You are on page 1of 17

Danielle Changala graduated cum laude from

the University of California, San Diego, with a


double major in Political Science and Psychology,
and completed her Masters in Environmental Law
and Policy in 2010 while earning the Certificate in
Energy Law. She has interned with New
Generation Energy, a non-profit renewable
investment firm focusing on extending capital
from private investors to community-level
renewable energy projects, and with the
Conservation Law Foundation in Boston, where
she worked in the Clean Energy and Climate
Change program area.

Michael Dworkin has been a utility regulator,


an appellate litigator and management partner in
Comparative Analysis of
a telecommunications engineering firm. He
currently is Professor of Law and Director of the Conventional Oil and Gas and
Institute for Energy and the Environment at
Vermont Law School and on the board of the
Vermont Energy Investment Corporation, which
Wind Project Decommissioning
manages ‘‘Efficiency Vermont.’’ In the past he has
been Chairman of the Vermont Public Service
Board, a board member of the Electric Power
Regulations on Federal, State,
Research Institute and American Council for an
Energy Efficient Economy, and a recipient of
NARUC’s Kilmarx Award for ‘‘contributions to
and County Lands
clean energy, good government and the
environment.’’
As the growth of renewable energy continues, it is
Jay Apt is Executive Director of the Carnegie
Mellon Electricity Industry Center at Carnegie imperative that adequate funds are secured to successfully
Mellon University’s Tepper School of Business
and the CMU Department of Engineering and
decommission projects at the end of their useful life.
Public Policy, where he is a Distinguished Service
Professor. He received an A.B. in Physics from
Additionally, it is important to ensure that regulatory
Harvard College in 1971 and a Ph.D. in decommissioning obligations do not disproportionately
Experimental Atomic Physics from the
Massachusetts Institute of Technology in 1976. burden any generation resource.
He received the NASA Distinguished Service
Medal in 1997 and the Metcalf Lifetime
Achievement Award for significant contributions
to engineering in 2002.
Danielle Changala, Michael Dworkin, Jay Apt and
Paulina Jaramillo
Dr. Paulina Jaramillo has a bachelor’s in Civil
and Environmental Engineering from Florida
International University (2003), as well as a
master’s and Ph.D. in Civil and Environmental
Engineering with an emphasis in green design
from Carnegie Mellon University (2004 and 2007, I. Introduction to develop a policy environment
respectively). Her past research has focused on life
cycle assessment of energy systems with an
that not only facilitates the
emphasis on climate change impacts and In the midst of an unstable integration of renewable energy
mitigation research. As a professor at CMU, she is
involved in key multi-disciplinary research
geopolitical environment, into the electric grid, but also
projects to better understand the social, economic concerns about global climate provides a regulatory system that
and environmental implications of energy
change, advancing clean energy ensures environmental
consumption and the public policy tools that can
be used to support sustainable energy development technologies, and progressive state accountability and a level playing
and consumption. She is now the executive and national policies, the interest field amongst domestic energy
director of the RenewElec project.
and need for renewable are at the resources. The integration of
forefront of the political agenda. In renewable energy must be done in
order to accommodate the growth a manner that not only provides for
of renewable energy, it is necessary successful implementation, but

Jan./Feb 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 29
also ensures that the addition of wind projects.1 The comparison project developments typically
renewable resources will not create between O&G extraction sites and involve such activities as:
additional environmental wind energy projects provides a creating site access; performing
problems in the wake of a clean particularly appropriate site grading; constructing lay-
energy solution. The comparison due to similarities in down areas and an on-site road
decommissioning requirements the projects’ land use patterns. A system; removing vegetation;
governing energy generation comparison of the regulations digging for and installing tower
projects are an imperative governing both O&G extraction foundations; erecting towers and
component of such a regulatory sites and wind energy projects installing nacelles and rotors;
structure—adequate demonstrates how regulations installing meteorological towers;
requirements and funds need to be differ for each of these energy constructing electrical
secured for reclamation and resources and the implications substations; and connecting all
decommissioning costs to ensure these regulatory structures have necessary structures with power-
that wind projects will not be on resource development. conducting and signal cables.5
abandoned without appropriate Though technological
securities after their useful developments in recent years
lifetime. While these II. Similar Land Use have supported growing
environmental assurances are Impacts Between O&G efforts to develop
necessary, it is also important to Extraction Site unconventional shale gas
recognize that these assurances Operations and Wind resources through the use of
must be similarly imposed on all Projects horizontal drilling, this article
energy resources, so as not to set focuses on the land use and
back or advance any particular O&G extraction sites and wind reclamation of conventional
resource over another. projects have some similarities in O&G wells drilled in single pads.
Fundamentally, resources should
be on a level playing field so that
selection amongst competing
their surface land use patterns.
The construction and operation
processes of each require the
G enerally, wind farms
require surface land use for
turbine foundations, roads, and
energy resources are not distorted removal of topsoil from the other infrastructure.6 Although
by disproportional regulatory well/turbine site, laying a the land required for a wind
burdens. cement/gravel pad (well pad for farm varies based on the specific

A comparative analysis of
decommissioning
requirements for oil, gas, and other
O&G, tower foundation for wind
turbine), and the construction of
roads and access ways for site
site and turbine configuration, it
is estimated that the direct land
effect in Pennsylvania for one
electricity generation resources on construction and maintenance.2 wind turbine is approximately 2
federal, state, and county land O&G extraction sites also require acres (Table 1).7 The land use
illustrates what regulations are generators and fuel tanks.3 effect of a conventional natural
currently required for particular Additionally, reserve pits are gas well is estimated to be
resources. Furthermore, it typically constructed to store or roughly 7.5 acres per well.8 This
demonstrates how dispose of water for O&G estimate includes land used for
decommissioning regulations extraction activities.4 Wind well pads, seismic lines,
affect the growth, development,
and integration of electricity
Table 1: Direct Land Use Estimates for Wind Turbines and Conventional Gas Wells
resources. This article will focus
primarily on the decommissioning Project Type Land Use Estimate Units
regulations of conventional oil and Wind turbine 2 Acres/turbine
gas (O&G) extraction sites and Single vertical natural gas well 7.5 Acres/well

30 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
pipelines, and access implement FLPMA on public B. Federal O&G extraction
roads.9 lands.15 As defined by FLPMA, site decommissioning

T he Bureau of Land
Management (BLM) has
recognized large wind potential in
‘‘public lands’’ are the ‘‘lands
and interests in lands
administered by the Secretary of
regulations

