Professional Documents
Culture Documents
Rev-00
Issued for
Review &
Approval
Table of Contents
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
1. PURPOSE:..........................................................................................................................................3
2. SCOPE:...............................................................................................................................................3
3. SPECIFICATIONS / REFERENCE DOCUMENTS:....................................................................3
4. RESPONSIBILITY............................................................................................................................3
5. METHODOLOGY.............................................................................................................................4
6. SAFETY PRECAUTION:.................................................................................................................8
7. DOCUMENTATION:........................................................................................................................8
1. PURPOSE:
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
The initial uplift load test is usually carried out to ensure the structural and
geotechnical soundness of the installed pile and to predict pullout capacity of the pile.
2. SCOPE:
The scope covers to execute 500 mm dia bored cast-in-situ pile at proposed
location. Installation of Bored Cast in-situ piling works involves various activities like
boring, liner installation, cage lowering, termite lowering, concrete etc. including co-
ordination of activities.
The intention of this document is to describe methodology for performing initial uplift
pile load tests on installed piles at the designated trial locations provided by ElL.
Pile Type Type I Type II
Dia. of Pile, mm 500 500
Design Load, MT 25 15
Test Load, TL, MT 75 45
(3xDL)
3. SPECIFICATIONS / REFERENCE DOCUMENTS:
4. RESPONSIBILITY
Following are the responsibilities and reporting structure of personnel involved in the
of the procedure:
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Site QA / QC In charge-
• Shall report to RCM at site
• Shall be responsible for overall implementation & control of this Procedure.
• Shall ensure proper implementation of this procedure.
• Shall checks and verifies the activities.
5. METHODOLOGY
a) Uplift Load Test Loading Arrangement
The proposed initial uplift pile load test will be carried out using reaction girder system.
The reaction may be provided by blocks supporting the reaction girder. A hydraulic jack
shall be used for load application.
b) Preparation for Uplift Pile Load Tests: -
Hydraulic jack system at the center of the reaction beam, vertically above the pile shall
be operated with pump. The reaction platform shall have same size and shape so that the
dial gauges are not damaged in the event of large uplift. Since the dial gauges shall be in
rewinding mode in such case, the gauges shall be set at a value close to the maximum.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Load will be applied by means of jacking the test pile against the reaction from two
supports on either side of pile.
Pile will be tested to an ultimate test load (3 times design load) each incremental load
shall be 20% of design load to be applied on pile. Each loading increment will be
maintained until the rate-of displacement is equal to less than either 0.1 mm per 30 min
or 0.2mm per hour or till 2 hours whichever is earlier. Table 2 summarizes the load
increments for uplift pile load test.
The loading and settlement/displacement monitoring records will be kept promptly
throughout the testing period and duly signed by the supervising authorities. A copy of
the same will be distributed to the supervising authorities, on request
For Type 1
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
For Type
D.Settlement Measurements
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT
Two calibrated dial gauges of least count 0.01mm will be mounted and recorded
independently for lateral pile load test. For plotting purposes, the average of the recorded
readings of the dial gauges will be taken. Readings will be recorded at 2 min, 4 min,
8min,15 min, 30 min ,60 min at every 2 hrs until application of next load increment as per
IS2911 Part 4 - 2013. Sample format of equipment details record & settlement recording
sheet are attached.
50% of the final load at which the total settlement equals to 10% of the pile's diameter
6. SAFETY PRECAUTION:
All Safety precautions and safety requirements to be followed as per the EHS guide lines.
7. DOCUMENTATION:
Quality documents shall be maintained as per approved ITP and recorded in approved inspection
formats as mentioned below.
Note: In case of any conflict between this procedure & EIL Specification the later will prevail.
PILING WORKS-II, A & B FOR RESIDUAL UTILITIES AND OFFSITE (RU&O) FACILITIES FOR HRRL PROJECT