Boiler plan schedule for precomm and commissioning acti

Nr Activity to be done start date end date total execute


1 mechanical completion

2 Pre-commissioning

Verify the field position of the valve without


3 Instrument Air. It must remain CLOSED
Connect IA but keep solenoid valve de-
4 energized. It must be CLOSED
Connect IA but keep solenoid valve de-
5 energized. It must be CLOSED

Verify valve close feedback from the


relevant limit switch is corresponding to
“close” in the
6 HMI (BMS/BPCS/SIS/ESD)

Energize the solenoid valve and verify that


7 the valve is smoothly OPENING

Verify valve open feedback from the


relevant limit switch is corresponding to
“open” in the
8 HMI (BMS/BPCS/SIS/ESD/….).

With solenoid valve energized remove IA


and check that on-off valve returns in closed
9 position.

Connect again IA and de-energize solenoid


valve: check that on-off valve returns in
closed
10 position
Boiler package internal and external
11 inspection

Steam drum internal and external


12 inspection
Water drum internal and external
13 inspection

Burner inspection / integrity/cleanessof


nozzle/fueland air lines tighted /Eletrical
conection/pneumatic conectionFlame
detectors/I/O instruments field -BPCSand
14 field -BMS

15 Economizer internal and external inspection


16 Air ductsinternal and external inspection

Flue gas ducts internal and external


17 inspection

18 Support and insulation visual inspection

19 Safety /Relief valves visual inspection


20 Piping inspection
Fuel gas piping /nitrogen purge and leak
21 test
22 Instrument air piping and leak check
23 Eletrical motors check
24 Bearing lubrication check
25 Fan blower check/ MRT 4 hours run
26 Dampers check

Fuel lines check /blowing and flushing of


lines /controll and shut off valves leakage
/instruments check/eletrical and pneumatic
27 conection
28 LT calibration
29 Control valves
30 Motor operating valves
31 Pneumatic on-off valves
32 Local Panels
33 BMS burner management system
34 Functional test
COMMISSIONING

Boiler firs firing /align flame scanner/flame


35 stability/start up and shut down sequenze
36 Boil out/cleaning internal of piping
37 Dry out
38 Passivation
39 superheater and stem line blowing
40 PSV hot testing
41 Tuning and line up
Cold and hot trip testing
42 Boiler preparation for cold test
MFT cold test/Test sequence of HH and LL
43 steam drum level
44 Boiler preparation for hot test
MFT hot test/sequence of HH and LL level in
45 steam drum level
comm and commissioning activities
doc required status doc doc done by remarks