Professional Documents
Culture Documents
APPRECIATION DOCUMENT ON
CONSTRUCTION CONTRACT (R0) BETWEEN
NHAI
AND
SCHEDULES
A SITE OF THE PROJECT
B DEVELOPMENT OF THE PROJECT EXPRESSWAY
C PROJECT FACILITIES
D SPECIFICATION S AND STANDARDS
E MAINTENANCE REQUIREMENTS
F APPLICABLE PERMITS
G FORM OF GUARANTEES
H CONTRACT PRICE WEIGHTAGES
I DRAWINGS
J PROJECT COMPLETION SCHEDULE
K TESTS ON COMPLETION
L PROVISIONAL/ COMPLETION CERTIFICATE FORMAT
M PAYMENT REDUCTION FOR NON-COMPLIANCE
N SELECTION OF AUTHORITY'S ENGINEER
O FORMS OF PAYMENT STATEMENTS
P FORMS FOR INSURANCE
Brij Gopal Construction Company P.Ltd.
Contract Appreciation Document (CAD)
Date of Review: 27-Feb-19
S. No. Item Unit Description Remarks
A General
Project _
Authority _
Contractor _
Authority's Engineer _
Contract price _
Type of contract _
Construction period _
Maintenance period _
Date of Agreement _
Date of Appointment _
Performance security &
Additional Performance _
Security
Works matrix related to Article 3 (Obligations of the Contractor) of EPC Agrrements
Article/Sub Linked or
Responsibility on part
Sl. Clauses of Reference Contractor Action Immediataly after signing Department
Synopsis of Clause Time limit/ frame of Remarks
No. Agreement Article/Sub of Agreement/ during execution responsible
Authority Contractor
no. Clause, if any
Remedying the loss or damage to the
1 3.1.4 project highway during the construction √ AE
period .
17.3 Remedying the loss or damage to the
2 3.1.5 17.2 project highway during the defects √ AE
14.1.2 liability period .
Remedying the loss or damage to the
3 3.1.6 14.1.2 project highway during the √ AE
maintainence period .
Obtain and Submission of Applicable
4 3.1.7 (a) Sch. F √ AE
Permits as per Sch.F
Contractor, whether Consortium/Joint
Venture or sole, shall not sub-contract
any works in more than 49% of total
3.2.1 length. √ AE
Contractor may Sub-divide the
aforesaid length of 51% in no more than
5 sections.
The Contractor shall communicate to the
Sub contracting the works when the
Authority the name and particulars, relevant
5 3.2.2 aggregate of contracts with a sub √
experience of the sub contractor before
contractor exceeds 5%
entering into any such contract
Authority examine the particulars of the
within 15 days
sub contractor from the national
from the date of
6 3.2.2 security and public interest perspective √ The Contractor shall comply AE
receiving
and may ask the contractor not to enter
communication
into such sub contract
If in the preceeding 3 years the sub
contractor had not undertaken atleast
one work of similar nature with a Within 15 days
contract value exceeding 40% of the from the date of
value of the sub contract to be awarded receiving
7 3.2.3 √ The Contractor shall comply AE
and received payments in respect communication
thereof for the amount equal to atleast from the
40%. The Authority may require the Contractor
Contractor not to proceed with such sub
contract.
Contractor will try to atleast hire 10%
trained Workmen as per NSQF.
Expenditure are
Trainees are to be paid stipend on
3.4.1 to be born by the √
basis of minimum wages to
Authority
compensate for loss of income (Subject
to Max. limit of Rs.15,000)..
Works matrix related to Article 3 (Obligations of the Contractor) of EPC Agrrements
Article/Sub Linked or
Responsibility on part
Sl. Clauses of Reference Contractor Action Immediataly after signing Department
Synopsis of Clause Time limit/ frame of Remarks
No. Agreement Article/Sub of Agreement/ during execution responsible
Authority Contractor
no. Clause, if any
Provided that any directions issued by the
Authority's Engineer specify the resons for
Removal of Contractors Personnel on Within 10 days of removal of such person, the Contractor shall
8 3.4.3 3.4.2 receiving a direction from Authority's the directions √ comply and ensure that such persons are AE
Engineer issued evicted from the site and have no further
connections with the works or maintainence
under this agreement
9
Linked or
Article/Sub Responsibility on part
Sl. Reference Contractor Action Immediataly after signing
Clauses of Synopsis of Clause Time limit/ frame of Department responsible Remarks
No. Article/Sub of Agreement/ during execution
Agreement no.
