Circuit Breaker- Failures

Gyanendra Sharma
Make wise CBs in service

Make Population
ABB 650 nos.
CGL 500 nos.
M&G 50 nos.
BHEL 300 nos
Alstom 140 nos.
Total 1640 nos.

03/27/2021 Circuit Breaker Failures 2


Performance of CBs

2 .5
2
1 .5
%age CB
failures

1
0 .5
0

Y EA R

03/27/2021 Circuit Breaker Failures 3


400kV BHEL CB

03/27/2021 Circuit Breaker Failures 4


Internal Details of Interrupter

03/27/2021 Circuit Breaker Failures 5


420kV INTERRUPTER CLOSING
OPERATION

03/27/2021 Circuit Breaker Failures 6


Operating Links

03/27/2021 Circuit Breaker Failures 7


BHEL make CB Operating
Mechanism

03/27/2021 Circuit Breaker Failures 8


420 kV SF6 GCB
With SP/Pneumatic Mechanism
03/27/2021 Circuit Breaker Failures 9
INTERRUPTER DESIGN

03/27/2021 Circuit Breaker Failures 10


Main and Arcing Contacts

03/27/2021 Circuit Breaker Failures 11


Driving Mechanism

03/27/2021 Circuit Breaker Failures 12


Reasons of CB Failures in
POWERGRID
MECHANICAL - 74%
(OPERATING COMPONENTS FAILURES)

ELECTRICAL - 16%
(DIELECTRIC FAILURE)

OTHERS - 10%

03/27/2021 Circuit Breaker Failures 13


Circuit Breaker Failures

• Due to
manufacturing
defects
• Due to design
defects

03/27/2021 Circuit Breaker Failures 14


CB failure - Helicoil problem

03/27/2021 Circuit Breaker Failures 15


Mechanical disengagement of moving
contact assembly from helicoil joint

03/27/2021 Circuit Breaker Failures 16


PIR ASSEMBLY FAILURES
• MECHANICAL • BLASTING OF CB
BREAKAGE OF PTFE
ROD DUE TO PIR
PROBLEM

03/27/2021 Circuit Breaker Failures 17


Bending of PIR pull rod

03/27/2021 Circuit Breaker Failures 18


PIR ASSEMBLY FAILURES
• PIR FIXED • BREAKAGE OF
CONTACT PTFE ROD FROM
JAMMING METALLIC TIP

03/27/2021 Circuit Breaker Failures 19


INTERRUPTER ASSEMBLY

03/27/2021 Circuit Breaker Failures 20


Condition Monitoring through DCRM

03/27/2021 Circuit Breaker Failures 21


Healthy Contacts of CB after 16
years

03/27/2021 Circuit Breaker Failures 22


Contact Condition of CB after 16 Years

03/27/2021 Circuit Breaker Failures 23


Some CB contacts even after 16 years of
service

03/27/2021 Circuit Breaker Failures 24


Eroded finger contact after 7-8 years
Old

New

03/27/2021 Circuit Breaker Failures 25


PROBLEMS IN CB AFTER 7-8 YEARS

03/27/2021 Circuit Breaker Failures 26


NEED FOR DCRM

 During normal contact resistance


measurement, healthiness of main
contacts is evaluated
Req = R*r/(R+r)= r/(1+r/R), r = Main contact
R = Arcing contacts
 DCRM signatures/finger prints indicate
true condition of CB arcing contacts.
 Arcing contact play vital role during CB
operation

03/27/2021 Circuit Breaker Failures 27


DYNAMIC CONTACT RESISTANCE
MEASUREMENT (DCRM)
 CONTACT RESISTANCE MEASUREMENT DURING
CLOSING AND TRIPPING OPERATION. C-O DELAY
TIME ABOUT 300MS.

 100 AMP CURRENT IS INJECTED THROUGH CB


CONTACTS.

 VOLTAGE DROP AND CURRENT IS MEASURED TO


COMPUTE CONTACT RESISTANCE.

 VARIATION IN FINGER PRINT OF DCRM INDICATE


PROBLEM IN ARCING AND MAIN CONTACTS.

03/27/2021 Circuit Breaker Failures 28


Basic connection arrangement for
DCRM Measurement

03/27/2021 Circuit Breaker Failures 29


DCRM can detect…
• Erosion of Arcing Contact
• Erosion of main contact
• Contact misalignments
• Contact wipe of main and arcing
contact
• Main & arcing contact resistance
• Healthiness of damping system
• Contact travel & speed

03/27/2021 Circuit Breaker Failures 30


BHEL Moving Contact

03/27/2021 Circuit Breaker Failures 31


Contact Configuration

03/27/2021 Circuit Breaker Failures 32


Operating Links

03/27/2021 Circuit Breaker Failures 33


Tie Rod

Loosening of Tie Rod

03/27/2021 Circuit Breaker Failures 34


Driving Mechanism

03/27/2021 Circuit Breaker Failures 35


Contact Travel and Insertion Details
Travel Total Main Arcing
Contact
Contact Contact Insertion
Insertion Insertion
CGL 230mm/ 28mm 12mm 16mm
140mm
BHEL 242/ 54 34 20
130mm
ABB 200mm 50mm 20mm 30mm
AREVA 180mm 45mm 25mm 20mm

03/27/2021 Circuit Breaker Failures 36


Contact insertion/ speed

Make Trip velocity Close


velocity
ABB 6-8 m/sec 3-4 m/sec

CGL 5-6 m/sec 3-4 m/sec


BHEL 6-8 m/sec 3-4 m/sec
AREVA 5-8 m/sec 2-4 m/sec

03/27/2021 Circuit Breaker Failures 37


Failure of PIR at Trichy
• Details
• PIR link failed
• Observations
• Reasons

03/27/2021 Circuit Breaker Failures 38


03/27/2021 Circuit Breaker Failures 39