Method Statement

Installation of Water Cooled Chillers


Rev.00

PREPARED BY DESIGNATION COMPANY NAME


SIGN & DATE

TECH ENGINEERING
JAY SERVANEZ QA/QC ENGINEER
LLC

APPROVED BY DESIGNATION COMPANY NAME


SIGN & DATE

HEAD OF TECH TECH ENGINEERING


MASOOD ALAM
ENGINEERING LLC

(TECH-MS-M09 Rev.00) Page 1/8


Installation Water Cooled Chillers
Method Statement

CONTENTS

1) PURPOSE and SCOPE

2) REFERENCES

3) RESPONSIBILITIES

4) TOOLS and EQUIPMENTS

5) MATERIALS

6) WORK PROCEDURE

6.1 STORAGE
6.2 METHOD OF INSTALLATION

7) SAFETY and ENVIRONMENT

8) RECORDS

9) ATTACHMENTS

Inspection Test Plan


Installation Checklist

1.0 PURPOSE and SCOPE

(TECH-MS-M09 Rev.00) Page 2/8


Installation Water Cooled Chillers
Method Statement

The purpose of this document is to lay down the systematic procedures for the various activities
required for Installation of Water Cooled Chillers. Ensure that all works are carried out in accordance
with the contract specification and approved shop drawings.

2.0 REFERENCES
 Project Specification
 Manufacturer Recommendations
 Approved Shop Drawings
 Approved Technical Submittal

3.0 RESPONSIBILITIES

 TECH ENGINEERING LLC is responsible for carrying out the works specified in this method
statement.
 Project Manager
Will oversee the whole project ensuring that the necessary information to perform their job rules.
 Construction Manager
Will ensure that the relevant department is aware and understand the requirements of this method
statement. He ensures that all relevant safety precautions in the delivery of the job are adhered to
and will implemented the company safety standards and compliances.
 Site Engineer
Will ensure that the all works are being carried out as per the latest shop and specification and
coordinates with the QA/QC Departments for inspection and approval and will ensure that all
relevant safety precautions in the execution of the job are adhered to all times and implement
company safety standards and compliances.
 QA/QC Engineer
Will ensure that any discrepancies are highlighted, recorded systematically convey to relative and
responsible construction manager/site engineer and QA/QC Manager for correction and action.
 Foreman
Will ensure that his crew understands the method statement and works are to be executed safely,
within the time of schedule and specified finishes. All foremen will provide the crew with
appropriate PPE and approved drawings for the works and make sure it is implemented.
 Installation Team
Will execute the works safely, within time schedule and under the direct supervision of the Charge
Hands and Foreman and they are also responsible for keeping the work area clean and tidy.

4.0 TOOLS and EQUIPMENTS

(TECH-MS-M09 Rev.00) Page 3/8


Installation Water Cooled Chillers
Method Statement

 Tool Box with tools


 Spirit level
 Welding Machine
 Chain Block
 Hydraulic Jack
 Scaffolding
 Electric drill
 Open socket wrenches
 Grinding Machine
 Cutting Machine
 Ladders

5.0 MATERIALS
 Water Cooled Chillers and Accessories
 Bolt and Nut

6.0 WORK PROCEDURE


Installation of Chilled Water Pumps and Accessories activities shall be as per approved shop drawing,
calculation and complying with the contract requirements.

6.1 STORE - GENERAL REQUIREMENTS

 Upon receipt of materials on site, these will be inspected immediately by the QC Engineer/Inspector
to ensure correctness of material as per the Employer’s Approved Material Submittals and
quantities.
 A material inspection request (MIR) will be prepared by QA/QC Engineer for submission to
Engineer for review and acceptance.
 The materials delivered will be sorted with protection against damage during handling, transport,
warehousing and installation.
 Store keeper will verify all documents are forwarded as per the requirements of the purchase
order.
 Site engineer will inspect the equipment as per manufacturer's recommendation prior to
installation.
 Store keeper will inspect for any damage during shipping, handling and storage and review the
document as per packing list.

(TECH-MS-M09 Rev.00) Page 4/8


Installation Water Cooled Chillers
Method Statement

 Any items found damaged or not suitable as per project requirements shall be removed from site. If
required to store temporally, they shall be clearly marked and stored separately to prevent their
use.
 All materials will be delivered to site store in self supporting framed units.
 Check all materials thoroughly for physical damages & defects and return all defective and
damaged items.
 Any unapproved or damaged materials shall be shifted away from the site.
 Material storage shall be as per manufacturer recommendation.
 Verify actual quantities delivered to site with respect to packing list, delivery note etc.
 Only approved material will be stored in site and material inspection will be carried out every
delivery.
6.2 METHOD OF INSTALLATION

References
Project Specification
Standard Regulations
Approved Shop Drawings
Approved Technical Submittal
Manufacturer Instructions

Pre-installation Checks

 All installation will be carried out in accordance with the specifications Contract Specifications.
 All materials will be approved and material inspection will completed in advance before installation.
 Physical verification of the materials will be carried out for any damages prior to taking from the
stores.
 Ensure that the approved materials area available to carry out the works.
 Ensure the installation areas are free from debris and foreign materials.
 Ensure that adequate number of technicians and proper tools are present at site.
 Ensure that all materials are ready during installation.
 Ensure that all the sleeves are provided as per approved latest builders work drawing.
 A safety barrier is to be erected around the area and warning signs will be provided.
 Ensure that latest approved shop drawing for the installation is present and all the personnel are
working on the same drawings.
 All materials will be approved and material inspection will completed in advance before installation.