Clause, if any Authority Contractor
Prepare in detail site inventory and comparative
Authority is responsible for Correctness statement with Sch. A and the provisions in
of Scope of Project, Project Facilities, Sch. B. Design Section and Project
1 4.1.2 - N/A √
Specifications and Standards and the Monitoring
criteria of testing of completed work Variations, if any to be intimated to Authority in
consultantion with CMC
Request to Authority, immediately after signing
Authority to Procure 90% land of total
of Agreement, to nominate representative of
length of Project within 30 days from the
Authority to have joint site visit and prepare
5.2 (h), 7.1.1, date of signing of Agreement as per
4.1.3 (a) 30 days from the Memo & Appendix. AE+CMC+Management
2 8.2, provision of cl:8.2, 8.3 √
ROW Agreement date
8.3 cl: 7.1.1 refers submission of
Decsion regarding Appointed Date shall be
Performance Security to be submitted
taken as per availability of Land as assesed in
by the Contractor
Memo & Appendix.
Authority to provide approved GAD of
ROB from Railways within 60 days from
the date of Appointed Date. Correspondance with Authority for availability of
4.1.3 (b) 60 days from the approved GAD from Railways of ROB. Ensure AE+CMC+Management
3 - √
GAD of ROB All expanses incurred by the Contractor Appointed date the Notification for same may be given to
to the railway authorities in this respect Authority immediately after 60 days.
shall be reimbursed to the Contractor by
the Authority
4.1.4 Compensation of delay on the part of
AE+CMC+Management
EOT & 4.1.3, Authority in form of (i) Extension of Immediately after delay in providing ROW as
As per Sched-B
Damages 8.3, Time (ii) Damages. In case of delay in √ per Schedule B of Annex-I, notification shall be
Annex-1 CMC to calculate damage in
Payable to 10.5 providing the ROW shall be as per given to Authority.
case of delay
Contractor cl:8.3
Compensation of delay on the part of
4.1.4
Authority in form of (i) Extension of
EOT & 4.1.3, Project Monitoring for follow-up.
Time (ii) Damages. In case of delay in Intimation to Authority for EoT and damages
4 Damages 8.3, N/A √ CMC to calculate damage and
approval of GAD, damage equal to 2 km upon receiving approval of approved GAD
Payable to 10.5 case prepartion of EoT.
shall be payble to the Contractor as per
Contractor
cl:8.3
The aggregate damages payable under
clauses 4.1.4, 8.3, 9.2 shall not exceed
1% of the contract price.
4.1.5 Both parties agree that payment of
Cap on 4.1.4 these damages shall be full and final
5 damages 8.3 settlement of all claims of the CMC+AE
payable to 9.2 Contractor and such compensation shall
Contractor be the sole remedy against delays of
the Authority and both parties further
agree this as final cure against delays
of the authority
Works matrix related to Article 4 (Obligations of the Authority) of EPC Agrrements
Linked or
Article/Sub Responsibility on part
Sl. Reference Contractor Action Immediataly after signing
Clauses of Synopsis of Clause Time limit/ frame of Department responsible Remarks
No. Article/Sub of Agreement/ during execution
Agreement no.
Clause, if any Authority Contractor
Immediately after receiving of LOA, Project Site
AE & CMC to follow-up, in
4.2 Maintenace obligation prior to Appointed to be inspected and maintenance requirement,
6 - 10 days √ maintenace requirement is
Maintenance Date if any to be intimated to the Authority in
apprihanded.
accordance with cl:4.2
otherwise the
Authority shall
encash and
Should pay damages for the extended period in
appropriate
a sum calculated at the rate of 0.01% of the
such
In case Contractor fails to provide the contract price per day until the performance
7.1.3 A maximum of performance
2 performance security within 10 days of √ security is provided. On expiry of the 30 days Finance+PMC
EOT 30 days security as
the agreement, it may seek for the EOT the agreement shall be deemed to be
damages. And
terminated and the Bid security shall be
this agreemtn
encashed by the Authority
shall be
deemed to be
terminated
Option provided that the Contractor
7.2
may submit the PBG intially for 2 Years
PBG and
3 only, however, which needs to be √ Finance+PMC
Extension of
extended appropriately, as per DLP,
PBG
before 2 month of expiry of said PBG.
