Lifting plan

1. 1. Crane Lifting Plan LIFTING OPERATION METHOD STATEMENT/LIFT PLAN & RISK
ASSESSMENT DETAILS FOR THE PROVISION OF A LIFT OPERATION IN COMPLIANCE
WITH BS7121 – PARTS 1 & 3 AND LOLER REGULATIONS Please tick as appropriate: 
Completed by appointed person for crane hired by Weston Homes, or  Completed by
contractor who has hired a crane as part of their work Client Weston Homes Plc Project Site
Address Date of Operation Time on Site Client/Site Contact Contact Number Appointed
Person Contact Number Appointed Person’s Acceptance of Responsibilities: I confirm that
the lifts in the Method Statement have been planned and will be carried out in accordance
with current legislation and British Standard 7121 and that I accept responsibility for the
preparation of this Method Statement and Risk Assessment. I accept that it is my
responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately
briefed on the contents of this Method Statement. Signed Date CONTENTS Page Page
Introduction 28 Crane Set Up Procedure 37 General Conditions 29 Lift Procedure 37
Weather Conditions 29 Crane De-Rig Procedure 39 Ground Conditions 29 On Site Changes
39 Operation Outline 30 Risk Assessment 40 Site Details 31 Site Register & Toolbox Talk 43
Load & Radius Details 32 Drawings Attached Crane & Lift Information 34
2. 2. 1 INTRODUCTION 1.1 It is the aim of this Method Statement to define and describe the
equipment and safety procedures which are to be employed by the crane lifting company to
carry out the lifting operation. The operation will be carried out in accordance with the
following Legislation & Approved Codes of Practice. BS7121 Safe Use of Cranes (part 1)
2006 General & (part 3) 2000 Mobile Cranes Lifting Operations & Lifting Equipment
Regulations 1998 (LOLER) Health & Safety at Work Act 1974 - Provision and Use of Work
Equipment Regulations (PUWER) 1998 Manual Handling Operations Regulations 1992 -
Noise at Work Regulations 2006 Control of Substances Hazardous to Health Regulations
2002 (COSHH) Construction Design and Management Regulations 2007 - Working at Height
Regulations 2007 1.2 THE LIFT The lift will be carried out in line with the guidance contained
in BS7121. 1.3 SITE INSPECTION The Appointed Person shall carry out a detailed site
inspection to ascertain the full requirements of the Site Manager and determine the required
crane capacity and make an assessment as far as possible/practicable of any other site
issues such as access, ground conditions, overhead obstructions, local authority interaction
etc. 1.4 THE APPOINTED PERSON The Appointed Person who has prepared the Method
Statement carries full responsibility for the safe completion of all works carried out during the
operation. It is the responsibility of the Appointed Person to ensure that the Crane
Supervisor is adequately briefed on the contents of this Method Statement. 1.5 THE CRANE
SUPERVISOR Prior to the commencement of the works, the Crane Supervisor must ensure
that all site personnel are adequately briefed on the contents of this Method Statement. This
briefing shall take the form of a short ‘Toolbox Talk’. The Crane Supervisor must liaise with
the Appointed Person should site circumstances require material change to the methods to
be employed during the operation. 1.6 THE CRANE OPERATOR or OPERATORS All lifting
operators or any operators working on behalf of the lifting company shall be fully trained and
competent on the machines they operate and will have undergone full manufactures
induction and training. 1.7 PERSONNEL All lifting personnel or any personnel working on
behalf of the lifting company will be fully trained and hold the relevant certification for the role
they undertake on the day of operation. Any non lift company personnel or personnel
supplied by the client that will be involved in the lifting operation and taking on a specified
role will be required to produce the relevant certification to the Appointed Person or Crane
Supervisor prior to the commencement of the operation. Failure to produce the required
certification will result in the suspension and possible cancellation of the lifting operation. 1.8
PERSONAL PROTECTIVE EQUIPMENT All lifting personnel will be supplied with standard
PPE which consists of, Hard Hat, Safety Boots, Overalls, Gloves, Hi-Vis (and Safety Goggles
if required). The Site Manager must inform all Personnel of any specific requirements in
advance of the operation date. 1.9 CERTIFICATION Copies of statutory test certification and
inspection reports will be available for inspection prior to the lifting operation taking place.
