GO-NO-GO VOIDED SLAB AND PCI GIRDER ERECTION


BY PT.JATRA SEJAHTERA

SSHE
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

NO Classification SECT. REQUIRED DELIVERABLES REQUIRED AVAILABLE STATUS Remarks

1 SSHE
1 SSHE Plan RH

2 PPE for workers (based on PPE list) √ JS

3 First Aider is dedicated at the worksite RH


4 First Aid Kit is available at the site √ JS

5 Safety Area barricade available at site √ JS


6 Safety Signs available at site √ JS
Working Signs √ JS
Working at Height Signs √ JS
Working at Height Boat N/A
Authorized Worker Signs N/A
Safety Bulletin Boards √ JS
7 Employee Badge
ID Badge √ JS
Work at height training √ JS
Scaffolder training
Confined space training
Defensive Driving Course for
Operators and Drivers RH
8 Inspections
Welding transformer/machine and
cables √ JS
Crane / Lifting Equipment √ RH
Lifting Gear (inspected, records, and
color-coded) √ JS
Power tool (with GFCI, i fused
outside) √ JS
Generator set (with proper size
grounding rod) √ JS
Hand tools √ JS
Scaffolding (inspector and builder
certifications checked) N/A
Fire extinguisher N/A
Gas detector (calibrated) N/A
Ladder √ JS
Eye wash √ JS
Full Bodyhardness √ JS
Special PPE (face shield, special
gloves, clothing) N/A
9 Health and Hygiene
shelter /shed area √ JS
fresh drinking water √ JS
trash bin √ JS
toilet √ JS
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

sosec : engagement with local partners


10 started early and issues resolved RH
Coordination
11 Emergency Response Plan with RH

Prepared by Approved by Acknowledged by MCL

PT. JATRA SEJAHTERA SSHE/QUALITY/CONSTRUCTION SSHE/QUALITY/CONSTRUCTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

1. SSHE PLAN
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

Safety, Health & Environment Commitment

PT. JATRA SEJAHTERA ensure and careful the PT. JATRA SEJAHTERA bertekat dan hati-hati
safety and healthful working environment also untuk menyediakan tempat dan lingkungan
free from recognized hazard for its employees. kerja yang aman dan sehat untuk karyawan.
Each employees, sub-contractor will have a Setiap karyawan dan sub-contractor akan
thorough knowledge of the Safety Health mendapatkan pengalaman dan pengetahuan
Environmental Plan and therefore, we will be yang mendetail tentang keselamatan kerja dan
responsible for the safe performances of the oleh karena itu, kami akan bertanggungjawab
work as an integral part of the assigned duties. untuk mengawasi keselamatan kerja sebagai
bagian penting dari pekerjaan yang diberikan.

Our commitment are : Tanggung jawab / kewajiban kami adalah :


1. Managememnt always commit that 1. Manajemen selalu yakin bahwa
Health, Safety and Environment persyaratan Keselamatan, Kesehatan
requirement is important thing dan Lingkungan merupakan hal yang
penting.

2. Ensuring a safe work environment and 2. Memastikan agar semua lingkungan


proper equipment to perform each pekerjaan aman, serta penggunaan
task peralatan yang layak untuk
mengerjakan setiap pekerjaan.

3. Management will conducting regularly 3. Manajemen akan mengadakan inspeksi


scheduled safety and health inspection keselamatan kerja secara rutin untuk
to identify and eliminate unsafe work mengenal, menetapkan dan
conditions and/or practices, to control mengurangi setiap kondisi yang tidak
health hazard, and to comply fully with aman, dengan tujuan untuk
the safety and health requirements of mengontrol bahaya terhadap
every task kesehatan kerja, dan tunduk secara
penuh pada ketentuan keselamatan
kerja dari setiap pekerjaan.

4. Management will develop and 4. Manajemen akan menjaga dan


maintain the culture of Safety and meningkatkan budaya sehat dan aman.
Health
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

5. Management will provide training and 5. Manajemen menyelenggarakan


motivating supervisors to instruct their training dan memberi motivasi kepada
personnel thoroughly in all safety supervisor untuk menginstruksikan
aspects of their work secara langsung kepada pekerja
mengenai segala aspek keselamatan
kerja yang berhubungan dengan
pekerjaan mereka.

