Professional Documents
Culture Documents
Section: L01
Semester: Spring 2020
Course Code: ELEC423
CRN: 24705
1. Project Objectives
To Design a Distribution System for a Typical Residential Compound in Qatar according to
Kahramaa Standards and Regulations
2. Theoretical Background
4. Project Work
The Project work has been divided into 3 Main Sections viz.
Load Estimation
Equipment Design
MATLAB Simulation
Load Estimation
As mentioned earlier, the aim of this project was to design a distribution system for a typical
compound in Qatar. A typical compound in Qatar might contain 10 to 300+ villas depending on the
size and the design of the equipment for the compound will solely depend on the Total Connected
Load (TCL), Maximum Diversified Demand (MDD), diversity factor (which is more or less same for
most compounds), Demand Factor, Coincidence Factor, Load Factor, so on and so forth. In short, the
load for the compound needs to be estimated first before designing the equipment (e.g. Cables,
Circuit Breakers (CBs), Fuses, Distribution Boards (DBs), Transformers, etc.). For this case, it was
instructed to design for 10 Villas, 1 Mosque and 1 Gym.
The Load Estimation is called an “Estimation” since the engineers estimate the types of loads and
maximum amount of load demanded by the consumers (residential or industrial) since,
It is never possible to find the exact amount of load at any moment since demands are always
changing.
The maximum demand might vary a lot depending on the season, time of the day,
increment/decrement in the number of customers, so on and so forth.
For all these reasons, design engineers estimate the electrical loads based on the electrical standards
(national, international and company’s own standards), Issued for Construction (IFC) Drawings for
the relevant project, and their own experience and jurisdiction. The aim is to find a reasonable
estimate for the diversified load required for the network so that the equipment chosen are not so
underrated that they get damaged due to slight overloading, or the equipment chosen are rated way
above the required level (imagine using industry level equipment for a small residential compound)
which is not economically beneficial at all. The designer should consider the types of loads used in
per unit of the network (e.g. per villa), number of each type of loads, and an estimation of the
maximum possible number of loads connected to the outlets. Inside construction sites in Qatar, it is
mainly done based on the Kahramaa standards which have largely been derived from the British
Standards (BS). For this project, the load estimation was performed based on Kahramaa standard
2018 for “Electricity Wiring Code”. In case of villas, the load estimation for one was estimated at
first based on Kahramaa Standard; then for 10 villas, it was just multiplied by 10 to find the total
required load for villas.
Table 2: Kahramaa Standard for “Current Demand to be Assumed at Point of Installation” [1]
As it can be seen in Table 1, the MNDD per villa was estimated to be around 77 kW which would
make the total MNDD for 10 villas to be around 767 kW. Now, one other important factor needs to
be assessed, which is the “Diversity Factor”. Certainly, all the loads do not run all day for all
customers. For example, the refrigerator runs all day for almost everyone, making its Diversity
Factor 1. On the contrary, the Oven or Exhaust Fan, even the lights remain on differently for
different part of the day. Air Conditioners (AC) remain on for different duration of depending on the
season or part of the day. So, if the Diversity Factor (F D) is not considered, which is MNDD here, the
equipment will be designed based on the consideration that all the equipment in for all the customers
remains on for 100% of time, which is not only impractical but also economically non-beneficial.
The economical toll increases for the bigger projects due to buying of electrical equipment way
above the requirement. Kahramaa has their own standard for Diversity Factor values to be
considered while designing the electrical power distribution system only inside Qatar, as seen in
Table 3. It is mentionable that the standards contain the most common load types and provides with a
general guideline. The designer can change the values of these load types or use Diversity Factors for
loads outside the scope of the common loads mentioned in the standard based on his own
justifications and company instructions, but will have to provide with the relevant documents to
Kahramaa along with the design documents.
Transformer Design
In order to design the transformer, mainly 3 factors are needed to be considered, viz.