3. 3. 2 GENERAL CONDITIONS 2.1 The Site Manager will provide details of all items to be
lifted, including weights, dimensions and any specific lifting tackle requirements. The Site
Manager is responsible for the structural integrity of all loads to be lifted including any
specified lifting points or slinging recommendations. 2.2 The Site Manager must ensure safe
access to and egress from site for all lifting personnel and vehicles, and also ensure that the
working area is clear of all obstructions to allow the safe assembly and working of the crane.
The Site Manager will be responsible for supplying suitable floodlighting where necessary or
when required. The Site Manager must carry out any enabling works required prior to crane
arrival. 2.3 The Site Manager must ensure that the area where the crane is to stand/operate
is firm and level and this it is capable of withstanding the expected loadings that will be
imposed upon it. 2.4 The Site Manager must ensure that any Traffic Management (not
supplied by the lift company) is in place prior to the positioning of the crane. 2.5 Any
personnel not directly concerned with the lift must be kept out of the crane assembly and
working area. The working area should be cordoned off with barrier tape, temporary fencing
or otherwise secured, to prevent non lift associated personnel or the general public from
entering the lifting area. 2.6 The Crane Supervisor shall make himself known to all relevant
personnel on site, and conduct a ‘Toolbox Talk’ prior to commencing operations. The Site
Manager should arrange for a site specific induction for the lifting personnel prior to the
commencement of work. The Site Managers Site Risk Assessment, which identified any site
hazards should be made available and brought to the attention of the lifting personnel. 2.7 All
cranes to be left unattended for a period, shall be left in safe condition (jib retracted or laid
down if possible), with not load on the crane hook. Cranes shall be shut down and isolated
as per manufacturer’s instructions, secured and locked. Under no circumstances shall the
crane be moved for lifting purposes if not under the instruction of the Crane Supervisor. 2.8
In the event that specified cranes or lifting tackle, cannot be supplied on the day of operation
due to operational issues, breakdown or any unforeseen circumstances. The lift company
has the discretion to supply cranes or equipment that is of a suitable alternative to that
detailed in this Method Statement, (at no extra cost to the client). In the event of this situation
arising, the Appointed Person and the Site Manager will be notified. The AP/Crane
Supervisor will ensure that any changes do not infringe on the factors or safety within this
method statement. 3 WEATHER CONDITIONS 3.1 In the event of extreme weather
conditions the lift company may need to suspend the lifting operation until such time as it is
safe to proceed. Although the safe workable wind speed varies from crane to crane, as a
guide, the maximum wind speed at which lifting operations can take place is 10 metres per
second, (22mph). In the event that man riding duties are required the maximum workable
wind speed reduces to 7 metres per second, (16mph). Please note that local conditions and
the safety of personnel may dictate the Crane Supervisor and Crane Operator have to
suspend lifting operations at a lower wind speed than specified in this Method Statement. In
addition, lifting operations must stop during storms or when there is a risk of lightning strikes.
4 GROUND CONDITIONS 4.1 The lift company will endeavour to advise the client regarding
ground conditions, after a visual inspection (or where necessary/provided, perusal of a client
ground survey report) and supply suitable plates, mats where required. The Client is required
to advise the lifting company of any known underground services, voids or vaults as state in
BS7121. Safe Use of Cranes.
