A. PEKERJAAN PERSIAPAN
1. Pembersihan Lahan
Luas = 32,8 m x 87,2 m = 2860,16 m2
Pagar Proyek = 2 (32,8 + 87,2) m = 240 m
Pemasangan Bowplank
= Keliling Bangunan + 1
= 23+30+9,1+10+12,1+14+35,23+29+54+1
= 217,43 m
B. PEKERJAAN PONDASI
2. Pekerjaan Tanah
Urugan Pile Cap PC1
Volume Timbunan Tanah Kembali = 0,5 x 44,1
= 22,05 m³
Urugan Pile Cap PC3
Volume Timbunan Tanah Kembali = 0,5 x 28,13
= 14,07 m³
Urugan Pile Cap PC4
Volume Timbunan Tanah Kembali = 0,5 x 136,69
= 68,35 m³
Urugan Pile Cap PC5
Volume Timbunan Tanah Kembali = 0,5 x 248
= 124 m³
Urugan Pile Cap PC6
Volume Timbunan Tanah Kembali = 0,5 x 297,68
= 148,84 m³
Urugan Pile Cap PC7
Volume Timbunan Tanah Kembali = 0,5 x 474,1
= 237,05 m³
Urugan Pile Cap PC9
Volume Timbunan Tanah Kembali = 0,5 x 66,15
= 33,08 m³
Urugan Pile Cap PC10
Volume Timbunan Tanah Kembali = 0,5 x 628,43
= 314,22 m³
Urugan Pile Cap PC11
Volume Timbunan Tanah Kembali = 0,5 x 359,1
= 179,55 m³
Urugan Pile Cap PC13
Volume Timbunan Tanah Kembali = 0,5 x 340,2
= 170,1 m³
Urugan Tanah Tie Biem 1
Volume Timbunan Tanah Kembali = 0,5 x 41,13
= 20,57 m³
Urugan Tanah Tie Biem 2
Volume Timbunan Tanah Kembali = 0,5 x 13,81
= 6,91 m³
Urugan Tanah Tie Biem 3
Volume Timbunan Tanah Kembali = 0,5 x 3,51
= 1,76 m³
Urugan Tanah Tie Biem 4
Volume Timbunan Tanah Kembali = 0,5 x 0,84
= 0,42 m³
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Kolom 2A 60/50
Jumlah Kolom 2A = 14
Volume = (0,6 x 0,5 x 4,1) x 14
= (1,23) x1 4
= 17,22 m3
Pembesian
Panjang Sengkang = 2,05 m
22 D 22 = Jml Tulangan x BJ x P
= 22 x 2,984 x 1
= 65,648 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 78,2965 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
22 D 22 = Jml Tulangan x BJ x P
= 22x 2,984 x 1
= 65,648 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 74,080 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Kolom 3 50x50
Jumlah Kolom k3 =5
Volume = (0,5 x 0,5 x 4,1) x 5
= (1,025) x 5
= 5,125 m3
Pembesian Tumpuan
Panjang Sengkang = 2,05 m
16 D 22 = Jml Tulangan x BJ x P
= 16 x 2,985 x 1
= 47,76 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,648 kg
Total Pembesian = 60,408 kg
Bekisting = 4 x sisi
= 4 x 0,5
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
16 D 22 = Jml Tulangan x BJ x P
= 16 x 2,985 x 1
= 47,76 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,4323 kg
Total Pembesian = 56,192 kg
Bekisting = 4 x sisi
= 4 x 0,5
= 2 m2
Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3
Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-200 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 4,566 kg
Total Pembesian = 7,034 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Tumpuan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984 x 1
= 71,616 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Kolom 1B 60/60
Jumlah Kolom 1B = 25
Volume = (0,6 x 0,6 x 4,1) x 25
= (1,476) x 25
= 36,9 m3
Pembesian
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
=59,68 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 72,3285 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
= 59,68 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 68,112 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Kolom 2B 60/50
Jumlah Kolom 2 = 14
Volume = (0,60 x 0,50 x 4,1) x 14
= (1,23) x 14
= 17,22 m3
Pembesian
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,984 x 1
= 53,712 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,648 kg
Total Pembesian = 66,3605 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,985 x 1
= 53,712 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 62,162 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3
Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-200 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 4,566 kg
Total Pembesian = 7,034 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Tumpuan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984 x 1
= 71,616 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Kolom 1B 60/60