There are currently


11 western states10: Arizona, the Interior, through the BLM.’’16 approximately 85,000 O&G wells
California, Colorado, Idaho, The BLM manages 261 million on federal public lands.21
Montana, Nevada, New Mexico, acres of public surface lands and Generally, as part of the
Oregon, Utah, Washington, and about 700 million acres of application and planning process
Wyoming.11 Similarly, the subsurface lands.17 Additionally, for O&G operations, the BLM
majority of O&G operations on the BLM is responsible for requires that O&G operators
federal public lands occur in 12 managing federally owned provide a bond to the agency to
western states: Alaska, Arizona, mineral resources in the ensure that there are sufficient
California, Colorado, Idaho, funds available to complete the
Montana, Nevada, New Mexico, required reclamation and fulfill all
Oregon, Utah, Washington, The Bureau other terms and conditions of the
and Wyoming.12 Seventy of Land lease, including payment of
percent of the BLM’s O&G permits Management federal royalties.22 The process of
are for wells in just two western obtaining a lease and permit for
states, Wyoming and New
has recognized O&G operations on federal public
Mexico.13 Consequently, the large wind lands begins when O&G operators
majority of O&G operations and potential in submit an ‘‘expression of interest,’’
wind energy facilities are sited in or pre-sale offer, on land they are
11 western
similar regions of the nation, interested in leasing.23 The BLM
thereby affecting similar states. reviews the submission, and if the
geographically situated agency deems that the land is
environments. eligible for lease, it places the land
subsurface of both federal public up for a competitive oil and gas
lands and privately owned lease sale.24 Once an operator has
III. Decommissioning surface estates, known as ‘‘split obtained a lease, the operator must
Regulations on Federal estates.’’18 apply for a permit to drill from the
Land BLM administers O&G BLM prior to preparing or drilling
operations and wind energy new oil or gas wells.25 In the
A. Federal regulatory agency project developments on application for a drilling permit,
Under the Federal Land Policy federal public lands. The BLM the operator must include proof of
and Management Act (FLPMA) manages O&G operations bond coverage and a surface use
of 1976, the Department of the through administrative plan of operations, which must
Interior (DOI) is directed to regulations and the development include a reclamation plan and the
manage ‘‘public lands under of wind energy resources on process required to accomplish the
principles of multiple use and federal public lands through reclamation plan.26 Under
sustained yield’’ and is charged right-of-way (ROW) FLPMA, the BLM generally does
‘‘to prevent unnecessary or authorizations.19 The BLM grants not require operators to submit
undue degradation of the ROW authorizations in cost estimates for completing
lands.’’14 From this statutory accordance with FLPMA and the reclamation—proof of bond
directive, the DOI authorized the BLM’s Wind Energy coverage and a reclamation plan
Bureau of Land Management to Development Policy.20 are sufficient. However, the

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 31
Mineral Leasing Act of 1920, as reclamation.’’31 The BLM set when the operator and the BLM
amended, does requires minimum bond levels to ensure determine that the well has no
demonstration of an adequate compliance with all legal more economic value.36 The final
bond or surety before the O&G requirements. The BLM requires reclamation plan is the approved
operators can begin to prepare bond coverage through one of plan in the operator’s permit. In an
land for drilling.27 several mechanisms: individual effort to reclaim the well site to

T he bond required by federal


regulations is intended to
ensure that the operator complies
lease bonds, statewide bonds, or
nationwide bonds.32 These bonds,
presented in Table 2, were set in
match the surrounding natural
environment, plans generally
include tasks like ‘‘plugging wells,
with the reclamation requirements 1951 and 1960 and have not been removing visual evidence of the
and all other terms and conditions updated or adjusted for inflation well and drill pad, recontouring
of the lease.28 The BLM reviews the since then.33 the affected land, and revegetating
application for a permit to drill by: Reclamation of an O&G well can the site with native species.’’37
‘‘(1) evaluating the operator’s occur at various points in the oil or Once the BLM determines that
proposal to ensure that the gas extraction process. Interim reclamation has been successful
proposed drilling plan conforms reclamation is the reclamation of (through a monitoring process
to the land use plan and applicable surfaces that were disturbed while which typically takes several
laws and regulations;’’ and, ‘‘(2) preparing a well for drilling, but years), it will approve a Final
inspects the proposed drilling site are no longer needed to safely Abandonment Notice.38 If the
to determine if additional site- service the well.34 For example, an O&G operations are managed by
specific conditions must be operator might initially require a another agency or if the well is on a
addressed before the operator can 3.7-acre area to safely drill a single split estate owned by a private
begin drilling.’’29 Once the BLM well, but needs only 1.5 acres to surface owner, the BLM will
approves the proposal, the service the well. Consequently, the obtain consent from that agency or
operator can commence drilling operator could reclaim the 2.2 private owner prior to approving
operations. In some states, drilling acres no longer needed in the the Final Abandonment Notice.39
operations must also be approved drilling operations. Although the O&G operators are also
by the state.30 BLM does not usually require permitted to delay reclamation

U nder the amended Mineral


Leasing Act of 1920, federal
regulations require operators to
interim reclamation, it sometimes
necessitates such reclamation for
specific O&G operations.35 Final
processes and allow the well to sit
idle.40 The BLM periodically
reviews idle wells to ensure that
establish bonds or sureties to reclamation refers to the the operator has legitimate
ensure ‘‘complete and timely reclamation process that occurs reasons, such as the future

Table 2: O&G Extraction Site Minimum Bonding Requirements


Bond Type Coverage Defined Set In Amount
Individual lease bond Cover all wells operator drills under one lease 1960 $10,000
Statewide bond Covers all of an operator’s leases in one state 1951 $25,000
Nationwide bond Covers all of an operator’s leases in the US 1951 $150,000
Other bonds Unit Operator Bonds: cover all operations conducted on leases within specific unit agreement,
determined on case-by-case basis.
National Petroleum Reserve in Alaska (NPR-A) Bonds: set in regulation; not less than $100,000
for single lease, or less than $300,000 for reserve wide bond.
Source: GAO-10-245, Oil and Gas Bonds: Bonding Requirements and BLM Expenditures to Reclaim Orphaned Wells, 13 (2010); 43 C.F.R. §§ 3104.2, 3.104.3.

