Question 2
API 510 Inspection Code is only applicable to pressure vessels used by the petroleum and chemical
process industries that:
Question 3
Which of the following is an example of a pressure vessel covered by API 510? (AII of the vessels are
in-service).
Question 4
If there is a conflict between the ASME Code and API 510 for vessels that have been placed in
service, the requirements of:
Question 5
One type of Authorized Inspection Agency is:
Question 6
The term "minimum allowable shell thickness" is the thickness:
Question 7
Lowering of the maximum allowable working pressure or temperature rating of a vessel or both below
the design conditions is:
Question 8
An owner-user is responsible for developing, documenting, implementing, executing, and assessing
pressure vessel inspection systems and inspection procedures that will meet the requirements of API
510. These systems and procedures will be:
Question 9
Safety precautions are important in pressure vessel inspection because of the limited access to and
the confined spaces of pressure vessels. Out of the organizations listed, which is the primary one that
should be reviewed and followed?
o ASME
o OSHA
o NFPA
o NBIC
Question 10
______________________ may occur if equipment is subjected to temperatures above those for
which it is designed.
o Creep
o Brittle fracture
o Stress Corrosion
o Erosion
Question 11
lf a probable corrosion rate cannot be determined from reviewing data from the same or similar
service vessels or estimated form published data, on-stream determinations shall be made after
approximately _____________ hours of service by using NDE methods and a corrosion rate is
established.
o 500
o 1000
o 5000
o 10000
Question 12
The maximum allowable working pressure for the continued use of a pressure vessel shall be based
on computations determined by using the:
o Latest edition of the National Boiler Inspection Code or the construction code lo which the
vessel was built.
o Latest edition of the ASME Code or the construction code to which the vessel was built.
o Latest edition of the API/ASME Code or the construction code to which the vessel was built.
o Latest edition of the Underwriters Laboratories Code or the construction code lo which the
vessel was built.
Question 13
Out of the many methods of inspection ____________________ is considered the most important
and the most universally accepted method of inspection.
o Radiographic examination
o Careful visual inspection
o Ultrasonic thickness measurement
o Hammer testing
Question 14
If external or internal coverings, such as insulation, refractory protective linings, and corrosion
resistant linings are in good condition and there is no reason to suspect that an unsafe condition is
behind them,:
Question 15
What API standard provides more information on the inspection of piping, valves and fittings
associated with pressure vessels?
Question 16
For a corroded area of considerable size in which the circumferential stresses govern, the least
thickness along the most critical element of the area may be averaged over a length not exceeding
the following: 16a. For vessels with inside diameters less than or equal to 60 inches— 16b. For
vessels with inside diameters greater than 60 inches--
o 1 inch on either side of the weld or twice the minimum thickness on either side of the weld,
whichever is greater
o 2 inches on either side of the weld or 2 times the minimum thickness on either side of the
weld, whichever is greater
o 4 inches on either side of the weld or 4 times the minimum thickness on either side of the
weld, whichever is greater
o 6 inches on either side of the weld or 6 times the minimum thickness on either side of the
weld, whichever is greater
Question 18
Under what conditions is an internal field inspection of a newly installed pressure vessel waived?
o The contractor installing the vessel assures the owner-user that the vessel is satisfactory for
its intended service.
o A manufacturer’s data report assuring the vessel is satisfactory for its intended service is
available.
o The owner-user assures the inspector that the vessel is satisfactory for its intended service.
o The manufacturer orally assures the owner-user that the vessel is satisfactory for its intended
service
Question 19
An above ground pressure vessel shall be given a visual external inspection, preferably while in
operation, at least every _________ years or at the same interval as the internal, whichever is less
o 2
o 3
o 5
o 10
Question 20
The period between internal or on-stream inspections for a remaining life of four years or greater shall
not exceed one-half the estimated remaining life of the vessel based on corrosion rate or __________
years whichever is less.
o 10
o 15
o 5
o 12
Question 21
In cases where the remaining safe operating life is estimated to be less than 4 years, the inspection
interval may be the full remaining safe operating life up to a maximum of ____ years.
o 1
o 2
o 3
o 4
Question 22
If both the ownership and the location of a vessel are changed, what must happen before it is reused?
o It must be internally and externally inspected
o AII lhe records must be reviewed.
o It must be thoroughly ultrasonically checked.
o It must have all the paper work transferred to the new owner.
Question 23
A pressure vessel has been in service for 12 years and has shown a history of corrosion over its
service life. The original thickness was 1.9375" thick and the present thickness is 1.405". What is the
corrosion rate for this vessel?
o 0.266250 inches/year
o 0.532500 inches/ year
o 0.088750 inches/year
o 0.044375 inches/year
Question 24
When must a pressure test be performed on a pressure vessel?
