Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
Section 1 – Objective
The objective of this document is to provide the project plan to implement 2nd phase of
municipality portal development for UNDP Timor-Leste.
The document will outline the Municipal system migration implementation, the
development phases for additional features of the existing Portal Municipal and the
assessment of 12 municipalities for preparation of installation of municipality conference
room.
This document will also cover about the project management and its implementation to
ensure the second phase development of Portal Municipal meets the deadline as per
required by the scope of work of second phase development for the Municipal Portal.
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
3 Geospatial Tools including - The Portal should have some geospatial tools
GPS localization and
such as Remote Sensing/Geographic
Tracking Visitor
Information Systems (GIS) and other tools for
the visualization,
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
4 Mobile App (offline viewing) - The Portal should provide an offline viewing
option to guarantee citizens access when they
do not have the internet in the remote areas.
Confidential Page 3
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
Section 3 – Timeline
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
Mission,
MSA and
TIK-Timor.
4 Additional Features Development for Municipal Portal
User requirements Gathering and
7 days
4.1 Analysis
Data collections (User manuals,
UNDP, R2M
4.1.1 brochures, system documentation, forms 6-Jan-21 8-Jan-21 3 days
and MSA
and other relevant information) In Progres X
Not
4.1.2 User requirement analysis 11-Jan-21 14-Jan-21 4 days R2M X
started
4.2 System Design and Development 30 days
System Prototype Design (system front-
4.2.1 end layout, use case, activities and class 11-Jan-21 14-Jan-21 5 days R2M Not X
diagram) started
Prototype presentation and technical UNDP, R2M Not
4.2.2 18-Jan-21 19-Jan-21 2 days X
requirement approval and MSA started
Not
4.2.3 Design the database schema 18-Jan-21 22-Jan-21 5 days R2M X
started
Coding the business services and system Not
4.2.4 18-Jan-21 5-Feb-21 15 days R2M X X X
layout started
Review the system according to the user
requirements including system integration 10-Feb-
4.2.5 8-Feb-21 3 days R2M X
(Data model business service and view 21 Not
layout) started
4.3 System Testing and Staging 25 days
Unit testing for functionality of system 11-Feb- 15-Feb- Not
4.3.1 3 days R2M X X
including fix the bugs found 21 21 started
Release the system into staging UNDP, R2M,
16-Feb- 17-Feb-
4.3.2 environment for User Acceptance testing 2 days MSA and Not X
21 21
(UAT) TIK Timor started
18-Feb- 24-Feb- UNDP, R2M Not
4.3.3 User Acceptance Testing (UAT) 5 days X X
21 21 and MSA started
System approval to release into 25-Feb- 26-Feb- UNDP, R2M Not
4.3.4 2 days X
production 21 21 and MSA started
UNDP, R2M Not
4.3.5 Socialization or Dissemination to staff 1-Mar-21 3-Mar-21 3 days X
and MSA started
12-Mar- UNDP, R2M Not
4.3.6 User Training 4-Mar-21 10 days X X
21 and MSA started
Not
Deployment 15 days
4.4 started
UNDP, R2M,
Install and configure the system into 15-Mar- 19-Mar-
4.4.1 5 days MSA and Not X
production environment 21 21
TIK Timor started
22-Mar- 26-Mar- UNDP, R2M, Not
4.4.2 Go Live 5 days X X
21 21 MSA and started
Confidential Page 3
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
TIK Timor
15-Mar- 25-Mar- UNDP, R2M Not
4.4.3 User Training 10 days X X
21 21 and MSA started
Documentation (user manual, system
architecture, UAT testing report and final 15-Mar- 29-Mar-
4.4.3 11 days R2M X X
project report) including hand-over 21 21 Not
certificate started
4.5 Maintenance
On-going support and continual 30-Mar- 30-Mar- Not
4.5.1 12 months R2M
improvement 21 22 started
5 Assessment for Preparation of Installation of Video Conference in 12 Municipalities
Perform Site Survey in the 12 12-Feb- UNDP, R2M, Not
5.1 18-Jan-21 20 days X X X X
Municipalities for physical observations. 21 MSA started
UNDP, R2M,
19-Feb- MSA, TIK-
5.2 Conduct Meeting with Key Stakeholders 1-Feb-21 15 days X X X
21 Timor and Not
DNICT-MTC started
Collect and review technical 26-Feb- UNDP and Not
5.3 1-Feb-21 20 days X X X X
documentation. 21 R2M started
22-Feb- Not
5.4 Conduct the gap analysis 5-Mar-21 10 days R2M X X
21 started
Develop the Initial Draft of Assessment
10-Mar- UNDP, R2M
5.5 Report for Key Stakeholder to review and 8-Mar-21 3 days Not X
21 and MSA
giving feedback. started
UNDP, R2M,
11-Mar- 11-Mar- MSA, TIK-
5.6 Presentation of the result of assessment. 1 day X
21 21 Timor and Not
DNICT-MTC started
12-Mar- 12-Mar- UNDP, R2M Not
5.7 Final Delivery of Assessment Report. 1 day X
21 21 and MSA started
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
Communication
In the principle, all project related communication will be between the Customer
Project Responsible and R2M Project Responsible.
In case of non-resolvable issue that required other teams from UNDP side, then the
UNDP Project Responsible will facilitate us to communicate with them.
Meetings
The meetings would also be arranged on need basis with required participants.
Reports
Palm Business & Trade Center, Hudi-laran/Osindo Block A, A2-01
Dili, Timor-Leste
Email: info@r2m.tl
Website: www.r2m.tl
Telephone: +670-3310347, 3310453
We will provide a weekly status report every Monday morning to the designated UNDP
Project Responsible.
In case there is no sign off due to the delivery issue, we will continue to work, for a
reasonable amount of time, at no cost to UNDP, to complete the deliverable.
In case the milestones are missed due to non-availability or delay of UNDP resources,
response, guidance, or data the deliverable will be deemed accepted. Designated
UNDP Project Responsible will sign off as such.
In case of non-receipt of the approval within 24 hours of a given project milestone
delivered the milestone will be deemed achieved, and approved.
Document ID R2M/2021/01/01
Version 1.0
bernardino.pereira@undp.org