Professional Documents
Culture Documents
Jan./Feb 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 29
also ensures that the addition of wind projects.1 The comparison project developments typically
renewable resources will not create between O&G extraction sites and involve such activities as:
additional environmental wind energy projects provides a creating site access; performing
problems in the wake of a clean particularly appropriate site grading; constructing lay-
energy solution. The comparison due to similarities in down areas and an on-site road
decommissioning requirements the projects’ land use patterns. A system; removing vegetation;
governing energy generation comparison of the regulations digging for and installing tower
projects are an imperative governing both O&G extraction foundations; erecting towers and
component of such a regulatory sites and wind energy projects installing nacelles and rotors;
structure—adequate demonstrates how regulations installing meteorological towers;
requirements and funds need to be differ for each of these energy constructing electrical
secured for reclamation and resources and the implications substations; and connecting all
decommissioning costs to ensure these regulatory structures have necessary structures with power-
that wind projects will not be on resource development. conducting and signal cables.5
abandoned without appropriate Though technological
securities after their useful developments in recent years
lifetime. While these II. Similar Land Use have supported growing
environmental assurances are Impacts Between O&G efforts to develop
necessary, it is also important to Extraction Site unconventional shale gas
recognize that these assurances Operations and Wind resources through the use of
must be similarly imposed on all Projects horizontal drilling, this article
energy resources, so as not to set focuses on the land use and
back or advance any particular O&G extraction sites and wind reclamation of conventional
resource over another. projects have some similarities in O&G wells drilled in single pads.
Fundamentally, resources should
be on a level playing field so that
selection amongst competing
their surface land use patterns.
The construction and operation
processes of each require the
G enerally, wind farms
require surface land use for
turbine foundations, roads, and
energy resources are not distorted removal of topsoil from the other infrastructure.6 Although
by disproportional regulatory well/turbine site, laying a the land required for a wind
burdens. cement/gravel pad (well pad for farm varies based on the specific
A comparative analysis of
decommissioning
requirements for oil, gas, and other
O&G, tower foundation for wind
turbine), and the construction of
roads and access ways for site
site and turbine configuration, it
is estimated that the direct land
effect in Pennsylvania for one
electricity generation resources on construction and maintenance.2 wind turbine is approximately 2
federal, state, and county land O&G extraction sites also require acres (Table 1).7 The land use
illustrates what regulations are generators and fuel tanks.3 effect of a conventional natural
currently required for particular Additionally, reserve pits are gas well is estimated to be
resources. Furthermore, it typically constructed to store or roughly 7.5 acres per well.8 This
demonstrates how dispose of water for O&G estimate includes land used for
decommissioning regulations extraction activities.4 Wind well pads, seismic lines,
affect the growth, development,
and integration of electricity
Table 1: Direct Land Use Estimates for Wind Turbines and Conventional Gas Wells
resources. This article will focus
primarily on the decommissioning Project Type Land Use Estimate Units
regulations of conventional oil and Wind turbine 2 Acres/turbine
gas (O&G) extraction sites and Single vertical natural gas well 7.5 Acres/well
30 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
pipelines, and access implement FLPMA on public B. Federal O&G extraction
roads.9 lands.15 As defined by FLPMA, site decommissioning
T he Bureau of Land
Management (BLM) has
recognized large wind potential in
‘‘public lands’’ are the ‘‘lands
and interests in lands
administered by the Secretary of
regulations
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 31
Mineral Leasing Act of 1920, as reclamation.’’31 The BLM set when the operator and the BLM
amended, does requires minimum bond levels to ensure determine that the well has no
demonstration of an adequate compliance with all legal more economic value.36 The final
