Rev-00
Issued for
Review &
Approval
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Table of Contents
1) PURPOSE...........................................................................................................................................3
2) SCOPE.................................................................................................................................................3
3) REFERENCES...................................................................................................................................3
4) RESPONSIBILITY............................................................................................................................3
5) Methodology........................................................................................................................................4
Construction material:..........................................................................................................................4
Procedure:.............................................................................................................................................4
Reinforcement Steel.............................................................................................................................5
Reinforced Cement Concrete...............................................................................................................5
Detailed Construction sequence...........................................................................................................6
Quality Assurance and Quality Control...............................................................................................8
6) Pile Testing..........................................................................................................................................9
7) HEALTH, SAFETY AND ENVIRONMENT..................................................................................9
Safety Procedure of Boring Rig & Lifting by Crane..........................................................................10
Safety Procedure of Night Work.....................................................................................................10
Risk Identifications...........................................................................................................................10
Risk Management.............................................................................................................................11
8) DOCUMENTATION & RECORDS..............................................................................................11
9) ITP’S / FORMATS...........................................................................................................................11
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
1) PURPOSE
This procedure is generated in part conformance of purpose to follow proper activities to carry out the
sequences involved in piling works for Residual Utilities and Offsite (RU&O) for Rajasthan Refinery
project of HRRL.
2) SCOPE
The scope covers the execution of load bearing reinforced concrete 500 mm dia bored cast in situ pile at
proposed location. Installation of Bored Cast in situ piling works involves various activities like boring,
liner installation, cage lowering, tremmie lowering, concrete etc. Including co-ordination of activities.
3) REFERENCES
Following documents in totality or in part shall form the reference documents:
EIL’s specification/Guidelines (i.e. 6-74-0006 Rev.03, 6-74-0011 Rev.03, 6-74-0013 Rev.03)
Contract (Bid), AFC Drwaings etc
Relevant/Applicable IS codes IS:2911 (relevant parts), IS 456:2000, ASTM D-5882, ASTM D-
4945, IS 383:2016, IS 1786:2008, IS 6186:2010, IS 9103:1999, IS 455:1989
4) RESPONSIBILITY
Following are the responsibilities and reporting structure of personnel involved in the
of the procedure:
Site QA / QC In charge-
Shall report to RCM at site
Shall be responsible for overall implementation & control of this Procedure.
Shall ensure proper implementation of this procedure.
Shall checks and verifies the activities.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
• To verify and ensure that the communication system is working properly and that
emergency equipment is in place.
5) Methodology
Construction material:
Concrete-As per approved design mix production of piles.
Steel-Reinforcement steel shall comply the requirement of IS 1786:2008. The stresses
Allowed in steel should confirm IS:456-2000
Water-Clean water conforming IS:456
Procedure:
The piles shall be installed as accurately as possible according to AFC drawing.
The pile is going to be founded on competent strata with cut-off level as mentioned in the
respective drawings
The location of the pile will be marked using Total Station with utmost care.
The hydraulic rig will be cantered over the designated pile location.
The pile hole will be bored continuously with regular draw out of drilled or cut soil.
The hydraulic rig/TMR will be placed at the pile location after that we will start the initial
boring as required depth. Then place the permanent liner in the bore hole and push with
hydraulic rig rotary till required level.
Permanent liner depth shall be insured during lowering the same and maintaining the
record before concreting started.
Temporary casing will be used from col to ground level.
All along this process do it as per site condition, the pile shaft will be kept dry bore or
filled with bentonite fluid for stabilizing the hole and the bore will be flushed to the bottom
before concreting by using bentonite slurry.
The density of the bentonite will be maintained as 1.03g/cc to 1.10g/cc during boring
operation and <1.25g/cc prior to concrete pour.
Pile shall be terminated in hard silty clay/clay silt/very dense sand/rock strata with
minimum pile length of 15m below COL.
Note
1) If rock layer (SPT-N value>100) is encounter in pile shall be terminated by embedding
2500mm inside rock.