The Contractor shall replenish in case of partial
appropriation to its original level of the otherwise the
Upon the encashment and performance security and in case of entire Authority shall
Appropriation of Performance security appropriation the Contractor should provide a encash and
7.3.2
as damages (Partial) for Contractor's fresh performance security. appropriate
4 Replenishing 23 Within 30 days √ Finance+PMC
default, the Contractor has to replenish Failing which Authority shall entitle to terminate such
the PBG
the performance security to its original the agreement as per article 23. However the performance
level from the date of appropriation Contractor shall be entitled to an additional security as
cure period of 30 days for furnishing the PBG damages.
under this clause.
The Contractor shall notify to the Authority
Additional Performance Security shalll
Under clause 10.5.2 for any event causes
be encashed, in case the Contractor not
7.3.3 √ delay in achivement of MileStone or for any AE
achieve the Milestone II/III/IV within the
default on the part of the Authority or any
prescribed period as per the agreement
reason not attributable to the Contractor.
Works matrix related to Article 7 (Performance Security) of EPC Agreements
Linked or
Article/Sub Responsibility on part
Sl. Reference Time limit/ Contractor Action Immediately after signing Department
Clauses of Synopsis of Clause of Remarks
No. Article/Sub frame of Agreement/ during execution responsible
Agreement no. Authority Contractor
Clause, if any
Within 60 days
of the later of
7.4.1 the expiry of
6 17.1.1 Release of Performance security √ CMC+Finance
Relese of PBG DLP or
Maintenance
Period
7.4.2 Within 28 days
on 28th day from the day of receving of the
Relese of Release of Additional Performance form the date
12 √ Completion Certificate The Contractor shall
additional security of Completion
submit a request to release of Additional PBG
PBG Certificate
Retention money shall be deducted at
7.5.1
the rate of 6% and the maximum
5 Retention 19.5
amount of retention money shall not
money
exceed 5% of the contract price
Refunding the retention money on
7.5.3
Sch. G Annex-II submission of BG as per format
Refund of The Contractor may furnish an irrevocable and
7 7.5.1 provided in Sch.G √ CMC+Finance
Retention unconditional bank guarantee.
19.5 The refund shall be made in tranches of
money
not less than 1% of the contract price
7.5.4
Discharging Discharging of Bank Guarantee and Within 15 days
7.5.2
Retention BG refunding of balance retention money after issue of
8 7.5.3 √ Finance+AE
& refund of by the Authority to the Contractor after Completion
12.4.1
retention issuance of "Completion Certificate" Certificate
money
In the event of termination of
agreement , the retention money and
7.5.5 bank guarantee shall be treated as if The Contractor should prepare and submit it's
9 Payment of 23.6 they are performance security and shall √ √ claims if the termination of the agreement is
retention BG be reckoned as such for the purposes due to the Authority's default
of termination payment under clause
23.6
Authority shall Provide the ROW as per As Specified in Sch. A, Annex-II To keep a regular check on the parts of site
8.2.2
Sch. A the signed memorandum by the date (or) within 90 days from the handed over and examine if the contractor is
4 Providing √ CMC
8.3 specified in the Sch.A for those part of appointed date (for the part of site eligible to claim damages as per the clause 8.3
ROW
the site referred therein not specified in Sch. A) for non performance of duties of Authority.
Contract price
8.3.3 Schedule -H, Within 240 days from the Notify the authority after 240 days regarding
Withdrawn of any work subject to 10% reduced to
Withdrawn of 8.3.4 Scheduled ROW as per Sch-A √ the non Availbaility of ROW if it falls under CMC +AE
of the Contract Price 90% of value of
works Annex-II municipal limitsor any reserved area.
works.
