Measurement Sheet (MS.

) Status for IPC 22 7-Mar-21

Submitted (S) / Approved (A) (nos.) Target date to


Remained
Q'ty of MS. Approximate Previous 11-Jan-21 12-Jan-21 16-Jan-21 17-Jan-21 23-Jan-21 27-Jan-21 28-Jan-21 30-Jan-21 3-Feb-21 11-Feb-21 13-Feb-21 15-Feb-21 17-Feb-21 18-Feb-21 22-Feb-21 23-Feb-21 28-Feb-21 1-Mar-21 Total get back
Part Measurement Sheet (MS.) Status Position
(no.s) Amount (BDT)
Submitted Approved
S A S A S A S A S A S A S A S A S A S A S A S A S A S A S A S A S A S A S A (nos.)
(S) (A)

I. Total Approval

Substructure Work 143 118,094,384 SMCC-ITD JV 2 2 4 4 1 1 6 6 3 3 - 5 5 2 2 12 12 6 6 27 27 2 2 - 10 10 7 7 16 16 24 24 15 15 1 1 143 143 -

Segment Casting 114 67,884,091 SMCC-ITD JV - 2 2 - - - - - - - 1 1 50 50 8 8 7 7 13 13 7 7 19 19 4 4 3 3 - 114 114 -


Segment Erection 10 42,442,939 SMCC-ITD JV - - - - - - - - - - - 8 8 - 1 1 1 1 - - - - 10 10 -
Part (1) Approved
Parapet Wall SMCC-ITD JV - - - - - - - - - - - - - - - - - - - - - -

V.O. 10 35,711,123 SMCC-ITD JV - - - - - - - - - 1 1 - - - 4 4 - - - 4 4 1 1 10 10 -


Bill 1incl. Breakdown
11 32,995,831 SMCC-ITD JV - - - - - 1 1 - - - - 1 1 - - 1 1 4 4 1 1 2 2 - 1 1 11 11 -
Lump Sum
Total (I) 288 297,128,368 2 2 6 6 1 1 6 6 3 3 1 1 5 5 2 2 12 12 8 8 78 78 18 18 7 7 29 29 19 19 36 36 30 30 22 22 3 3 288 288 -

Total Submission for Approval


II. SUBMISSION, RE-SUBMISSION, CORRECTION
Substructure Work 11 39,746,054 NKDM - 3 - - - - - - - - 4 - - - 4 - - - 11 - 11
Segment Casting - - NKDM - - - - - - - - - - - - - - - - - - - - -
Waiting for Segment Erection - - NKDM - - - - - - - - - - - - - - - - - - - - - -
Part (2) NKDM QS.
Approval Parapet Wall 1 362,772 NKDM - - - - - - - - - - - - - - - 1 - - - 1 - 1
V.O. 9 8,752,448 NKDM - 1 - - - - - - - 1 2 - - 4 1 - - - 9 - 9
Bill 1 incl. Breakdown
- - NKDM - - - - - - - - - - - - - - - - - - - - - -
Lump Sum
Subtotal (2) 21 48,861,274 - - 4 - - - - - - - - - - - - - - - 1 - 6 - - - - - 4 - 5 - 1 - - - - - - - 21 - 21

Substructure Work 24 12,374,009 SMCC-ITD JV - - - - - - - - - - - - - - - - - - - 24 - 24

Segment Casting - - SMCC-ITD JV - - - - - - - - - - - - - - - - - - - - - -

PMS Correction Segment Erection - - SMCC-ITD JV - - - - - - - - - - - - - - - - - - - - - -


Part (3)
by SMCC-ITD JV Parapet Wall - - SMCC-ITD JV - - - - - - - - - - - - - - - - - - - - - -

V.O. 16 781,842 SMCC-ITD JV - - - - - - - - - - - - - - - 2 - - - 16 - 16


Bill 1 incl. Breakdown
- - SMCC-ITD JV - - - - - - - - - - - - - - - - - - - - - -
Lump Sum
Subtotal (3) 40 13,155,851 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 2 - - - - - - - 40 - 40

Total (II) 61 62,017,125 - 4 - - - - - - - 1 6 - - 4 5 3 - - - 61 - 61

Grand Total (I + II ) 349 359,145,493 2 2 10 6 1 1 6 6 3 3 1 1 5 5 2 2 12 12 9 8 84 78 18 18 7 7 33 29 24 19 39 36 30 30 22 22 3 3 349 288 61

S = Submitted (S) After retention + Advance (35%) 233,444,571 BDT (EXPECTED MAXIMUM BILL FOR IPC-22)
A= Approved (A) After retention + Advance (35%) 193,133,439 BDT (ACTUAL BILLED FOR IPC-22)