bond or surety before the O&G requirements. The BLM requires reclamation plan is the approved
operators can begin to prepare bond coverage through one of plan in the operator’s permit. In an
land for drilling.27 several mechanisms: individual effort to reclaim the well site to
32 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
economic viability of the well, to insufficient for reclamation and an area for competitive wind
delay reclamation.41 Although there are no responsible or liable energy leasing, whether through
operators are required to complete parties, wells are often federal or local land use planning
reclamation, some wells become abandoned.46 Consequently, the processes.50
orphaned wells. Orphaned wells are BLM is required to expend A FLPMA ROW is the
wells that have insufficient bonds federal funds to reclaim the mechanism used to authorize all
to cover reclamation and there are abandoned sites. commercial wind energy
no responsible or liable parties development projects on public
to reclaim the wells.42 In such C. Federal wind project lands.51 ROW authorizations
cases, the BLM uses federal decommissioning regulations approve all onsite access roads,
funding to reclaim the well. electrical and distribution
From 1998 through 2009, the Wind energy projects on federal facilities, and other support
BLM spent approximately $3.8 public lands are governed by the facilities, and require an annual
million reclaiming 295 orphaned rental fee and bonding amount.52
wells.43 As of December 2010, there
Wind
I n total, the BLM holds
approximately $162 million in
individual bonds for O&G
energy
were 29 approved wind
development projects on
BLM-administered lands with a
developments
reclamation processes.44 total installed capacity of
However, as noted by BLM
on federal 437 MW.53 The BLM has
officials, these bonds are not lands require identified seven additional
generally based on full two specific projects with a total potential
reclamation costs and would be capacity of 800 MW.54
bonding
insufficient if the government Wind energy developments on
were to have to complete requirements. federal lands require two specific
reclamation.45 As mentioned bonding requirements. First, a
above, most bonding bond is required for site testing
requirements are based on BLM’s Wind Energy Development and monitoring authorizations to
regulatory minimums that are Policy, which provides guidance ensure that the developer
designed only to account for to process ROW applications for complies with all terms and
compliance with the terms and site testing and monitoring conditions of the authorization.55
conditions of the lease, such as facilities for wind energy This bond is a minimum of $2,000
reclaiming disturbed lands, development on federal public per meteorological tower.56 The
plugging wells, and payment of lands.47 The policy states that all second bond is required with the
government royalties. These wind energy development project ROW authorization for the wind
bonds do not account for site- applications are to be processed project development. The
specific characteristics and according to the requirements of minimum bond amount for wind
reclamation costs that a FLPMA and the federal energy development on federal
particular well might require. regulations regarding ROWs.48 public lands is $10,000 per
Furthermore, the regulatory The BLM has the authority to turbine, considering salvage
minimums were established in identify public lands that are values of turbines and towers.57
the 1950s and 1960s, leaving the applicable for competitive bidding However, the precise amount of
minimum bonding amounts very for ROW authorizations.49 the bond is determined by site-
outdated and not reflective of, or However, the BLM is authorized to specific and project-specific
adequate for, actual reclamation do so only if a land use planning factors during the ROW
costs. When bonds are decision has specifically identified authorization process.58
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 33
Table 3: Comparison of Federal Decommissioning Bonding Requirements
Resource Required By Minimum Bonding Amount Set In Acceptable Forms of Bond
Oil and gas Bond required in permit Independent bond: $10,000 1960 Surety bond, third-party guarantee from private
to drill. Statewide bond: $25,000 1951 insurance company, or personal bond accompanied
Nationwide bond: $150,000 1951 with a cashier’s check or Treasury bond.
Wind ROW authorization $10,000/turbine 2010 Cash, cashier’s or certified check, Treasury bond,
or surety bond.