The site shall be made available by the
6 8.4 8.2 Authority to the Contractor free from all √
encumbrances and occupations
2 9.3.4 9.3 Works affected by a new utility. √ Contractor shall be entitled to EOT. CMC
The Authority shall assist the Contractor in
obtaining the applicable permits for Felling
of trees. Contractor should identify the part or parts of
9.4
The cost of such felling shall be borne by site that can cause adverse effect on the
Felling of
the authority and in the event of any delay construction of the project and shall
trees &
3 beyond the control of contractor , it shall √ √ communicate with the Authority. AE
procuring
be excused for failure to perform any After receiving forest clearance approach the
applicable
obligations. concerned forest office to initiate the felling of
permits
If the felling of trees is in forest area , the trees
applicable permit shall be procured by the
Authority
Works matrix related to Article 10 (Design & Construction of project highway ) of EPC Agreements
Linked or
Article/Sub Responsibility on part
Sl. Reference Contractor Action Immediately after signing Department
Clauses of Synopsis of Clause Time limit/ frame of Remarks
No. Article/Sub of Agreement responsible
Agreement no. Authority Contractor
Clause, if any
Within 20 days from the appointed
date: Arrangement and submission of the POA of the
a. Should appoint Representative, Contractor's representative to the Authority
10.1.1 b. Should appoint Design director Within 20 days Submit the details of Contarctor's Design
1 Contractor's c. Obtain aapplicable permits for from the √ director to the Authority AE
obligations commencement of works appointed date Initiate the process and obtain the necessary
d. Arrangements for the quarrying of permits and quarrying of materials required for
materials shall be made in accordance the execution of the project
with the applicable laws and permits.
Appointment of Authority's Engineer by
10.1.2 Within 30 days
the Authority
2 Authority's from the √
Should appoint an Engineer and shall
obligations agreement date
notify to the contractor.
A Programme shall be submitted for the
10.1.3 10.2 Within 30 days of Prepare the program and submit the same to
works, developed using networking
3 Submission of work Sh. J the appointed √ the Authority's Engineer after the appointed
techniques under clause 10.1.3 Part I,
program Sh. H date date
Part II & Part III
A panel of three names shall be proposed to
Authority's consent in appointing the Within 15 days of the Authority.
10.1.5
safety consultant to carry out safety receiving a Authority's failure in conveying its consent of
4 Appointment of √
audit during the design stage of the proposal from the appointment from the panel leaves the
safety consultant
project highway. contractor contractor to engage a safety consultant of his
choice.
The safety audit shall be carried out by
the safety consultant . The
recommendations of the safety
consultant shall be incorporated in the
10.1.6
design of the project highway.
Safety audit;
5 10.1.5 In the event that any works required by √ √
recommendations;
the safety consultant fall beyond the
Contractor's report
scope of Sch.B, Sch.C or sch.D, the
Contractor shall make a report and seek
the instructions of authority for change
in scope
A panel of three names shall be proposed to
Within 15 days of the Authority.
10.2.2
Authority's consent in appointing the receiving a Authority's failure in conveying its consent of
6 Appointment of √
proof consultant proposal from the appointment from the panel leaves the
Proof Consultant
contractor contractor to engage a proof consultant of his
choice.
The Contractor shall prepare and submit
10.2.4 (a) three copies each of design and Design and prepare the drawings and get it
7 Submission of drawings duly certified by the proof √ certified by the proof consultant to the
design and drawings consultant , to the Authority's Engineer Authority's Engineer
for review
Works matrix related to Article 10 (Design & Construction of project highway ) of EPC Agreements
Linked or
Article/Sub Responsibility on part
Sl. Reference Contractor Action Immediately after signing Department
Clauses of Synopsis of Clause Time limit/ frame of Remarks
No. Article/Sub of Agreement responsible
Agreement no. Authority Contractor
Clause, if any
Within 15 days of the receipt of the
drawings, The Authority's Engineer shall
review the same and convey its
observations to the Contractor
10.2.4 (c) Beyond the said period of 15 days, the Within 15 days of
Review & contractor shall not be obliged to await the receipt of the
8 √
Observations of the observations of the Authority and drawings from the
Authority may begin the works at its discretion Contractor
and risk.
