1. Purpose
YF series medical incinerators are mainly used in hospitals to burn
postoperation garbage, virulent materials and inflammable solid rubbish. It
has the properties of automatic, little incendiary agent, thorough combustion
and no re-pollution, etc..There are various types of incinerators available for
users.
2. Technical Details
Capacity
20-30 50 100 150
(kg/h)
Votage
220 220 220 220
(v)
Power
750 1000 1500 1500
(w)
Available
200 500 1000 1500
(beds)
Weight
1700 2400 4300 4800
(kg)
Size(mm)
1600x1400x1900 2120x1500x2050 2120x1650x2900 3000x2300x3100
LxV/xH
Note
(1) The capacity listed above refers to the weight of inflammable solid
rubbish having 1000-3000 kcal/kg calorific value being disposed per hour
2
3
by the unit.
(2) Oil available are kerosene and diesel oil below -10#.
(3) The size does not include the smokestack
combustion begins now, and the combustion engine stops when reach
the scheduled time, the "combustion supporting" lamp blacks out, the
blower will continue work for 30 minutes to cool down the chamber.
3.2.3 Self-combustion
The combustion of inflammable material can be started in the mode of
3.2.1 or 3,1.2, if the combustion supporting needs to be stopped, press
the "stop" and "self-combustion" button successively, self ,combustion
begins with the blower working continuously . The blower needs .to
work for 20 minutes after the combustion finished, then switch off the
power.
4. Instruction
4.1 Connect the outer circuit according to the wiring diagram of the cont-
rol system. Generally, the control box should be set up according to
actual need.
4.2 An oil filter must be added ahead to the oil entrance pump. The outlet
switch of the oil tank is not suitable to be near the bottom. The oil ta-
nk and oil filter should be cleaned termly. The oil pipeline should be
chec- ked after the connection of oil pipe to avoid gas and oil leak-
age.
4.3 The motor of combustion engines starts up once the start button being
pressed, spark is created by the ignition electrode, the electromagnetic
valve automatically open after 7 seconds blow, oil mist is sprayed by
the oil nozzle, ignited by electric sparkle and flame is formed. Then
the brightness of the flame is detected by the photoelectric detector
and the controller enters lock mode. The combustion engine begins to
work normally after the ignition electrode ignites for 15seconds.
4.4 f flame doesn't appear due to failure of ignition or the photoelectric
detector can riot detect the brightness of the flame, the safety alarm
5
6
system will break off the startup program of the combustion engine
and the red failure lamp will shine after 23 seconds.
4.5 If the photoelectric detector has detected brightness when the combus-
tion engine begins to start up, the safety system acts so that the contr-
ollercan not enter into normal procedure and the electromagnetic val-
ve can not be opened. Flame can not be formed at the puzzle, and the
red failure lamp will shine after about 23 seconds. So, cover the pho-
toelectric with hand when start up the combustion engine in bright pl-
ace, unclinch it immediately when flame is sprayed by the combustion
engine, otherwise, the combustion engine can not work normally.
4.6 The reset button cannot be pressed before 3 minutes since the red fail-
ure lamp shine.
4.7 The position of the air door must match the size of nozzle. Generally it
has been adjusted in the factory, but there may be some differences d-
epends on the pressure in the chamber of the stove . The intensity of
wind should be adjusted by the adjustment of the air door when the c-
ombustion engine has sprayed flame. The intensity of the wind is pro-
per when the flame is stable without black smoke, too low of it may c
ause black smoke, too high may blow out the , flame.
4.8. When a gas combustion engine is used, blow off the air remained in
the pipeline before connect the combustion engine and coal gas (na-
ture gas) pipeline, open all the doors and windows of the room. It con
not work normally in the atmosphere of below -15°C.
4.9 The gas supply pressure is proper between 300-400mmHg, apressure
reductor valve is needed when the pressure is above 400mmHg, the
minimum diameter of the connect pipe is 14mm.
4.10 The combustion engine enters into the blowing procedure when the
power is switched on. If the air pressure exceeds the set value of the
6
7
tup.
6. Trouble Shooting
Check for external reasons if the unit failed.
6.1 Whether the power supply is working.
6.2 Whether the oil stored in the oil tank is adequate and the oil valve is
opened.
6.3 Whether the pressure controller has been adjusted.
6.4 Whether the gas volume in the gas supply is adequate.
6.5 Whether the combustion time has been adjusted. If above external
reasons have been excluded, check in the sequencebelow:
The pressure in the oil pump Check after loose the axle
is too high, the charge is too head , reduce the oil
high. pressure.
The controller fails. Replace
8
9
9
10
The air door is too big and Start up with smaller air
the fiame is diown off. door
6. No flame after
The pressure of the oil Increase oil pressure or
the oil spraying
pump is insufficient. replace the oil pump.
and ignition.
There is moisture in the oil. Replace
10
11
11
12
12
13
Incinerator 1
Combustion 3
Oil Tank 1
smokestack 4 sections
Ash harrow 1
Quality Certificate 1
Instruction manual 1
Environmental
protection appraisal
1
certificate
Control box 1
M10X40 44 pieces for
type 150.100 and 50
M8X40 33 pieces for
Bolt type 20
Asbestus rope 4m
13
14
Technical requirement:
Technical requirement:
wire is 2.5mm2.
3. The height of the unit in the room is 2.6m the height of the room is
suggested to be over, 4m.
4. The height when the unit enters into the door is above 2.8m.
5. The floor should be tamped with concrete, then be covered with a
layer of 12cm concrete.
15
16
Technical requirement:
16