Professional Documents
Culture Documents
A The construction of green buildings have no major significant cost difference to non-green buildings
B A shortage of PV panels led to a 2% rise in LEED buildings in the past 2 years
C LEED teams are achieving certification through widely diverse expensive methods
D Green design is a cost neutral add-on
Question 2
Parking footprints are large contributors to the heat island effect. What are local ordinances?
Question 2 Explanation:
This question just asks what local ordinances are. Projects should prepare and review a list of the
appropriate and applicable laws, codes, local ordinances, statutes, and industry-related standards
relevant to the project.
A Owner
B LEED Fellow
C Commissioning Authority
D Building Engineer
E Green Rater
Question 5
What aspect of the EPD credit is required to know if it leads to LEED points or not?
Question 5 Explanation:
For LEED a product must be a permanently installed building product, and is defined as 'an item that
arrives on the project site either as a finished element ready for installation or as a component to
another item assembled on-site.' - USGBC Example products include: steel, wood, drywall, carpet.
Things that are not considered products that count towards the MR credits include: • Scaffolding •
Concrete formwork • Anything temporary
A Risk of litigation
B Ability to control costs
C Cost of renewable technologies
D Cost of design changes
Question 7
A project is located in northern Ontario where no mass transit infrastructure exists. How can
this project still earn LEED points? (CHOOSE 2)
Question 7 Explanation:
Transportation demand strategies that can reduce single-occupancy vehicle use include: • Locating a
project near public transportation • Encouraging carpooling • Encouraging walking or bicycling •
Providing preferred parking for green vehicles • Discounted transportation passes for buses, rails,
ferry's, etc. • Telecommuting • Compressed workweeks
A Land Consumption
B Reduced need for irrigation
C Automobile dependence
D Oil Leaks
E Rainwater runoff
Question 10
Open space can contribute to many credits in multiple credit categories. Select the quality open
space:
Question 10 Explanation:
A walking trail around a natural wetland encourages social interaction and physical activity, so it
would count as open space. The other options are either off site or exclusive.
A To incorporate LEED Pilot Credits into the rating systems, where relevant
B Maintenance of the current version of the rating systems
C Development of Addenda to supplement the rating system(s)
D Reference to/inclusion of items addressed through previous Credit Interpretation Rulings (CIRs)
E Major updates to provide the next versions of the rating systems
F Clarification of LEED Interpretations
Question 14
The integrative process is an integral part of sustainable design and construction. When does
commissioning take place?
Question 14 Explanation:
Commissioning is the process of verifying and documenting that a building and all of its systems and
assemblies are planned, designed, installed, tested, operated, and maintained to meet the owner's
project requirements. The systems cannot be commissioned until they are installed. The process
takes place prior to occupancy (usually) when the building is substantially completed. For example,
all of the HVAC systems are in, the building has water and power, etc. Things that don't need to be in
place are painting, carpets, tile, etc.'
A Schematic Design
B Before occupancy
C Discovery Phase
D Substantial completion phase
Question 15
A facility manager is looking for information on how to improve IAQ throughout the life of the
building. Which of the following strategies will support this goal?
Question 15 Explanation:
This question is easy if you identify that all options but one must be completed prior to occupancy
and thus are not a part of Operation and Maintenance. Part of green cleaning involves including the
custodians in the integrative process to get their input and to work together to create goals and
procedures for reducing indoor contaminants from cleaning chemicals.
A Precipitation data
B Location of drip irrigation system
C Occupancy counts
D Evaporation Rates in the sky
E Size of high SRI roof
Question 24
The most significant difference between a conventional linear design process versus an
integrative process is:
Question 24 Explanation:
The integrative process is an iterative, collaborative approach that involves a project's stakeholders
in the process from visioning through completion of construction and throughout building operation.
Both involve all project team members. In integrative process, all team members will meet at least
once as a group. In conventional design, the landscape designer may never speak to the plumber.