As Table 3 demonstrates, the resources.64 The goal of orphaned wells between 1998 and
acceptable bond instruments decommissioning is to restore the 2009.66 Accordingly, based on
under BLM regulations include turbine site to the physical these figures, the average actual
cash, cashier’s or certified check, condition of the land as it existed reclamation cost of these wells can
negotiable U.S. Treasury bonds, prior to development of the wind be assumed to be approximately
or surety bonds payable to the project. As demonstrated through $13,000 per well. The
BLM from the approved list of the decommissioning procedures, Pennsylvania Department of
sureties.59 The BLM does accept a the decommissioning of wind Environmental Protection (DEP)
letter of credit as an acceptable projects consists primarily of reported the average cost of
form of a bond.60 The BLM equipment removal and soil plugging a well and restoring the
periodically reviews—at least restoration. Despite the paucity of site averaged $60,000 per well.67
every five years—all bonds in data concerning the effectiveness Some reports estimate
order to ensure the adequacy of of wind project decommissioning, reclamation costs of up $100,000
the bonds.61 wind projects generally have a per well.68 Figure 1 shows these
D ecommissioning guidelines
for a wind energy project
must be developed and approved
higher minimum bond
requirement than O&G projects
creating a greater likelihood
reclamation costs and the
minimum BLM bonding
requirements normalized
by the BLM.62 Generally, that decommissioning will (divided) by the land use values
decommissioning procedures restore the land to its prior reported in Table 1. In Figure 1,
include the dismantling and condition.65 the minimum O&G bond is
removal of all towers, turbine $10,000 per independent well.69
generators, transformers, and
overhead cables; removal of all
underground cables; removal of
D. Comparison of Federal
O&G Extraction Site and
Wind Project
A review of permit
applications for different
wind farms illustrates
foundations, buildings, and Decommissioning decommissioning cost estimates
ancillary equipment; removal of Regulations ranging between $11,000 and
surface road material; and $50,000 per turbine.71 Figure 1
restoration of the roads and Beyond the basic regulatory also depicts the normalized
turbine sites to a substantially minimum bond amounts for O&G minimum bonding requirements
similar condition prior to the and wind projects, it is also useful compared to the actual
construction of the wind facility.63 to compare the bond amounts decommissioning costs for wind
Decommissioning procedures versus the actual cost of turbines. This comparison
include the restoration of the decommissioning. Reclamation demonstrates that, albeit
topography of the site, as well as cost data for O&G sites is scarce. significant uncertainty about the
restoring topsoil and reseeding As previously reported, the BLM actual decommissioning and
the surface to restore the natural spent $3.8 million reclaiming 295 restoration costs, the current
34 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
[(Figure_1)TD$IG]
bonding requirements for wind will not likely cover the full minimum generally have
will also likely be insufficient. costs of reclamation and minimum bond amounts that are
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 35
[(Figure_2)TD$IG]
include Alaska, Idaho, Montana, decommissioning requirements renewable energy facilities on the
Nevada, New Mexico, and bonds rely on various establishment of a
Pennsylvania, Washington, and mechanisms to implement decommissioning plan and
Wyoming. These states have a decommissioning requirements. financial assurance. In order to be
regulatory minimum greater than While a more comprehensive list approved by the state utility
the BLM’s $25,000 bond per well, of state decommissioning regulatory body in Vermont, the
except for Idaho, which has an requirements is set out in Vermont Public Service Board
equal minimum bonding Table A1 in Appendix A, a few of (PSB), energy facilities must
requirement.80,81 the more illustrative requirements receive a ‘‘certificate of public
Figure 2 shows the normalized are analyzed here. In Minnesota, a good.’’84 The PSB has consistently
bonding requirement for state statute requires the public conditioned a certificate of public
individual wells and reclamation utilities commission (PUC) to good on a facility’s
costs for particular states. develop rules to govern the site decommissioning plan, which
Alaska’s bonding requirements restoration of large wind energy must include a detailed cost
closely resemble actual projects, called large wind energy estimate of decommissioning, as
reclamation costs. Conversely, conversion systems (LWECS).82 well as a mechanism to guarantee
Pennsylvania’s bonding Accordingly, the Minnesota PUC a secured fund to be available
requirements are demonstrably promulgated regulations for when decommissioning is
inadequate.68 decommissioning and restoration necessary.85 Similarly, in Indiana,
requirements, including the the Utility Regulatory
B. State wind mandatory assurance from wind Commission requires facilities to
decommissioning regulations developers that funds will be establish a decommissioning plan
available for decommissioning that includes a financial assurance
Currently, relatively few states and restoration.83 equal to the estimated amount for
demolition and removal costs.86
have decommissioning and bond
requirements for wind energy
projects. The states that do impose
A lternatively, some states—
like Vermont and
Indiana—condition approval of
The plan must be secured through
the form of a bond, letter, or
36 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
credit, or other acceptable procedures of wind projects more information, see
guarantee.87 The under a specified nameplate Appendix A.