Question 25
Who is authorized to test and repair a pressure relief valve?
Question 26
What is the maximum inspection or testing interval of a pressure-relieving device?
o 15 years.
o 12 years.
o 10 years.
o 20 years.
Question 27
What determines the inspection interval of pressure-relieving devices?
Question 28
The following is not normally found in pressure vessel records.
Question 29
When repairs or alterations are to be performed on a pressure vessel, all materials, and all welding
procedures that are to be used must be approved by:
o the insurance carrier for the company that the pressure vessel belongs to and the owner-user
of the pressure vessel.
o the owner-user and the contractor performing the repairs or alterations lo the pressure vessel.
o the API authorized pressure vessel inspector and, if necessary, by an engineer experienced
in pressure vessel design, fabrication, or inspection.
o the original vessel fabricator and the insurance carrier for the company that owns the
pressure vessel.
Question 30
What type of repairs can an authorized inspector give prior general authorization for?
Question 31
When does an inspector normally approve all specified repair and alteration work?
o Work is approved after the work contractor certifies the work to be satisfactory and the
contractor has pressure tested the vessel.
o Work is approved by a process/chemical engineer for the owner-user and the contractor has
pressure tested the vessel.
o Work is approved after an inspection by the authorized inspector has proven the work lo be
satisfactory and any required pressure test has been witnessed by the him.
o Work is approved after an inspection and test by the contractor and the unit operators accept
the vessel.
Question 32
Who should be consulted before repairing a crack at a discontinuity, where stress concentrations may
be serious?
Question 33
All repair and alteration welding shall be in accordance with the applicable requirements of the:
o NBIC Code
o AWS D1.1 Welding Code
o ASME Code Section VIII.
o NFPA Welding Code
Question 34
The repair organization shall use qualified welders and welding procedures qualified in accordance
with the applicable requirements of:
o Section V of the ASME Code
o Section IX of the ASME Code
o AWS 01.1 Welding Code
o API Standard 1104, Welding.
Question 35
The repair organization shall maintain records of its qualified welding procedures and its welding
performance qualifications. These records shall be available to the prior to the start of welding.
o operator
o owner·-user·
o welder
o inspector
Question 36
For alterations or repairs of vessels initially post weld heat treated as a code requirement and
constructed of P-1 and P-3 steels listed in the ASME Code, preheating to not less than ______
degrees F may be considered as an alternative to PWHT when impact testing is not required.
o 200
o 300
o 400
o 500
Question 37
A carbon steel (A-285 GR C) vessel must be repaired by welding in a flush patch (replacing a
corroded area). Impact testing is not required the vessel is in caustic service and was originally post
weld heat treated. Which of the following is correct?
Question 38
If local post welds heat treatment is approved for a vessel repair (a completed 360 degree band
around the vessel is not used - only a localized spot), what are the minimum number of
thermocouples required around the localized area to monitor the temperature?
o 1
o 2
o 4
o 6
Question 39
When repairing vessels with stainless steel weld overlay and cladding (vessels constructed of P-3, P-
4, or P-5 base materials) the base metal in the area of repair should be examined for cracking by UT
per ASME Section V. This UT inspection should be made ___________ hours after repairs have been
completed for equipment in hydrogen service, especially for chromium-molybdenum alloys that could
be affected by delayed cracking.
o 12
o 24
o 36
o 42
Question 40
When are fillet welded patches (lap patches) allowed.
o They may be only used in vessels with shells 3/8" thick or less.
o They may be used only if approved by the operators.
o They may be used only on low pressure vessels.
o They are used for only temporary repairs.
Question 41
Carbon 01' alloy steel with a carbon content over ______ percent shall not be welded.
o 0.30
o 0.35
o 0.40
o 0.45
Question 42
Acceptance criteria for a welded repair 01' alteration should include NDE techniques that are in
accordance with the:
Question 43
A pressure test is normally required after:
o an alteration.
o a repair.
o a lightning strike.
o a unit upset.
Question 44
When is a rerating of a pressure vessel considered complete?
Question 45
An API certified inspector who has not been actively engaged, as such, within the previous three
years can be recertified by:
Question 47
77. A 12 in. nozzle is being installed in a vessel where the largest existing opening is 10 in. This is
considered:
o 1. A repair
o 2. An alteration
o 3. A rerating
o 4. A maintenance activity
Question 48
78. How many years of experience are required when the candidate does not have an education level
equivalent to a high school education?
o 1. 5
o 2. 3
o 3. 2
o 4. 10
Question 49
79. May the API 510 Inspector be assisted by non-certified individuals when visual inspections are
performed?