A Green Vehicles
B Rainwater Management
C Heat island reduction
D Sensitive Land Protection
E Reduced Parking Footprint
Question 27
The Location and Transportation credit category awards points for selecting a site within
walkable proximity to a number of diverse uses which does not include:
Question 27 Explanation:
A diverse use is a distinct, officially recognized business, nonprofit, civic, religious, or governmental
organization, or dwelling units (residential use) or offices (commercial office use). It has a stationary
postal address and is publicly available. It does not include automated facilities such as ATMs,
vending machines, and touchscreens.
A A police station
B A grocery store
C An Automated Teller Machine
D A public park
E A barber shop
Question 28
A project has reduced its water consumption by 65% from EPA’s baseline. The owner can now
ensure a healthy work environment by monitoring 2 of the following: (CHOOSE 2)
Question 28 Explanation:
Ventilation takes fresh outdoor air and pushes it inside. The monitors on the outside measure how
much air the system is moving to make sure it is adequate. CO2 monitoring indicates the quality of
the air in a space. If there is too much CO2, the system can increase airflow to improve quality.
Question 29
What is true about credit forms submitted via LEED Online?
Question 29 Explanation:
Question demonstrates knowledge of how to use LEED online and its features
A The forms can be changed until they are submitted for review to the GBCI
B The project administrator must sign off on all credits prior to submittal
C Other projects and the public can view them for assistance
D Each form is reviewed within 2 weeks after document submittal
Question 30
In the site selection credit, which 2 governing bodies discourage developing on sensitive
habitats? (CHOOSE 2)
Question 30 Explanation:
Natural Resources Conservation Service (NRCS) is used for prime farmland. US Army Corps’ of
Engineers’ is used for wetlands. The International Society of Arboriculture is used for tree conditions
on site.
A Wall paint
B Acoustic insulation
C Granite counters
D Granite floors
E ETS signs on the exterior
F Desks
Question 35
Which of the following statements is true regarding occupant surveys?
Question 35 Explanation:
Consideration should be given to implementing an occupant comfort survey and complaint response
system to collect anonymous responses about thermal comfort, acoustics, indoor air quality, lighting
levels, building cleanliness and other occupant comfort issues. The survey must be collected from a
representative sample of building occupants making up at least 30% of the total occupants, and it
must include an assessment of overall satisfaction with building performance and identification of
any comfort-related problems. Document survey results and corrective actions to address comfort
issues identified through the surveys.
A Must be a permanent structure, use a reasonable site boundary, and have a minimum floor area
B Must have access to public transportation, manage rainwater, and have a floor to site area ratio of at least 1.5
C Must have a minimum building height, have a daylighting strategy, and provide for occupant comfort
D Have a minimum score of 50 points and achieve all prerequisites
E Must have a minimum outdoor air rate, a maximum daylight requirement and a minimum occupancy number
Question 38
A project development team just purchased an entire city on the coast of Oregon. Which of the
following is one way that the project developer could successfully complete adaptive reuse?
Question 38 Explanation:
Adaptive reuse is the practice of redesigning and using a structure for a use that is significantly
different from the building's original use. The office/apartment option is an example of design for
flexibility.
A Designing a building with a flexible floor plan that can accommodate offices or apartments
B Retrofitting a historic home to ENERGY STAR certification
C Plan a school so that classrooms can be divided into separate class spaces
D Renovating an old steel mill into an apartment complex
Question 39
Smart growth is a commonly used term to describe a best practice. Which of the following does
not comply with this best management practice?
Question 39 Explanation:
Smart growth is developing in areas near transportation, housing, and jobs in order to leave open
spaces and farmland free from development. A site far away from existing development is probably a
Greenfield.
A Mission Statement
B Shareholder Report
C Guiding Principles
D Charter of Values
E Vision
Question 42
As the global building codes continue to become more stringent, the LEED rating system must
continue to push the envelope and ensure it is improving over time. Who develops the ongoing
improvements?