decommissioning plan is capacity (i.e., 100 MW).93 In South
developed and approved through Dakota, the Public Utilities C. Comparison of state O&G
the renewable energy project’s Commission requires extraction site and wind
review and approval.88 decommissioning plans, cost project decommissioning
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 37
in Appendix B, though not operations generally supplement generation potential of a specific
exhaustive, provides a sample of federal and state regulations and natural gas well or wind turbine is
county wind ordinances across do not include specific language highly dependent on the project, a
the country. A survey of these or requirements for natural gas well generally
ordinances reveals that most decommissioning O&G wells on provides energy that can be
ordinances include language that, local land.99 turned into more electricity over
in effect, requires a secure Wind projects on county land the lifetime of the well compared
financial assurance for the costs of have likely caught the attention of to a wind turbine. Thus, although
decommissioning and reclaiming local regulators because of the wind turbines may have more
a site.96 Although the ordinances recentness of wind energy stringent bonding requirements
do not specify particular financial development and the lack of a than natural gas wells, more wind
amounts, they generally provide longstanding regulatory regime. turbines are required to produce
that the decommissioning funds Without complete details on the same amount of electricity as a
be adequate for the full cost of decommissioning funding natural gas well produces.
decommissioning and require requirements for wind or O&G Table 4 shows lifetime
approval by the appropriate resources at the county level, a electricity generation estimates
county, town, or regulatory quantitative analysis of the effect assuming different project
authority.97 Thus, and implication of these lifetimes, average lifetime gas
decommissioning requirements ordinances cannot be undertaken. generation rates, and wind
and financial securities are capacity factors. These numbers
approved on a case-by-case basis. assume a 2 MW turbine and a
VI. Electricity
F or example, in Vermilion
County, Ill., a wind energy
project was approved with the
Generation Potential
natural gas power plant efficiency
of 50 percent. These values are
highly dependent on the specific
contractual obligation that the Although the paramount project and site so a generalized
developer was responsible for the concern with decommissioning comparison of these values is not
full costs of decommissioning the regulations centers around the appropriate. As an example,
project—an estimated $98,000 per environmental impacts associated however, the normalized BLM
turbine.98 with inadequately restored sites, bonding requirement for a well
Conversely, county ordinances it is also useful to note the that produces natural gas for 30
for oil and gas wells are not as differences in electricity years at a rate of 0.2 MMcf/day is
widespread. Again, though not an generation potential between roughly $4,000/acre-TWh of
exhaustive review, county wind turbines and natural gas electricity generated. The
ordinances regulating O&G wells. Although the electricity restoration costs for this well
Table 4: Lifetime Electricity Generation for Wind Turbines and Natural Gas (MWh/Project Lifetime)a
Project Lifetime (yr) Average Lifetime Production Rate for
Vertical Well (MMcf/day) Wind Turbine Capacity Factor
0.05 0.1 0.2 0.15 0.25 0.4
10 28,000 55,000 110,000 26,000 44,000 70,000
20 55,000 110,000 220,000 53,000 88,000 140,000
30 83,000 165,000 330,000 79,000 130,000 210,000
a
Average lifetime production rate for vertical wells was chosen based on average production rates for natural gas wells between 1989 and 2009. Production of natural gas declines
over the years. In this analysis, however, we are interested in total production, so an average number for the entire well lifetime is appropriate. A heat rate of 6,828 Btu/kWh was used
for the natural gas plant. See U.S. ENERGY INFO. ADMIN., Natural Gas: Number of Production Wells (Nov. 29, 2011), at http://www.eia.gov/dnav/ng/ng_prod_wells_s1_a.htm; U.S. Energy
Info. Admin., Natural Gas: Natural Gas Gross Withdrawals and Production (Nov. 29, 2011), at http://www.eia.gov/dnav/ng/ng_prod_sum_dcu_NUS_a.htm.
38 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
could be as high as $40,000/acre-
TWh. For a wind turbine with a
30-year lifetime and a capacity
However, it is evident that the
bonding requirements imposed
by the regulations are insufficient.