As calculated above, the maximum demand load (MDL) for the system was calculated as 482 kW.
The Nominal pf for the Transformer was chosen same as the system i.e. 0.9. The loading factor was
chosen as 1.11. Considering the Loading Factor ensures that the circuit can supply the extra bit of
energy the transformers require while loading, without failing any part or the circuit breakers
tripping. So, the minimum required rating of the transformer was,
482∗1.11
T R= ≅ 595 kVA
0.9
But Transformers are bulky, high cost devices which comes in discrete ratings. The ratings available
from companies varies but comes in discrete ratings, but standards for every country fixes some
transformer ratings to be used inside that country’s territory in order to create an organized system
guided by laws which are the standards and monitored by experts from the government. It also
makes it easy to ensure compatible and optimum-quality devices to be bought, sold and used within
that region. The Kahramaa permissible transformer ratings are provided in Table 5.
The Protection current needs to be greater than the Design Current (i.e. I n> I t ¿ , obviously in
order to protect the system.
Tabulated Current Carrying Capacity (It): After taking account of the derating factors, the
derated cable capacity is calculated based on the combined derating factor determined by 4
factors as mentioned by the IEEE standard or other methods and divide In by that. According
to IEEE Standards [2], which has been derived from British Standard (BS 7671), there are 4
types of sources of derating factors for electric cables such as,
i. Ambient Temperature – Cables in Air or Underground (Ca)
ii. Grouping of the Cables (Cg)
iii. Conductors Surrounded by Thermal Insulation (Ci)
iv. Semi-enclosed Fuses (Cc)
So, the combined derating factor, C = C a C g C i C c. Then, the Tabulated Current,
In
It ≥ … … …(i)
C a C g Ci C c
So, from equation (i), it is evident that the Tabulated Current should be at least equal to the
Protection Current Rating divided by the derating factor. In any IDEAL condition, the
derating factor is 1, which makes the Tabulated Current same as the Protection Current. But
the conditions are never ideal in real world and the cables performance always gets
deteriorated by various factors, temperature being one prominent one. Dealing with these
derating factors let the designer choose a cable with a bit higher rating so that the cables do
not burn down after being deteriorated due to the surroundings. Among the derating factors,
1st two are the most prominent one, especially the temperature. For this reason, in cable
manufacturer manuals, same cables have different current ratings if laid in air or passed
through the underground.
Derated Cable Size (Iz): This is the total cable size as selected from the manufacturer’s cable
table. Like the transformer, cables also come in a discrete rating, so cables are also not
available for continuous values. This current can be equal to or greater than I t i.e. I z ≥ I t .
Normally it is chosen greater since the cable ratings are discrete and keeping a distance from
the rating makes the system more robust.
The IEEE document explains this concisely through the diagram in Figure 2.
But this does not represent the overloading current due to the transformer loading at its worst
condition since it is rated as 630 kVA (not 595 kVA as calculated form the total load) due to it being
available in discrete ratings. So, the revised Load Current, which is also the Design Current,
becomes,
630
I L(revised)=I b= ≅ 877 A ≡ I n (min)
√ 3∗0.415
Now, Circuit Breakers (CB) also come in discrete rating, being a rated product, which is shown in
Table 6, which is based on the Kahramaa regulations [1]. The closest CB is the one rated with
1000A, type Air Circuit Breaker (ACB) i.e. I n=1000 A . This CB was used in the electrical
substation nearest to the load, just after the transformer designed beforehand. There will be similar
CBs in front every load (e.g. villa), as depicted in the Simulink model provided afterwards. But these
CBs will be much smaller in size since they must handle a much lower current. But the small cable
design inside the buildings have not been considered under the scope of cable design in this project.
In the manual, Doha Cables put more advanced type of Derating Factor able to comprise all types of
scenarios during cable layout inside buildings in Qatar. Only the 2 basic types are considered for this
project. The cables are mostly laid out underground for Power Distribution in Qatar, even though it
costs more. Qatar government have chosen this extravagant option due to maintain the aesthetics of
the country. For this reason, the cables designed for this project are also laid underground and the
derating factors will depend on this as seen in Table 8.
