Professional Documents
Culture Documents
106-Article Text-230-1-10-20200929
106-Article Text-230-1-10-20200929
01 Juli 2020
COMPARATIVE ANALYSIS OF MINE DEWATERING COST WITH LOAD AND HAUL METHOD
AND MUD PUMPING METHOD IN ANNUAL PLAN PT ABC
Abstract: Coal is an abundant natural resource in Indonesia and is an alternative energy source that is currently
highly developed. Coal mining activities have a positive impact on the economic development of the surrounding area.
However, coal mining activities also have a large impact on the environment, especially in mining with the open pit
method. One of the big problems in mining activities using the open pit method is the handling of water and mud
carried by runoff water from rainwater or ground water. Especially at PT ABC on sump pit Z has a large actual mud
volume, which is 147,412 m3 with a large catchment area of 1.99 km2 in June 2020. The height difference between
Sump Pit Z and the processing pond on EOY 2020 is 132 m, so 1 mud pump with 2 booster are needed to pump mud
from Sump to the sediment pond. With the actual SG sump being 1.4 and total head on EOY 2020 is 132 m,, a slurry
pump with specifications is needed that is capable of pumping water that approaches the actual SG. Using a Dragflow
HY85-160B pump and 2 Medso 150 booster pumps, 148.800 m3 per month can be pumped into the treatment pond,
with a total cost incurred if using the mud pumping method is $ 842.403. This cost is smaller compared to the costs
required for the load and haul method with saving cost up to 57%.
Keywords: Coal mining, runoff water, pumps, mud, load and haul
Abstrak: Batubara adalah sumberdaya alam yang melimpah di Indonesia dan menjadi sumber energi alternatif yang
saat ini sangat berkembang. Kegiatan penambangan batubara memiliki dampak positif bagi perkembangan ekonomi
daerah sekitarnya. Namun kegiatan penambangan batubara juga memiliki dampak yang besar terhadap lingkungan,
khususnya pada penambangan dengan metode open pit. Salah satu permasalahan besar dari kegiatan penambangan
dengan metode open pit adalah penanganan air dan lumpur oleh air limpasan hujan maupun air tanah. Khususnya di
PT ABC pada sump pit Z memiliki volume lumpur aktual yang besar, yaitu 147,412 m 3 dengan luas area tangkapan
hujan sebesar 1,99 km2 pada bulan Juni 2020. Perbedaan ketinggian antara Sump Pit Z dengan kolam pengolahan
hingga akhir tahun 2020 adalah 132 m sehingga dibutuhkan 1 pompa lumpur ditambah 2 booster untuk memompa
lumpur dari sump hingga ke kolam pengendapan. Dengan SG aktual sump adalah 1,4 dan head hingga akhir tahun 132
m, maka dibutuhkan pompa lumpur dengan spesifikasi yang sesuai yaitu menggunakan pompa Dragflow HY85-160B
dan 2 booster pump Medso 150. Kapasitas pemompaan per bulan adalah 148,800 m 3 dengan total biaya sebesar $
842,403. Biaya ini lebih rendah jika dibandingkan terhadap total biaya yang dibutuhkan jika menggunakan metode
load and haul dengan penghematan mencapai 57%.
Kata kunci: Penambangan batubara, air limpasan, pompa, lumpur, load and haul
57
Volume 11 No. 01 Juli 2020
58
Volume 11 No. 01 Juli 2020
Mei 2020 s.d. Desember 2020, data curah Dec-20 8.24 0.54 9.82 79.00
59
Volume 11 No. 01 Juli 2020
Q = 0,278 x 0,7 x 2,05 mm/hours x 24 average. Dengan anggapan bahwa setiap air
hours/day x 2,08 km2 x 1.000 yang masuk ke sump 30% persen dari
m.m2/mm.km2 volumenya adalah material yang tererosi
Q = 19,939 m3/day ketika air limpasan melaju di atas permukaan
Contoh perhitungan debit air limpasan tanah.
