Project Name : PENGECORAN LANTAI KANAL

Project No. : 0
Contract No. : 0
Location : CDC CILINCING
Expected Site Start Date ASAP Issue Date : 6-November-2020 Rev. 0
Summary
Item
Work Item Unit Qty Rate Total
No

SUMMARY

I GENERAL REQUIREMENTS 35,500,000


II PENGECORAN LANTAI KANAL 120,251,728

TOTAL 155,751,728
TAX 10% 15,575,173
TOTAL 171,326,901
Project Name : PENGECORAN LANTAI KANAL
Project No. :
Contract No. :
Location : CDC CILINCING
Expected Site Start Date ASAP Issue Date : 6-November-2020 Rev. 0
Bill of Quantities
Item
Item Description Unit Qty Rate Total
No.

I GENERAL REQUIREMENTS

I.1 Generally
General requirements shall include : Item 1.00 25,000,000 25,000,000
- mobilisation and demobilisation
- transportation of as specified, employer's supplied material from
employer's storage to the site

- field engineering and site management


- temporary site office and stockyard
- temporary equipments and disposal equipments
- shop drawings and as-built drawing
- reporting, and documentation
- health and safety equipments
- projects sign, safety line, and all necessary safety provision
- all necessary construction tools and equipments
- site cleaning

I.2 Sewa Pompa Sedot Air 2 unit untuk pengurasan kanal hr 7.00 1,000,000 7,000,000

I.3 Sewa Ventilator Blower untuk sirkulasi udara di kanal hr 7.00 500,000 3,500,000

TO COLLECTION 35,500,000

REMEASUREMENT
The Contractor shall note that all items and quantities stated below will
subject to remeasure based on site implementation and condition

II PENGECORAN LANTAI KANAL


a Pembersihan Lumpur Dasar Kanal m2 128.40 150,000 19,260,000

b Gelar Plastik Cor m2 128.40 65,000 8,346,000

c Gelar Wiremesh m10 m2 128.40 375,000 48,150,000


d Pengecoran Ready Mix K - 225 tebal 12cm m3 15.04 1,755,700 26,405,728

e Sewa Pompa Beton ls 1.00 4,500,000 4,500,000

III Bongkar Sepatu Kolom Beton unit 14.00 185,000 2,590,000

IV Akses Masuk Kanal


Bongkar Akses Masuk Kanal ls 1.00 3,500,000 3,500,000
Perapihan kembali Akses Masuk Kanal Seperti Semula ls 1.00 7,500,000 7,500,000
TO COLLECTION 120,251,728

SUMMARY

I GENERAL REQUIREMENTS 35,500,000


II PENGECORAN LANTAI KANAL 120,251,728

TO SUMMARY 155,751,728

Page 2 of 2