6. Management will investigate , 6. Manajemen akan mengadakan


promptly and thoroughly , every investigasi secara tepat dan langsung
accident, incident, and near miss pada setiap kejadian kecelakaan yang
involving Contractor, Subcontractor berhubungan dengan Contractor
personnel to determine the cause and dan/ataupun sub kontrak untuk
remedial action required preventing menentukan penyebab kecelakaan
recurrence serta tindakan pencegahan yang
diperlukan untuk mencegah supaya
tidak terulang lagi.

7. Management will manage the 7. Manajemen akan mengelola


operation to minimize environment / operasional untuk meminimalkan
human impact and provide workplace dampak negatif lingkungan dan
free of recognized hazard menyiapkan tempat kerja yang
terbebas dari bahaya.

8. Management will monitor, evaluate 8. Manajemen akan memantau,


,report and audited all performance in mengevaluasi, melaporkan, dan
Health, Safety and Environment mengaudit setiap kinerja dari program
program regularly. pelaksanaan perlindungan lingkungan,
keamanan, dan kesehatan kerja secara
berkala.

PT. JATRA SEJAHTERA

BAMBANG WARSITO
Direktur Utama
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

2. PPE FOR WORKERS

3. FIRST AIDER IS DEDICATED AT THE WORKSITE

COVER BY RH

4. FIRST AID KIT


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

5. SAFETY AREA BARRICADE

6. SAFETY SIGNS
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

7. EMPLOYEE BADGE

ID Badge for employee still on process

8. TOOLS INSPECTION

No Description Merk Type Fitur Qty Status


1 Gantry fabrikasi Electricity 120 Ton 2
2 Crane Sumitomo 2
3 Launcher fabrikasi Electricity 120 ton, 48 m 1
4 Power fabrikasi Diessel 125 kVA 1
generator
5 Measuring tape Local 3
6 hammer Local 2
7 ladder Local 2
8 Welding Focus Manual 400 A 2
machine &
cable
9 Wrench set Local 1
10 pliers Local 2
11 cutter Local 2
12 Screwdriver Local 4
13 Scissor Local 2

a. Hand tools
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

b. Welding machine set

c. Power Generator

d. Launcher
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

e. Gantry

9. HEALTH AND HYGIENE


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

GO-NO-GO VOIDED SLAB AND PCI GIRDER ERECTION


BY PT.JATRA SEJAHTERA

QUALITY PLAN
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

NO Classification SECT. REQUIRED DELIVERABLES REQUIRED AVAILABLE STATUS Remarks


2 QUALITY
12 Quality Plan √ RH
13 ITP (Inspection Test Plan) √ RH
14 WPS PQR N/A
15 Welder List + Certificates N/A
16 Certificate of QC Personnel N/A
17 Readiness NDT Company N/A
18 Forms Record/Report √ JS
19 Procedures √ JS

Prepared by Approved by Acknowledged by MCL

PT. JATRA SEJAHTERA SSHE/QUALITY/CONSTRUCTION SSHE/QUALITY/CONSTRUCTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