L astly, although both O&G
and wind decommissioning
regulations are insufficient to
factor of 40 percent, the The federal government has also cover the actual costs of
normalized bonding requirement enacted federal regulations for decommissioning, it is important
is roughly $25,000/acre-TWh, decommissioning requirements to note the disparity in the
while the decommissioning cost and minimum bond securities for regulatory requirements. In
can be as high as $125,000/acre- wind projects on federal lands. order to adequately integrate
TWh. Thus, while the bond However, few states have renewable energy, the policy
required for the wind farm developed decommissioning environment must ensure that
accounts for 20 percent of the regulations for wind facilities. wind projects are constructed,
normalized decommissioning Regulatory bonding requirements operated, and retired in an
costs, the bond for the O&G well for wind projects on federal lands, environmentally sensitive
accounts for only 10 percent of the although established more manner, and that the cost of
reclamation costs. recently than the O&G bonding doing so does not
requirements, also seem to be disproportionately disadvantage
insufficient. However, the states the facilitation of renewable
VII. Conclusions which have established energy. Accordingly, equitable
decommissioning regulations for regulatory burdens are necessary
A comparison of federal, state, wind projects require bonding for all energy activities so that
and county decommissioning amounts on a case-by-case basis. each resource is subject to
regulations for O&G extraction Evaluating decommissioning environmental accountability
sites and wind energy projects bonding requirements on a case- and proportional regulatory
reveals that, generally, regulatory by-case basis will most likely burdens. Creating a level playing
requirements are wholly produce more accurate bond field amongst energy resources is
insufficient to adequately secure amounts. Consequently, state imperative so that resource
the costs of decommissioning. decommissioning requirements selection amongst competing
Appendix A
Table A1: State Decommissioning Regulations
Renewable
Facility
Decommissioning
Rules/Fund Type/Notes
Alabama No –
Arizona No –
Arkansas No –
California No Have general facility closure requirements for energy facility licensing, but no bond. Cal. Pub. Res.
Code § 25532 (2010).
Colorado No –
Delaware No –
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 39
Table A1 (Continued )
Renewable
Facility
Decommissioning
Rules/Fund Type/Notes
Florida No –
Georgia No –
Hawaii Yes Decommissioning rules, but no fund requirements. Hawaii Rev. Stat. § 269-1(G).
Idaho No –
Iowa No –
Indiana Yes Decommissioning rules and funds for wind projects. Indiana Utility Regulation Commission, Order
No. 43602; Order No. 43759; Order No. 43678.
Kansas No Only local ordinances.
Massachusetts No Generally, decommissioning procedures are established within specific agreements between
developers and site owners.
Maine Yes Me. Rev. Stat. tit. 38, § 481–490. In pertinent part, § 490 (2), ‘‘Bonds. The department may require
a bond payable to the State with sureties satisfactory to the department or such other security as
the department may determine will adequately secure compliance with this chapter, conditioned
upon the faithful performance of the requirements set forth in this chapter and of the rules of the
board.’’
See also, Spruce Mountain Wind Project Maine DEP Site Location of Development Act Permit
Application, Section 29 (Jan. 21, 2010).
Michigan No –
Minnesota Yes MINN. STAT. § 216F.05; MN ADC 7854.0500, Subpart 13.
Montana No –
New Mexico No –
New York Yes, if over 80 MW Municipal ordinances if below 80 MW; otherwise under Public Service Law Article X certification
nameplate capacity. requirements (expired 2003).
North Dakota Yes Decommissioning of commercial wind energy facilities.
N.D. Admin. Code §§ 69-09-09-06, 69-09-09-07 (2008).
Ohio Yes, if over 5 MW Public Utility Commission of Ohio requires plan for decommissioning and discussion of financial
nameplate capacity. arrangements designed to assure requisite financials to carry out the plan. Ohio Admin. Code
Chapter 4906-17.
Oregon Yes Under jurisdiction of Energy Facility Siting Board which estimates costs of restoration and
mandates bond or letter of credit as financial security for site restoration.
