Work Process for Site Installation Verification

LZU 108 6732 R1 2 GSM RNS 2216/2116 Installation Verification 2006-05-16


Tools and equipment

LZU 108 6732 R1 3 GSM RNS 2216/2116 Installation Verification 2006-05-16


Inspecting the cable connections

Ensure that all cable connections at the front of the cabinet are correctly connected

Switching on the RBS

1. Switch on the RBS main power


2. Swicth on all applicable breakers on the IDM
3. Switch on the battery fuse switch (if the RBS is configured with a battery back up system)
4. Wait until all units are powered up

It can take up to 10 minutes before all units in the cabinet are in operation.

LZU 108 6732 R1 4 GSM RNS 2216/2116 Installation Verification 2006-05-16


Reading Fault Status

1. Read the IDB


2. On the Maintenance menu, click Monitor
3. In the Monitor window, expand the Managed Object (MO) fault maps, select RBS,
then select Run
4. Select RBS, press the right arrow, and click Start Monitor
5. Check the RBS Event Monitor window to see if any faults are indicated and correct them
before continuing

LZU 108 6732 R1 5 GSM RNS 2216/2116 Installation Verification 2006-05-16


Testing External Alarms
1. On the Maintenance menu, click Monitor to open the Monitor window.

LZU 108 6732 R1 6 GSM RNS 2216/2116 Installation Verification 2006-05-16


Testing External Alarms

2. In the Available monitors box, select External Alarm Status, and click → to add Alarm Inlets
In the Monitors to start box.
3. Click Start Monitor.
4. Remove the external alarm covers.
5. Ensure that the eexternal alarm cable on the RBS side of each Overvoltage Protection (OVP) module,
and the wires of the external alarm cable are properly connected.
6. Trigger the alarm by either closing or breaking it at the OVP module or by triggering the alarm detector
7. Check that the alarm is correctly recognized

8. Release the trigger on the alarm and check that the alarm disappears.

LZU 108 6732 R1 7 GSM RNS 2216/2116 Installation Verification 2006-05-16


Testing the Battery Backup

The test must be performed only if a BBS is connected to the RBS


• Switch off the incoming AC power to the RBS, using the main switch outside the cabinet

2. Turn on the incoming AC power to the RBS.

LZU 108 6732 R1 8 GSM RNS 2216/2116 Installation Verification 2006-05-16


Performing Concluding Routines
Saving the IDB
1. On the Configuration menu, click Save IDB.
2. Give the IDB file an RBS-specific name and save the file on the PC

LZU 108 6732 R1 9 GSM RNS 2216/2116 Installation Verification 2006-05-16


Performing Concluding Routines

Completing the Test Record

LZU 108 6732 R1 10 GSM RNS 2216/2116 Installation Verification 2006-05-16


Performing Concluding Routines

Filling in a Trouble Report


Write a trouble report when system components are not operating as expected, or when
Disturbances occur repeatedly.

Filling in a Blue Tag Repair Delivery Note

When a faulty unit is returned, it must always be accompanied by a repair delivery note. When the repair
Delivery note has been completed, it must be attached to the faulty unit before sending it to repair.

LZU 108 6732 R1 11 GSM RNS 2216/2116 Installation Verification 2006-05-16


Performing Concluding Routines

Filling in the Checklist

LZU 108 6732 R1 12 GSM RNS 2216/2116 Installation Verification 2006-05-16