Boiler plan schedule for precomm and commissioning acti
Nr Activity to be done start date end date total execute
1 mechanical completion
2 Pre-commissioning
Verify the field position of the valve without
3 Instrument Air. It must remain CLOSED Connect IA but keep solenoid valve de- 4 energized. It must be CLOSED Connect IA but keep solenoid valve de- 5 energized. It must be CLOSED
Verify valve close feedback from the
relevant limit switch is corresponding to “close” in the 6 HMI (BMS/BPCS/SIS/ESD)
Energize the solenoid valve and verify that
7 the valve is smoothly OPENING
Verify valve open feedback from the
relevant limit switch is corresponding to “open” in the 8 HMI (BMS/BPCS/SIS/ESD/….).
With solenoid valve energized remove IA
and check that on-off valve returns in closed 9 position.
Connect again IA and de-energize solenoid
valve: check that on-off valve returns in closed 10 position Boiler package internal and external 11 inspection
Steam drum internal and external
12 inspection Water drum internal and external 13 inspection
Burner inspection / integrity/cleanessof
nozzle/fueland air lines tighted /Eletrical conection/pneumatic conectionFlame detectors/I/O instruments field -BPCSand 14 field -BMS
15 Economizer internal and external inspection
16 Air ductsinternal and external inspection
Flue gas ducts internal and external
17 inspection
18 Support and insulation visual inspection
19 Safety /Relief valves visual inspection
20 Piping inspection Fuel gas piping /nitrogen purge and leak 21 test 22 Instrument air piping and leak check 23 Eletrical motors check 24 Bearing lubrication check 25 Fan blower check/ MRT 4 hours run 26 Dampers check
Fuel lines check /blowing and flushing of
lines /controll and shut off valves leakage /instruments check/eletrical and pneumatic 27 conection 28 LT calibration 29 Control valves 30 Motor operating valves 31 Pneumatic on-off valves 32 Local Panels 33 BMS burner management system 34 Functional test COMMISSIONING
Boiler firs firing /align flame scanner/flame
35 stability/start up and shut down sequenze 36 Boil out/cleaning internal of piping 37 Dry out 38 Passivation 39 superheater and stem line blowing 40 PSV hot testing 41 Tuning and line up Cold and hot trip testing 42 Boiler preparation for cold test MFT cold test/Test sequence of HH and LL 43 steam drum level 44 Boiler preparation for hot test MFT hot test/sequence of HH and LL level in 45 steam drum level comm and commissioning activities doc required status doc doc done by remarks