Question 42 Explanation:
LEED is developed by USGBC member-based volunteer committees, subcommittees, and working
groups in conjunction with staff. LEED development follows a structure that includes a balanced
representation of stakeholders and management of conflict of interest, to ensure that the
development of LEED is transparent and consensus-based. The LEED committee structure balances
market needs and constraints with consistency and technical rigor in the development and
improvement of the credits within LEED, to ensure the quality and integrity of the LEED brand..
Under the direct management of the LEED Technical Committee, Technical Advisory Groups (TAGs)
recommend technical solutions to rating system development and maintenance issues.
A SCAQMD
B Uniform Plumbing Code (UPC)
C International Plumbing Code (IPC)
D EPAct 1992
Question 45
Which strategy can the project team suggest if the building owner wants to maintain ongoing
energy efficiency and performance?
Question 45 Explanation:
Building Automation Systems (BAS) are systems that use computer controls to monitor and control
building subsystems for maximum operating efficiency and reporting. There are additional options
that can identify problems that should be addressed by the facilities manager: • Building-Level
Energy Metering supports energy management and identifies opportunities for additional energy
savings by tracking building-level energy use. • System-Level Energy Metering supports energy
management and identifies opportunities for additional energy savings by tracking building-level
and system-level energy use.
A Handling of certain items such as electronic waste and mercury containing lamps
B Special equipment
C Separate dumpster for each material
D Access to waste haulers
Question 48
Northeastern University is attempting to create a LEED Platinum laboratory for its engineering
department. What must the integrative project team complete?
Question 48 Explanation:
Before any design takes place, every team member is gathered and every issue hashed out. Each
team member will take their expertise and bring the relevant information and data they have. The
team then analyzes the data and starts to compare notes in order to identify synergies between
different strategies and systems. This is a repeating cyclical process of research, analysis, and
meeting that continues to further refine solutions, with the goal of achieving the greatest cost
effectiveness and environmental performance.
A Selecting a renewable energy technology that reduces environmental impact but costs more than grid energy
B Salvaging more waste and recycling through a waste-to-energy on site plant
C Selecting materials with a higher initial cost but lower life cycle cost
D Replacing an asphalt parking lot with a cheaper cool coloured gravel
Question 51
LeadingGreen is taking an integrative approach to ENERGY STAR. An integrated project team is
reliant on:
Question 51 Explanation:
The success of any project depends on sticking to their goals from the beginning. Building codes
would be reviewed first in the process and the design would have to revolve around those mandatory
codes so this is not correct when talking about IP.
A Building codes
B Commitment to the sustainability goals
C Meeting the project schedule
D The choice of materials used
Question 52
Which of the following sustainable strategies would not assist with the outdoor water use
reduction strategy?
Question 52 Explanation:
Closets or toilets help reduce indoor, not outdoor water use
A 50%
B 25%
C 2%
D 45%
E 10%
Question 54
Production of CFCs are banned under the Montreal protocol and HCFCs will be phased out by
when?
Question 54 Explanation:
Hydrochlorofluorocarbons (HCFCs) are a class of ozone-depleting chemicals used now primarily as
refrigerants and foam blowing agents to replace CFCs. Although their ozone-depleting potential is
less than that of CFCs, their global warming potential is quite high. Developed countries are already
reducing their consumption of HCFCs to meet their phaseout obligations under the Montreal Protocol
which call for a 90% reduction from baseline by 2015 and a 100% reduction by 2030.
A 2015
B 1992
C 1995
D 2020
E 2030
Question 55
Which LEED Rating system has performance periods?
Question 55 Explanation:
Performance periods are encouraging all buildings to measure and improve performance, focusing on
outcomes from ongoing sustainability efforts. Additionally, to leverage a global consistent method of
performance verification through a streamlined and data-based pathway to LEED certification.