Question 50
80. When can preheat at 3000 F in lieu of PWHT not be applied in the repairs of a pressure vessel?
Question 51
81. Which of the following conditions must be met to qualify vessels for on-stream inspections when
the general corrosion rate is less than 0.005 in. per year and has a remaining life greater than 10
years?
Question 52
82. The definition of "t required" is:
Question 53
83. Which of the following widely scattered pitting cannot be ignored?
o 1. The total area of the pits does not exceed 7 square inches within an 9 inch diameter circle
o 2. No pit depth is greater than 1/3 the vessel thickness
o 3. The sum of the pit dimensions along any straight line within the circle does not exceed 2.5
inches
o 4. The total area of the pits does not exceed 7 square inches within an 8 inch diameter circle
Question 54
84. Which of the following is not an alteration:
Question 55
85. A pressure vessel whose thickness does not exceed 2 inches has a MDMT of - 20° F. Per API
510 what is the minimum test temperature permitted?
o 1. 30° F
o 2. - 10° F
o 3. - 30° F
o 4. 10° F
Question 56
86. If a filler metal is used that has a minimum specified tensile strength that is lower than that of the
base metal, which of the following conditions must be met?
Question 57
87. How are safety relief devices isolated from the vessel during hydrostatic testing?
Question 58
107. Which of the following is a requirement when installing a patch?
Question 59
108. Who decides how long a temporary patch may remain in place?
o 1. Owner-user
o 2. Pressure vessel engineer & API Inspector
o 3. Pressure vessel engineer
o 4. API Inspector
Question 60
109. You have a corroded area which is 0.900 in. thick. The minimum thickness is calculated to be
1.000 in. the corrosion rate is 0.01 in. per year. Assuming a constant corrosion rate how much weld
overlay must be applied to have a 10 year life?
o 1. 0.10 in.
o 2. 0.20 in.
o 3. 1.300 in.
o 4. repair not permitted by API 510
Question 61
110. Who is notified when a repair to an ASME Section VIII, Division 2 vessel is required?
Question 62
111. Who is responsible to keep records of pressure vessel inspections & repairs?
o 1. Owner -user
o 2. API Inspector
o 3. Pressure vessel engineer
o 4. Engineering manager
Question 63
114. Which of the following is defined as a repair organization?
o 1. MT
o 2. UT
o 3. RT
o 4. VT
Question 65
113. Quality assurance can be simply defined as:
o 1. The work necessary to restore a vessel to a condition suitable for safe operation
o 2. All planned, systematic, and preventative actions required to determine if materials,
equipment or services will meet specified requirements
o 3. Work done by the OA Manager
o 4. Planned actions which determine that all NDE is performed correct
Question 66
115. How long must the temper bead repair be he Id at temperature after completion of the weld
repair for an API 510 applications?
o 1. 5 hours
o 2. 1 hour
o 3. 4 hours
o 4. 2 hours
Question 67
116. Which of the following must be considered by the pressure vessel engineer when repairs are
made to stainless steel weld overlay for equipment in hydrogen service?
Question 68
121. During an internal inspection of a pressure vessel a blister is found in one of the heads between
knuckle and circumferential head to shell weld. What would be the most appropriate action?
Question 69
122. A pressure vessel contains the following nozzles, (2-NPS 6, 1-NPS 10 and 4-NPS 3). Which of
the following would be an alteration?
o 1. Fatigue
o 2. Likelihood of failure
o 3. Associated consequence of failure
o 4. Both 2 & 3
Question 71
126. Examples of degradation mechanisms are:
o 1. Corrosion
o 2. Cracking
o 3. Creep
o 4. All the above
Question 72
127. It is essential that all RBI assessments be:
Question 73
128. An RBI assessment may be used to ______ the 10 year inspection limit.
o 1. Increase or decrease
o 2. Increase
o 3. Decrease
o 4. Limit
Question 74
130. What is the maximum interpass temperature for a repair weld using the controlled deposition
method that was originally PWHT’d?
o 1. 400°F
o 2. 600°F
o 3. 300°F
o 4. Not greater than that used in procedure qualification test.
1 2 3 4 5 6 7 8 9 10
11 12 13 14 15 16 17 18 19 20
21 22 23 24 25 26 27 28 29 30
31 32 33 34 35 36 37 38 39 40
41 42 43 44 45 46 47 48 49 50
51 52 53 54 55 56 57 58 59 60
61 62 63 64 65 66 67 68 69 70
71 72 73 74