Jumlah Kolom 1B = 25
Volume = (0,6 x 0,6 x 4,1) x 25
= (1,476) x 25
= 36,9 m3
Pembesian
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
=59,68 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,6485 kg
Total Pembesian = 72,3285 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
= 59,68 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 68,112 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Kolom 2B 60/50
Jumlah Kolom 2 = 14
Volume = (0,60 x 0,50 x 4,1) x 14
= (1,23) x 14
= 17,22 m3
Pembesian
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,984 x 1
= 53,712 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 12,648 kg
Total Pembesian = 66,3605 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,985 x 1
= 53,73 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 2,05
= 8,432 kg
Total Pembesian = 62,162 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3
Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
= x 0,617 x 1,85
= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-200 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 4,566 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-200 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 4,565 kg
Total Pembesian = 7,033 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,44 kg
Total Pembesian = 63,28 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 34,48 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,44 kg
Total Pembesian = 63,28 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Balok G2a 30 x 60
Panjang Total = (7 x 14) + (1 x 6)
= 104 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 104 m
= 18,72 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Balok G3a 30 x 50
Panjang Total = (3 x 6) + (2 x 5)
= 28 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 28 m
= 4,2 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,41 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,41 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Balok G4 30 x 40
Panjang Total = (4 x 3) + (4 x 9)
= 48 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 48 m
= 5,76 m3
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Balok B2 25 x 60
Panjang Total = (11 x 7) + 9
= 86 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 86 m
= 12,9 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,41
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Balok B3 25 x 40
Panjang Total = (5 x 4) + (4 x 15) + (3 x 7)
= 101 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 101 m
= 10,1 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Balok B4 20 x 40
Panjang Total = 167,25 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 167,25 m
= 13,38 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Balok B5 15 x 40
Panjang Total = 5,10 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 5,10 m
= 2,19 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Balok B5L 15 x 40
Panjang Total = (5,13 x 2) + 3,00 + 3,46
= 16,72 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 16,72 m
= 1,003 m3
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Balok B2T 25 x 60
Panjang Total = 6,5
Volume = p x l x panjang total
= 0,25 x 0,6 x 6,5 m
= 0,68 m3
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,45 m2
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Balok B1k 25 x 40
Panjang Total = (4 x 1,7)
= 6,8 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 6,8 m
= 0,68 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\
Balok B2k 25 x 40
Panjang Total = 2,45
Volume = p x l x panjang total
= 0,25 x 0,4 x 2,45 m
= 0,25 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 3,16 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Balok G1k 30 x 40
Panjang Total = 1,7
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,7 m
= 0,204 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -75 = x BJ x P. Sengkang
= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Balok G2k 30 x 40
Panjang Total = 1,25
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,25 m
= 0,15 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -75 = x BJ x P. Sengkang
2D 10 -100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
= 2x x 0,617 x 1,85
= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 34,47 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Balok G2a 30 x 60
Panjang Total = (7 x 13) + (1 x 6)
= 97 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 97 m
= 17,46 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Balok G3a 30 x 50
Panjang Total = (3 x 6) + (4 x 5)
= 38 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 38 m
= 5,7 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Balok G4 30 x 40
Panjang Total = (3 x 4) + (4 x 8) + 4,3
= 48,3 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 48,3 m
= 5,79 m3
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 22,23 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Balok B2 25 x 60
Panjang Total = (11 x 7)
= 77 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 77 m
= 11,55 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,41
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Balok B3 25 x 40
Panjang Total = (9 x 4) + 2,15 + (6 x 3)
= 56,15 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 56,15 m
= 5,62 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Balok B4 20 x 40
Panjang Total = 170,6 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 170,6 m
= 13,65 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Balok B5 15 x 40
Panjang Total = 5,10 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 5,10 m
= 2,19 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 21,89 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 29,79 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 21,89 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Balok B5L 15 x 40
Panjang Total = (5,13 x 2) + 3 + 3,46
= 16,72 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 16,72 m
= 1,003 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 37,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 45,59 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 37,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Balok B2T 25 x 60
Panjang Total = 3,4 + 4
Volume = p x l x panjang total
= 0,25 x 0,6 x 7,4 m
= 1,11 m3
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,58 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Balok B1k 25 x 40
Panjang Total = (4 x 1,7)
= 6,8 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 6,8 m
= 0,68 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 36,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\
Balok B2k 25 x 40
Panjang Total = 2,45
Volume = p x l x panjang total
= 0,25 x 0,4 x 2,45 m
= 0,25 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Balok G1k 30 x 40
Panjang Total = 1,7
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,7 m
= 0,204 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -75 = x BJ x P. Sengkang
= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Balok G2k 30 x 40
Panjang Total = 1,25
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,25 m
= 0,15 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,985 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -75 = x BJ x P. Sengkang
= 30,49 kg
Total Pembesian = 60,34 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 34,74 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Balok G1b 30 x 85
Panjang Total = (18 x 10) + (11 x 9) + (5 x 7) + (2 x 6) + (2 x 5)
= 336 m
Volume = p x l x panjang total
= 0,30 x 0,85 x 336 m
= 85,68 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,49 kg
Total Pembesian = 57,3 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang
= 2x x 0,617 x 1,85
= 30,49 kg
Total Pembesian = 57,3 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Balok G2b 30 x 60
Panjang Total = (7 x 11)
= 77 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 77 m
= 13,86 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Balok G3b 30 x 50
Panjang Total = (2 x 6) + (2 x 5)
= 22 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 22 m
= 3,3 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Balok G4 30 x 40
Panjang Total = (3 x 4) + (4 x 9) + 4,3
= 52,3 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 52,3 m
= 6,28 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Balok B2 25 x 60
Panjang Total = (13 x 7)
= 91 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 91 m
= 13,65 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Balok B3 25 x 40
Panjang Total = (15 x 4) + (6 x 3)
= 78 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 78 m
= 7,8 m3
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Balok B4 20 x 40
Panjang Total = 147 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 147 m
= 11,76 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Balok B5L 15 x 40
Panjang Total = 195,42 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 195,42 m
= 11,73 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
D 8-150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
D 8 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Balok B1k 25 x 40
Panjang Total = 37 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 37 m
= 3,7 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -150 = x BJ x P. Sengkang
= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\
Balok G1k 30 x 40
Panjang Total = 29 m
Volume = p x l x panjang total
= 0,3 x 0,4 x 29 m
= 3,48 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -75 = x BJ x P. Sengkang
= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10 -100 = x BJ x P. Sengkang
= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Plat Tangga
Tebal = 0,15 m
Lebar = 1,4 m
Panjang = 3,6 m
Volume = (0,15 x 1,4 x 3,6) x 2
= 0,756 m3 x 2
= 1,512 m3
Penulangan
Pembesian Bordes
=2x
= 3,286 kg
=2x
= 55,568 kg
Pembesian Tangga
= 29,573 kg
=2x
= 6,174 kg
Pembesian Anak Tangga
Tulangan 1 = L x BJ x Jml Anak Tangga
= 1,4 x 0,617 x 22
= 19,004 kg
= x 22
= 237,709 kg
C. PEKERJAAN PASANGAN
Pekerjaan Pasangan Batu Bata
1. LANTAI 1
= x 4,1
= 6457 m2
Luas CW 1
Jumlah CW =1
Luas CW = 2,1 x 4,1 x 1
= 8,61 m2
Total Luas CW 1 = 8,61 m2
Luas CW 2
Jumlah CW =1
Luas CW = 3,08 x 4,1 x 1
= 12,63 m2
Total Luas CW 2 = 12,63 m2
Luas CW 3
Jumlah CW =3
Luas CW = 0,8 x 4,1 x 3
= 9,84 m2
Total Luas CW 3 = 9,84 m2
Luas CW 4
Jumlah CW =3
Luas CW4 = 0,8 x 4,1 x 3
= 9,84 m2
Total Luas CW = 9,84 m2
Luas CW 5
Jumlah CW =5
Luas CW = 0,8 x 4.1 x 5
= 16,4 m2
Total Luas CW 5 = 16,4 m2
Luas CW 6
Jumlah CW =1
Luas CW = 14 x 0,8 x 1
= 11,2 m2
Total Luas CW 6 = 11,2 m2
Luas CW 7
Jumlah CW =3
Luas CW = 0,8 x 10,4 x 3
= 24,96 m2
Total Luas CW 7 = 24,96 m2
Luas CW 8
Jumlah CW =1
Luas CW = 10,62 x 2,78 x 1
= 29,5 m2
Total Luas CW 8 = 29,5 m2
Luas CW 9
Jumlah CW =1
Luas CW = 9,4 x 11,35 x 1
= 106,69 m2
Total Luas CW 9 = 106,69 m2
Luas FD1
Jumlah =3
Luas = 9,5 x 3 x 3
= 85,5 m2
Total Luas = 85,5 m2
Luas F3
Jumlah =1
Luas = 4,2 x 4,1 x 1
= 17,22 m2
Total Luas = 17,22 m2
Luas F4
Jumlah =1
Luas = 5,63 x 3 x 1
= 16,89 m2
Total Luas = 16,89 m2
Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,68 x 2,7) x 2
= 9,07 m2
Total Luas Pintu = 9,07 m2
Luas Pintu PD 2
PD 2 Jumlah Pintu =1
Luas Pintu = 1,68 x 2,14 x 1
= 3,59 m2
Total Luas Pintu = 3,59 m2
Luas Pintu PF 1
PF 1 Jumlah Pintu =1
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2
Luas Pintu PF 2
PF 2 Jumlah Pintu =1
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2
Luas Pintu PF 3
PF 3 Jumlah Pintu =1
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2
Luas Pintu P1
P PS Jumlah Pintu =2
Luas Pintu = 2,7 x 0,88 x 2
= 4,7 m2
Total Luas Pintu = 4,7 m2
Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,88 x 4
= 4,7 m2
Total Luas Pintu = 9,5 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2
LANTAI 2
= x 4,1
= 6457 m2
Luas CW 10
Jumlah CW =1
Luas CW = 7,23 x 7,25 x 1
Total Luas CW = 52,42 m2
Luas CW11
Jumlah CW =1
Luas CW = 7,15 x 2,45 x 1
Total Luas CW = 17,52 m2
Luas CW12
Jumlah CW =1
Luas CW = 10,6 x 7,25 x1
Total Luas CW = 76,85 m2
Luas CW13
Jumlah CW =1
Luas CW = 9,4 x 3x1
Total Luas CW = 28,2 m2
Luas CW14
Jumlah CW =1
Luas CW = 6,05 x 3,7 x1
Total Luas CW = 22,38 m2
Luas CW 15
Jumlah CW =1
Luas CW = 23,8 x 7,25 x 1
Total Luas CW = 172,55 m2
Luas FD3
Jumlah =1
Luas = 6,4 x 3 x 1
= 19,2 m2
Total Luas = 19,2 m2
Luas FD4
Jumlah =1
Luas = 3,45 x 3 x 1
= 10.35 m2
Total Luas = 10,35 m2
Luas F5
Jumlah =4
Luas = 3,3 x 3 x 4
= 39,6 m2
Total Luas = 39,6 m2
Luas F6
Jumlah =1
Luas = 2,7 x 3 x 1
= 8,1 m2
Total Luas = 8,1 m2
Luas F7
Jumlah =1
Luas = 6,3 x 3 x 1
= 18,9 m2
Total Luas = 18,9 m2
Luas F8
Jumlah =2
Luas = 2,15 x 3 x 2
= 12,9 m2
Total Luas = 12,9 m2
Luas F9
Jumlah =1
Luas = 1,94 x 3 x 1
= 5,82 m2
Total Luas = 5,82 m2
Luas F10
Jumlah =1
Luas = 6,65 x 3 x 1
= 19,95 m2
Total Luas = 19,95 m2
Luas F11
Jumlah =1
Luas = 2,77 x 3 x 1
= 8,31 m2
Total Luas = 8,31 m2
Luas F12
Jumlah =1
Luas = 1,87 x 3 x 1
= 5,61 m2
Total Luas = 5,61 m2
Luas F13
Jumlah =1
Luas = 9,4 x 3 x 1
= 28,2 m2
Total Luas = 28,2 m2
Luas F14
Jumlah =1
Luas = 4,77 x 3 x 1
= 14,31 m2
Total Luas = 14,31 m2
Luas F15
Jumlah =1
Luas = 4,4 x 3 x 1
= 13,2 m2
Total Luas = 13,2 m2
Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,68 X 2,7) X 2
= 9,07 m2
Total Luas Pintu = 9,07 m2
Luas Pintu PF 8
PF8 Jumlah Pintu =2
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2
Luas Pintu PF 9
PF9 Jumlah Pintu =4
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2
Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2
Luas Pintu P1
P1 Jumlah Pintu =1
Luas Pintu = 2,7 x 0,88 x 1
= 2,37 m2
Total Luas Pintu = 2,37m2
Luas Pintu P2
P2 Jumlah Pintu =5
Luas Pintu = 2,7 x 0,88 x 5
= 11,88 m2
Total Luas Pintu = 11,88 m2
Luas Pintu P5
P5 Jumlah Pintu =2
Luas Pintu = 0,98 x 2,1 x 2
= 4,11 m2
Total Luas Pintu = 4,11 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2
LANTAI 3
= x 4,1
= 6457 m2
Luas CW 13
Jumlah CW =1
Luas CW = 9,4 x 3 x 1
Total Luas CW = 28,2 m2
Luas FD1
Jumlah =1
Luas = 6,4 x 3 x 1
= 19,2 m2
Total Luas = 19,2 m2
Luas F8
Jumlah =1
Luas = 2,15 x 3 x 1
= 6,45 m2
Total Luas = 6,45 m2
Luas F9
Jumlah =2
Luas = 1,94 x 3 x 2
= 11,64 m2
Total Luas = 11,64 m2
Luas F11
Jumlah =1
Luas = 2,78 x 3 x 1
= 8,34 m2
Total Luas = 8,34 m2
Luas F13
Jumlah =1
Luas = 9,4 x 3 x 1
= 28,2 m2
Total Luas = 28,2 m2
Luas F14
Jumlah =1
Luas = 4,78 x 3 x 1
= 14,34 m2
Total Luas = 14,34 m2
Luas F16
Jumlah =1
Luas =3 x3 x1
= 9 m2
Total Luas = 9 m2
Luas F17
Jumlah =1
Luas = 5,15 x 3 x 1
= 15,45 m2
Total Luas = 15,45 m2
Luas F18
Jumlah =1
Luas = 6,87 x 3 x 1
= 20,61 m2
Total Luas = 20,61m2
Luas F19
Jumlah =2
Luas = 8,4 x 3 x 2
= 50,4 m2
Total Luas = 50,4 m2
Luas Pintu PD 1
PD 1 Jumlah Pintu =1
Luas Pintu Utama = (1,68 X 2,7) X 1
= 4,54 m2
Total Luas Pintu = 4,54 m2
Luas Pintu PF 8
PF 1 Jumlah Pintu =2
Luas Pintu = 3,14 x 3 x 2
= 18,84 m2
Total Luas Pintu = 18,84 m2
Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,91 x 3 x 2
= 17,46 m2
Total Luas Pintu = 17,46 m2
Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,88 x 4
= 9,5 m2
Total Luas Pintu = 9,5 m2
Luas Pintu P6
P6 Jumlah Pintu =1
Luas Pintu = 1,48 x 2,1 x 1
= 3,1 m2
Total Luas Pintu = 3,1 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2
Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,6 x 2,7) x 2
= 8,64 m2
Total Luas Pintu = 8,64 m2
Luas Pintu PD 2
PD 2 Jumlah Pintu =1
Luas Pintu = 1,6 x 2,14 x 1
= 3,42 m2
Total Luas Pintu = 3,42 m2
Luas Pintu PF 1
PF 1 Jumlah Pintu =1
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2
Luas Pintu PF 2
PF 2 Jumlah Pintu =1
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2
Luas Pintu PF 3
PF 3 Jumlah Pintu =1
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2
Luas Pintu P1
P PS Jumlah Pintu =2
Luas Pintu = 2,7 x 0,8 x 2
= 4,32 m2
Total Luas Pintu = 4,32 m2
Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,8 x 4
= 8,64 m2
Total Luas Pintu = 8,64 m2
Luas Pintu P4
P4 Jumlah Pintu =1
Luas Pintu = 0,9 x 2,1 x 1
= 2,05 m2
Total Luas Pintu = 1,89 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2
LANTAI 2
Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,6 x 2,7) x 2
= 8,64 m2
Total Luas Pintu = 8,64 m2
Luas Pintu PF 8
PF8 Jumlah Pintu =2
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2
Luas Pintu PF 9
PF9 Jumlah Pintu =4
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2
Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2
Luas Pintu P2
P2 Jumlah Pintu =5
Luas Pintu = 2,7 x 0,8 x 5
= 10,8 m2
Total Luas Pintu = 10,8 m2
Luas Pintu P5
P5 Jumlah Pintu =2
Luas Pintu = 0,9 x 2,1 x 2
= 3,78 m2
Total Luas Pintu = 3,78 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2
LANTAI 3
Luas Pintu PD 1
PD 1 Jumlah Pintu =1
Luas Pintu Utama = (1,6 x 2,7) x 1
= 4,32 m2
Total Luas Pintu = 4,32 m2
Luas Pintu PF 8
PF 1 Jumlah Pintu =2
Luas Pintu = 3,14 x 3 x 2
= 18,84 m2
Total Luas Pintu = 18,84 m2
Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,91 x 3 x 2
= 17,46 m2
Total Luas Pintu = 17,46 m2
Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,8 x 4
= 8,64 m2
Total Luas Pintu = 8,64 m2
Luas Pintu P6
P6 Jumlah Pintu =1
Luas Pintu = 1,4 x 2,1 x 1
= 2,94 m2
Total Luas Pintu = 2,94 m2
Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2
2. Pekerjaan Plafond
Luas Langit-Langit Lantai 1 = luas lantai 2
= 1424,2 m2
Luas Langit-Langit Lantai 2 = luas lantai 3
` = 1235,2 m2
Luas Langit-Langit Lantai 3 = luas dak
= 1460 m2
6. PEKERJAAN KERAMIK
Lantai Keramik 60 x 60 luas lantai 1 sampai 3 = 3924,4 m²
Lantai Keramik 30 x 30 luas = 190 m2
7. PEKERJAAN INSTALASI
Pekerjaan Instalasi Air
Lantai 1
Closet duduk = 5 bh
Kran 0,5" = 6 bh
Shower + kran = 18 bh
Floor Drain Stainless = 28 bh
Tanda Toilet Male / Female = 2 bh
Kitchen Zink + Kran = 2 bh
Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
Pipa PPR 32mm (1”) Klas PN 10 = 74 m
Material Bantu = 1 ls
Pipa PVC Tipe AW 3” = 84 m
Pipa PVC Tipe AW 4” = 24 m
Pipa PVC Tipe AW 6” = 25 m
Lantai 2
Closet duduk = 9 bh
Kran 0,5" = 9 bh
Shower + kran = 18 bh
Floor Drain Stainless = 28 bh
Tanda Toilet Male / Female = 2 bh
Kitchen Zink + Kran = 2 bh
Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
Pipa PPR 32mm (1”) Klas PN 10 = 74 m
Material Bantu = 1 ls
Pipa PVC Tipe AW 3” = 84 m
Pipa PVC Tipe AW 4” = 24 m
Lantai 3
Closet duduk = 8 bh
Kran 0,5" = 8 bh
Shower + kran = 18 bh
Floor Drain Stainless = 28 bh
Tanda Toilet Male / Female = 2 bh
Kitchen Zink + Kran = 2 bh
Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
Pipa PPR 32mm (1”) Klas PN 10 = 74 m
Material Bantu = 1 ls
Pipa PVC Tipe AW 3” = 84 m
Pipa PVC Tipe AW 4” = 24 m
2. LANTAI 2
Saklar dan Stop Kontak
Pas. Saklar Tunggal = 28 bh
Pas. Saklar Ganda = 14 bh
Pas. Saklar Putar = 3 bh
Pas. Greed Switch 8 Gang = 1 bh
Pas. Stop Kontak 250 W = 22 bh
Titik Instalasi
Kabel NYM 3 x 2,5 mm + Konduit PVC = 97 titik
Stop Kontak, NYM 3 x 2,5 mm2 + Konduit PVC = 46 titik
Fixtures Lampu Lengkap Armatur
Pas. Lampu Baret Emergency 32 Watt = 3 bh
Pas. Lampu Downlight LED 7 W = 6 bh
Pas. Lampu Downlight LED EMERGENCY 7 W = 3 bh
Pas. Lampu Downlight DL CFL 8 W = 82 bh
Pas. Lampu Exit 10 W = 3 bh
Exhaust Fan 1183.04 CFM
Kipas Angin = 8 bh
Cealing Fan 37 W = 8 bh
3. LANTAI 3
Saklar dan Stop Kontak
Pas. Saklar Tunggal = 28 bh
Pas. Saklar Ganda = 14 bh
Pas. Saklar Putar = 3 bh
Pas. Greed Switch 8 Gang = 1 bh
Pas. Stop Kontak 250 W = 22 bh
Titik Instalasi
Kabel NYM 3 x 2,5 mm + Konduit PVC = 97 titik
Stop Kontak, NYM 3 x 2,5 mm2 + Konduit PVC = 46 titik
Fixtures Lampu Lengkap Armatur
Pas. Lampu Baret Emergency 32 Watt = 3 bh
Pas. Lampu Downlight LED 7 W = 6 bh
Pas. Lampu Downlight LED EMERGENCY 7 W = 3 bh
Pas. Lampu Downlight DL CFL 8 W = 82 bh
Pas. Lampu Exit 10 W = 3 bh
Exhaust Fan 1183.04 CFM
Kipas Angin = 8 bh
Cealing Fan 37 W = 8 bh