4. 4. 5 OPERATION OUTLINE 5.1 LIFT CLASSIFICATION LIFT CLASSIFICATION Basic Lift
Standard Lift Complex Lift Full Contract Lift Supervisor Only Contract Lift Note: If a
“Supervisor Only Contract Lift” is the chosen option, it is imperative that any personnel
supplied by the client, be fully trained, competent and experienced in lifting operations and
hold current, valid and legislatively required certification, which must be available for our
Appointed Person or Crane Supervisor to inspect prior to commencement of the lifting
operation. Any personnel supplied by the Site Manager must work under the instruction of
the Appointed Person or Crane Supervisor. Failure to comply with the above will results in
the suspension of lifting until the aforementioned is adhered to. 5.2 PERSONNEL The
following numbers of personnel for this lift are needed: Crane Operator Crane Supervisor
Slinger/Signaller 5.3 COMMUNICATIONS Communications between the lifting crew and
Crane Operator/s shall be maintained by means of Two-Way Radios Supplied by the Crane
Company Two-Way Radios Supplied by Site Manager Hand Signals 5.4 WEATHER
CONDITIONS Maximum Workable Wind Speed for the Crane is: Weather forecast to be
obtained on morning of lift, confirming wind direction and strength. Wind speed forecast
15.6mph. Guide: 10 metres per second (22mph) for load lifting. 7 metres per second
(16mph) for man riding duties. 5.5 BRIEF SCOPE OF WORK/NOTABLE FEATURES OF
THIS LIFTING OPERATION
5. 5. 6 SITE DETAILS 6.1 ENABLING WORKS Any enabling works discussed and agreed to at
the site inspection, should be carried out prior to arrival of the crane. Are any enabling works
required 6.2 ACCESS & EGRESS The Site Manager shall ensure that the crane and all
associated vehicles have safe and unimpeded access and egress to and from site. Details of
site access & egress 6.3 GROUND CONDITIONS – including any underground services,
voids or vaults. Details of ground conditions 6.4 OVERHEAD CABLES, OBSTRUCTIONS
OR REGULATIONS & ANY SLEWING RESTRICTIONS Details of any overhead or slewing
restrictions
6. 6. 6.5 TRAFFIC AND PEDESTRIAN MANAGEMENT Traffic Management Required
Pedestrian Management Required Arranged by Details of any Restrictions & Local
Authorities Concerned 7 LOAD & RADIUS DETAILS 7.1 LOAD DETAILS (to be provided by
The Site Manager) In the event of there being multiple lifts of different weights and
dimensions, only the details of the maximum required lifts will be shown. Description
Dimensions Weight 7.2 LIFTING POINTS It is the Site Managers/Plant Managers
responsibility to ensure that any manufactured Lifting Points are certified & tested for lifting
purposes. This also applies to specified slinging methods where no lifting points are
provided. Does the load have Manufactured Lifting Points or Manufacturer guidance for the
method of lifting that has been approved for use by the Site Manager? If “No” to the above:
Has the Appointed Person assessed and agreed a method of slinging with the Site
Manager? Has the Centre of Gravity been taken into account for all proposed lifts? Have the
lifting points and/or the lifting method been approved for use by the Appointed Person?
7. 7. 7.3 LIFTING TACKLE Please Note: In the event that the specified lifting tackle cannot be
supplied on the day of operation due to operational changes, breakdown or any unforeseen
circumstances. The crane company can supply and use lifting tackle/equipment that is of a
suitable alternative to that detailed above. In the event of this situations arising, the
Appointed Person and Site Manager should be notified. The AP/Crane Supervisor will
ensure that any changes do not infringe on the factors of safety within this Method
Statement. All Lifting Tackle certification to be available on site. The Crane Supervisor shall
inspect all Lifting Tackle prior to each use. Any Lifting Tackle supplied by the Site Manager to
be fit for purpose, fully certified and in good condition. Any damaged tackle shall be marked
“Not For Use” and returned to the depot for disposal. Nylon Slings must be protected from
sharp edges using sling guards or suitable packaging. 7.4 CALCULATED MAXIMUM LIFT
WEIGHTS In the event of there being multiple lifts of different weights, only the details of the
maximum required lift/s will be shown. Weight of Load Weight of Hook Block Weight of Lifting
Tackle Weight of Fly/S-Lift on Boom 7.5 CALCULATED MAXIMUM RADIUS Maximum
Required Radius 7.6 MAXIMUM CALCULATED LIFTS Gross lift weight In the event that any
loads (lighter than the maximum load) are required to be lifted to a greater radius than the
maximum loads, see below: Maximum required radius Gross Lift Weight To be lifted to a
radius of Weight to be lifted at max radius
8. 8. 8 CRANE & LIFT INFORMATION 8.1 CRANE/S DETAIL CRANE Crane (make & model)
Registration and/or Plant No. 4 Yearly Test and Thorough Examination 12 Month Thorough
Examination (6 Months if Crane is used for Lifting People) Weekly Crane Inspection YES NO
Certificate Expiry Date YES NO 8.2 REQUIRED WEIGHT & RADIUS Gross Lift Weight
Required Radius SWL of Crane at Required Radius Safety Margin In the event that any
loads (lighter than the maximum load) are required to be lifted to a greater radius than the
maximum loads, see below: LOAD Maximum Required Radius Gross Weight at Max Radius
SWL of Crane Safety Margin 8.3 OUTRIGGER LOADINGS & MATS Outrigger Point Load
Mat Size Mat Area Provided Please Note that the Site Manager is responsible for ensuring
that the ground conditions are suitable to accept the above loadings and pressures.
