You are on page 1of 39

Bus bar & LBB Protection

03/27/2021 Gyanendra Sharma - NPTI Delhi 1


OBJECTIVE OF STATION PROTECTION

 To protect all such elements or sections in


a substation which are not covered either
under line protection or equipment
protection

Station protection include

 Bus Bar protection


 Stub line / Teed protection
 LBB protection
03/27/2021 Gyanendra Sharma - NPTI Delhi 2
Zone of Protection

CB
CT
03/27/2021 Gyanendra Sharma - NPTI Delhi 3
CT CORES

 CORE 1  BUS BAR CHECK ZONE


 CORE 2  BUS BAR MAIN ZONE
 CORE 3  METERING
 CORE 4  MAIN I LINE PROTECTION
 CORE 5  LBB & MAIN II LINE
PROTECTION

03/27/2021 Gyanendra Sharma - NPTI Delhi 4


NEED FOR BUS BAR PROTECTION

 In Absence Of BUSBAR Protection,


Fault Clearance takes place
in Zone II of Distance Relay by
Remote End Tripping

 This Means Slow & Unselective Tripping


and wide spread blackout

03/27/2021 Gyanendra Sharma - NPTI Delhi 5


NEED FOR BUS BAR PROTECTION

 Minimizing damage at fault location

 Maintaining system stability

 Localizing isolation to avoid wide


spread disruption

 Delayed clearance create shock to inter


connected equipment like Generator shaft
and windings of Transformer
03/27/2021 Gyanendra Sharma - NPTI Delhi 6
REQUIREMENT OF BUS BAR PROTECTION

 High speed operation

 Selectivity – shall isolate the faulty bus bar only

 Stability – stable for through faults upto 40 KA


fault level

 Reliability – Check feature

 Applicable for any type of bus bar protection

 Shall provide zone indication


03/27/2021 Gyanendra Sharma - NPTI Delhi 7
REQUIREMENT OF BUS BAR PROTECTION

 Continuous supervision for CT Secondaries


against any possible Open Ckt.

 In case of detection of any Open Circuiting of CT


secondary, after a time delay, the affected zone
of protection shall be rendered in-operative and
an alarm initiated.

03/27/2021 Gyanendra Sharma - NPTI Delhi 8


RECOMMENDATIONS FOR PROVIDING BUS BAR
PROTECTION

 Bus bar protection must be provided in all new 400kV and


220kV Substations as well as Generation Switch Yards

 For existing substations, provision of bus bar protection is


considered a must at 400kV level and for 220kV level it is
essential at substations having multiple feed.

 In case of radially fed 220kv substations, having more


than one bus it is desirable to have bus bar protection but
is not a must
03/27/2021 Gyanendra Sharma - NPTI Delhi 9
TYPES OF BUS BAR PROTECTION

 High Impedance
 Low Impedance

Both use Circulating Current Differential


Principle - To isolate the entire bus bar section
by disconnecting all the feeders connected to
the bus.

03/27/2021 Gyanendra Sharma - NPTI Delhi 10


CIRCULATING CURRENT DIFF.PROTN.
CURRENT DISTRIBUTION FOR BUS FAULT

BUS FAULT

A B C D
DIFF.
S1 RELAY
P1 - - - -
1000/ 1 0.25A 0.45A 0.3A 0.5A 87
P2 + + + +
S2
1.5A
250A 450A 300A 500A

RELAY CURRENT = 0.25 + 0.45 + 0.3 + 0.5 = 1.5 A

ALL C.Ts HAVE


03/27/2021 IDENTICAL
Gyanendra POLARITY
Sharma - NPTI Delhi 11
CIRCULATING CURRENT DIFF.PROTN.
CURRENT DISTRIBUTION FOR EXTERNAL FAULT

A B C D
DIFF.
S1 RELAY
P1 - - - -
1000/ 1 0.25A 0.45A 0.3A 1A 87
P2 + + + +
S2
1500A 1000A
250A 450A 300A 500A

03/27/2021 Gyanendra Sharma - NPTI Delhi 12


HIGH IMPEDENCE BUSBAR PROTECTION SCHEME

 Relay branch made High Impedance to limit Diff.


