

84 Toilet Detail - Kindergarten A70.01 A


85 Toilet Detail - Primary and Middle School A70.02 A
86 Toilet Detail - Primary and Middle School A70.02A A
87 Toilet Detail - High School A70.03 A
88 Toilet Detail - Admin - Toilet 1,2,3 A70.04 A
89 Toilet Detail - Typical - Admin & Gym 2nd floor A70.05 A
90 Toilet Detail - Gym - Boys & Girls 2nd Floor A70.06 A
91 Toilet Detail - Gym - Men&Women 1st Floor A70.07 A
92 Toilet Detail - Gym - Girls Changing Room A70.08 A
93 Toilet Detail - Gym - Girls Changing Room A70.08A A
94 Toilet Detail - Gym - Boys Changing Room A70.09 A
95 Toilet Detail - Gym - Boys Changing Room A70.09A A
Day 23 18 15 05 28 10 24 30 18 7 14 15 22 25 28 5 11 18 22
ARCHITECTURE DRAWINGS Month 01 03 07 09 09 11 11 11 12 01 01 01 01 01 01 02 02 02 02
Year 20 20 20 20 20 20 20 20 20 21 21 21 21 21 21 21 21 21 21
Drawing Tittle PT AMNT Dwg.No Arch. Dwg. No.
96 Stair & Ramp 1 Detail - Plan A80.01 P1 A
97 Stair & Ramp 1 Detail - Section A80.01A P1 A
98 Stair & Ramp 1 Detail - Section A80.1B A
99 Stair & Ramp 2 Detail A80.02 P1
100 Stair & Ramp 3 Detail A80.03 P1 A
101 Stair & Ramp 4 Detail 1 A80.04 A
102 Stair & Ramp 4 Detail 2 A80.04A A
103 Stair & Ramp 5 Detail 1 A80.05 A
104 Stair & Ramp 5 Detail 2 A80.05A A
105 Stair & Ramp 6 Detail - Kindergarten A80.06 A
106 Stair & Ramp 7 Detail - Kindergarten A80.07 A
107 Stair & Ramp 8 Detail - Plan A80.08 P1
108 Stair & Ramp 8 Detail - Section A80.08A P1
109 Stair & Ramp 8 Detail - Section A80.08B P1
110 Stair 9 Detail - High School A80.09 P1
111 Stair 10 Detail - Admin A80.10 P1
112 Stair 11 Detail - Library A80.11 P1
113 Stair 12 Detail - Gym A80.12 P1
114 Stair 13 Detail - Music Room A80.13 P1 A
115 Stair 14 Detail - Admin Roof Garden A80.14 A
116 Stair & Ramp 15 - South West Walkway A80.15 A
117 Ramp 16 - Curve Main Walkway A80.16 A
118 Ramp 17 - West Walkway A80.17 A
119 Ramp 18 - North walkway A80.18 A

120 Pool Detail Plan A81.01 P1


121 Pool Detail Section A81.02 P1
122 Pool Typical Detail A81.03 P1
123 Kids Pool Detail A81.04

124 Ethnic Lasercut Panel Detail A82.01

125 Partial Section - Kindergarten A83.01


126 Partial Section - Primary School A83.01
127 Partial Section - Middle School A83.01
128 Partial Section - High School A83.01
129 Partial Section - Admin Block A83.02
130 Partial Section - Gym A83.03

123 Canopy Detail - Kindergarten 1 A86.01 P1


124 Canopy Detail - Kindergarten 2 A86.02 P1
125 Canopy Detail - Primary School A86.03 P1
126 Canopy Detail - Middle School A86.04 P1

127 Typical Railing Detail A88.01


128 Typical Roof Detail A88.02

129 Typical Finishing Detail A89.01


130 Typical Finishing Detail A89.02

131 Door Window Keyplan A90.01 A C


132 Door Window Keyplan A90.02 A C
133 Door Window Keyplan A90.03 A C
134 Door Window Keyplan A90.04 A C
135 Door Schedule 1 A91.01 A C
136 Door Schedule 2 A91.02 A C
137 Window Schedule 1 A92.01 A C
138 Window Schedule 2 A92.02 A C
139 Window Schedule 3 A92.03 A C
140 Window Schedule 4 A92.04 A C
141 Window Schedule 5 A92.05 A C

DISTRIBUTION
1 PT AMNT Owner V V V V V V V V V V V
2 KANDU Project Manager V V V V V V V V V V V V V V V V V V
3 TTW Structure V V V V V V V V V V V V V V V V V
4 BEMACOM MEP V V V V V V V V V V V V V V V V V
5 REYNOLDS PARTNERSHIP QS V V V V V V V V V V V V V V V V V