9. 9. REGISTER OF LIFTING EQUIPMENT – TO BE COMPLETED BY CRANE SUPERVISOR
Project: Lifting equipment (e.g. chains or strops) Description ID No. / Reg. Supplier: Test
Cert. Expiry Date: 12 Monthly Thorough Examination Expiry Date: Used for lifting persons?
Y/N. (If so, 6 Monthly Thorough Exam’n?) Weekly Inspections carried out by:
10. 10. THIS PAGE IS INTENTIONALLY BLANK
11. 11. CRANE & LIFT INFORMATION (Continued) 9 CRANE SET UP PROCEDURE THE
CRANE TEAM Crane Supervisor: CITB CTA Card Expiry Date: Appointed Person:
Slinger/Signaller(s): CITB CTA Card Expiry Date: Crane Driver: 9.1 The crane, together with
the associated operating crew will arrive on site at the specified and agreed date and time.
9.2 Crane Supervisor will meet the Site Manager and carry out “Toolbox Talk” with all
personnel involved in the lifting operation. Once this has been completed, all involved in the
lifting operation must sign the register for this Method Statement. Any site inductions that are
required will also be carried out. 9.3 Any traffic management, ancillary pans, mats or
temporary roadways etc that are required to be positioned by hi-ab or other means, prior to
the crane or cranes manoeuvring into position, will be done under the instruction of the
Crane Supervisor. 9.4 The crane will then manoeuvre into position as shown on attached
drawing. All manoeuvring to be carried out under the guidance of a member of the lifting
crew. 9.5 The crane will then commence set-up procedure and rig to the configuration stated
in section 8.1. All personnel assisting with rigging will be under the guidance of the crane
operator, at all times. The set- up procedure will be carried out as per crane manufactures
manual. 9.6 Upon completion of the rigging procedure, the crane operator will carry out
procedural safety and computer checks, implementing any specific operational requirements,
i.e. slewing restrictions, short rig configurations or fly jib configurations. 9.7 The Crane
Supervisor will then carry out a radio communications check between the crane operator and
the lifting crew. 9.8 Hook block of crane will then be lowered and required lifting tackle placed
on the hook, Lift Supervisor will ensure that the correct lifting tackle has been selected. 9.9
The crane operator will then be instructed to hoist lifting tackle clear of any obstructions and
position the crane ready for the first required lift. Any delivery/removal vehicles will now be
positioned adjacent to the crane as per attached drawings, ready for work to commence. 10
LIFTING PROCEDURE 10.1 Slinger/Signallers will issue instructions via hand signals or
two-way radios to the crane operator to position the crane over first required lift,
Slinger/Signallers will plumb the boom head, directly over the load or set short to allow for jib
deflection where necessary.