permukaan maksimum pada bulan May 2020 Debit air limpasan per hari yang masuk
adalah sebagai berikut: ke sump Pit Z dikalikan 30 hari, untuk
Q = 0,278 x C x I x Amax mendapatkan total volume sump dalam 1
Q = 0,278 x 0,7 x 3,9 mm/hours x 24 bulan.
hours/day x 2,08 km2 x 1.000 Total vol air per bulan = Water ingress/day x
m.m2/mm.km2 30 days
Q = 54,137 m3/day Total vol air perbulan = 16,718 m3/day x 30
days
Total vol air perbulan = 16,718 m3/day x 30
days
Total vol air perbulan = 598,182 m3
Volume lumpur yang terdapat di sump
Pit Z pada setiap bulan di tahun 2020 sebagai
berikut:
60
Volume 11 No. 01 Juli 2020
61
Volume 11 No. 01 Juli 2020
Gambar 3.5 Perhitungan SG Sump Pit Z 3.2.4 Perhitungan Biaya Kebutuhan Pompa
Lumpur
Berdasarkan pertimbangan tersebut, Dari analisis kebutuhan pompa, maka
maka spesifikasi submersible pump yang biaya yang akan dikeluarkan untuk
sesuai adalah Dragflow HY85-160B dan slurry pengoperasian pompa lumpur sesuai
booster yang sesuai adalah Metso HM150. konfigurasi tersebut seperti pada tebel 3.7.
Pompa tersebut dapat menerima input SG
sebesar 1,3 s.d.1,4. Tabel 3.7 Total Biaya Penanganan Lumpur
dengan Metode Pemompaan
Mud Pump (PT REL)
Item/Month
HY85 to Metso HM 150 Support Mud Pump
Toal Hose (m) - Komatsu Hitachi
Unit Hose 1 (m) Hose 2 (m) EX-350
Cost/month Layflat D85ESS ZX210LC-5G
Billing Rate ($/hr) $ 52,816.90 30.68 52.17 36.85
Max Length Max Length Max Length
No Unit 1 1 1 1
WH 496 347 347
May-20 $ 52,816.90 100 750 250
Operating cost $ 15,217.28 $ 18,113.42 $ 12,794.32
WH 480 336 336
Jun-20 $ 52,816.90 100 750 250
Operating cost $ 14,726.40 $ 17,529.12 $ 12,381.60
WH 496 347 347
Jul-20 $ 52,816.90 100 850 250
Operating cost $ 15,217.28 $ 18,113.42 $ 12,794.32
WH 496 347 347
Aug-20 $ 52,816.90 100 500 600
Operating cost $ 15,217.28 $ 18,113.42 $ 12,794.32
WH 480 336 336
Sep-20 $ 52,816.90 100 500 600
Operating cost $ 14,726.40 $ 17,529.12 $ 12,381.60
WH 496 347 347
Oct-20 $ 52,816.90 100 500 600
Operating cost $ 15,217.28 $ 18,113.42 $ 12,794.32
WH 480 336 336
Nov-20 $ 52,816.90 100 500 600
Operating cost $ 14,726.40 $ 17,529.12 $ 12,381.60
WH 496 347 347
Dec-20 $ 52,816.90 100 500 600
Operating cost $ 15,217.28 $ 18,113.42 $ 12,794.32
Total Operating Cost ($) $ 422,535.21 $ 25,150.91 $ 30,181.09 $ 120,265.60 $ 143,154.48 $ 101,116.40
Total ($) $ 842,403.68
Gambar 3.6 Dragflow HY85-160B
Total biaya yang dibutuhkan untuk
Hasil perhitungan kebutuhan pompa penanganan lumpur dengan pengoperasian
dengan kriteria di atas dapat dilihat pada tabel
3.6.
62
Volume 11 No. 01 Juli 2020
63
Volume 11 No. 01 Juli 2020
64