32 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
economic viability of the well, to insufficient for reclamation and an area for competitive wind
delay reclamation.41 Although there are no responsible or liable energy leasing, whether through
operators are required to complete parties, wells are often federal or local land use planning
reclamation, some wells become abandoned.46 Consequently, the processes.50
orphaned wells. Orphaned wells are BLM is required to expend A FLPMA ROW is the
wells that have insufficient bonds federal funds to reclaim the mechanism used to authorize all
to cover reclamation and there are abandoned sites. commercial wind energy
no responsible or liable parties development projects on public
to reclaim the wells.42 In such C. Federal wind project lands.51 ROW authorizations
cases, the BLM uses federal decommissioning regulations approve all onsite access roads,
funding to reclaim the well. electrical and distribution
From 1998 through 2009, the Wind energy projects on federal facilities, and other support
BLM spent approximately $3.8 public lands are governed by the facilities, and require an annual
million reclaiming 295 orphaned rental fee and bonding amount.52
wells.43 As of December 2010, there
Wind
I n total, the BLM holds
approximately $162 million in
individual bonds for O&G
energy
were 29 approved wind
development projects on
BLM-administered lands with a
developments
reclamation processes.44 total installed capacity of
However, as noted by BLM
on federal 437 MW.53 The BLM has
officials, these bonds are not lands require identified seven additional
generally based on full two specific projects with a total potential
reclamation costs and would be capacity of 800 MW.54
bonding
insufficient if the government Wind energy developments on
were to have to complete requirements. federal lands require two specific
reclamation.45 As mentioned bonding requirements. First, a
above, most bonding bond is required for site testing
requirements are based on BLM’s Wind Energy Development and monitoring authorizations to
regulatory minimums that are Policy, which provides guidance ensure that the developer
designed only to account for to process ROW applications for complies with all terms and
compliance with the terms and site testing and monitoring conditions of the authorization.55
conditions of the lease, such as facilities for wind energy This bond is a minimum of $2,000
reclaiming disturbed lands, development on federal public per meteorological tower.56 The
plugging wells, and payment of lands.47 The policy states that all second bond is required with the
government royalties. These wind energy development project ROW authorization for the wind
bonds do not account for site- applications are to be processed project development. The
specific characteristics and according to the requirements of minimum bond amount for wind
reclamation costs that a FLPMA and the federal energy development on federal
particular well might require. regulations regarding ROWs.48 public lands is $10,000 per
Furthermore, the regulatory The BLM has the authority to turbine, considering salvage
minimums were established in identify public lands that are values of turbines and towers.57
the 1950s and 1960s, leaving the applicable for competitive bidding However, the precise amount of
minimum bonding amounts very for ROW authorizations.49 the bond is determined by site-
outdated and not reflective of, or However, the BLM is authorized to specific and project-specific
adequate for, actual reclamation do so only if a land use planning factors during the ROW
costs. When bonds are decision has specifically identified authorization process.58

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 33
Table 3: Comparison of Federal Decommissioning Bonding Requirements
Resource Required By Minimum Bonding Amount Set In Acceptable Forms of Bond
Oil and gas Bond required in permit Independent bond: $10,000 1960 Surety bond, third-party guarantee from private
to drill. Statewide bond: $25,000 1951 insurance company, or personal bond accompanied
Nationwide bond: $150,000 1951 with a cashier’s check or Treasury bond.
Wind ROW authorization $10,000/turbine 2010 Cash, cashier’s or certified check, Treasury bond,
or surety bond.

As Table 3 demonstrates, the resources.64 The goal of orphaned wells between 1998 and
acceptable bond instruments decommissioning is to restore the 2009.66 Accordingly, based on
under BLM regulations include turbine site to the physical these figures, the average actual
cash, cashier’s or certified check, condition of the land as it existed reclamation cost of these wells can
negotiable U.S. Treasury bonds, prior to development of the wind be assumed to be approximately
or surety bonds payable to the project. As demonstrated through $13,000 per well. The
BLM from the approved list of the decommissioning procedures, Pennsylvania Department of
sureties.59 The BLM does accept a the decommissioning of wind Environmental Protection (DEP)
letter of credit as an acceptable projects consists primarily of reported the average cost of
form of a bond.60 The BLM equipment removal and soil plugging a well and restoring the
periodically reviews—at least restoration. Despite the paucity of site averaged $60,000 per well.67
every five years—all bonds in data concerning the effectiveness Some reports estimate
order to ensure the adequacy of of wind project decommissioning, reclamation costs of up $100,000
the bonds.61 wind projects generally have a per well.68 Figure 1 shows these

D ecommissioning guidelines
for a wind energy project
must be developed and approved
higher minimum bond
requirement than O&G projects
creating a greater likelihood
reclamation costs and the
minimum BLM bonding
requirements normalized
by the BLM.62 Generally, that decommissioning will (divided) by the land use values
decommissioning procedures restore the land to its prior reported in Table 1. In Figure 1,
include the dismantling and condition.65 the minimum O&G bond is
removal of all towers, turbine $10,000 per independent well.69
generators, transformers, and
overhead cables; removal of all
underground cables; removal of
D. Comparison of Federal
O&G Extraction Site and
Wind Project
A review of permit
applications for different
wind farms illustrates
foundations, buildings, and Decommissioning decommissioning cost estimates
ancillary equipment; removal of Regulations ranging between $11,000 and
surface road material; and $50,000 per turbine.71 Figure 1
restoration of the roads and Beyond the basic regulatory also depicts the normalized
turbine sites to a substantially minimum bond amounts for O&G minimum bonding requirements
similar condition prior to the and wind projects, it is also useful compared to the actual
construction of the wind facility.63 to compare the bond amounts decommissioning costs for wind
Decommissioning procedures versus the actual cost of turbines. This comparison
include the restoration of the decommissioning. Reclamation demonstrates that, albeit
topography of the site, as well as cost data for O&G sites is scarce. significant uncertainty about the
restoring topsoil and reseeding As previously reported, the BLM actual decommissioning and
the surface to restore the natural spent $3.8 million reclaiming 295 restoration costs, the current

34 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
[(Figure_1)TD$IG]

Figure 1: Normalized Minimum Bonding Requirements and Reclamation/Decommissioning Costs70

bonding requirements for wind will not likely cover the full minimum generally have
will also likely be insufficient. costs of reclamation and minimum bond amounts that are