Now, the average high temperature in Qatar is normally during June, are is around 40-45℃ So, the
derating factor from this was chosen as 0.9 considering the worst-case scenario. On the other hand,
the Buying Depth for the cables was taken as 0.8m, making the derating factor 0.94. So, the
combined Derating Factor, C = 0.9∗0.94=0.85.
Now, dividing the protection current with the derating factor, we get,
In 877
It ≥ = ≅ 1031 A
C a C g Ci C c 0.85
After than the cables were selected for the conductor carrying the current from the local substation to
the compound (all of these are considered as part of the distribution system here). From Table 8, it
can be visualized that cables are available with different ratings from as low as 51A to as high as
605A depending on the cross-sectional area. The ampacity and loss in the cable depends on the
factors like cross-section of the cable, number of cores inside the cable, layout of the cables (air,
ducts or underground), so on and so forth. For the main cable connecting the substation to the loads,
the cable with an “laid underground” ampacity of 305A was chosen with 4 in each bundle. So, the
total Current Carrying Capacity (CCC) of the cables become, 305∗4=1220 A. But the derating or
the correction factor of the circuit will derate the ampacity of the cable to make the final ampacity,
I z =1220∗0.85 ≅1037 A . Now, as devised by IEEE, there should be at least 2 protection criteria must
be fulfilled in order to explain the efficiency of the system [2], viz.
a) I z > I n
b) 1.45∗I z > I b
1.45 times of the Design Current is equal to 1271A and Iz is less than that. So, both conditions are
fulfilled. While choosing the cable, another thing which was taken care of is the economical loss in
the cable selection. In this case, the loss was about (1037-1000) A = 37A, which is very low! So, the
cable selection was optimum. Cables could be chosen, even after fulfilling all the conditions but with
a loss of 100+ Amperes. That would obviously be a lesser economically efficient option than this.
Notice that the CCC per cable and the number of cables per bundle has been chosen carefully from
Table 8, among many other acceptable combinations, in order to achieve this efficiency.
Table 9: Current Ratings for 3, 4-Core Cables from Kahramaa Standards [1]
The CBs protecting each load (i.e. villas, etc.) are also designed in the same way. As shown in the
Simulink model, there is one protective CB in front of every load, which are needed to be designed.
They cannot be the same (or even near) to that of the main CB located near the transformer since the
current is being distributed in each load. So, a much lower current will require a much lower rate CB.
The Design Current for each villa was around 69A. So, an 80A Moulded Case Circuit Breaker
(MCCB), the nearest one above the design current, was chosen for each villa. Voltage Drop for each
villa was calculated to be around 0.018%. MCB was enough for the masjid while an MCCB was
used for the gym depending on their respective diversified loads. The voltage drop for the masjid
was around 0.041% while for the gym, it was around 0.057%. So, among the loads, the gym has the
highest amount of voltage drop. So, the total voltage drop from the transformer to the end load
becomes about,
(2.693 + 0.057) % ≈ 2.75% maximum, which is well within the limit (5%).
*All the data, calculations, formulas are presented inside the smart excel sheet prepared for this
project.
SIMULINK Model
The Simulink model was developed based on Dr Adel Gastli’s model used in one of the labs. All 12
loads of the circuit were arranged in the manner shown in the lecture where there is a virtual load
center among all the loads (somewhat like the center of gravity). The villas were arranged like two
opposite facing loads, and the mosque and the gym were near the center of the compound so that
customers in all villas have similar access to these facilities. In order to design the model in Simulink
and run, there should be a feeder in the circuit supplying the necessary power to the network. In this
model, the 66kV Grid feeder goes to a main substation which consists of fuse blocks in per phase, 3-
phase 11kV circuit breaker, and a 66/11kV step down transformer. Then the power is transmitted to
the next substation through a transmission line to the substation near the load where the voltage is
again stepped down from 11kV to 416V and supplied to the loads. The generation and transmission
part of the network is out of the scope of this power distribution project.