12. QUALITY PLAN

ITP QC CIVIL

MATERIAL
TOOL CONTROL SITE INSPECTION LABORATORY
CONTROL

1. AFI/Log sheet 1. AFI 1. AFI 1. AFI


2. Calibration report 2. Inspection check 2. Inspection check 2. Inspection check
3. Sampling

REPORTING

QC ADMIN

13. ITP (INSPECTION and TEST PLAN

ITP STILL IN PROCESS


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

18. FORM RECORD / REPORTS

19. PROCEDURES
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

GO-NO-GO VOIDED SLAB AND PCI GIRDER ERECTION


BY PT.JATRA SEJAHTERA

CONSTRUCTION
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

NO Classification SECT. REQUIRED DELIVERABLES REQUIRED AVAILABLE STATUS Remarks


3 CONSTRUCTION
20 Required IFC Drawing
1. Structural Plan View, Elevation
View & Section View √ JS
2. Structural Element Details √ JS
3. Architectural Layout & Schedule
(Door & Window, Finishing, etc) N/A
4. Equipment Layout (HVAC,
Mechanical, Piping, Telecom/IT,
Instrument) N/A
5. Electrical SLD, Panel &
Receptacle Layout N/A
6. Construction Sequence √ JS
21 CWP √ RH
Site Organization chart (with phone
22
numbers) √ JS
23 Level 4 Construction Schedule √ JS
Structural √ JS
Civil & Architectural N/A
MEP & Instrument N/A
Telecom & Security N/A
24 Welding map N/A
Workday start and end times; days per
25 week N/A
26 List which CEP’s are required
1. Civil and Structural Works √ RH
2. Architectural Works N/A
3. Mechanical &Instrument Works N/A
4. Electrical & Telecom Works N/A
5. Commisioning, Completion & As-
built works N/A
27 Authorized Worker List for each area (site) √ JS
28 Permit
PTW √ RH
Confined space N/A
Working on the roof permit (if any) N/A
29 JSA (Job Safety Analysis) √ JS
30 SOP (Standard Operating Procedure) √ JS
Dosier (All data completed collected for
31
mechanical completion) N/A
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

20. IFC DRAWING

A. PLAN VIEW OF VOIDED SLAB ERECTION 1ST STAGE


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

B. PLAN VIEW OF VOIDED SLAB ERECTION 2ND STAGE


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

C. PLAN VIEW OF VOIDED SLAB ERECTION 3rd STAGE


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

D. ELEVATION VIEW OF VOIDED SLAB ERECTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

E. RIGGING DETAIL VIEW OF VOIDED SLAB ERECTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

F. PLAN VIEW OF GIRDER ERECTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

G. ELEVATION DETAIL VIEW OF GIRDER ERECTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

H. RIGGING DETAIL VIEW OF GIRDER ERECTION


PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

21. CWP

IN PROGRESS

22. SITE ORGANIZATION CHART

Project Manager
Samsul
082141868000

Adm & Logistik Site Manager Engineering


Sunarto
081332052633

Man Power
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

23. CONSTRUCTION SCHEDULE

BULAN KE-01 BULAN KE-02


ITEM PEKERJAAN VOLUME SATUAN

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
A. ZONE 2
a. PREPARATORY WORK

1. Gantry Setting
2 UNIT
2. Trial

b. PCI GIRDER ERECTION= 3


X 12 SPAN

1. P20 - P21
3 bh
2. P21 - P22 bh
3
3. P22 - P23 bh
3
4. P23 - P24 bh
3
5. P24 - P25 bh
3
6. P25 - P26 bh
3
7. P29 - P30 bh
3
8. P30 - P31 bh
3
9. P31 - P32 bh
3
10. P32 - P33 bh
3
11. P33 - P34 bh
3
12. P34 - P35 bh
3

B. ZONE 1
a. VOIDED SLAB ERECTION =
12 X 11 SPAN

1. P1 -P2
12 bh
2. P2 -P3 bh
12
3. P3 -P4 bh
12
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

4. P4 -P5 bh
12
5. P5 -P6 bh
12
6. P6 -P7 bh
12
7. P7 -P8 bh
12
8. P8 -P9 bh
12
9. P9 -P10 bh
12
10. P10 -P11 bh
12
11. P11 -P12 bh
12

C. ZONE 3
a. PREPARATORY WORK

1. Launcher Setting
1 UNIT
2. Trial

b. PCI GIRDER ERECTION = 5


X 6 SPAN & 6 X 4 SPAN

1. P14 - P15
5 bh
2. P15 - P16
5 bh
3. P16 - P17
5 bh
4. P17- P18
5 bh
5. P18 - P19
5 bh
6. P12 - P13
6 bh
7. P13 - P14
6 bh
8. P27 - P36
6 bh
9. P28 - P37
6 bh
PT.HUTAMA KARYA (PERSERO)
CIVIL ENGINEERING & GENERAL CONTRACTORS

26. CONSTRUCTION EXECUTION PLAN

IN PROGRESS

27. AUTHORIZED WORKER LIST FOR EACH AREA

ID Badge for employee still on process

28. PERMIT

29. JOB SAFETY ANALYSIS

30. STANDARD OPERATION PROCEDURE