A lthough both O&G


operations and wind project
operations have seen a substantial
decommissioning. at least equal to or higher than
BLM’s minimum bond.76 States
have three types of bonds:
increase in recent years, the IV. Decommissioning statewide blanket bonds which cover
regulatory structures governing Regulations on State all the operator’s wells in the
O&G and wind development Land state, blanket bonds which cover
have not similarly developed.72 multiple wells in the state, or an
While the BLM has promulgated A. State O&G extraction site individual well bond.77 Of the
recent guidelines, policies, decommissioning regulations states that set individual well
and bonding requirements for States regulate O&G extraction minimum bonds by regulation,
wind development site operations through several some greatly exceed the BLM
decommissioning, it has not state authorities and minimum. For example, Alaska
updated O&G minimum bonds mechanisms.73 The 12 western and Washington require $100,000
since the 1950s and 1960s. states in which the majority of oil and $50,000 per well, respectively.
Consequently, regulations for and gas production occurs However, Idaho and Nevada
projects on federal public lands provide particularly illustrative require a $10,000 individual bond
impose a greater burden on wind examples of how state oil and gas per well, equal to the BLM
energy projects than O&G bonding requirements differ from regulatory minimum.78 Some
extraction activities. Furthermore, the BLM’s bonding requirements states require minimum bonds
notwithstanding the greater on federal lands.74 Many of these that are less than the federal
regulatory burden on wind states determine the bond amount minimum. For example, in
projects, it is evident that current based on characteristics of the Pennsylvania, the bond amount
bonding requirements for wind well—well depth or total number for a single well is $2,500.79 Some
and O&G development foster of wells covered by the bond.75 states require minimum
inadequate environmental Alternatively, states that set bond statewide bonds regardless of a
protection, as the required bonds amounts by a regulatory well’s characteristics—these

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 35
[(Figure_2)TD$IG]

Figure 2: O&G State Bonding and Reclamation Cost Comparison

include Alaska, Idaho, Montana, decommissioning requirements renewable energy facilities on the
Nevada, New Mexico, and bonds rely on various establishment of a
Pennsylvania, Washington, and mechanisms to implement decommissioning plan and
Wyoming. These states have a decommissioning requirements. financial assurance. In order to be
regulatory minimum greater than While a more comprehensive list approved by the state utility
the BLM’s $25,000 bond per well, of state decommissioning regulatory body in Vermont, the
except for Idaho, which has an requirements is set out in Vermont Public Service Board
equal minimum bonding Table A1 in Appendix A, a few of (PSB), energy facilities must
requirement.80,81 the more illustrative requirements receive a ‘‘certificate of public
Figure 2 shows the normalized are analyzed here. In Minnesota, a good.’’84 The PSB has consistently
bonding requirement for state statute requires the public conditioned a certificate of public
individual wells and reclamation utilities commission (PUC) to good on a facility’s
costs for particular states. develop rules to govern the site decommissioning plan, which
Alaska’s bonding requirements restoration of large wind energy must include a detailed cost
closely resemble actual projects, called large wind energy estimate of decommissioning, as
reclamation costs. Conversely, conversion systems (LWECS).82 well as a mechanism to guarantee
Pennsylvania’s bonding Accordingly, the Minnesota PUC a secured fund to be available
requirements are demonstrably promulgated regulations for when decommissioning is
inadequate.68 decommissioning and restoration necessary.85 Similarly, in Indiana,
requirements, including the the Utility Regulatory
B. State wind mandatory assurance from wind Commission requires facilities to
decommissioning regulations developers that funds will be establish a decommissioning plan
available for decommissioning that includes a financial assurance
Currently, relatively few states and restoration.83 equal to the estimated amount for
demolition and removal costs.86
have decommissioning and bond
requirements for wind energy
projects. The states that do impose
A lternatively, some states—
like Vermont and
Indiana—condition approval of
The plan must be secured through
the form of a bond, letter, or

36 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
credit, or other acceptable procedures of wind projects more information, see
guarantee.87 The under a specified nameplate Appendix A.
decommissioning plan is capacity (i.e., 100 MW).93 In South
developed and approved through Dakota, the Public Utilities C. Comparison of state O&G
the renewable energy project’s Commission requires extraction site and wind
review and approval.88 decommissioning plans, cost project decommissioning

O ther states govern the


decommissioning of
renewable energy facilities
estimates, and may require a bond
or other guarantee for wind farms
over 100 MW.94 If the wind
regulations

Generally, although state O&G


through energy facility siting project does not exceed 100 MW, extraction site decommissioning
evaluation committees. Although city and county ordinances are regulations impose greater
these committees vary greatly bonding requirements than
depending on the state enabling federal regulations for O&G
statute, the purpose of an energy decommissioning, the bonding
facility siting evaluation requirements are still insufficient
committee is to create a state- to meet the actual costs of
sponsored entity to review and decommissioning. Additionally,
oversee large energy facilities and although, state O&G extraction
infrastructure.89 In Oregon, the site decommissioning regulations
Oregon Energy Facility Siting appear to be more widely
Council (OREFSC) has broad adopted across states that
public interest authority, decommissioning regulations for
including the authority to impose wind turbines, the required state
decommissioning standards on wind decommissioning bonds are
any facility within its jurisdiction expected to adequately meet the
through the site certification often passed to impose permitting actual costs of decommissioning.
process.90 Under this authority, requirements.95 Under state wind
the OREFSC developed However, state decommissioning regulations, all
requirements for retirement and decommissioning regulations are bonds and financial assurances
financial assurances for not common. A review of state are set on a case-by-case basis.
decommissioning facilities.91 decommissioning requirements Consequently, decommissioning
Accordingly, in order to be reveals that only a few states have bonding requirements are likely
granted a site certificate to requirements for more reflective of the actual costs
construct a facility, an applicant decommissioning wind projects, of project decommissioning and
must detail its proposal for site or renewable energy projects site reclamation.
restoration and costs, the OREFSC more generally. Of the states that
reviews the plan and cost do impose requirements on wind
estimate, sets a required fund for energy developers, the V. Decommissioning
decommissioning, and then requirements are not Regulations at the
requires a bond or letter of credit standardized and are assessed on County Level
to be established before the a case-by-case basis. Unlike
applicant can begin decommissioning requirements Many counties throughout the
construction.92 on federal land, there is no United States have enacted

I n other states, like South


Dakota, local ordinances
regulate the decommissioning
generally adopted minimum
bonding requirements for
developments on state lands. For
ordinances to regulate the
development of wind energy
resources on local lands. Table B1