Installation of Water Cooled Chillers and Accessories

 Prepare all the materials and safety precaution prior for installation.

(TECH-MS-M09 Rev.00) Page 5/8


Installation Water Cooled Chillers
Method Statement

 Close coordination with the safety manager for the safety of unloading the of the material at site.
 Check the type, required capacity, pressure & temperature rating of the pump to be installed is
same as indicated in the approved material submittal.
 Examine the area for the foundation for installation tolerances and clearances required for
periodic service as mentioned in the project specification.
 The factory assembled chillers comprises of evaporator, condenser, compressor, expansion
valve, microprocessor control center and interconnecting piping.
 After receiving the chiller on site, examine the concrete base, coordinate its size with actual size
of chiller. It should be 100 mm larger in all directions than overall dimensions of chiller.
 Examine the installation location for easy installation as well tolerances and clearances after
installation for periodic services as specified in the contract specification.
 Mark the location of housed spring as per construction drawings.
 Place the housed spring of approved quality and brand, on the base at marked position, before
fixing springs fill the place with neoprene rubber.
 Water cooled chiller with packing will be off loaded from the transportation with the help of
mobile crane on the I-Beam pre fabricated platform adjacent to ground floor level outside
building at G/L.
 When lifting by crane, wire ropes slings will be secured with lifting eye available on the top of the
chiller. The attaching rope must be rated for the load.
 After removing packing, manually transport the chillers to ground floor towards assigned plinth
and finally place the chiller on the pre-installed springs.
 Check the level of chiller by using spirit level and adjust the unit on the spring.
 After verifying the correct installation of chiller, connect the condenser & chilled water pipe with
condenser & evaporating unit respectively as per construction drawing.
 Supports will be provided to hang the connected pipes, to avoid the load on chiller.
 Insulate the evaporating unit and compressor piping with approved rubber insulation as per
specification.
 Connect the refrigerant recovery unit at the bottom of evaporating and condensing part of chiller
through welded stain steel pipes. While connecting, use isolating valves and pressure gauges.
 Install field wiring, controls, distribution board and connect these with chiller, tighten connections
and terminal as per the recommended torque.
 Install thermometers, pressure gauges, flow switch and valve of approved brand as per the
approved construction drawings. Provide additional support to pipes connecting expansion
valves.
 After completing the installation of chillers, remove construction debris and leave the SITE in a
clean and tidy manner.

(TECH-MS-M09 Rev.00) Page 6/8


Installation Water Cooled Chillers
Method Statement

 Attach and fix the identification labels, safety and warning signs of approved material and correct
lettering at their locations as per approved drawings.
 Make sure the proper safe covering of chillers until to proceed with final system commissioning
and final handing over to consultant/client.  

 After the installation is completed, an Inspection Request will be formally raised to the Engineer to
ensure accuracy and high quality of works.

7.0 SAFETY and ENVIRONMENT


Control Measures

 Working at height requires edge protection (at the correct height) and in most cases harnesses
with the correct length for the height of work and attached correctly.
 Slab openings are to be well protected.
 Prevention of falling materials from height, this would involve toe boards on scaffolding etc.
 All workers to wear appropriate PPE for the task, i.e. goggles, mask, gloves etc. The foreman
should provide all the necessary PPE and implement the wearing of it.
 Electrical power tools will be approved, double insulated or grounded to avoid electrical shock.
 Fire extinguishers are to be placed within reaching distance any works that is within risk of a fire.
 Plant and equipment will have third party inspection certificates and be inspected prior to use.
 All personnel entering the site will wear the appropriate PPE.

Personnel Protective Equipment
 Safety helmet
 Safety shoes
 Dust Mask
 Goggles
 Gloves
 Mask

Emergency Arrangements

 The Health & Safety officer will be responsible for coordinating the emergency procedure.
If there is an emergency the Health & Safety officer will be notified immediately.
 The Health & Safety officer will then notify the relevant emergency services if required
997 – Fire
998 – Ambulance

(TECH-MS-M09 Rev.00) Page 7/8


Installation Water Cooled Chillers
Method Statement

999 – Police
 The Health & Safety officer will notify the Safety Advisor of the emergency, if the site nurse is
required he will be notified, the Safety Advisor will attend the emergency and take control of the
emergency.
 The required notification, investigation and reporting of the incident will be conducted in
accordance with the site HSE Plan.

8.0 RECORDS
1. Inspection request duly signed by the consultant.

9.0 ATTACHMENTS
TECH-CL-M-009 (Check List)
TECH-ITP-M-009 (ITP)

(TECH-MS-M09 Rev.00) Page 8/8