A ASHRAE 55
B ASHRAE 62.1
C ASHRAE 90.1
D ASHRAE 189.1
Question 60
The USGBC requires reporting different building parameters at least every 5 years to increase
transparency as well as:
Question 60 Explanation:
USGBC collects water and energy usage from LEED projects. This information helps the development
of future LEED rating system versions
A Ending the green building process when the project team hands the site over to the owner
B Working isolated to complete each stakeholders task efficiently
C Focussing on the initial cost of bamboo flooring
D The mechanical designer completing their design and handing it off to the electrical designer
E Establishing water saving metrics for measuring success
Question 62
A municipality has been losing a lot of tourism due to its coal power plant and the detrimental
environmental attributes associated with it. How can the city financially incentivize a developer
to develop green buildings? (CHOOSE 3)
Question 62 Explanation:
For more information about different incentives please read here: http://leadinggreen.ca/wp-
content/uploads/2014/08/Green-Building-Incentive-Strategies.pdf Structural incentives include: •
Expedited review / permitting process • Density and height bonuses Financial incentives include: •
Tax credits • Fee reductions / waivers • Grants • Revolving loan funds (low-interest loans) Non-
financial incentives include: • Technical assistance • Marketing assistance
A Tax credits
B Increases in the allowable density
C Allowing a building to be have an increased height
D Revolving loan funds
E Percentage increase in the floor area ratio
F Fee waivers
Question 63
Conventionally, which of the following has been primarily used to replace CFC-11?
Question 63 Explanation:
Although not the best option especially for LEED, HCFC were the first refrigerant to replace CFCs
A CFC-12
B CFC-114
C HCFC-123
D HFC-23
Question 64
LeadingGreen wants to establish green building goals and objectives across the entire design
while utilizing stakeholders’ expertise. What workshop helps achieve this?
Question 64 Explanation:
A charrette is an intense collaborative session where participants make a concerted effort to solve a
problem or plan the design of something. The charrette is one of the first things that should occur on
a new project. During the initial charrette the project team will: •Decide what rating system to use
•Determine the projects green building goals •Set a preliminary rating using the LEED Project
Checklist A charrette should be held no later than the design development phase and preferably
during schematic design.
Question 67
Evaluation of the economic performance of a product over its useful life is determined using
which procedure?
Question 67 Explanation:
The key term here is economic performance over life.
A By increasing grid reliability through demand response programs and thus lowering operational fees
B By permitting additional renewable energy access
C By increasing the availability of conventional grid source energy
D By reducing infrastructure costs
Question 69
The existing TD office towers in downtown Toronto which were constructed with single-pane
windows is retrofitting to include double pane glass which can lead to:
Question 69 Explanation:
The design of the building envelope (including the glazing) impacts the energy demand of the
building. While more glazing (windows) increases daylighting, the heat gain from allowing more light
in may increase HVAC loads. Double-pane glazing is a better insulator than single-pane glazing.
Energy efficiency is using less energy to accomplish the same amount of work which is not the case
here.
A Sustainable product
B Cradle to cradle
C Passive
D Cradle to Gate
E Rapidly renewable
Question 75
According to LEED, who defines the site’s open space requirements?
Question 75 Explanation:
The intent of Open Spaces is to provide the building occupants opportunities to connect with the
outdoors, where they exhibit improved well-being and productivity. Open spaces also provide many
positive environmental benefits—habitat creation, linked habitat corridors in urban areas, increased
rainwater infiltration, and reduced heat island effect. In LEED v4, the credit is no longer tied to the
presence of a local zoning code—the same open space requirement applies to all projects, which is
why open spaces are linked to the Integrative Process. However, this does not relieve the project from
complying with local zoning ordinances if the ordinance is more stringent.
A A consultant hired by the owner to negotiate permitting with the local authorities having jurisdiction
B The local building department
C The project’s civil engineer
D The local zoning authority
Question 76
A manufacturing company has the idea of recycling used orange juice cartons for flooring which
would result in: (CHOOSE 2)
Question 76 Explanation:
Carpets made from virgin materials or recycled content have similar costs and durability
performance. Using materials that contain recycled content reduces virgin materials use. Post-
consumer recycled content is defined by ISO 14021 - 'the percentage of material in a product that
was consumer waste'. The recycled material was generated by household, commercial, industrial, or
institutional end-users and can no longer be used for its intended purpose. It includes returns of
materials from the distribution chain. Examples include construction and demolition debris, materials
collected through recycling programs, discarded products (e.g., furniture, cabinetry, decking), and
landscaping waste (e.g., leaves, grass clippings, tree trimmings).