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 37
in Appendix B, though not operations generally supplement generation potential of a specific
exhaustive, provides a sample of federal and state regulations and natural gas well or wind turbine is
county wind ordinances across do not include specific language highly dependent on the project, a
the country. A survey of these or requirements for natural gas well generally
ordinances reveals that most decommissioning O&G wells on provides energy that can be
ordinances include language that, local land.99 turned into more electricity over
in effect, requires a secure Wind projects on county land the lifetime of the well compared
financial assurance for the costs of have likely caught the attention of to a wind turbine. Thus, although
decommissioning and reclaiming local regulators because of the wind turbines may have more
a site.96 Although the ordinances recentness of wind energy stringent bonding requirements
do not specify particular financial development and the lack of a than natural gas wells, more wind
amounts, they generally provide longstanding regulatory regime. turbines are required to produce
that the decommissioning funds Without complete details on the same amount of electricity as a
be adequate for the full cost of decommissioning funding natural gas well produces.
decommissioning and require requirements for wind or O&G Table 4 shows lifetime
approval by the appropriate resources at the county level, a electricity generation estimates
county, town, or regulatory quantitative analysis of the effect assuming different project
authority.97 Thus, and implication of these lifetimes, average lifetime gas
decommissioning requirements ordinances cannot be undertaken. generation rates, and wind
and financial securities are capacity factors. These numbers
approved on a case-by-case basis. assume a 2 MW turbine and a
VI. Electricity
F or example, in Vermilion
County, Ill., a wind energy
project was approved with the
Generation Potential
natural gas power plant efficiency
of 50 percent. These values are
highly dependent on the specific
contractual obligation that the Although the paramount project and site so a generalized
developer was responsible for the concern with decommissioning comparison of these values is not
full costs of decommissioning the regulations centers around the appropriate. As an example,
project—an estimated $98,000 per environmental impacts associated however, the normalized BLM
turbine.98 with inadequately restored sites, bonding requirement for a well
Conversely, county ordinances it is also useful to note the that produces natural gas for 30
for oil and gas wells are not as differences in electricity years at a rate of 0.2 MMcf/day is
widespread. Again, though not an generation potential between roughly $4,000/acre-TWh of
exhaustive review, county wind turbines and natural gas electricity generated. The
ordinances regulating O&G wells. Although the electricity restoration costs for this well

Table 4: Lifetime Electricity Generation for Wind Turbines and Natural Gas (MWh/Project Lifetime)a
Project Lifetime (yr) Average Lifetime Production Rate for
Vertical Well (MMcf/day) Wind Turbine Capacity Factor
0.05 0.1 0.2 0.15 0.25 0.4
10 28,000 55,000 110,000 26,000 44,000 70,000
20 55,000 110,000 220,000 53,000 88,000 140,000
30 83,000 165,000 330,000 79,000 130,000 210,000
a
Average lifetime production rate for vertical wells was chosen based on average production rates for natural gas wells between 1989 and 2009. Production of natural gas declines
over the years. In this analysis, however, we are interested in total production, so an average number for the entire well lifetime is appropriate. A heat rate of 6,828 Btu/kWh was used
for the natural gas plant. See U.S. ENERGY INFO. ADMIN., Natural Gas: Number of Production Wells (Nov. 29, 2011), at http://www.eia.gov/dnav/ng/ng_prod_wells_s1_a.htm; U.S. Energy
Info. Admin., Natural Gas: Natural Gas Gross Withdrawals and Production (Nov. 29, 2011), at http://www.eia.gov/dnav/ng/ng_prod_sum_dcu_NUS_a.htm.

38 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
could be as high as $40,000/acre-
TWh. For a wind turbine with a
30-year lifetime and a capacity
However, it is evident that the
bonding requirements imposed
by the regulations are insufficient.
L astly, although both O&G
and wind decommissioning
regulations are insufficient to
factor of 40 percent, the The federal government has also cover the actual costs of
normalized bonding requirement enacted federal regulations for decommissioning, it is important
is roughly $25,000/acre-TWh, decommissioning requirements to note the disparity in the
while the decommissioning cost and minimum bond securities for regulatory requirements. In
can be as high as $125,000/acre- wind projects on federal lands. order to adequately integrate
TWh. Thus, while the bond However, few states have renewable energy, the policy
required for the wind farm developed decommissioning environment must ensure that
accounts for 20 percent of the regulations for wind facilities. wind projects are constructed,
normalized decommissioning Regulatory bonding requirements operated, and retired in an
costs, the bond for the O&G well for wind projects on federal lands, environmentally sensitive
accounts for only 10 percent of the although established more manner, and that the cost of
reclamation costs. recently than the O&G bonding doing so does not
requirements, also seem to be disproportionately disadvantage
insufficient. However, the states the facilitation of renewable
VII. Conclusions which have established energy. Accordingly, equitable
decommissioning regulations for regulatory burdens are necessary
A comparison of federal, state, wind projects require bonding for all energy activities so that
and county decommissioning amounts on a case-by-case basis. each resource is subject to
regulations for O&G extraction Evaluating decommissioning environmental accountability
sites and wind energy projects bonding requirements on a case- and proportional regulatory
reveals that, generally, regulatory by-case basis will most likely burdens. Creating a level playing
requirements are wholly produce more accurate bond field amongst energy resources is
insufficient to adequately secure amounts. Consequently, state imperative so that resource
the costs of decommissioning. decommissioning requirements selection amongst competing

A t both the federal and state


level, agencies have
enacted decommissioning
may potentially serve as a useful
regulatory model for establishing
adequate decommissioning
resources is not
disproportionately burdened by
differences or inadequacies in
regulations for O&G activities. requirements. regulatory systems.

Appendix A
Table A1: State Decommissioning Regulations
Renewable
Facility
Decommissioning
Rules/Fund Type/Notes
Alabama No –
Arizona No –
Arkansas No –
California No Have general facility closure requirements for energy facility licensing, but no bond. Cal. Pub. Res.
Code § 25532 (2010).
Colorado No –
Delaware No –

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 39
Table A1 (Continued )

Renewable
Facility
Decommissioning
Rules/Fund Type/Notes
Florida No –
Georgia No –
Hawaii Yes Decommissioning rules, but no fund requirements. Hawaii Rev. Stat. § 269-1(G).
Idaho No –
Iowa No –
Indiana Yes Decommissioning rules and funds for wind projects. Indiana Utility Regulation Commission, Order
No. 43602; Order No. 43759; Order No. 43678.
Kansas No Only local ordinances.
Massachusetts No Generally, decommissioning procedures are established within specific agreements between
developers and site owners.
Maine Yes Me. Rev. Stat. tit. 38, § 481–490. In pertinent part, § 490 (2), ‘‘Bonds. The department may require
a bond payable to the State with sureties satisfactory to the department or such other security as
the department may determine will adequately secure compliance with this chapter, conditioned
upon the faithful performance of the requirements set forth in this chapter and of the rules of the
board.’’