12. 12. 10.2 The Slinger/Signallers will instruct crane operator, the lower the hooks with lifting
tackle to allow Slinger/Signaller to attach lifting tackle to load. LIFTING PROCEDURE
(Continued) 10.3 All slinging will be carried out by fully trained, certificated and experienced
slingers. Slinging methods adopted will be as specified by load manufacturers, using
specified lifting points or, in the event that no manufacturer instruction or lifting points are
provided, our Slingers will work to the Appointed Persons recommendations and to Health &
Safety executives guidelines for safe slinging for lifting loads, (see section 7.2 & 7.3). The
lifting tackle used, will be as stated in section 7.3 and will have current test certification
available. 10.4 Upon completion of the attachment of the lifting tackle to the load, the
Slinger/Signaller will instruct the operator by hand signals or radios, to hoist up to take the
slack out of the lifting tackle. Once the lifting tackle has started to take the weight and has
tightened the Slinger/Signaller will instruct operator or operators to stop hoisting. The
Slinger/Signaller will then carry out a check around the load to ensure that the lifting tackle is
sitting correctly, angled correctly and also check any lifting points for security and correct
operation. 10.5 Once lifting tackle check has been carried out the Slinger/Signaller will
instruct the crane operator or operators, to hoist the load to a height that allows the lifting
tackle to take the full weight of the load and again instruct the operator to stop hoisting when
the load is just airborne to allow a final check of the lifting tackle and lifting points and also
check the structural integrity of the load. 10.6 Once the Slinger/Signaller is confident that the
lifting tackle and the load are secure, any tag lines that may be required will be attached to
the load. Instructions will then be given to the crane operator or operators to hoist the load
clear of any obstructions, ensuring that any site specific risks are monitored throughout the
hoisting procedure. 10.7 Once the load is clear of all obstructions, the Slinger/signaller will
give instructions to the crane operator to manoeuvre the load as required for railing, or
manoeuvre to the required landing area for single crane lifts. 10.8 In the event that the
landing area is at a different level or should access not permit, the Slinger/Signaller will pass
control of the crane signalling to a second strategically placed Slinger/Signaller at the landing
area. 10.9 The landing area Slinger/Signaller will then commence giving instructions to the
crane operator or operators to manoeuvre and lower the load to the required landing point,
ensuring that any site specific risks are monitored throughout the landing procedure. 10.10
The Slinger/Signaller will guide the load to the correct orientation as the load becomes
contactable by hand or by attached tag lines. 10.11 The Slinger/Signaller will instruct the
crane operator to lower the load to just above the landing position and then instruct the
operator to stop lowering to allow the Site Manager to confirm position and orientation of
load prior to landing. 10.12 Once the position is confirmed by the Site Manager, the
Slinger/Signaller will instruct the operator to slowly lower load into position. Once landed, a
final position check will be made before the Slinger/Signaller instructs the operator to lower
off all load weight. 10.13 Slinger/Signaller will instruct the operator to lower off, to allow lifting
tackle to be released from the load. In the event that any load is too large or high for safe
access by ladder, powered access equipment or a lifted man basket will be used to remove
slings from loads. 10.14 Once lifting tackle is detached from the load, the Slinger/Signaller
will instruct the operator to slowly hoist the lifting tackle clear of the load and any site specific
risks ensuring that no snagging occurs.
13. 13. 10.15 Once the lifting tackle is clear of all obstructions the Slinger/signaller will instruct
the crane operator to manoeuvre the crane ready for any further lifts that may be required
and had over to another Slinger/Signaller were required. 10.16 All other required lifts will be
carried out as stated in sections 11.1 to 11.5. The Lift Supervisor will ensure that all lifting
and operational procedures are followed as per the Appointed Persons recommendations
and that any queries or deviation from this Method Statement are notified immediately to the
Site Manager and the Appointed Person. 11 DE-RIG PROCEDURE 11.1 Upon completion of
the lifting operation, the Crane Supervisor will instruct the crane operator to load any
ancillary equipment or heavy lifting tackle onto relevant transport ready for removal from site.
11.2 The Crane Supervisor will then instruct the crane operator to lower all lifting tackle to
the ground to allow removal from hook. 11.3 The crane operator will then instigate the
removal of any lifting tackle stored on the crane and then commence the de-rig procedure.
11.4 All personnel assisting with de-rigging will be under the guidance of the crane operator
at all times. The de-rig procedure will be carried out as per crane manufacturers manual.