South Dakota Yes, if over 100 MW PUC encourages use of local ordinances based on draft model if rated under 100 MW.
nameplate capacity.
Texas No –
Virginia No DEQ regulations may apply.
Vermont Yes Condition for Public Service Board approval of Certificate of Public Good under 30 V.S.A. §248
which establishes requirements for in-state electric transmission and generation construction
projects. See Order Re Lease Language, Decommissioning Plan, and Request for Hearing,
Docket No. 7156 (2007).
Source: Decommissioning Funds for Renewable Energy Facilities, Danielle Changala and Jonathan Voegele, Vermont Law School Institute for Energy and the Environment (2010),
Presented at First Integration and Policy Workshop for the RenewElec Project, Oct. 21–22, 2010, Carnegie Mellon University, Pittsburgh.
40 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
Appendix B
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 41
Table B1 (Continued )
42 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
Table B1 (Continued )
A comparison of federal, state, and county decommissioning regulations reveals that, generally,
regulatory requirements are wholly insufficient to adequately secure the costs of decommissioning.
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 43
2010), at http://www.nature.org/ 22. 43 C.F.R. §§ 3160–3162; OIL AND federal rate of return multiplied by
media/pa/pa_energy_assessment_ GAS BONDS, supra note 2, at 1. $0.03 average price per kilowatt.
report.pdf (estimating land use
23. Id. at 6. 53. BLM Fact Sheet, supra note 11.
impacts of wind turbines by
using digitalized aerial images 24. Id. 54. Id.
of wind development areas before
25. OIL AND GAS BONDS, supra note 2, 55. WIND ENERGY DEVELOPMENT POLICY,
and after wind turbine installation.
at 7. supra note 20, at 5; 43 C.F.R.
The Nature Conservancy analyzed
2804.12(a)(5); 43 C.F.R. 2804.24(a)(5).
roughly 320 turbines in 12 sites across 26. Id.
the state of Pennsylvania.). 56. Id.
27. Id.
8. Sarah M. Jordaan, David W. Keith 57. Id. at 8. The minimum bonding
28. Id.
and Brad Stelfox, Quantifying land use amount of a wind turbine has
of oil sands production: a life cycle 29. Id. been updated since the BLM’s 2006
perspective, ENVIRON. RES. LETT. 4 Wind Energy Development Policy,
30. Id. at 8.
(2009). where the bonding requirement was
31. Id. at 12. $2,500/per turbine. See generally WIND
9. Id. ENERGY DEVELOPMENT POLICY, supra
32. Id. note 20.
10. U.S. Dep’t of the Interior Bureau of
Land Mgmt., BLM Fact Sheet: 33. Id. at 13. 58. WIND ENERGY DEVELOPMENT POLICY,
Renewable Energy and the BLM, at 34. Id. supra note 20, at 8.
http://www.blm.gov/pgdata/etc./
medialib/blm/wo/MINERALS__ 35. Id. 59. Id.
REALTY__AND_RESOURCE_ 36. Id. 60. Id.
PROTECTION_/energy/renewable_
references.Par.95879.File.dat/2010% 37. Id. 61. Id.
20Renewable%20Energy%20 62. U.S. Dep’t of the Interior, BLM
38. Id.
headed.pdf. Wind Energy Program Policies and Best
39. Id. Mgmt. Practices, Attachment 1–19
11. FINAL PROGRAMMATIC
ENVIRONMENTAL IMPACT STATEMENT ON 40. Id. (2009).
WIND ENERGY DEVELOPMENT, supra note 41. Id. at 8–9. 63. N.D. CENT. CODE § 28-32-02; 49-02-
5, at 4–33. 27 (2008).
42. Id. at 9.
12. OIL AND GAS BONDS, supra note 2, at 64. Id.; South Dakota Permit
22–23. 43. Id. at 16. Requirements, Docket No. EL08-031,
44. The $162 million figure reflects the at: http://puc.sd.gov/commission/
13. Id. at 10. dockets/electric/2008/el08-031/
total amount secured in bonds. A well
can only access the bond secured for Appendix%20h.pdf (2008).