See also, Spruce Mountain Wind Project Maine DEP Site Location of Development Act Permit
Application, Section 29 (Jan. 21, 2010).
Michigan No –
Minnesota Yes MINN. STAT. § 216F.05; MN ADC 7854.0500, Subpart 13.
Montana No –
New Mexico No –
New York Yes, if over 80 MW Municipal ordinances if below 80 MW; otherwise under Public Service Law Article X certification
nameplate capacity. requirements (expired 2003).
North Dakota Yes Decommissioning of commercial wind energy facilities.
N.D. Admin. Code §§ 69-09-09-06, 69-09-09-07 (2008).
Ohio Yes, if over 5 MW Public Utility Commission of Ohio requires plan for decommissioning and discussion of financial
nameplate capacity. arrangements designed to assure requisite financials to carry out the plan. Ohio Admin. Code
Chapter 4906-17.
Oregon Yes Under jurisdiction of Energy Facility Siting Board which estimates costs of restoration and
mandates bond or letter of credit as financial security for site restoration.
South Dakota Yes, if over 100 MW PUC encourages use of local ordinances based on draft model if rated under 100 MW.
nameplate capacity.
Texas No –
Virginia No DEQ regulations may apply.
Vermont Yes Condition for Public Service Board approval of Certificate of Public Good under 30 V.S.A. §248
which establishes requirements for in-state electric transmission and generation construction
projects. See Order Re Lease Language, Decommissioning Plan, and Request for Hearing,
Docket No. 7156 (2007).
Source: Decommissioning Funds for Renewable Energy Facilities, Danielle Changala and Jonathan Voegele, Vermont Law School Institute for Energy and the Environment (2010),
Presented at First Integration and Policy Workshop for the RenewElec Project, Oct. 21–22, 2010, Carnegie Mellon University, Pittsburgh.

40 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
Appendix B

Table B1: County Wind Decommissioning Ordinances


County State Ordinance Enacted In Requires Project Examples
Chautauqua NY County requires 2010 Requires a financial security in the Ripley-Westfield Wind
‘‘Draft Environmental form of a letter of credit, a bond, or cash. Farma (2009).
Impact Statement’’ Amount of financial security will be in an Estimated
Available at: http://www. amount sufficient to adequately perform decommissioning
ripleywestfieldwind.ene. the required decommissioning pursuant cost per turbine to
com/files/EIS/Appendix% to local, state, and federal environmental be $64,680.
20F%20-%20 regulations. The amount of the financial
Decommissioning% assurance can be modified to reflect
20Plan.pdf changes in the decommissioning costs
or salvage value of the project
equipment.
Clay MN Clay County Wind 2009 Requires a decommissioning plan,
Ordinance No. 2009-2 which includes the decommissioning
costs—determined by a competent
party—and identifies the financial
resources which will be used to fund the
decommissioning.
Fillmore MN Wind Energy Conversion 2007 Requires each commercial wind
System Ordinance energy conversion system (WECS) to
Available at: http://www.co. have a decommissioning plan that
fillmore.mn.us/zoning/ details the anticipated means and cost of
documents/2008wind_ decommissioning the project. The cost
energy_conversion_ estimate should be made by a person
systems_ord.pdf with competent expertise or experience
with decommissioning. The
decommissioning plan should also
identify the financial resources that will
be available to pay for the project’s
decommissioning.
Hyde County NC Hyde County Ordinance 2008 –
2008-10-01
Huron MI Huron County Wind Energy 2010 Requires a performance bond or –
Conversion Facility Overlay equivalent financial instrument at an
Zoning Ordinance amount determined by the County to be
used for decommissioning and site
Available at: http://www.deq. restoration.
state.mi.us/documents/deq-
ess-p2-agp2-ArticleIII(Revised).
pdf

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 41
Table B1 (Continued )

County State Ordinance Enacted In Requires Project Examples


Pike County IL Available at: 2011 Requires a financial assurance equal to Affinity Wind Farm;
http://suretybond.ca/ 20% of the total project first project phase
news/Article.aspx?id= decommissioning cost in years 1–4 of to be constructed at
176643&page=windfarm- operation; the level rises each year until end of 2011.b
surety-bond-will- it reaches 100% of decommissioning
ensure-eventual- costs for years
decommissioning- 17–20 of operation. Licensee
176643 reassesses project decommissioning
costs at years 8, 16, 20 and every
consecutive year there after.
Riley County KS County Regulations for 2006 Requires a security assurance, in the –
Wind Energy Conversion form of a letter of credit, a cash escrow
Systems, Special Uses, account, a performance bond, or other
Section 22 form of security acceptable to the
Available at: http://www. County, to be used to pay the costs of
rileycountyks.gov/documents/ decommissioning and site reclamation.
Planning%20and%20 The financial security should equal
Development/Zoning%20 100% of the estimated
Regulations/y)%20Section decommissioning and reclamation
%2022%20-%20Special costs, and shall provide for an annual
%20Uses.pdf adjustment based on inflation.
Redwood MN Redwood County Zoning 2009 Decommissioning plan must include how –
Ordinance, Section 19, the decommissioning costs will be
Wind Power Management covered; applicants may be required to
Available at: http://www.co. establish an escrow account to fund the
redwood.mn.us/Zoning_ decommissioning costs.
Ordinance/SECTION% Decommissioning plan must include the
2019%20WINDPOWER% estimated costs of decommissioning.
20MANAGEMENT.pdf
Shawano WI Wind Energy Conversion 2005 Developer must provide a financial –
System Ordinance security to insure decommissioning and
Available at: http://www.co. removal of the facility.
shawano.wi.us/departments/
page_aa67df910805/
?department=c61420c
5769b&subdepartment=
05e3b7e00867 (follow ‘‘Wind
Energy Conversion System’’).
Solano CA Solano County Zoning Ordinance; 1987 Liens, surety bonds or other security may Montezuma Wind
Wind Turbine Siting Plan be required as part or condition of any Plant Projectc
Available at: http://www.co. wind turbine generator project.
solano.ca.us/civicax/
filebank/blobdload.aspx?
blobid=5369

42 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
Table B1 (Continued )

County State Ordinance Enacted In Requires Project Examples


Vermilion IL Vermilion County Wind Energy 2009 A secure financial assurance of a California Ridge Wind
Structure Ordinance, reasonable amount agreed to by the Energy Project;
Ordinance No. 09-0102. relevant parties. included a
Available at: http://www. contractual
vercounty.org/ctybrd/ agreement to cover
Vermilion%20County% cost of
20-%20California%20 decommission
Ridge%20wind%20project equivalent to
%20building%20permit $98,000 per
%20application.pdf turbine.
This is not an exhaustive survey of county wind ordinances; it is provided to illustrate and highlight common language and requirements found throughout many county wind
ordinances.
a
Decommissioning Plan, Ripley-Westfield Wind Farm, at http://www.ripleywestfieldwind.ene.com/files/EIS/Appendix%20F%20-%20Decommissioning%20Plan.pdf (2009).
b
Pike County Requires Surety Bond from Wind Farm Developers, WHIG.COM (Sept. 1, 2011), at http://suretybond.ca/news/Article.aspx?id=176643&page=windfarm-surety-bond-will-
ensure-eventual-decommissioning-176643.
c
See Amendment Final Environmental Impact Report, Montezuma Wind Plant Project (U-06-06), at http://www.co.solano.ca.us/civicax/filebank/blobdload.aspx?blobid=7860
(2010).

