4.3 Installing the gantry

4.3.1 Routing the System Cables

System cables connection diagram

W123

Gantry Couch
W108
LAN CABLE
W124

W125

W301

Power
filter
Console box RPU
W403

Figure 44 System connect cables diagram

1. Connect the cable from gantry to RPU.


List 3

No. Cable Type From To

W301 Power supply (L1, L2, L3, N, RPU output Gantry right column
PE) X101

W403 Power supply (L, N, PE) RPU output Console X401

W124 Signal (console to gantry) CT-box Console Interface board CT-box gantry interface
board

454110230332 53 V2.1
NeuViz Dual, NeuViz Installation Manual

W125 Signal (console to gantry) CT-box Console Interface board CT-box gantry interface
board

W119 Network (LAN Cable) Console Switch Switcher CT-box Gantry interface
board

W108 Power supply to patient table Gantry Patient table

W123 Signal Gantry Patient table

W402 Signal CT-box CT-box interface board