Relay Coordination: The first and most important thing ensured through this model is the
coordination between the relays inside the circuit breakers. In this model, there are 3 layers of CBs,
Circuit Breakers in all the branches are in the layer and they have the same CB curve. The loads are
designed in such a way that CB tripping in one of the branches should not impact other, but it might
impact the 416V Main CB if necessary, conditions are fulfilled. But the CB curves for any layer of
CB should not touch the other in any condition, otherwise it would result into an unnecessary
tripping of the upper layer due to any minor power outrage or overloading. For example, if the 416V
main CV trips due to a small fault in any of the branches, it would cease the supply to the whole
network. A system behaviour like is inefficient and undesirable since a minor fault in one of the
villas might shut-down the whole compound.
The relay and fuse coordination plot have been shown in Figure 6. As it can be seen, the CB plots do
not intersect with each other, which has been ensured through few parameters viz, the Rated Current
(Ir), Nominal Current (In), Long Time Pickup Unit (LTPU), Long Time Delay (LTD), Short Time
Pickup Unit (STPU), Short Time Delay (STD), Instantaneous Pickup Current (IPU) and
Instantaneous Delay (ID). The values set are as follows:
Table 8: CB Parameters in Simulink
Units 11kV CB 416V Main CB 416V Branch CB
Ir 80 1000 80
In 80∗√ 2 1000∗√ 2 80∗√ 2
LTPU 0.8 0.9 1
LTD 2 4 4
STPU 3 3.1 3
STD 0.1 0.27 0.4
IPU 5 5.3 7
ID 0.02 0.015 0.01
Here, the rated current ratings have been imported from the calculations done beforehand (e.g.
1000A ACBs were selected for the CB used in the 416V Main and 80A MCCBs were used for
villas). The value of the rated current in the CB 11kV side should be at least same as the end CB
ratings in order to make the plots continuous. 2 layers of Fuses were also coordinated in the same
way. All the 8 parameters stated in Table 8 along with their values for each layer of CB has been
initialized in a MATLAB file and input to a bus inside the tripping system as shown in Figure 7. The
parameter values are imported from the MATLAB script and input into the Simulink Model.
Figure 8: Individual Relay Coordination Plots from Respective m-files (a)11kV Main, (b) 416 V Main,
and (c) 416V Branches
Now, the relay tripping time and the CB response
can be regulated from the Fault and STOP
Simulation subsystem. The fault it triggered using
a step function and the triggering time after the
simulation starts is set inside the step function.
This time is represented as Fs inside the block as
shown in Figure 9. Now, this has been compared
Figure 9: Relay System
with the time-delay of each CB and the Simulink
model is automatically closed after a certain period the CB trips, as set inside the constant and timer
block shown in Figure 10.
After ensuring that the CBs are well-coordinated, for certain values of fault, CB of the Branch where
the fault located at might trip, without effecting the 416V main CB. If that can be ensured, the model
is perfectly, selectively, coordinated. But it also depends on other model parameters.
Now, as it can be seen from Figure 4, the fault is at Branch No. 9. So, after the fault occurs, the CB
here should trip, and it should not affect the 416V Main CB and thus other loads connected to it by
tripping faster. So, it was tested with a very high fault by setting the fault resistance to ground very
low. Ideally it should trip the CB at branch 9 instantly, which is exactly what happened as shown in
Figure 12.
Figure 13: Current Waveform in 416V CB Main, a Temporary Distortion can be seen at around 0.1s
References
[1] I. E. Commission, "You & IEC," International Electrotechnical Commission, [Online]. Available:
https://www.iec.ch/perspectives/?ref=menu. [Accessed 22 4 2020].