A comparison of federal, state, and county decommissioning regulations reveals that, generally,
regulatory requirements are wholly insufficient to adequately secure the costs of decommissioning.

Endnotes: EXPENDITURES TO RECLAIM ORPHANED 5. U.S. DEP’T OF THE INTERIOR BUREAU OF


WELLS, 6 (2010); U.S. DEP’T OF THE LAND MGMT., FES 05-11, FINAL
1. Comparisons of other energy INTERIOR BUREAU OF LAND MGMT., FES PROGRAMMATIC ENVIRONMENTAL IMPACT
resources like uranium mining, 05-11, FINAL PROGRAMMATIC STATEMENT ON WIND ENERGY
coal mining, solar projects, etc., could ENVIRONMENTAL IMPACT STATEMENT ON DEVELOPMENT ON BLM-ADMINISTERED
also provide useful comparisons and WIND ENERGY DEVELOPMENT ON BLM- LANDS IN THE WESTERN UNITED STATES, 3–
could be analyzed in subsequent ADMINISTERED LANDS IN THE WESTERN 2 (2005).
research. UNITED STATES, 3–2 (2005).
6. Id.
2. U.S. GOV’T ACCOUNTABILITY OFFICE, 3. OIL AND GAS BONDS, supra note 2, at 6.
GAO-10-245, OIL AND GAS BONDS: 7. See Nels Johnson, Pennsylvania
BONDING REQUIREMENTS AND BLM 4. Id. Energy Impact Assessment (Nov. 15,

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 43
2010), at http://www.nature.org/ 22. 43 C.F.R. §§ 3160–3162; OIL AND federal rate of return multiplied by
media/pa/pa_energy_assessment_ GAS BONDS, supra note 2, at 1. $0.03 average price per kilowatt.
report.pdf (estimating land use
23. Id. at 6. 53. BLM Fact Sheet, supra note 11.
impacts of wind turbines by
using digitalized aerial images 24. Id. 54. Id.
of wind development areas before
25. OIL AND GAS BONDS, supra note 2, 55. WIND ENERGY DEVELOPMENT POLICY,
and after wind turbine installation.
at 7. supra note 20, at 5; 43 C.F.R.
The Nature Conservancy analyzed
2804.12(a)(5); 43 C.F.R. 2804.24(a)(5).
roughly 320 turbines in 12 sites across 26. Id.
the state of Pennsylvania.). 56. Id.
27. Id.
8. Sarah M. Jordaan, David W. Keith 57. Id. at 8. The minimum bonding
28. Id.
and Brad Stelfox, Quantifying land use amount of a wind turbine has
of oil sands production: a life cycle 29. Id. been updated since the BLM’s 2006
perspective, ENVIRON. RES. LETT. 4 Wind Energy Development Policy,
30. Id. at 8.
(2009). where the bonding requirement was
31. Id. at 12. $2,500/per turbine. See generally WIND
9. Id. ENERGY DEVELOPMENT POLICY, supra
32. Id. note 20.
10. U.S. Dep’t of the Interior Bureau of
Land Mgmt., BLM Fact Sheet: 33. Id. at 13. 58. WIND ENERGY DEVELOPMENT POLICY,
Renewable Energy and the BLM, at 34. Id. supra note 20, at 8.
http://www.blm.gov/pgdata/etc./
medialib/blm/wo/MINERALS__ 35. Id. 59. Id.
REALTY__AND_RESOURCE_ 36. Id. 60. Id.
PROTECTION_/energy/renewable_
references.Par.95879.File.dat/2010% 37. Id. 61. Id.
20Renewable%20Energy%20 62. U.S. Dep’t of the Interior, BLM
38. Id.
headed.pdf. Wind Energy Program Policies and Best
39. Id. Mgmt. Practices, Attachment 1–19
11. FINAL PROGRAMMATIC
ENVIRONMENTAL IMPACT STATEMENT ON 40. Id. (2009).
WIND ENERGY DEVELOPMENT, supra note 41. Id. at 8–9. 63. N.D. CENT. CODE § 28-32-02; 49-02-
5, at 4–33. 27 (2008).
42. Id. at 9.
12. OIL AND GAS BONDS, supra note 2, at 64. Id.; South Dakota Permit
22–23. 43. Id. at 16. Requirements, Docket No. EL08-031,
44. The $162 million figure reflects the at: http://puc.sd.gov/commission/
13. Id. at 10. dockets/electric/2008/el08-031/
total amount secured in bonds. A well
can only access the bond secured for Appendix%20h.pdf (2008).
14. FEDERAL LANDS MGMT. POLICY ACT
OF 1976, 43 U.S.C. § 1732(a)–(b) (2006). its individual project. Id. at 10.
65. WIND ENERGY AMERICA, Frequently
45. Id. Asked Questions, at http://www.
15. Id. at § 1701 et seq.
windenergyamerica.com/faqs.html.
16. U.S. DEP’T OF THE INTERIOR BUREAU OF 46. Id.
LAND MGMT., 135 DM 1, DEP’T MANUAL 47. WIND ENERGY DEVELOPMENT POLICY, 66. Id. at 16.
(effective Sept. 20, 2007). supra note 20, at 1. 67. Austin L. Mitchell and Elizabeth
17. OIL AND GAS BONDS, supra note 2, 48. 43 C.F.R. § 2800. Casman, Economic Incentives and
at 1. Regulatory Framework for Shale Gas Well
49. 43 C.F.R. § 2803.23(c). Site Reclamation in Pennsylvania (2011),
18. Id. ENVTL. SCI. & TECH., 45 (22) at 9506–
50. WIND ENERGY DEVELOPMENT POLICY,
19. 43 C.F.R. § 3160–3165; U.S. DEP’T OF supra note 20, at 9. 9514.
THE INTERIOR BUREAU OF LAND MGMT., IM
51. Id. at 7. 68. Matt Andersen, Roger Coupal and
2009-043, WIND ENERGY DEVELOPMENT Bridgette White, Reclamation Costs and
POLICY, 9 (2008). 52. Id. at 7–8. The annual rental fee is Regulation of Oil and Gas Development
equal to the anticipated total installed with Application to Wyoming, Western
20. 43 U.S.C. § 1730 et seq.; WIND
capacity in kilowatts on public lands Economics Forum (2009), at http://
ENERGY DEVELOPMENT POLICY, supra note
as identified in the approved plan of ageconsearch.umn.edu/bitstream/
19, at 9.
development (POD) multiplied by 8,760 92846/2/0801005.pdf.
21. OIL AND GAS BONDS, supra note 2, at hours per year multiplied by a 30%
11. capacity factor multiplied by 5.27% 69. See Table 3.