14. FEDERAL LANDS MGMT. POLICY ACT
OF 1976, 43 U.S.C. § 1732(a)–(b) (2006). its individual project. Id. at 10.
65. WIND ENERGY AMERICA, Frequently
45. Id. Asked Questions, at http://www.
15. Id. at § 1701 et seq.
windenergyamerica.com/faqs.html.
16. U.S. DEP’T OF THE INTERIOR BUREAU OF 46. Id.
LAND MGMT., 135 DM 1, DEP’T MANUAL 47. WIND ENERGY DEVELOPMENT POLICY, 66. Id. at 16.
(effective Sept. 20, 2007). supra note 20, at 1. 67. Austin L. Mitchell and Elizabeth
17. OIL AND GAS BONDS, supra note 2, 48. 43 C.F.R. § 2800. Casman, Economic Incentives and
at 1. Regulatory Framework for Shale Gas Well
49. 43 C.F.R. § 2803.23(c). Site Reclamation in Pennsylvania (2011),
18. Id. ENVTL. SCI. & TECH., 45 (22) at 9506–
50. WIND ENERGY DEVELOPMENT POLICY,
19. 43 C.F.R. § 3160–3165; U.S. DEP’T OF supra note 20, at 9. 9514.
THE INTERIOR BUREAU OF LAND MGMT., IM
51. Id. at 7. 68. Matt Andersen, Roger Coupal and
2009-043, WIND ENERGY DEVELOPMENT Bridgette White, Reclamation Costs and
POLICY, 9 (2008). 52. Id. at 7–8. The annual rental fee is Regulation of Oil and Gas Development
equal to the anticipated total installed with Application to Wyoming, Western
20. 43 U.S.C. § 1730 et seq.; WIND
capacity in kilowatts on public lands Economics Forum (2009), at http://
ENERGY DEVELOPMENT POLICY, supra note
as identified in the approved plan of ageconsearch.umn.edu/bitstream/
19, at 9.
development (POD) multiplied by 8,760 92846/2/0801005.pdf.
21. OIL AND GAS BONDS, supra note 2, at hours per year multiplied by a 30%
11. capacity factor multiplied by 5.27% 69. See Table 3.
44 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 The Electricity Journal
70. Reclamation costs and the the land use estimates reported in representatives from various
minimum BLM bonding requirements Table 1. regulatory agencies, public citizens
were normalized by dividing them by and governor appointees. EFSECs are
82. MINN. STAT. ANN. § 216F.05 (2008).
the land use values reported in Table 1. typically responsible for reviewing
83. MINN. R. 7854.0500, Subpart 13. conventional thermal power plants,
71. Hounsfield Wind Farm:
Neither the statute or regulations pipelines and storage facilities,
Decommissioning Plan (Aug. 12,
specify what method must be transmission lines, and renewable
2008), at http://www.dec.ny.gov/
employed to ensure adequate generation projects which meet a
docs/permits_ej_operations_pdf/
funds for decommissioning, just certain capacity.
hnsfldappendixu.pdf; Record Hill
that the developer ensure that
Wind Project: Decommissioning Plan 90. See OR. ADMIN. R. 345-022-0050;
adequate funds be available. In
(2009), at http://www.maine.gov/ OREFSC jurisdiction for renewables
Commission review, the commission
dep/blwq/docstand/sitelaw/ includes any geothermal, solar, or
requires only ‘‘[t]he owner will be
Selected%20developments/ wind project of 35 MW or more.
responsible for costs to decommission
Record_Hill/Section%2029%20
the project and associated facilities.’’ 91. Id.
Decommissioning%20Plan.pdf;
In the Matter of the Site Permit
Buffalo Ridge II Wind Farm: 92. OR. ADMIN. R. 345-022-0050(1); The
Application for a 20 Megawatt Large
Decommissioning Plan (Oct. 2008), at OREFSC’s determination is a case-by-
Wind Energy Conversion System in
http://puc.sd.gov/commission/ case factual evaluation.
