Contractors Name:

PT. SARANA ABADI RAYA


HSE DAILY REPORT
DAYS : TUESDAY Today Workers
104
DATE : 27 Des 2022 Total Man Hours
840
ACTIVITY INFORMATION
HSE PERFORMANCE WEATHERS PERMIT
NO. EXPLANATION NO YES REMARKS TIME CONDITION RELEASED
1 Safety Talk before Work √
Working height permit:
2 Personal Protective Equipment √
Normal day Scaffold anti termite
3 First Aid Kit √ Casting concrete
Scaffold renovation parking
4 Fatality Case √
Scaffold roof paint parking
5 Medical Treatment Case √ Scaffold roof paint admin
HSE ISSUE Scaffold install hollow
6 First Aid Case √
Scaffold install steel frame
7 Near miss Case √
Hot work permit:
8 Fire Case √ Steel cutting utility
√ Steel cutting Silos
9 Property Damage Case
Steel cutting IWL
10 Environmental Damage Case √ Fabrication hollow parking
Remind fellow workers about
√ General Permit:
Environmental Case safety equipment
Boring Casting – UB
Renovation Parking
Renovation Admin
11 Excavation soil walk way
Install fence panel R-pet
Pile cap Silos
Boring Casting ETP area

12 Hazard Findings NOTES AND RECOMMENDATION:
08.00-17.00 Reminding each other about wearing work safety equipment to all
13 Working Hours workers, be it close friends or other companies when working in the
Others same area..don't discriminate between each other because this is a
14 sense of concern for others

Fire Extinguisher Performance Equipment Performance


Item Pin Pressure Hose Cylinder Equipment Proper Not Proper Remarks
APAR SAR/01 √ √ √ √ Cutting Well √

APAR SAR/02 √ √ √ √ Grinder √

Cutting torch √

Welding machine √

Electric welding
machine 

HSE DOCUMENTATION

TOOL BOX MEETING INSTAL WALL ADMIN FIIL SOIL SILOS