Current due to C.T. errors / Unequal CT saturation
on external faults

 Requires exclusive C.T. core and C.T. of identical


ratio / ratings

 Simple in design and execution

03/27/2021 Gyanendra Sharma - NPTI Delhi 13


HIGH IMPEDENCE BUSBAR PROTECTION SCHEME

• Stabilizing high impedance resistor included


in the Diff. Circuit

• Setting in terms of voltage drop across the


resistor
• Examples
o PBDCB
o FAC34
o RADHA
03/27/2021 Gyanendra Sharma - NPTI Delhi 14
HIGH IMPEDENCE BUSBAR PROTECTION SCHEME

RCT RL RL RCT

RR

03/27/2021 Gyanendra Sharma - NPTI Delhi 15


Calculation of Relay Voltage Setting

• Vs = If (RL + RCT)
Vs  relay circuit voltage setting
If  steady state secondary through
fault current (A)
RL  CT lead loop resistance to relay
tapping point (ohms)

Non linear resistor to limit the peak voltage


during IN ZONE fault

03/27/2021 Gyanendra Sharma - NPTI Delhi 16


Bus Bar Protection

Ckt-1
Ckt-2
R
Y
B
N

87 Check Zone
87
Main Zone
R
03/27/2021 Gyanendra Sharma - NPTI Delhi 17 Y
B
CT wire fault relay

03/27/2021 Gyanendra Sharma - NPTI Delhi 18


LIMITATIONS OF HIGH IMPEDENCE B/B PROT.

• Stringent requirements on CTs

• Need for dedicated CT cores

• Identical CT Ratio, Magnetizing charac.

• Aux. CTs for ratio correction unacceptable

• Inability to cope with increasing fault current

03/27/2021 Gyanendra Sharma - NPTI Delhi 19


LOW IMPEDENCE BUS BAR PROTECTION SCHEME

B B

D
I1 I2

Through Current Bias (Restraint) increases diff.


Pick up on external faults to ensure stability.

Diff. Current = I1 – I2 Bias current = I1 + I2


(Operate) (Restraint) 2
03/27/2021 Gyanendra Sharma - NPTI Delhi 20
LOW IMPEDENCE BUS BAR PROTECTION SCHEME

• Operating current for external fault varies


as through fault current does unlike in high
impedance relay

• Tolerant to CT mismatch & can use shared


core

• Comparatively more complex in design &


execution

• Examples  RADSS, REB, MBCZ


03/27/2021 Gyanendra Sharma - NPTI Delhi 21
Restraint Current due to Bias Setting of 30 %
30 % of (10+9) / 2 = 2.85 A
Diff Current is 1.0 A, so Relay restrains
1000/1A 1000/1A

9A 10 A

EX.
B B FAULT
10000A
D 1.0 A

03/27/2021 Gyanendra Sharma - NPTI Delhi 22


Low Impedance Bus Bar protection

03/27/2021 Gyanendra Sharma - NPTI Delhi 23


LOCAL BREAKER BACK UP (LBB) RELAY
OR

STRUCK BREAKER PROTECTION


OR

BREAKER FAILURE RELAY (BFR)

03/27/2021 Gyanendra Sharma - NPTI Delhi 24


NEED FOR LBB

Duplication in EHV System

TWO Main Protections


  TWO Trip Coils
  TWO Battery Source
TWO PLCC
 
The Operating Mechanism of the Breaker (CB)
is NOT Duplicated
03/27/2021 Gyanendra Sharma - NPTI Delhi 25
FEATURES OF LBB