In caseof a major bridge the foresaid
period of 15 days may be extended upto
30 days
If the observations of Authority's
Engineer indicate that drawings are not
in confirmity with the scope of the
10.2.4 (d)
project, such drawings shall be revised within 10 days Revise and submit the drawings as per the
AE's observations
and resubmitted to the Authority's from the date of Authority's Engineer observations and get it
9 on revised and 19.5.4 √
Engineer for review. receipt of revised certified by the proof consultant to the
resubmitted
The Authority's Engineer shall give its drawings Authority's Engineer
drawings
observations within 10 days from the
date of receipt of revised drawings
Maintenance manual
wihtin 60 days prior to Project
Completion Date, the Contractor shall
20 10.7 within 60 days √ AE
submit the Maintenance Manual with
other specifications and requirements
as per CA
15 days prior The contractor shall submit the methodology to The AE shall Review the
11.3 Submission of Methodology to be adopted to the be adopted for executing the works, giving methodology and convey
2 Submission of for executing the works to the Authority's commencem √ details of equipments to be deployed, traffic AE the comments to the
methodology Engineer ent of the management and measures for ensuring contractor within a period of
construction safety. 10 days
within10 days
11.7 The Contractor shall submit a Monthly
from the A monthly progress report on the progress of
3 Submission of progress report to the Authority's Engineer √ AE
closure of work shall be submitted to the Authority
MPR and Authority
month
The test checks by the Authority's In case fail or any defect,
11.10.1 Engineer shall comprise atleast 20% of the the contractor shall
The Contractor shall raise the inspection
4 Test checks by quantity or number of tests prescribed for √ AE resubmit the test after
request for test
AE each category or type of test for quality carrying out proper
control by the Contractor remedial measures
The Authority Engineer can issue on notice
11.14 to the Contractor for the slow progress. On Within 15
AE's notice to receipt of the notice The Contractor shall days from the The Contractor shall reply immediately on
5 √ AE+CMC
Contractor on inform the Authority's Engineer within receipt of receipt of the notice
slow progress 15days the reasonable details about the notice
action taken to expedite the progress
No later than
15 days after
11.16 The Contractor shall provide to the Authority
the closing of
Contractor's for every calender quarter, a video recording The Contractor shall prepare the video
6 each quarter √ AE
Video recording in a 3 hour compact disc covering the status recording and submit it to the Authority
after the
in CD & progress of works in that quarter
Appointed
date
If the suspension of the works under clause
11.7.4 The Contractor shall submit the claim for the
11.17.1 are not attributable to the contractor,
7 EOT due to √ EOT for the suspension of works under clause CMC
The Contractor is entitled for the EOT
suspension 11.17.1
determined by the AE
Punch list work The Contractor shall raise the request for PC
AE shall issue a PC on the request of
12.2.5 shall be completed
12.2.1 Contractor in the form set forth in Sch.L,
10.5 Within a period of The Contractor shall complete The punch list
2 Provisional if the tests for and in respect of the √ AE+CMC
Sch.L 30 days from the (List of outstanding items of works) items in
certificate completed work was successful
date of issuance of respect of those sections for which provisional
PC certificate is issued.
The PC appended thereto a punch list.
No PC shall be issued until the
12.2.5 Contractor has submitted valid claims
3 19.1.1 √ AE+CMC
for payment of atleast 80% of the
Contract price
12.3
Delay in completion of punch list items
Punch list 10.3.2
4 entitles the Authority to recover the √ AE+CMC
items - Sch.J
damages from the Contractor .
Damages
12.4.1 Issuance of Completion certificate on
5 Completion Sch.L completion of works including the √ AE+CMC
Certificate punch list and successful tests
The Contractor shall remove its equipment,
Within 30 days
materials, debris and temporary works from
12.4.2 from the date of
Upon receiving the completion site. If the Contractor fails to do so The
6 Contractor's receiving the √ AE
certificate authority may remove them and recover the
Obligation completion
amount equal to 120% of the actual cost of
certificate
removal incurred.
14.1.2
Obligations of the Contractor during
2 Contractor's √
maintenance period
obligations
14.1.3
Defects& The Contractor shall at its own cost, undertake
Action of the Contractor to the defects &
3 deficiencies - Sch.E √ repair or rectification in accordance with good AE
deficiencies not specified in the Sch.E
Contractor's industry practice
action
No later than 10
14.3.1 days prior to the
The Contractor shall prepare a monthly
Submission of Submission Maintenace program to the commencement of
4 √ √ maintenance program in consultation with the AE
maintenance Authority's Engineer the month in which
Authority's Engineer
program to AE the maintenance is
to be carried out
17.6
The DLP is deemed to be extended till
8 Extension of 17.2 √ AE+CMC
the identified defects have been
DLP
remedied.
Within 10
The Contractor shall furnish the Authority
days from
notarised true copies of the certificates of
5 20.3 Evidence of insurance cover the AE through HO
Insurance ,copies of insurance policies and
appointed
premia payment receipts…..
date