11.5 Once the crane has been de-rigged and all safety checks for road travel have been
carried out the crane operator will manoeuvre the crane/s off site, under the guidance of a
member of the lifting crew. The crane will then proceed on its way. 11.6 The remaining
members of the lifting crew will ensure that any ancillary mats or equipment etc are removed
from site or placed in an appropriate position ready for collection prior to them leaving site.
11.7 Any traffic or pedestrian management arranged by the lift company will be
unimplemented and removed. 11.8 The Crane Supervisor will inform the Site Manager or site
representative of the completion of the operation and address any issues that may be raised
and inform of any equipment left on site for later collection. 12 ON SITE
CHANGES/ADDITIONAL LIFTS 12.1 Any changes to this Method Statement & Lifting Plan
must be notified to and approved by the Appointed Person. Any crane position changes or
amendments to drawings must also be notified and approved by the Appointed Person.
Amendment Details
14. 14. 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) Changed discussed with and approved by the Appointed
Person Crane Supervisor Date (Sign & Print) 13 RISK ASSESSMENT The aim of this risk
assessment is to highlight any possible hazards that are likely to occur during the lifting
operation. Upon its completion with either a “High, Medium, Low or N/A” in the Risk Rating
Box and either a “” or “N/A” in the Risk Managed box, the document coverts to a site
specific assessment. Identified Hazards Risk Risk rating Prevention Measures Risk
Managed Access to and Egress from Site Interaction with public highway and members of
the public. Interaction with other site operations and operatives. Interaction with delivery
vehicles. Risk to: Public/ Operators/ Site Operatives High Banksman with hi-vis to control
traffic and public while crane manoeuvring into site. Flashing amber lights and audible
alarms when reversing. Site management to be aware of intended route on site. All other site
operatives to be made aware of crane movement.  Low Medium Low N/A Ground
Conditions Crane travelling over unprepared or uneven ground possible damage to ground
surface and or crane and property. Ground collapse beneath outriggers causing possible
overturning. Risk to: Public/ Operators/ Site Operatives High Ground to be assessed at time
of site inspection. Ground improvement to be implemented where needed. Operator/Crane
Supervisor to inspect on day of operation. Outrigger pans to be used with additional heavy
duty mats where needed. Client to inform the crane company of any known risks  Low
Medium Low N/A Underground Services Damage to sub-surface service lines causing
possible flooding, explosion, High A full assessment and mapping of the 
15. 15. asphyxiation or electrocution. Risk to: Public/ Operators/ Site Operatives Medium
travelling and working area of the crane will be made at the site inspection. The Site
Manager to make the crane operator aware of any known risk. Permit to work in place where
applicable. Operator/ Crane Supervisor to check on day of operation for any new or unseen
risks. Low Low N/A Crane Positioning - Set up Procedure - De-rig Procedure Crane
positioned incorrectly for required lift. Possible damage to crane or property during set up or
de-rig procedure. Risk to: Public/ Operators/ Site Operatives High Crane working position
clearly identified in Method Statement drawings and made known to crane operators and
marked out where required. Crane manufacturer’s instructions for set up and de-rig
procedure followed. Only trained and competent personnel to operate and assist with
rigging. No one but lift associated personnel within crane set up area.  Low Medium Low
N/A Plant Operations Crane operation, causing damage to property or injury to personnel.
Mechanical breakdown or structural damage. Risk to: Public/ Operators/ Site Operatives
High Trained, certified and competent crane operators. Cranes fully maintained with full
service and testing history. Manufacturer’s instructions adhered to at all times.  Low
Medium Low N/A
16. 16. Identified Hazards Risk Risk rating Prevention Measures Risk Managed Manual Handling
- Sling of Loads - Signalling - Tailing Operations - Multiple Crane Operations Incorrect
slinging of loads. Unsuitable lifting equipment used. Failure of lifting equipment. Incorrect
signals give to crane operator causing damage to loads, property or injury to personnel.
Crane operator lifting unseen loads. Risk to: Public/ Operators/ Site Operatives High Trained,
certified and competent Slingers to sling all loads. Only specified lifting tackle and lifting
tackle with current and valid certification to be used. Visual inspection to be carried out on all
lifting tackle prior to use. Qualified Signallers to use recognised hand signals or radio
commands to communicate with crane operators. Radios used for unsighted lifts.  Low
Medium Low N/A Working at Height - Ladders - Scaffolding - Access Platforms - Man
Baskets Personnel falling from height during crane assembly and or lifting operations.