Stevens County, Minnesota, NO. IP-
dockets/electric/2008/el08-031/
6824, 2010 WL 750957 (Minn. PUC 93. S.D. CODIFIED LAWS § 49-41B-2 (5),
Appendix%20h.pdf. These estimates
2010). (6), (12).
include a credit for the scrap steel that
can be recovered from the turbine. 84. 30 V.S.A §248.
94. S.D. ADMIN. R. 20:10:22:33, 33.01,
72. From 1988 to 2008, the number of 85. Order Re Lease Language, and 33.02.
O&G wells on federal lands increased Decommissioning Plan, and Request for
from almost 50,000 wells to 85,000 95. See, e.g., S.D. Public Utilities
Hearings, Docket No. 7156 (VT PSB
wells—with the increase occurring Comm’n, Model Ordinance for Siting
Aug. 8, 2007); see also Order Re Lease
primarily in the last decade. OIL AND of Wind Energy Systems (WES)
Language, Decommissioning Plan, and
GAS BONDS, supra note 2, at 11. Overview, at http://puc.sd.gov/
Request for Hearings, Docket No. 7156
commission/twg/WindEnergy
(VT PSB May 14, 2008) (finding that
73. See National Energy Technology Ordinanceoverview.pdf.
the applicant’s ‘‘revisions to its
Laboratory, Protecting Our Country’s
decommissioning plan adequately 96. See Appendix B.
Resources: The States’ Case, 27–61
address the issues that the Department
(2008), at http://iogcc.publishpath. 97. See, e.g., Ripley Westfield Wind
had previously raised regarding the
com/Websites/iogcc/pdfs/2008- Decommissioning Plan, at http://
plan: the revised plan includes an
Protecting-Our-Country’s-Resources- www.ripleywestfieldwind.ene.com/
appropriate adjustment for inflation; it
The-States’-Case.pdf. files/EIS/Appendix%20F%20-%20
provides for full decommissioning of
74. OIL AND GAS BONDS, supra note 2, at the substation; and it includes as a Decommissioning%20Plan.pdf (2009)
20. reporting mechanism the requirement (‘‘Any bond or letter of credit will be in
that UPC file with the Board the a form reasonably acceptable to the
75. Id. at 20–21. Towns and issued by an institution
project’s annual energy production as
76. Id. at 23. reported to ISO-New England.’’). reasonably acceptable to the
Towns. . .The financial security will be
77. Id. at 20. 86. In the Matter of the Petition by in an amount sufficient to adequately
78. Id. at 23. Meadow Lake Wind Farm LLC, perform the required
79. Although it is important to note Docket No. 43602 (Indiana Utility decommissioning per this plan and all
Pennsylvania’s statewide minimum Regulatory Comm’n 2008); In the local, state and federal environmental
bond is $25,000 which is equal to the Matter of the Petition by Meadow regulations.’’).
federal minimum bonding amount. Lake Wind Farm III LLC, Docket No.
43759 (Indiana Utility Regulatory 98. Vermilion County Wind Energy
COMMONWEALTH OF PENNSYLVANIA Structure Ordinance Building Permit
DEPARTMENT OF ENVIRONMENTAL Comm’n 2009); In the Matter of the
Petition by Meadow Lake Wind Farm Application, California Ridge Wind
PROTECTION, Oil and Gas Well Drilling Energy Project, Section 4.3.6
and Production in Pennsylvania, at II LLC, Docket No. 43678 (Indiana
Utility Regulatory Comm’n 2009). Decommissioning and Restoration, at
http://www.columbiacountyema. http://www.vercounty.org/ctybrd/
org/Oil%20%20&%20Gas%20Wells. 87. Id. Vermilion%20County%20-%20
pdf (2007). California%20Ridge%20wind%20
88. Id.
80. Id. project%20building%20permit%20
89. Although they vary, EFSECs are application.pdf (2011).
81. The costs presented in the y-axis typically one-stop licensing
have been normalized (divided) by committees consisting of 99. Id.
Jan./Feb. 2012, Vol. 25, Issue 1 1040-6190/$–see front matter # 2012 Elsevier Inc. All rights reserved., doi:/10.1016/j.tej.2011.12.004 45