44 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
70. Reclamation costs and the the land use estimates reported in representatives from various
minimum BLM bonding requirements Table 1. regulatory agencies, public citizens
were normalized by dividing them by and governor appointees. EFSECs are
82. MINN. STAT. ANN. § 216F.05 (2008).
the land use values reported in Table 1. typically responsible for reviewing
83. MINN. R. 7854.0500, Subpart 13. conventional thermal power plants,
71. Hounsfield Wind Farm:
Neither the statute or regulations pipelines and storage facilities,
Decommissioning Plan (Aug. 12,
specify what method must be transmission lines, and renewable
2008), at http://www.dec.ny.gov/
employed to ensure adequate generation projects which meet a
docs/permits_ej_operations_pdf/
funds for decommissioning, just certain capacity.
hnsfldappendixu.pdf; Record Hill
that the developer ensure that
Wind Project: Decommissioning Plan 90. See OR. ADMIN. R. 345-022-0050;
adequate funds be available. In
(2009), at http://www.maine.gov/ OREFSC jurisdiction for renewables
Commission review, the commission
dep/blwq/docstand/sitelaw/ includes any geothermal, solar, or
requires only ‘‘[t]he owner will be
Selected%20developments/ wind project of 35 MW or more.
responsible for costs to decommission
Record_Hill/Section%2029%20
the project and associated facilities.’’ 91. Id.
Decommissioning%20Plan.pdf;
In the Matter of the Site Permit
Buffalo Ridge II Wind Farm: 92. OR. ADMIN. R. 345-022-0050(1); The
Application for a 20 Megawatt Large
Decommissioning Plan (Oct. 2008), at OREFSC’s determination is a case-by-
Wind Energy Conversion System in
http://puc.sd.gov/commission/ case factual evaluation.
Stevens County, Minnesota, NO. IP-
dockets/electric/2008/el08-031/
6824, 2010 WL 750957 (Minn. PUC 93. S.D. CODIFIED LAWS § 49-41B-2 (5),
Appendix%20h.pdf. These estimates
2010). (6), (12).
include a credit for the scrap steel that
can be recovered from the turbine. 84. 30 V.S.A §248.
94. S.D. ADMIN. R. 20:10:22:33, 33.01,
72. From 1988 to 2008, the number of 85. Order Re Lease Language, and 33.02.
O&G wells on federal lands increased Decommissioning Plan, and Request for
from almost 50,000 wells to 85,000 95. See, e.g., S.D. Public Utilities
Hearings, Docket No. 7156 (VT PSB
wells—with the increase occurring Comm’n, Model Ordinance for Siting
Aug. 8, 2007); see also Order Re Lease
primarily in the last decade. OIL AND of Wind Energy Systems (WES)
Language, Decommissioning Plan, and
GAS BONDS, supra note 2, at 11. Overview, at http://puc.sd.gov/
Request for Hearings, Docket No. 7156
commission/twg/WindEnergy
(VT PSB May 14, 2008) (finding that
73. See National Energy Technology Ordinanceoverview.pdf.
the applicant’s ‘‘revisions to its
Laboratory, Protecting Our Country’s
decommissioning plan adequately 96. See Appendix B.
Resources: The States’ Case, 27–61
address the issues that the Department
(2008), at http://iogcc.publishpath. 97. See, e.g., Ripley Westfield Wind
had previously raised regarding the
com/Websites/iogcc/pdfs/2008- Decommissioning Plan, at http://
plan: the revised plan includes an
Protecting-Our-Country’s-Resources- www.ripleywestfieldwind.ene.com/
appropriate adjustment for inflation; it
The-States’-Case.pdf. files/EIS/Appendix%20F%20-%20
provides for full decommissioning of
74. OIL AND GAS BONDS, supra note 2, at the substation; and it includes as a Decommissioning%20Plan.pdf (2009)
20. reporting mechanism the requirement (‘‘Any bond or letter of credit will be in
that UPC file with the Board the a form reasonably acceptable to the
75. Id. at 20–21. Towns and issued by an institution
project’s annual energy production as
76. Id. at 23. reported to ISO-New England.’’). reasonably acceptable to the
Towns. . .The financial security will be
77. Id. at 20. 86. In the Matter of the Petition by in an amount sufficient to adequately
78. Id. at 23. Meadow Lake Wind Farm LLC, perform the required
79. Although it is important to note Docket No. 43602 (Indiana Utility decommissioning per this plan and all
Pennsylvania’s statewide minimum Regulatory Comm’n 2008); In the local, state and federal environmental
bond is $25,000 which is equal to the Matter of the Petition by Meadow regulations.’’).
federal minimum bonding amount. Lake Wind Farm III LLC, Docket No.
43759 (Indiana Utility Regulatory 98. Vermilion County Wind Energy
COMMONWEALTH OF PENNSYLVANIA Structure Ordinance Building Permit
DEPARTMENT OF ENVIRONMENTAL Comm’n 2009); In the Matter of the
Petition by Meadow Lake Wind Farm Application, California Ridge Wind
PROTECTION, Oil and Gas Well Drilling Energy Project, Section 4.3.6
and Production in Pennsylvania, at II LLC, Docket No. 43678 (Indiana
Utility Regulatory Comm’n 2009). Decommissioning and Restoration, at
http://www.columbiacountyema. http://www.vercounty.org/ctybrd/
org/Oil%20%20&%20Gas%20Wells. 87. Id. Vermilion%20County%20-%20
pdf (2007). California%20Ridge%20wind%20
88. Id.
80. Id. project%20building%20permit%20
89. Although they vary, EFSECs are application.pdf (2011).
81. The costs presented in the y-axis typically one-stop licensing
have been normalized (divided) by committees consisting of 99. Id.

Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 45

You might also like