Assignment 2 – Project Crashing

Questions:

1. Perform the activities crashing until it can no longer be crashed. What is the total cost?
Answer:

The total cost after all the activities have been crashed is $7,200.00 (including finished early bonuses) or $6,575.00 (excluding finished early

bonuses).

Note: Both methods produced the same result (please refer to the attachment below)

2. If there is a bonus of $125 per day for finishing early, what activities would be crashed, and how fast would the project be completed?
Answer:

Activities B, D, E, F, G are the activities that can be crashed. This project can be finished 5 days earlier to 20 days from the expected project

duration, which is 25 days. The total finished early bonuses earned is at $625.00 (5 days x $125.00). However, by crashing the whole project, the

overall cost of the project will increase by $5,125 from $2,075 to $7,200 which is an increase of nearly 247%.

In my opinion, cost increment for project crashing that is too high which is over 200%, is not viable to proceed, entirely. The most acceptable

cost and the number of days shorten is only for 1 day, which in activity E (from initial 3 days to 2 days duration), with the crash cost of $300 and

shorten the entire project to 24 days. The overall project will cost $2,500 including $125 for 1 day finished early bonus.

P a g e 1|9
Assignment 2 – Project Crashing

METHOD 1A

P a g e 2|9
Assignment 2 – Project Crashing

METHOD 1A (CONTINUED)

P a g e 3|9
Assignment 2 – Project Crashing

METHOD 1B

P a g e 4|9
Assignment 2 – Project Crashing

METHOD 1B (CONTINUED)

P a g e 5|9
Assignment 2 – Project Crashing

METHOD 1B (CONTINUED)

P a g e 6|9
Assignment 2 – Project Crashing

METHOD 2

P a g e 7|9
Assignment 2 – Project Crashing

P a g e 8|9
Assignment 2 – Project Crashing

P a g e 9|9