Personnel falling from delivery vehicles during slinging of loads. Operation of mechanical
platforms. Personnel working from man Baskets. Risk to: Public/ Operators/ Site Operatives
High Operators to work from footed ladders for crane assembly. Slingers to work from footed
ladders for slinging loads where reasonably practicable. Work platforms or lifted man basket
to be used where a height risk is deemed excessive. Access operators to be IPAF trained.
Site to ensure all working areas at height are safe with suitable guard rails. Harnesses to be
worn where required / practicable. All scaffolds to be certified for working use.  Low Medium
Low N/A Protection of Public & Site Operatives - Falling Objects Injury to public or site
personnel from falling objects or materials. Damage to vehicles or property during lifting
operations. Risk from suspended loads. Risk to: Public/ Operators/ Site Operatives High
Work area to be cordoned off as an exclusion zone. Sufficient barrier & signage to be in
place to warn non lift associated persons of overhead & ground level risks. All over-sail to be
addressed, monitored and evacuation implemented where practicable. Lift crew to be aware
of all lifting operations.  Low Medium Low N/A Traffic Pedestrian Management Damage to
property or plant. Risk of responsibility for collision or injury. Protection of personnel during
works. Risk to: Public/ Operators/ Site Operatives High Full assessment of required
restrictions on public highways, service roads or private roads to be made at site inspection.
Any Traffic Management contractors supplied by site or the crane company will be fully
certified and competent. Traffic Management supplied by the site should be set up prior to
arrival of crane.  Low Medium Low N/A Adverse Weather Conditions Crane operation, load
stability and control. Risk of injury to personnel and damage to property. Risk of lightning
strike. Bad visibility. Risk to: Public/ Operators/ Site High Weather reports obtained before
and during lifting operations. Crane operator to monitor wind speed equipment. Suspension
of lifting operation until risk subsides.  Low Medium Low
17. 17. Operatives N/A
18. 18. Identified Hazards Risk Risk rating Prevention Measures Risk Managed Overhead or
slewing Obstructions or Restrictions - Low Headroom Damage to crane or property if crane
boom or superstructure comes into contact with any restriction. Infringement of unauthorised
air space. Working in restricted work space. Risk to: Public/ Operators/ Site Operatives High
Full assessment of any risks made and addressed at site inspection. Safe system of work
adhered to where implemented. Work to zone alarms where implemented. Implement crane
swl computer working restrictions. All relevant authorities contacted and advised and any
restrictions adhered to.  Low Medium Low N/A ADDITIONAL SITE SPECIFIC RISKS
ADDITIONAL RISKS IDENTIFIED ON DAY OF OPERATIONS ADDITIONAL RISKS DUE
TO ON SITE CHANGES Identified Hazards Risk Risk Rating Prevention Measures Risk
Managed
19. 19. 14 SITE REGISTER/TOOLBOX TALK All operational staff involved in this lifting
operation must read this method Statement or have had the contents of it explained in detail
to them prior to commencing work. All persons involved in this lifting operation are to sign
below in acceptance that a detailed briefing of this operation has been given and
understood. All certification has been checked and verified prior to the lifting operation
commencing. Crane Supervisor’s Acceptance of Responsibilities: I confirm that I have been
fully briefed on the contents of this Method Statement and Risk Assessment and that I
accept the duty of ensuring that the lift/s will be carried out in accordance with the Methods
and Procedures set out in this Document. Signed Date Print Name Position Signature Date
Site Manager Acceptance of this Method Statement I confirm that I have read and
understood this Method Statement and Risk Assessment and that I accept the
responsibilities of the site management with respect to Safe Use of Cranes (part 1) 2006
General and (part 3) 2000 Mobile Cranes. Signed Date SUMMARY Crane Detail Site
ManagerCrane Site Project Detail Req Radius SWL SES Point Load Date Issue No