Remote And Local Back Up


 
Provides Local Isolation when a Breaker is
struck on Fault

Comparatively Faster Clearance is possible


than Remote Back Up

Avoids Wide Spread Interruption and


enables Fast Restoration 

03/27/2021 Gyanendra Sharma - NPTI Delhi 26


SCOPE OF LBB
• In the event of any CB failing to TRIP on
receipt of trip command , all CBs connected to
the Bus Section to which the faulty CB is
connected are required to be tripped with
minimum possible delay through 
LBB protection

• This protection also provides coverage for


faults between CB. and CT, which are not
cleared by other protections
03/27/2021 Gyanendra Sharma - NPTI Delhi 27
03/27/2021 Gyanendra Sharma - NPTI Delhi 28
RECOMMENDATIONS

In all NEW 400 kV and 220 kV substations as


well as Generating Stations Switchyards, LBB must
be provided for each circuit breaker

For existing switchyards, LBB is considered a


MUST at 400 kV level and also at 220 kV
switchyards having multiple feed. In case of
radially fed 220 kV substations, provision of LBB
protection is desirable but not essential
03/27/2021 Gyanendra Sharma - NPTI Delhi 29
REQUIREMENTS FOR LBB PROTECTION

  Have SHORT operation and drop off times

  Have three phase current elements with


facility for phase wise initiation

Have current setting range such that


these can be set at minimum 200 mA for
line (for 1A CT secondary)

Have one common associated timer with


adjustable setting
03/27/2021 Gyanendra Sharma - NPTI Delhi 30
SPECIAL CONSIDERATIONS

The relay is separate for each CB and is to


be connected in the secondary circuit of
the CTs associated with that particular CB.

This CT secondary may be a separate core,


if available. Otherwise it shall be clubbed
with Main I [OR] Main II protection core

03/27/2021 Gyanendra Sharma - NPTI Delhi 31


LBB TRIP ARRANGEMENT

• For line CBs, direct tripping of remote end


breakers should be arranged on operation of
LBB protection (Transmission of Direct Trip
Signal through PLCC)

• For transformer breakers, direct tripping of


breakers on the other side of the transformer
should be arranged on operation of LBB
protection
03/27/2021 Gyanendra Sharma - NPTI Delhi 32
LBB TRIP ARRANGEMENT

 For lines employing Single-phase Auto


Reclosing, LBB relays should be started on a
Single-Phase basis for the Trip Relays.

 This is to avoid load currents in the healthy


phases, after single phase tripping, leading
to unwarrented operation of LBB protection,
since the current setting is normally lower
than the load current.
03/27/2021 Gyanendra Sharma - NPTI Delhi 33
LBB TRIP ARRANGEMENT

In addition to other fault sensing relays, the


LBB Relay should be initiated by Busbar
Protection, since failure of CB to clear a bus
fault would result in the loss of entire station
if LBB is not initiated.

03/27/2021 Gyanendra Sharma - NPTI Delhi 34


TIME CHART OF LBB

A System Fault
40 ms
B Prot. Operated/CB Trip initiation
50 ms
C Trip relays initiate LBB
65 ms
D LBB contacts close
80 ms
E CB Trip completed

95 ms
F LBB drops OFF / Timer stops

AB -- Protn opern time BE -- CB tripping time


03/27/2021 Gyanendra Sharma - NPTI Delhi 35
40 ms 40 ms
TIME CHART OF LBB
DG -- LBB Timer FG – Discriminating Margin
F 200 ms 170 ms

265 ms
G Local LBB trip/Remote trip initiated
275 ms
H B/B trip relays optd.
295 ms
I Remote trip signal recd at Remote
305 ms
J Remote CB trip relays optd.
315 ms
K Fault cleared from Local end
345 ms
L Remote CB Trip / Fault fully isolated
03/27/2021 Gyanendra Sharma - NPTI Delhi 36
DC LOGICS

03/27/2021 Gyanendra Sharma - NPTI Delhi 37


CB
CT
Isolator
SR

03/27/2021 Gyanendra Sharma - NPTI Delhi 38


03/27/2021 Gyanendra Sharma - NPTI Delhi 39

You might also like