A 16%
B 20%
C 24%
D 8%
Question 83
Which of the following LEED Impact Categories aims at supporting local economies and
strengthening the green building industry through supply chain support?
Question 83 Explanation:
The Build a Greener Economy impact category components are: • Enhance the Value Proposition of
Green Building. • Strengthen the Green Building Industry and Supply Chain. • Promote Innovation
and Integration of Green Building Products and Services. • Incentivize Long Term Growth and
Investment Opportunities. • Support Local Economies.
A GreenScreen
B Global Reporting Initiative
C Green Seal – GS-32
D Cradle-to-Cradle Certified
E Health Product Declaration
F SMACNA
Question 87
A LEED consultant is reviewing project site plans and documentation prior to submitting the
project for review. What has the lowest priority in building design?
Question 87 Explanation:
Don’t forget that projects must always meet local, regional and fire codes first as they are law and
LEED is voluntary.
A 2.2 gpm
B 0.5 gpm
C 1.0 gpf
D 1.6 gpf
E 1.0 gpm
Question 89
How can a civil engineering team properly grade the site and determine the baseline
measurement for outdoor water use on a project?
Question 89 Explanation:
A water budget is a site-specific method of calculating an allowable amount of water to be used by
the landscape and then designing the landscape to meet this budget. The budget takes into account
plant type, plant water needs, irrigation system design, and applied water that the landscape receives
either by irrigation or by precipitation.
A EPAct 1992
B An analysis of neighbouring properties
C International plumbing codes
D EPA WaterSense Water Budget Tool
E ENERGY STAR Portfolio Manager
Question 90
MR has introduced numerous standards in version 4 and streamlined some credits. Which credit
would Environmental Product Declarations lead to?
Question 90 Explanation:
MRc2 – BPDO - Environmental Product Declarations rewards project teams for selecting products
from manufacturers who have verified improved environmental life-cycle impacts.
The integrative process can avoid delays a& costs resulting from design changes during the
A Construction Documents phase
A HCFCs (HydroChloroFluoroCarbons)
B CFCs (ChloroFluoroCarbons)
C CFC-500 (ChloroFluoroCarbons)
D HFCs (HydroFluoroCarbons)
Question 94
How is a project’s certification fees not affected?
Question 94 Explanation:
Prerequisites and MPRs must be met regardless so they are not the answer
A Unregulated load
B Plug load
C Process energy
D Process load
Question 97
A manufacturing company is trying to determine if its roofing shingles comply with LEED
requirements. Which factors help in this situation? (CHOOSE 2)
Question 97 Explanation:
Strategies for efficient roof are determined by SRI which evaluates the emissivity and reflectance of a
material
A Thickness of Material
B Gradient
C Vibration
D Emissivity
E Reflectivity
F Flame Retarder
Question 98
A project is located in northern Ontario and wants to take advantage of the areas environmental
assets. Which credit category would address this unique location's needs?
Question 98 Explanation:
Regional priority credits are bonus points projects can earn by addressing environmental concerns
(water shortages) and environmental assets (abundant sunlight) in their areas
A Prerequisites
B Regional Priority credits
C MPRs
D Local zoning
E Location and Transportation credits
Question 99
The integrative process is a crucial part of every credit category and results in money saved and
environmental protection. How can the architect work with the contractors to ensure that the
contractors purchase the correct materials?
Question 99 Explanation:
Specifications are created by architects and given to the contractor for the purposes of purchasing
the right quantity and type of materials. Specifications include drawings of what is to be built. They
are legally binding documents.
A Soil erosion
B Reduction of scope 2 emissions
C Reduction of scope 1 emissions
D Potable water consumption
E Waterway sedimentation
F Airborne dust
G Ozone Protection
Question 101
The overarching goal of the Materials and Resources credit category is to:
Question 101 Explanation:
Minimizing the embodied impacts associated with the entire life-cycle of building materials