2) Hard Silty Clay/Clay Slit/Very Dense sand (SPT-N value>50) will be confirmed as per
Engineer in Charge.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Reinforcement Steel
Check the reinforcement cage as per AFC drawing before lowering cage in the bore. 18
gauge SWG binding wire shall used for cage fabrication.
Stiffener ring and laps shall be welded as per standard working practices to keep the cage
intact as per requirements.
Check cover block to reinforcement, sufficient no. of blocks to be provided to ensure the
specified cover.
Reinforcement cage should not be dropped during lowering down.
Reinforcement cage to be kept hanged with in bore during concreting. During extraction of
casing the wire shall observed to avoid the lifting cage.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Set boring unit: Prior to boring, the following steps shall be carried out.
Offset surveyed pile position in two perpendicular direction by placing 2 offset markers at
appropriate distances from the pile position, to facilitate the installation of temporary steel
casing. The offset distance will be such that these markers shall not get disturbed during
installation process.
Adjust or extract the casing in case of deviation and reinstalling it unit the spirit level vertically
in two direction of the casing .
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
PILE POSITION
Verticality Check
The verticality of the pile bore will be ensured by checking inclination of installed casing. It
will be checked by using spirit-level as mentioned in above sections, simultaneously, plumb
bob setup will be placed in two perpendicular directions of casing circumferences and
alignment will be checked while driving the casing to control verticality of guide / permanent
casing, since it is proposed to use permanent liner, the Kelly of piling rig will not get deviated
from the vertically installed liner alignment which will ensure the verticality of pile beyond the
liner depth.
The tolerances shall be as per, IS 2911, Part 1 Section 2: 2010 or as specified in technical
specifications.
Measure the depth from the base of the borehole to the top of the casing.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Joint the sections of the tremie pipe prior to lowering it into the borehole.
Lower the tremie pipe into the borehole unit 200-300 mm above termination level to
facilitate flow of concrete.
Flushing:
Before concreting, flushing will be carried out based on the site conditions to ensure the
cleanliness of the pile bottom, Generally, flushing will be carried out if sand layers are
noticed in the pile bore.
Hoses will be laid for bentonite flow from mixer point to pile point and separate bund will
be prepared adjacent to pile with proper flow channel from it. The bund capacity will
accommodate to the bentonite discharge volume.
All circulation of bentonite fluid will be carried by flexible pipe to avoid disturbance of
working platform.
Tremie top will be fitting to flushing head in order to commence flushing by direct
circulation process.
The concrete cubes will be cast In frequencies based on the concrete quantity, as per the Field
Quality Plan.
The acceptability criteria of concrete cube in 28 days as per the given tender specifications.
6) Pile Testing
Pile load test such as (Vertical, Lateral, Pull out, Cyclic test) will be carried out in accordance with
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Contractor shall ensure that the machine operators involved must be an experienced /competent
person.
It is to be noted that the special care to be adopted against snake / insect bite.
During the movement of equipment, the operator must blow horn to caution the people around.
Safety is essential and imperative part of the construction process. All relevant personnel who are involved in
the piling activity will be issued with personnel protective equipment (PPE) such as safety boots, hard hats
and high visibility vests / clothing will be provided
Safety Supervisor will carry out and adhere to the following activities during execution:
Conduct toolbox meeting once or twice in a week prior to commencement of work.
Arrange safety induction for new workers who enters first time into the site.
Issue PPE for all workers and maintain record for the same.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Make sure that the working area is cordoned off with red-white safety tape when the boring rig /
service crane is in operation.
Ensure that no personnel other than the crane operator, safety supervisor and lifting supervisors are
allowed to engage in the lifting works.
Risk Identifications
Risk of accident during installation of the temporary steel casing using Rig
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Risk Management
Mark and display clearly the type of utilities.
Cover the borehole with steel mesh and cordon off the area around the opening.
Documentation shall be in the line with approved inspection / test plans. Quality document will be
maintained by systematic implementation of this procedure and generating necessary quality records.
Inspection reports in approved formats shall be raised upon carrying out the work.
9) ITP’S / FORMATS
ITP’s
3 IV
FORMAT FOR CONCRETE CUBE TEST
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT