PERHITUNGAN VOLUME PEKERJAAN

A. PEKERJAAN PERSIAPAN
1. Pembersihan Lahan
Luas = 32,8 m x 87,2 m = 2860,16 m2
Pagar Proyek = 2 (32,8 + 87,2) m = 240 m
Pemasangan Bowplank
= Keliling Bangunan + 1
= 23+30+9,1+10+12,1+14+35,23+29+54+1
= 217,43 m

B. PEKERJAAN PONDASI

1. Pondasi Tiang Pancang


 Tiang Pancang P1
Jumlah Pondasi Tiang Pancang P1 =6
Kedalaman (d) = 15 m
Lebar PC 1 = 0,7
Panjang (P1) = 0,7
Volume = 15 x 0,7 x 0,7x 6
= 44,1 m³
 Tiang Pancang P3
Jumlah Pondasi Tiang Pancang P3 =1
Kedalaman (d) = 15
Lebar PC 3 = 1,25
Panjang (P3) = 1,5
Volume = 15 x 1,25 x 1,5 x 1
= 28,13 m³
 Tiang Pancang P4
Jumlah Pondasi Tiang Pancang P4 =5
Kedalaman (d) = 15
Ukuran PC 4 = 1,35
Panjang (P4) = 1,35
Volume = 15 x 1,35 x 1,35 x 5
= 136,69 m³
 Tiang Pancang P5
Jumlah Pondasi Tiang Pancang P4 =6
Kedalaman (d) = 15
Ukuran PC 5 = 1,66
Panjang (P5) = 1,66
Volume = 15 x 1,66 x 1,66x 6
= 1240,02 m³
 Tiang Pancang P6
Jumlah Pondasi Tiang Pancang P6 =7
Kedalaman (d) = 15
Lebar PC 6 = 1,35
Panjang (P6) = 2,1
Volume = 15x 1,35 x 2,1 x 7
= 297,68 m³
 Tiang Pancang P7
Jumlah Pondasi Tiang Pancang P7 =7
Kedalaman (d) = 15
lebar PC 7 = 1,66
Panjang (P7) = 2,72
Volume = 15 x 1,66 x 2,72 x 7
= 474,1 m³
 Tiang Pancang P9
Jumlah Pondasi Tiang Pancang P9 =1
Kedalaman (d) = 15
Lebar PC 9 = 2,1
Panjang (P9) = 2,1
Volume = 15 x 2,1x 2,1 x 1
= 66,15 m³
 Tiang Pancang P10
Jumlah Pondasi Tiang Pancang P10 =7
Kedalaman (d) = 15
Lebar PC 10 = 2,1
Panjang (P10) = 2,85
Volume = 15 x 2,1 x 2,85 x 7
= 628,43 m³
 Tiang Pancang P11
Jumlah Pondasi Tiang Pancang P11 =4
Kedalaman (d) = 15
Lebar PC 11 = 2,1
Panjang (P11) = 2,85
Volume = 15 x 2,1 x 2,85x 4
= 359,1 m³
 Tiang Pancang P13
Jumlah Pondasi Tiang Pancang P13 =3
Kedalaman (d) = 15
Lebar PC 13 = 2,1
Panjang (P13) = 3,6
Volume = 15 x 2,1 x 3,6 x 3
= 340,2 m³

 Galian Tanah Tie Biem TB1


Panjang Total = 250,72 m
Kedalaman = 0,6 m
Lebar = 0,3 m
Volume Galian TB = 250,72 x 0,6 x 0,3
= 41,13 m³
 Galian Tanah Tie Biem TB2
Panjang Total = 92,06 m
Kedalaman = 0,5 m
Lebar = 0,3 m
Volume Galian TB = 92,06 x 0,5 x 0,3
= 13,81 m³
 Galian Tanah Tie Biem TB3
Panjang Total = 29,27 m
Kedalaman = 0,4 m
Lebar = 0,3 m
Volume Galian TB = 29,27 x 0,4 x 0,3
= 3,51 m³
 Galian Tanah Tie Biem TB4
Panjang Total = 7 m
Kedalaman = 0,50 m
Lebar = 0,25 m
Volume Galian TB = 7 x 0,50 x 0,25
= 0,84 m³

2. Pekerjaan Tanah
 Urugan Pile Cap PC1
Volume Timbunan Tanah Kembali = 0,5 x 44,1
= 22,05 m³
 Urugan Pile Cap PC3
Volume Timbunan Tanah Kembali = 0,5 x 28,13
= 14,07 m³
 Urugan Pile Cap PC4
Volume Timbunan Tanah Kembali = 0,5 x 136,69
= 68,35 m³
 Urugan Pile Cap PC5
Volume Timbunan Tanah Kembali = 0,5 x 248
= 124 m³
 Urugan Pile Cap PC6
Volume Timbunan Tanah Kembali = 0,5 x 297,68
= 148,84 m³
 Urugan Pile Cap PC7
Volume Timbunan Tanah Kembali = 0,5 x 474,1
= 237,05 m³
 Urugan Pile Cap PC9
Volume Timbunan Tanah Kembali = 0,5 x 66,15
= 33,08 m³
 Urugan Pile Cap PC10
Volume Timbunan Tanah Kembali = 0,5 x 628,43
= 314,22 m³
 Urugan Pile Cap PC11
Volume Timbunan Tanah Kembali = 0,5 x 359,1
= 179,55 m³
 Urugan Pile Cap PC13
Volume Timbunan Tanah Kembali = 0,5 x 340,2
= 170,1 m³
 Urugan Tanah Tie Biem 1
Volume Timbunan Tanah Kembali = 0,5 x 41,13
= 20,57 m³
 Urugan Tanah Tie Biem 2
Volume Timbunan Tanah Kembali = 0,5 x 13,81
= 6,91 m³
 Urugan Tanah Tie Biem 3
Volume Timbunan Tanah Kembali = 0,5 x 3,51
= 1,76 m³
 Urugan Tanah Tie Biem 4
Volume Timbunan Tanah Kembali = 0,5 x 0,84
= 0,42 m³

3. Pekerjaan Timbunan Pasir 10 cm


 Pekerjaan Timbunan Pile Cap PC1
Tinggi = 0,1 m
Lebar = 0,7 m
Panjang = 0,7 m
Jumlah = 6 buah
Volume Timbunan Pasir = 0,1 x 0,7 x 0,7 x 6
= 0,29 m³
 Pekerjaan Timbunan Pile Cap PC 3
Tinggi = 0,1 m
Lebar = 1,50 m
Panjang = 1,25 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,1 x 1,50 x 1,25 x 1
= 0,19 m³
 Pekerjaan Timbunan Pile Cap PC4
Tinggi = 0,1 m
Lebar = 1,35 m
Panjang = 1,35 m
Jumlah = 5 buah
Volume Timbunan Pasir = 0,1 x 1,35 x 1,35 x 5
= 0,91 m³
 Pekerjaan Timbunan Pile Cap PC5
Tinggi = 0,1 m
Lebar = 1,66 m
Panjang = 1,66 m
Jumlah = 6 buah
Volume Timbunan Pasir = 0,1 x 1,66 x 1,66 x 6
= 1,65 m³
 Pekerjaan Timbunan Pile Cap PC6
Tinggi = 0,1 m
Lebar = 2,10 m
Panjang = 1,35 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,1 x 2,10 x 1,35 x 7
= 1,98 m³
 Pekerjaan Timbunan Pile Cap PC7
Tinggi = 0,1 m
Lebar = 2,72 m
Panjang = 1,66 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,1 x 2,72 x 1,66 x 7
= 3,16 m³
 Pekerjaan Timbunan Pile Cap PC9
Tinggi = 0,1 m
Lebar = 2,10 m
Panjang = 2,10 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,1 x 2,10 x 2,10 x 1
= 0,44 m³
 Pekerjaan Timbunan Pile Cap PC10
Tinggi = 0,1 m
Lebar = 2,85 m
Panjang = 2,10 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,1 x 2,85 x 2,10 x 7
= 4,19 m³
 Pekerjaan Timbunan Pile Cap PC11
Tinggi = 0,1 m
Lebar = 2,85 m
Panjang = 2,10 m
Jumlah = 4 buah
Volume Timbunan Pasir = 0,1 x 2,85 x 2,10 x 4
= 2,39 m³
 Pekerjaan Timbunan Pile Cap PC13
Tinggi = 0,1 m
Lebar = 3,60 m
Panjang = 2,10 m
Jumlah = 3 buah
Volume Timbunan Pasir = 0,1 x 3,60 x 2,10 x 3
= 2,27 m³
 Pekerjaan Timbunan Tie Biem TB1
Tinggi = 0,6 m
Lebar = 0,3 m
Panjang = 250,72 m
Volume Timbunan Pasir = 0,1 x 0,6 x 0,3 x 250,72
= 4,51 m³
 Pekerjaan Timbunan Tie Biem TB2
Tinggi = 0,5 m
Lebar = 0,3 m
Panjang = 92,06 m
Volume Timbunan Pasir = 0,1 x 0,5 x 0,3 x 92,06
= 1,38 m³
 Pekerjaan Timbunan Tie Biem TB3
Tinggi = 0,4 m
Lebar = 0,3 m
Panjang = 29,27 m
Volume Timbunan Pasir = 0,1 x 0,4 x 0,3 x 29,27
= 0,35 m³
 Pekerjaan Timbunan Tie Biem TB4
Tinggi = 0,5 m
Lebar = 0,25 m
Panjang =7m
Volume Timbunan Pasir = 0,1 x 0,5 x 0,25 x 7
= 0,0875 m³

4. Pekerjaan Sirtu Bawah Lantai 30 cm


Luas Bangunan = 2860,16 m2
Tebal = 0,30 m
Volume = 2860,16 x 0,3
= 858,048 m³

5. Pekerjaan Kerja Lantai Tebal 5cm


 Pekerjaan Lantai Kerja Pile Cap PC1
Tebal = 0,05 m
Lebar = 0,7 m
Panjang = 0,7 m
Jumlah = 6 buah
Volume Timbunan Pasir = 0,05 x 0,7 x 0,7 x 6
= 0,147 m³
 Pekerjaan Lantai Kerja Pile Cap PC3
Tebal = 0,05 m
Lebar = 1,50 m
Panjang = 1,25 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 1,50 x 1,25 x 1
= 0,94 m³
 Pekerjaan Lantai Kerja Pile Cap PC4
Tebal = 0,05
Lebar = 1,35 m
Panjang = 1,35 m
Jumlah = 5 buah
Volume Timbunan Pasir = 0,05 x 1,35 x 1,35 x 5
= 0,46 m³
 Pekerjaan Lantai Kerja Pile Cap PC5
Tebal = 0,05
Lebar = 1,66 m
Panjang = 1,66 m
Jumlah = 6 buah
Volume Timbunan Pasir = 0,05 x 1,66 x 1,66 x 6
= 0,83 m³
 Pekerjaan Lantai Kerja Pile Cap PC6
Tebal = 0,05
Lebar = 2,10 m
Panjang = 1,35 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,05 x 2,10 x 1,35 x 7
= 0,99 m³
 Pekerjaan Lantai Kerja Pile Cap PC7
Tinggi = 0,05 m
Lebar = 2,72 m
Panjang = 1,66 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,05 x 2,72 x 1,66 x 7
= 1,58 m³

 Pekerjaan Lantai Kerja Pile Cap PC9


Tinggi = 0,05 m
Lebar = 2,10 m
Panjang = 2,10 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 2,10 x 2,10 x 1
= 0,22 m³
 Pekerjaan Lantai Kerja Pile Cap PC10
Tinggi = 0,05 m
Lebar = 2,85 m
Panjang = 2,10 m
Jumlah = 7 buah
Volume Timbunan Pasir = 0,05 x 2,85 x 2,10 x 7
= 2,09 m³
 Pekerjaan Lantai Kerja Pile Cap PC11
Tinggi = 0,05 m
Lebar = 2,85 m
Panjang = 2,10 m
Jumlah = 4 buah
Volume Timbunan Pasir = 0,05 x 2,85 x 2,10 x 4
= 1,2 m³
 Pekerjaan Lantai Kerja Pile Cap PC13
Tinggi = 0,05 m
Lebar = 3,60 m
Panjang = 2,10 m
Jumlah = 3 buah
Volume Timbunan Pasir = 0,05 x 3,60 x 2,10 x 3
= 1,13 m³

 Pekerjaan Lantai Kerja Tie Biem TB1


Tebal = 0,05 m
Lebar = 0,3 m
Panjang = 250,72 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 0,3 x 250,72 x 1
= 3,76 m³
 Pekerjaan Lantai Kerja Tie Biem TB2
Tebal = 0,05 m
Lebar = 0,3 m
Panjang = 92,06 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 0,3 x 92,06 x 1
= 1,38 m³
 Pekerjaan Lantai Kerja Tie Biem TB3
Tebal = 0,05 m
Lebar = 0,3 m
Panjang = 29,27 m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 0,3 x 29,27 x 1
= 0,44 m³
 Pekerjaan Lantai Kerja Tie Biem TB4
Tebal = 0,05 m
Lebar = 0,25 m
Panjang =7m
Jumlah = 1 buah
Volume Timbunan Pasir = 0,05 x 0,25 x 7 x 1
= 0,0875 m³
A. PEKERJAAN BETON
1. Pekerjaan Kolom Lantai 1
 Kolom 1A 60/60
Jumlah Kolom 1 = 28
Volume = (0,6 x 0,6 x 4,1) x 28
= (1,476) x 28
= 41,328 m3
Pembesian Tumpuan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984 x 1
= 71,616 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
 Kolom 2A 60/50
Jumlah Kolom 2A = 14
Volume = (0,6 x 0,5 x 4,1) x 14
= (1,23) x1 4
= 17,22 m3
Pembesian
Panjang Sengkang = 2,05 m
22 D 22 = Jml Tulangan x BJ x P
= 22 x 2,984 x 1
= 65,648 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 78,2965 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
22 D 22 = Jml Tulangan x BJ x P
= 22x 2,984 x 1
= 65,648 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 74,080 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2

 Kolom 3 50x50
Jumlah Kolom k3 =5
Volume = (0,5 x 0,5 x 4,1) x 5
= (1,025) x 5
= 5,125 m3
Pembesian Tumpuan
Panjang Sengkang = 2,05 m
16 D 22 = Jml Tulangan x BJ x P
= 16 x 2,985 x 1
= 47,76 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,648 kg
Total Pembesian = 60,408 kg
Bekisting = 4 x sisi
= 4 x 0,5
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
16 D 22 = Jml Tulangan x BJ x P
= 16 x 2,985 x 1
= 47,76 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,4323 kg
Total Pembesian = 56,192 kg
Bekisting = 4 x sisi
= 4 x 0,5
= 2 m2

 Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3
Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Kolom KP (13 x 13)


Jumlah Kolom KP = 112
Volume = (0,13 x 0,13x 4,1) x 112
= (0,069) x 112
= 7,760 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-200 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 4,566 kg
Total Pembesian = 7,034 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2

2. Pekerjaan kolom Lantai 2


 Kolom 1A 60/60
Jumlah Kolom 1 =3
Volume = (0,6 x 0,6 x 4,1) x 3
= (1,476) x 3
= 4,428 m3

Pembesian Tumpuan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984 x 1
= 71,616 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2

 Kolom 1B 60/60
Jumlah Kolom 1B = 25
Volume = (0,6 x 0,6 x 4,1) x 25
= (1,476) x 25
= 36,9 m3

Pembesian
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
=59,68 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 72,3285 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
= 59,68 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 68,112 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2

 Kolom 2B 60/50
Jumlah Kolom 2 = 14
Volume = (0,60 x 0,50 x 4,1) x 14
= (1,23) x 14
= 17,22 m3

Pembesian
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,984 x 1
= 53,712 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,648 kg
Total Pembesian = 66,3605 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,985 x 1
= 53,712 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 62,162 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2

 Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3

Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Kolom KP (13 x 13)


Jumlah Kolom KP = 95
Volume = (0,13 x 0,13x 4,1) x95
= (0,069) x 95
= 6,582 m3

Pembesian Tumpuan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-200 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 4,566 kg
Total Pembesian = 7,034 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2

3. Pekerjaan kolom lantai 3


 Kolom 1A 60/60
Jumlah Kolom 1 =3
Volume = (0,6 x 0,6 x 4,1) x 3
= (1,476) x 3
= 4,428 m3

Pembesian Tumpuan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984 x 1
= 71,616 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 84,2645 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
24 D 22 = Jml Tulangan x BJ x P
= 24 x 2,984x 1
= 71,616 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 80,048 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2

 Kolom 1B 60/60
Jumlah Kolom 1B = 25
Volume = (0,6 x 0,6 x 4,1) x 25
= (1,476) x 25
= 36,9 m3
Pembesian
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
=59,68 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,6485 kg
Total Pembesian = 72,3285 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
20 D 22 = Jml Tulangan x BJ x P
= 20 x 2,984 x 1
= 59,68 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 68,112 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,6
= 1,8 m2

 Kolom 2B 60/50
Jumlah Kolom 2 = 14
Volume = (0,60 x 0,50 x 4,1) x 14
= (1,23) x 14
= 17,22 m3
Pembesian
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,984 x 1
= 53,712 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 12,648 kg
Total Pembesian = 66,3605 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2
Pembesian Lapangan
Panjang Sengkang = 2,05 m
18 D 22 = Jml Tulangan x BJ x P
= 18 x 2,985 x 1
= 53,73 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 2,05

= 8,432 kg
Total Pembesian = 62,162 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,5
= 1,7 m2

 Kolom KL
Jumlah Kolom KL =2
Volume = (0,15 x 0,25x 0,4 x 4,1) x 2
= (0,0615) x 2
= 0,123 m3
Pembesian
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,415 kg
Total Pembesian = 30,351 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
12 D 16 = Jml Tulangan x BJ x P
= 12 x 1,578 x 1
= 18,936 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 26,546 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Kolom KP (13 x 13)


Jumlah Kolom KP = 80
Volume = (0,13 x 0,13x 4,1) x 80
= (0,069) x 80
= 5,543 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg
D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2

Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-200 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 4,566 kg

Total Pembesian = 7,034 kg


Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2

4. Pekerjaan kolom lantai dak


 Kolom KP Lantai Dak atap (13 x 13)
Jumlah Kolom KP = 106
Volume = (0,13 x 0,13x 4,1) x 106
= (0,069) x 106
= 7,314 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,088 kg
Total Pembesian = 8,556 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
4 D 10 = Jml Tulangan x BJ x P
= 4 x 0,617 x 1
= 2,468 kg

D 8-200 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 4,565 kg
Total Pembesian = 7,033 kg
Bekisting = (2 x T) + L
= (2 x 0,13) + 0,13
= 0,39 m2

5. Pekerjaan Balok Lantai 2



Balok G1a 30 x 85
Panjang Total = (19 x 10) + (13 x 9) + (2 x 7) + (1 x 6,2) + (2 x 5)
= 337,2 m
Volume = p x l x panjang total
= 0,30 x 0,85 x 337,2 m
= 85,99 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,28 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 34,48 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,28 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2

 Balok G2a 30 x 60
Panjang Total = (7 x 14) + (1 x 6)
= 104 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 104 m
= 18,72 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2

 Balok G3a 30 x 50
Panjang Total = (3 x 6) + (2 x 5)
= 28 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 28 m
= 4,2 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,41 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,41 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2

 Balok G4 30 x 40
Panjang Total = (4 x 3) + (4 x 9)
= 48 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 48 m
= 5,76 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 1,58 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

Pembesian Tumpuan Kanan


Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 1,58 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

 Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg
D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2

 Balok B2 25 x 60
Panjang Total = (11 x 7) + 9
= 86 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 86 m
= 12,9 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,41

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

 Balok B3 25 x 40
Panjang Total = (5 x 4) + (4 x 15) + (3 x 7)
= 101 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 101 m
= 10,1 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Balok B4 20 x 40
Panjang Total = 167,25 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 167,25 m
= 13,38 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2

 Balok B5 15 x 40
Panjang Total = 5,10 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 5,10 m
= 2,19 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2

 Balok B5L 15 x 40
Panjang Total = (5,13 x 2) + 3,00 + 3,46
= 16,72 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 16,72 m
= 1,003 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2

 Balok B2T 25 x 60
Panjang Total = 6,5
Volume = p x l x panjang total
= 0,25 x 0,6 x 6,5 m
= 0,68 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,45 m2

Pembesian Tumpuan Kanan


Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

 Balok B1k 25 x 40
Panjang Total = (4 x 1,7)
= 6,8 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 6,8 m
= 0,68 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\

 Balok B2k 25 x 40
Panjang Total = 2,45
Volume = p x l x panjang total
= 0,25 x 0,4 x 2,45 m
= 0,25 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 3,16 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Balok G1k 30 x 40
Panjang Total = 1,7
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,7 m
= 0,204 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -75 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -100 = x BJ x P. Sengkang

=2x x 0,617 x 1,41

= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

 Balok G2k 30 x 40
Panjang Total = 1,25
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,25 m
= 0,15 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -75 = x BJ x P. Sengkang

=2x x 0,617 x 1,85


= 30,44 kg
Total Pembesian = 60,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

6. Pekerjaan Balok Lantai 3


 Balok G1a 30 x 85
Panjang Total = (19 x 10) + (12 x 9) + (2 x 7)
= 312 m
Volume = p x l x panjang total
= 0,30 x 0,85 x 337,2 m
= 79,56 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 34,47 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2

 Balok G2a 30 x 60
Panjang Total = (7 x 13) + (1 x 6)
= 97 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 97 m
= 17,46 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,895 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 52,68 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2

 Balok G3a 30 x 50
Panjang Total = (3 x 6) + (4 x 5)
= 38 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 38 m
= 5,7 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 38,28 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2

 Balok G4 30 x 40
Panjang Total = (3 x 4) + (4 x 8) + 4,3
= 48,3 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 48,3 m
= 5,79 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
 Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 22,23 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2

 Balok B2 25 x 60
Panjang Total = (11 x 7)
= 77 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 77 m
= 11,55 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,41

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

 Balok B3 25 x 40
Panjang Total = (9 x 4) + 2,15 + (6 x 3)
= 56,15 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 56,15 m
= 5,62 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Balok B4 20 x 40
Panjang Total = 170,6 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 170,6 m
= 13,65 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2

 Balok B5 15 x 40
Panjang Total = 5,10 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 5,10 m
= 2,19 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 21,89 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 29,79 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 21,89 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2

 Balok B5L 15 x 40
Panjang Total = (5,13 x 2) + 3 + 3,46
= 16,72 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 16,72 m
= 1,003 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 37,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 45,59 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 37,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2

 Balok B2T 25 x 60
Panjang Total = 3,4 + 4
Volume = p x l x panjang total
= 0,25 x 0,6 x 7,4 m
= 1,11 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,58 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,45 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,58 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,98 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

 Balok B1k 25 x 40
Panjang Total = (4 x 1,7)
= 6,8 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 6,8 m
= 0,68 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 36,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\

 Balok B2k 25 x 40
Panjang Total = 2,45
Volume = p x l x panjang total
= 0,25 x 0,4 x 2,45 m
= 0,25 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Balok G1k 30 x 40
Panjang Total = 1,7
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,7 m
= 0,204 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -75 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

 Balok G2k 30 x 40
Panjang Total = 1,25
Volume = p x l x panjang total
= 0,3 x 0,4 x 1,25 m
= 0,15 m3

Pembesian Tumpuan
Panjang Sengkang = 1,85 m
7 D 22 = Jml Tulangan x BJ x P
= 7 x 2,985 x 1
= 20,985 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -75 = x BJ x P. Sengkang

=2x x 0,617 x 1,41

= 30,49 kg
Total Pembesian = 60,34 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

7. Pekerjaan Balok Lantai Dak


 Balok G1a 30 x 85
Panjang Total = (2 x 9) + 6,2 + 10
= 34,2 m
Volume = p x l x panjang total
= 0,30 x 0,85 x 34,2 m
= 8,72 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 34,74 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,49 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2

 Balok G1b 30 x 85
Panjang Total = (18 x 10) + (11 x 9) + (5 x 7) + (2 x 6) + (2 x 5)
= 336 m
Volume = p x l x panjang total
= 0,30 x 0,85 x 336 m
= 85,68 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,49 kg
Total Pembesian = 57,3 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85
= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 1,58 x 1
= 8,955 kg

2 D 10-75 = x BJ x P. Sengkang

= 2x x 0,617 x 1,85

= 30,49 kg
Total Pembesian = 57,3 kg
Bekisting = (2 x T) + L
= (2 x 0,85) + 0,30
= 2 m2

 Balok G2b 30 x 60
Panjang Total = (7 x 11)
= 77 m
Volume = p x l x panjang total
= 0,30 x 0,60 x 77 m
= 13,86 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
2D 10-100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 46,71 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,3
= 1,5 m2

 Balok G3b 30 x 50
Panjang Total = (2 x 6) + (2 x 5)
= 22 m
Volume = p x l x panjang total
= 0,30 x 0,50 x 22 m
= 3,3 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 31,49 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,5) + 0,3
= 1,3 m2

 Balok G4 30 x 40
Panjang Total = (3 x 4) + (4 x 9) + 4,3
= 52,3 m
Volume = p x l x panjang total
= 0,30 x 0,40 x 52,3 m
= 6,28 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg
4 D 22 = Jml Tulangan x BJ x P
= 4 x 2,985 x 1
= 11,94 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 28,51 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 22 = Jml Tulangan x BJ x P
= 5 x 2,985 x 1
= 14,925 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 35,29 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

 Balok B1 25 x 75
Panjang Total = (10 x 9)
= 90 m
Volume = p x l x panjang total
= 0,25 x 0,75 x 90 m
= 16,875 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,75) + 0,25
= 1,75 m2
 Balok B2 25 x 60
Panjang Total = (13 x 7)
= 91 m
Volume = p x l x panjang total
= 0,25 x 0,60 x 91 m
= 13,65 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

Pembesian Tumpuan Kanan


Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,6) + 0,25
= 1,45 m2

 Balok B3 25 x 40
Panjang Total = (15 x 4) + (6 x 3)
= 78 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 78 m
= 7,8 m3

Pembesian Tumpuan Kiri


Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
4 D 19 = Jml Tulangan x BJ x P
= 4 x 2,223 x 1
= 8,892 kg

D 10-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 20,95 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg
D 10-100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2

 Balok B4 20 x 40
Panjang Total = 147 m
Volume = p x l x panjang total
= 0,2 x 0,4 x 147 m
= 11,76 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2
Pembesian Tumpuan Kanan
Panjang Sengkang = 1,85 m
4 D 16 = Jml Tulangan x BJ x P
= 4 x 1,578 x 1
= 6,32 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 18,61 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,2
= 1 m2

 Balok B5L 15 x 40
Panjang Total = 195,42 m
Volume = p x l x panjang total
= 0,15 x 0,4 x 195,42 m
= 11,73 m3
Pembesian Tumpuan Kiri
Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg

D 8-150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 6,09 kg
Total Pembesian = 13,99 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2

Pembesian Tumpuan Kanan


Panjang Sengkang = 1,85 m
3 D 16 = Jml Tulangan x BJ x P
= 3 x 1,578 x 1
= 4,74 kg
2 D 16 = Jml Tulangan x BJ x P
= 2 x 1,578 x 1
= 3,16 kg

D 8 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 9,13 kg
Total Pembesian = 17,03 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,15
= 0,95 m2
 Balok B1k 25 x 40
Panjang Total = 37 m
Volume = p x l x panjang total
= 0,25 x 0,4 x 37 m
= 3,7 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -100 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 11,41 kg
Total Pembesian = 26,97 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
5 D 19 = Jml Tulangan x BJ x P
= 5 x 2,223 x 1
= 11,115 kg
2 D 19 = Jml Tulangan x BJ x P
= 2 x 2,223 x 1
= 4,446 kg

D 10 -150 = x BJ x P. Sengkang

= x 0,617 x 1,85

= 7,61 kg
Total Pembesian = 23,17 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,25
= 1,05 m2\

 Balok G1k 30 x 40
Panjang Total = 29 m
Volume = p x l x panjang total
= 0,3 x 0,4 x 29 m
= 3,48 m3
Pembesian Tumpuan
Panjang Sengkang = 1,85 m
8 D 22 = Jml Tulangan x BJ x P
= 8 x 2,985 x 1
= 23,88 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -75 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 30,44 kg
Total Pembesian = 63,27 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2
Pembesian Lapangan
Panjang Sengkang = 1,85 m
6 D 22 = Jml Tulangan x BJ x P
= 6 x 2,985 x 1
= 17,91 kg
3 D 22 = Jml Tulangan x BJ x P
= 3 x 2,985 x 1
= 8,955 kg

2D 10 -100 = x BJ x P. Sengkang

=2x x 0,617 x 1,85

= 22,83 kg
Total Pembesian = 49,69 kg
Bekisting = (2 x T) + L
= (2 x 0,4) + 0,3
= 1,1 m2

8. Pekerjaan Plat Lantai


 Lantai 1
Luas Lantai = 1460 m2
Volume = 1460 m2 x 0,1 m
= 146 m3
 Lantai 2
Luas Lantai 2 = 1460 m2
Luas Tangga A = 17,95 m2
Luas Tangga B = 17,85 m2
Jumlah = 1424,2 m2
Volume = 1424,2 m2 x 0,1 m2
= 142,2 m3
 Lantai 3
Luas Lantai 3 = 1460 m2
Luas Tangga A = 17,95 m2
Luas Tangga B = 17,85 m2
Void = 189 m2
Jumlah = 1235,2 m2
Volume = 1235,2 m2 x 0,1 m2
= 123,5 m3

Luas Lantai Dak = 1460 m2
Luas Lantai = 1460 m2
Volume = 1460 m2 x 0,1 m
= 146 m3
9. Pekerjaan Tangga
 Anak Tangga
Jumlah Anak Tangga = 22
Tinggi Anak Tangga = 0,18 m
Lebar Anak Tangga = 1,4 m
Lebar Pijakan = 0,3 m
Bordes = 9,65 m2

 Plat Tangga
Tebal = 0,15 m
Lebar = 1,4 m
Panjang = 3,6 m
Volume = (0,15 x 1,4 x 3,6) x 2
= 0,756 m3 x 2
= 1,512 m3
Penulangan
Pembesian Bordes

Memanjang = Jml Lapisan x

=2x

= 3,286 kg

Melintang = Jml Lapisan x

=2x

= 55,568 kg
Pembesian Tangga

Memanjang = Jml Lapisan x


=2x

= 29,573 kg

Melintang = Jml Lapisan x

=2x

= 6,174 kg
Pembesian Anak Tangga
Tulangan 1 = L x BJ x Jml Anak Tangga
= 1,4 x 0,617 x 22
= 19,004 kg

Tulangan 2 = x Jml Anak Tangga

= x 22

= 237,709 kg

C. PEKERJAAN PASANGAN
Pekerjaan Pasangan Batu Bata
1. LANTAI 1

 Luas Dinding Lantai 1 = x tinggi dinding

= x 4,1
= 6457 m2
 Luas CW 1
Jumlah CW =1
Luas CW = 2,1 x 4,1 x 1
= 8,61 m2
Total Luas CW 1 = 8,61 m2

 Luas CW 2
Jumlah CW =1
Luas CW = 3,08 x 4,1 x 1
= 12,63 m2
Total Luas CW 2 = 12,63 m2
 Luas CW 3
Jumlah CW =3
Luas CW = 0,8 x 4,1 x 3
= 9,84 m2
Total Luas CW 3 = 9,84 m2

 Luas CW 4
Jumlah CW =3
Luas CW4 = 0,8 x 4,1 x 3
= 9,84 m2
Total Luas CW = 9,84 m2
 Luas CW 5
Jumlah CW =5
Luas CW = 0,8 x 4.1 x 5
= 16,4 m2
Total Luas CW 5 = 16,4 m2

 Luas CW 6
Jumlah CW =1
Luas CW = 14 x 0,8 x 1
= 11,2 m2
Total Luas CW 6 = 11,2 m2

 Luas CW 7
Jumlah CW =3
Luas CW = 0,8 x 10,4 x 3
= 24,96 m2
Total Luas CW 7 = 24,96 m2

 Luas CW 8
Jumlah CW =1
Luas CW = 10,62 x 2,78 x 1
= 29,5 m2
Total Luas CW 8 = 29,5 m2

 Luas CW 9
Jumlah CW =1
Luas CW = 9,4 x 11,35 x 1
= 106,69 m2
Total Luas CW 9 = 106,69 m2

 Luas FD1
Jumlah =3
Luas = 9,5 x 3 x 3
= 85,5 m2
Total Luas = 85,5 m2

 Luas F3
Jumlah =1
Luas = 4,2 x 4,1 x 1
= 17,22 m2
Total Luas = 17,22 m2

 Luas F4
Jumlah =1
Luas = 5,63 x 3 x 1
= 16,89 m2
Total Luas = 16,89 m2

 Luas Pintu Utama


P01 Jumlah Pintu =1
Luas Pintu = 9,46 x 2,9 x 1
= 27,43 m2
Total Luas Pintu = 27,43 m2

 Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,68 x 2,7) x 2
= 9,07 m2
Total Luas Pintu = 9,07 m2

 Luas Pintu PD 2
PD 2 Jumlah Pintu =1
Luas Pintu = 1,68 x 2,14 x 1
= 3,59 m2
Total Luas Pintu = 3,59 m2

 Luas Pintu PF 1
PF 1 Jumlah Pintu =1
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2

 Luas Pintu PF 2
PF 2 Jumlah Pintu =1
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2

 Luas Pintu PF 3
PF 3 Jumlah Pintu =1
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2

 Luas Pintu PF4


PF4 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2

 Luas Pintu P1
P PS Jumlah Pintu =2
Luas Pintu = 2,7 x 0,88 x 2
= 4,7 m2
Total Luas Pintu = 4,7 m2

 Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,88 x 4
= 4,7 m2
Total Luas Pintu = 9,5 m2

 Luas Pintu P2a


P2a Jumlah Pintu =3
Luas Pintu PS = 0,78 x 2,7 x 3
= 6,32 m2
Total Luas Pintu = 6,32 m2
 Luas Pintu P4
P4 Jumlah Pintu =1
Luas Pintu = 0,98 x 2,1 x 1
= 2,05 m2
Total Luas Pintu = 2,05 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2

Total Luas Dinding Lantai 1 = L. Lantai 1 - L. CW - L. Pintu


= 6457 – 349,28 – 115,13 m2
= 5992,59 m2
Plesteran Lantai 1 = 5992,59 x 2
= 11985,18 m2
Acian Lantai 1 = 5992,59 x 2
= 11985,18 m2
Pek. Cat Dinding Lantai 1 = 5992,59 x 2
= 11985,18 m2

LANTAI 2

 Luas Dinding Lantai 2 = x tinggi dinding

= x 4,1
= 6457 m2

 Luas CW 10
Jumlah CW =1
Luas CW = 7,23 x 7,25 x 1
Total Luas CW = 52,42 m2

 Luas CW11
Jumlah CW =1
Luas CW = 7,15 x 2,45 x 1
Total Luas CW = 17,52 m2
 Luas CW12
Jumlah CW =1
Luas CW = 10,6 x 7,25 x1
Total Luas CW = 76,85 m2

 Luas CW13
Jumlah CW =1
Luas CW = 9,4 x 3x1
Total Luas CW = 28,2 m2

 Luas CW14
Jumlah CW =1
Luas CW = 6,05 x 3,7 x1
Total Luas CW = 22,38 m2

 Luas CW 15
Jumlah CW =1
Luas CW = 23,8 x 7,25 x 1
Total Luas CW = 172,55 m2

 Luas FD3
Jumlah =1
Luas = 6,4 x 3 x 1
= 19,2 m2
Total Luas = 19,2 m2

 Luas FD4
Jumlah =1
Luas = 3,45 x 3 x 1
= 10.35 m2
Total Luas = 10,35 m2

 Luas F5
Jumlah =4
Luas = 3,3 x 3 x 4
= 39,6 m2
Total Luas = 39,6 m2

 Luas F6
Jumlah =1
Luas = 2,7 x 3 x 1
= 8,1 m2
Total Luas = 8,1 m2

 Luas F7
Jumlah =1
Luas = 6,3 x 3 x 1
= 18,9 m2
Total Luas = 18,9 m2

 Luas F8
Jumlah =2
Luas = 2,15 x 3 x 2
= 12,9 m2
Total Luas = 12,9 m2
 Luas F9
Jumlah =1
Luas = 1,94 x 3 x 1
= 5,82 m2
Total Luas = 5,82 m2

 Luas F10
Jumlah =1
Luas = 6,65 x 3 x 1
= 19,95 m2
Total Luas = 19,95 m2

 Luas F11
Jumlah =1
Luas = 2,77 x 3 x 1
= 8,31 m2
Total Luas = 8,31 m2

 Luas F12
Jumlah =1
Luas = 1,87 x 3 x 1
= 5,61 m2
Total Luas = 5,61 m2
 Luas F13
Jumlah =1
Luas = 9,4 x 3 x 1
= 28,2 m2
Total Luas = 28,2 m2

 Luas F14
Jumlah =1
Luas = 4,77 x 3 x 1
= 14,31 m2
Total Luas = 14,31 m2

 Luas F15
Jumlah =1
Luas = 4,4 x 3 x 1
= 13,2 m2
Total Luas = 13,2 m2

 Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,68 X 2,7) X 2
= 9,07 m2
Total Luas Pintu = 9,07 m2

 Luas Pintu PF 8
PF8 Jumlah Pintu =2
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2

 Luas Pintu PF 9
PF9 Jumlah Pintu =4
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2

 Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2

 Luas Pintu PF11


PF11 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2

 Luas Pintu PF12


PF12 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2

 Luas Pintu PF13


PF13 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2

 Luas Pintu PF14


PF4 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2

 Luas Pintu PF15


PF15 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2

 Luas Pintu P1
P1 Jumlah Pintu =1
Luas Pintu = 2,7 x 0,88 x 1
= 2,37 m2
Total Luas Pintu = 2,37m2

 Luas Pintu P2
P2 Jumlah Pintu =5
Luas Pintu = 2,7 x 0,88 x 5
= 11,88 m2
Total Luas Pintu = 11,88 m2

 Luas Pintu P5
P5 Jumlah Pintu =2
Luas Pintu = 0,98 x 2,1 x 2
= 4,11 m2
Total Luas Pintu = 4,11 m2

 Luas Pintu P2a


P2a Jumlah Pintu =2
Luas Pintu = 0,78 x 2,7 x 2
= 4,21 m2
Total Luas Pintu = 4,21 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2

Total Luas Dinding Lantai 2 = L. Lantai 2 - L. Pintu - L. CW


= 6457 - 135,21 - 574,37 m2
= 5747,42 m2
Plesteran Lantai 2 = 5747,42 x 2
= 11494,84 m2
Acian Lantai 2 = 5747,42 x 2
= 11494,84 m2
Pek. Cat Lantai 2 = 5747,42 x 2
= 11494,84 m2

LANTAI 3

 Luas Dinding Lantai 3 = x tinggi dinding

= x 4,1
= 6457 m2
 Luas CW 13
Jumlah CW =1
Luas CW = 9,4 x 3 x 1
Total Luas CW = 28,2 m2

 Luas FD1
Jumlah =1
Luas = 6,4 x 3 x 1
= 19,2 m2
Total Luas = 19,2 m2

 Luas F8
Jumlah =1
Luas = 2,15 x 3 x 1
= 6,45 m2
Total Luas = 6,45 m2
 Luas F9
Jumlah =2
Luas = 1,94 x 3 x 2
= 11,64 m2
Total Luas = 11,64 m2

 Luas F11
Jumlah =1
Luas = 2,78 x 3 x 1
= 8,34 m2
Total Luas = 8,34 m2

 Luas F13
Jumlah =1
Luas = 9,4 x 3 x 1
= 28,2 m2
Total Luas = 28,2 m2

 Luas F14
Jumlah =1
Luas = 4,78 x 3 x 1
= 14,34 m2
Total Luas = 14,34 m2
 Luas F16
Jumlah =1
Luas =3 x3 x1
= 9 m2
Total Luas = 9 m2

 Luas F17
Jumlah =1
Luas = 5,15 x 3 x 1
= 15,45 m2
Total Luas = 15,45 m2

 Luas F18
Jumlah =1
Luas = 6,87 x 3 x 1
= 20,61 m2
Total Luas = 20,61m2

 Luas F19
Jumlah =2
Luas = 8,4 x 3 x 2
= 50,4 m2
Total Luas = 50,4 m2

 Luas Pintu PD 1
PD 1 Jumlah Pintu =1
Luas Pintu Utama = (1,68 X 2,7) X 1
= 4,54 m2
Total Luas Pintu = 4,54 m2

 Luas Pintu PF 8
PF 1 Jumlah Pintu =2
Luas Pintu = 3,14 x 3 x 2
= 18,84 m2
Total Luas Pintu = 18,84 m2

 Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,91 x 3 x 2
= 17,46 m2
Total Luas Pintu = 17,46 m2

 Luas Pintu PF11


PF11 Jumlah Pintu =1
Luas Pintu = 7,3 x 3 x 1
= 21,9 m2
Total Luas Pintu = 21,9 m2

 Luas Pintu PF12


PF12 Jumlah Pintu =1
Luas Pintu = 7,18 x 3 x 1
= 21,54 m2
Total Luas Pintu = 21,54 m2

 Luas Pintu PF13


PF13 Jumlah Pintu =1
Luas Pintu = 2,23 x 3 x 1
= 6,69 m2
Total Luas Pintu = 6,69 m2

 Luas Pintu PF17


PF17 Jumlah Pintu =1
Luas Pintu = 5,08 x 3 x 1
= 15,24 m2
Total Luas Pintu = 15,24 m2

 Luas Pintu PF18


PF18 Jumlah Pintu =1
Luas Pintu = 1,98 x 3 x 1
= 5,94 m2
Total Luas Pintu = 5,94 m2

 Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,88 x 4
= 9,5 m2
Total Luas Pintu = 9,5 m2

 Luas Pintu P6
P6 Jumlah Pintu =1
Luas Pintu = 1,48 x 2,1 x 1
= 3,1 m2
Total Luas Pintu = 3,1 m2

 Luas Pintu P2a


P2a Jumlah Pintu =2
Luas Pintu = 0,78 x 2,7 x 2
= 4,21 m2
Total Luas Pintu = 4,21 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,58 x 2,14 x 4
= 4,96 m2
Total Luas Pintu = 4,96 m2

Total Luas Dinding Lantai 3 = L. Lantai 3 - L. Pintu - L. CW


= 6457 – 133,92 – 211,83
= 6111,25 m2
Plesteran Lantai 3 = 6111,25 x 2
= 12222,5 m2
Acian Lantai 3 = 6111,25 x 2
= 12222,5 m2
Pek. Cat Lantai 3 = 6111,25 x 2
= 12222,5 m2

1. Pekerjaan Daun Pintu Dan Daun Jendela


LANTAI 1
 Luas Pintu Utama
P01 Jumlah Pintu =1
Luas Pintu = 9,46 x 2,9 x 1
= 27,43 m2
Total Luas Pintu = 27,43 m2

 Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,6 x 2,7) x 2
= 8,64 m2
Total Luas Pintu = 8,64 m2
 Luas Pintu PD 2
PD 2 Jumlah Pintu =1
Luas Pintu = 1,6 x 2,14 x 1
= 3,42 m2
Total Luas Pintu = 3,42 m2

 Luas Pintu PF 1
PF 1 Jumlah Pintu =1
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2

 Luas Pintu PF 2
PF 2 Jumlah Pintu =1
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2

 Luas Pintu PF 3
PF 3 Jumlah Pintu =1
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2

 Luas Pintu PF4


PF4 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2

 Luas Pintu P1
P PS Jumlah Pintu =2
Luas Pintu = 2,7 x 0,8 x 2
= 4,32 m2
Total Luas Pintu = 4,32 m2

 Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,8 x 4
= 8,64 m2
Total Luas Pintu = 8,64 m2

 Luas Pintu P4
P4 Jumlah Pintu =1
Luas Pintu = 0,9 x 2,1 x 1
= 2,05 m2
Total Luas Pintu = 1,89 m2

 Luas Pintu P2a


P2a Jumlah Pintu =3
Luas Pintu PS = 0,7 x 2,7 x 3
= 5,67 m2
Total Luas Pintu = 5,67 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2

LANTAI 2
 Luas Pintu PD 1
PD 1 Jumlah Pintu =2
Luas Pintu Utama = (1,6 x 2,7) x 2
= 8,64 m2
Total Luas Pintu = 8,64 m2

 Luas Pintu PF 8
PF8 Jumlah Pintu =2
Luas Pintu = 4,63 x 3 x 1
= 13,89 m2
Total Luas Pintu = 13,89 m2

 Luas Pintu PF 9
PF9 Jumlah Pintu =4
Luas Pintu = 4,4 x 3 x 1
= 13,2 m2
Total Luas Pintu = 13,2 m2

 Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,75 x 3 x 1
= 8,25 m2
Total Luas Pintu = 8,25 m2

 Luas Pintu PF11


PF11 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2
 Luas Pintu PF12
PF12 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2

 Luas Pintu PF13


PF13 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2

 Luas Pintu PF14


PF4 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,27 m2

 Luas Pintu PF15


PF15 Jumlah Pintu =1
Luas Pintu = 4,25 x 3 x 1
= 12,75 m2
Total Luas Pintu = 12,75 m2
 Luas Pintu P1
P1 Jumlah Pintu =1
Luas Pintu = 2,7 x 0,8 x 1
= 2,16 m2
Total Luas Pintu = 2,16 m2

 Luas Pintu P2
P2 Jumlah Pintu =5
Luas Pintu = 2,7 x 0,8 x 5
= 10,8 m2
Total Luas Pintu = 10,8 m2

 Luas Pintu P5
P5 Jumlah Pintu =2
Luas Pintu = 0,9 x 2,1 x 2
= 3,78 m2
Total Luas Pintu = 3,78 m2

 Luas Pintu P2a


P2a Jumlah Pintu =2
Luas Pintu = 0,7 x 2,7 x 2
= 3,78 m2
Total Luas Pintu = 3,78 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2

LANTAI 3
 Luas Pintu PD 1
PD 1 Jumlah Pintu =1
Luas Pintu Utama = (1,6 x 2,7) x 1
= 4,32 m2
Total Luas Pintu = 4,32 m2

 Luas Pintu PF 8
PF 1 Jumlah Pintu =2
Luas Pintu = 3,14 x 3 x 2
= 18,84 m2
Total Luas Pintu = 18,84 m2

 Luas Pintu PF 10
PF10 Jumlah Pintu =2
Luas Pintu = 2,91 x 3 x 2
= 17,46 m2
Total Luas Pintu = 17,46 m2

 Luas Pintu PF11


PF11 Jumlah Pintu =1
Luas Pintu = 7,3 x 3 x 1
= 21,9 m2
Total Luas Pintu = 21,9 m2

 Luas Pintu PF12


PF12 Jumlah Pintu =1
Luas Pintu = 7,18 x 3 x 1
= 21,54 m2
Total Luas Pintu = 21,54 m2

 Luas Pintu PF13


PF13 Jumlah Pintu =1
Luas Pintu = 2,23 x 3 x 1
= 6,69 m2
Total Luas Pintu = 6,69 m2

 Luas Pintu PF17


PF17 Jumlah Pintu =1
Luas Pintu = 5,08 x 3 x 1
= 15,24 m2
Total Luas Pintu = 15,24 m2

 Luas Pintu PF18


PF18 Jumlah Pintu =1
Luas Pintu = 1,98 x 3 x 1
= 5,94 m2
Total Luas Pintu = 5,94 m2

 Luas Pintu P2
P2 Jumlah Pintu =4
Luas Pintu = 2,7 x 0,8 x 4
= 8,64 m2
Total Luas Pintu = 8,64 m2

 Luas Pintu P6
P6 Jumlah Pintu =1
Luas Pintu = 1,4 x 2,1 x 1
= 2,94 m2
Total Luas Pintu = 2,94 m2

 Luas Pintu P2a


P2a Jumlah Pintu =2
Luas Pintu = 0,7 x 2,7 x 2
= 3,78 m2
Total Luas Pintu = 3,78 m2

 Luas Pintu PS
PS Jumlah Pintu =4
Luas Pintu = 0,5 x 2,14 x 4
= 4,28 m2
Total Luas Pintu = 4,28 m2

2. Pekerjaan Plafond
Luas Langit-Langit Lantai 1 = luas lantai 2
= 1424,2 m2
Luas Langit-Langit Lantai 2 = luas lantai 3
` = 1235,2 m2
Luas Langit-Langit Lantai 3 = luas dak
= 1460 m2

6. PEKERJAAN KERAMIK
Lantai Keramik 60 x 60 luas lantai 1 sampai 3 = 3924,4 m²
Lantai Keramik 30 x 30 luas = 190 m2

7. PEKERJAAN INSTALASI
Pekerjaan Instalasi Air
Lantai 1
 Closet duduk = 5 bh
 Kran 0,5" = 6 bh
 Shower + kran = 18 bh
 Floor Drain Stainless = 28 bh
 Tanda Toilet Male / Female = 2 bh
 Kitchen Zink + Kran = 2 bh
 Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
 Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
 Pipa PPR 32mm (1”) Klas PN 10 = 74 m
 Material Bantu = 1 ls
 Pipa PVC Tipe AW 3” = 84 m
 Pipa PVC Tipe AW 4” = 24 m
 Pipa PVC Tipe AW 6” = 25 m

Lantai 2
 Closet duduk = 9 bh
 Kran 0,5" = 9 bh
 Shower + kran = 18 bh
 Floor Drain Stainless = 28 bh
 Tanda Toilet Male / Female = 2 bh
 Kitchen Zink + Kran = 2 bh
 Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
 Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
 Pipa PPR 32mm (1”) Klas PN 10 = 74 m
 Material Bantu = 1 ls
 Pipa PVC Tipe AW 3” = 84 m
 Pipa PVC Tipe AW 4” = 24 m

Lantai 3
 Closet duduk = 8 bh
 Kran 0,5" = 8 bh
 Shower + kran = 18 bh
 Floor Drain Stainless = 28 bh
 Tanda Toilet Male / Female = 2 bh
 Kitchen Zink + Kran = 2 bh
 Vanity Counter 120 x 60 cm utk Kitchen Zink = 2 bh
 Pipa PPR 25mm (3/4”) Klas PN 10 = 132 m
 Pipa PPR 32mm (1”) Klas PN 10 = 74 m
 Material Bantu = 1 ls
 Pipa PVC Tipe AW 3” = 84 m
 Pipa PVC Tipe AW 4” = 24 m

Pekerjaan Instalasi Listrik


1. LANTAI 1
Saklar dan Stop Kontak
 Pas. Saklar Tunggal = 28 bh
 Pas. Saklar Ganda = 14 bh
 Pas. Saklar Putar = 3 bh
 Pas. Greed Switch 8 Gang = 1 bh
 Pas. Stop Kontak 250 W = 22 bh
Titik Instalasi
 Kabel NYM 3 x 2,5 mm + Konduit PVC = 99 titik
 Stop Kontak, NYM 3 x 2,5 mm2 + Konduit PVC = 38 titik
Fixtures Lampu Lengkap Armatur
 Pas. Lampu Baret Emergency 32 Watt = 3 bh
 Pas. Lampu Downlight LED 7 W = 6 bh
 Pas. Lampu Downlight LED EMERGENCY 7 W = 3 bh
 Pas. Lampu Downlight DL CFL 8 W = 84 bh
 Pas. Lampu Exit 10 W = 3 bh
 Pas. Lampu Taman GL SQ 135 18 W = 16 bh
Exhaust Fan 1183.04 CFM
Kipas Angin = 8 bh
Cealing Fan 37 W = 8 bh

2. LANTAI 2
Saklar dan Stop Kontak
 Pas. Saklar Tunggal = 28 bh
 Pas. Saklar Ganda = 14 bh
 Pas. Saklar Putar = 3 bh
 Pas. Greed Switch 8 Gang = 1 bh
 Pas. Stop Kontak 250 W = 22 bh
Titik Instalasi
 Kabel NYM 3 x 2,5 mm + Konduit PVC = 97 titik
 Stop Kontak, NYM 3 x 2,5 mm2 + Konduit PVC = 46 titik
Fixtures Lampu Lengkap Armatur
 Pas. Lampu Baret Emergency 32 Watt = 3 bh
 Pas. Lampu Downlight LED 7 W = 6 bh
 Pas. Lampu Downlight LED EMERGENCY 7 W = 3 bh
 Pas. Lampu Downlight DL CFL 8 W = 82 bh
 Pas. Lampu Exit 10 W = 3 bh
Exhaust Fan 1183.04 CFM
Kipas Angin = 8 bh
Cealing Fan 37 W = 8 bh

3. LANTAI 3
Saklar dan Stop Kontak
 Pas. Saklar Tunggal = 28 bh
 Pas. Saklar Ganda = 14 bh
 Pas. Saklar Putar = 3 bh
 Pas. Greed Switch 8 Gang = 1 bh
 Pas. Stop Kontak 250 W = 22 bh
Titik Instalasi
 Kabel NYM 3 x 2,5 mm + Konduit PVC = 97 titik
 Stop Kontak, NYM 3 x 2,5 mm2 + Konduit PVC = 46 titik
Fixtures Lampu Lengkap Armatur
 Pas. Lampu Baret Emergency 32 Watt = 3 bh
 Pas. Lampu Downlight LED 7 W = 6 bh
 Pas. Lampu Downlight LED EMERGENCY 7 W = 3 bh
 Pas. Lampu Downlight DL CFL 8 W = 82 bh
 Pas. Lampu Exit 10 W = 3 bh
Exhaust Fan 1183.04 CFM
Kipas Angin = 8 bh
Cealing Fan 37 W = 8 bh