UPGRADING WORK
METHOD STATEMENT
CONTRACTOR :
MEWAH KOTA SDN BHD
NO. 2 JALAN APOLLO U5/190
BANDAR PINGGIRAN SUBANG
SEKSYEN U15
40150 SHAH ALAM
SELANGOR
CONSULTANT :
UNITI CONSULTANTS SDN BHD
25. Jalan Bunga Raya 8,
Senawang Business Centre,
Taman Tasik Jaya,
70450 Seremban, NSDK.
Tel: +606 - 678 0203 / Fax: +606-679 2308
__________________________________________________________________________________
Page No.1 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
CONTENTS
C. RESOURCE REQUIREMENTS
1) MAN POWER
2) MACHINARIES
3) MATERIALS
D. WORK PROGRAMME
1) ADMINISTRATION TEAM
2) QUANTITY SURVEYOR AND PROCUMENT TEAM
3) DESIGN TEAM
4) PROJECT TEAM
__________________________________________________________________________________
Page No.2 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
Before the commencement of the site mobilization and site clearing works we will
appoint a licensed Surveyor to search for the Approved Plan of the contractual site with
Client or the Survey Department. Upon having the necessary plan the survey team will
conduct site survey to check for boundary stone and boundary demarcation by setting
boundary peg to prevent potential encroachment into neighbouring land. Temporary
Bench Mark (TBM) will also be set up at a few location inside and outside the
contractual boundary for future reference during the construction period.
Having successfully doing the above task they will conduct the leveling survey to
determine the original ground level, slopes and terrain for the detail design and
Construction purposes.
Endorsed Drawing for the above survey works will be submitted to the client for their
approval and safekeeping.
The whole process of data searching, site surveying, pegging and producing of drawings
will take about 1 week to complete. One gang three person survey team will involve in
this process.
Using the above survey data by licensed surveyor , our design team will proceed with
their detail design and decide on their process flow, hydraulic head calculations,
hydraulics profiles of each process and positioning of structures. The design team will
then finalized their Layout and submit it to client and relevant authorities for approval.
Upon approval of the layout drawing will be passed to the surveyor for the preparation
of Pre computation drawing. Subsequently building alignment, invert levels and
earthwork peg can be set up for construction.
2/ SOIL INVESTIGATION
In this specific job, the client has carried out the Soil Investigation reports, however if
this scope is necessary the scope are as follows :
A soil investigation specialist contractor will be appointed during the preliminary stage.
They will conduct at least three borehole 30m deep within the contractual boundary to
determine:-
a/ Soil type
b/ Soil layer and dip
c/ Soil properties
d/ Standard Penetration Test
e/ Ground water table
__________________________________________________________________________________
Page No.3 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
Other than the above test, Mackintosh Probe Test will also be conducted two numbers at
every big structure position.
One gang consist of five team member will involve in the above tests while the
equipment required will be one set of Mackintosh Probe, one set of Borehole equipment,
a small 415V Generator Set.
The whole process of site works and data assessment will take about two weeks to
complete.
3/ SITE CLEARING
Site Clearing works shall commence and coordinate with the site surveyor and soil
investigator. This is because certain areas needs to be cleared to allow the smooth works
of the other parties.
All vegetation, weeds and tall grass or other unsuitable materials obstruct the working
environment will be removed. It will be removed from site to our dumping yard.
A backhoe, two number of lorries, 2 sets of grass cutter, 2 sets of portable water pump, a
ladder one gang of five person daily workers will be employ to do this task .
4/ EXCAVATION
Upon approval of construction drawings, machineries and survey team will be mobilized
to site. The survey team will establish survey control such as Temporary Bench Mark
(TBM) and alignment control to mark the limit of excavation. The area that need to be
excavated will be pegged and volume of excavation will be determined.
Long arm excavator 300 series will be required for the deep of excavation more than six
meter. The proposed structure that will require this type of excavator shall be the Jacking
and Receiving Pit.
For excavation less than six meter deep we proposed to use a normal excavator 300 series
or 200 series depending on the volume of excavation.
Excavated material will be hauled immediately to fill the idling area within the site or to
be disposed to our own dumping site. Tipper Trucks will be employ to do the hauling. A
backhoe and a bulldozer will be used to level the dumped excavated material. No
excavated material shall be stockpile within the vicinity of an excavated area or a newly
constructed structures to avoid slope failure.
__________________________________________________________________________________
Page No.4 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
During excavation, a team of surveyor will regularly monitor the excavation level to
avoid over cutting. For slope stability we propose that any excavation up to four meter
deep shall have a gradient of 1: 1.
Excavation more than four meter deep we propose to stabilize the slope with sheet piling
or timber pile to avoid any untoward happenings.
We expect the ground water table are quite high in this area, probably 2.0 meter below
the original ground level. To ensure smooth excavation, we will provide water pumps to
pump out water from the excavated area.
A one ton vibro hammer mounted to the excavator shall be used to drive the sheet pile
into position. Care should be taken to ensure the pile is properly interlocked. The sheet
pile walls then need to be sufficiently braced with universal beam to avoid collapse.
6/ CONCRETING
During the preliminary stage we will scout the nearby potential concrete suppliers to this
project. The potential supplier will be requested to submit their design mix for approval.
Upon approval they will be required to carry out trial mix base on their design. The trial
mix will then be tested to check their crushing strength at 3 days, 7 days and 28 days.
The mix that conform to the strength requirement will be deem to be approved.
All concrete batch arriving at site from the approved supplier will still need to be checked
on their workability by means of slump test. A batch that fail the slump test will be
rejected and asked to leave the site immediately. Cube Test will be conducted to every
50m3 of concrete supply at the same day or less if the day volume is smaller. For
concrete casting volume up to 80m3 we propose to use normal mobile crane to hoist the
concrete from trucks to the working area, volume more than 80m3 we propose to use
pumping crane.
Sufficient number of poker vibrator will be used to spread and vibrate the concrete. For
a casting up to 80m3 of concrete, at least three number of poker vibrator will be used
casting more than 80m3 shall require five number of vibrators.
__________________________________________________________________________________
Page No.5 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
The following steps will be carried out for the construction of the above structures :
A/ BASE CONSTRUCTION
1) Setting out by a survey team to determine locations and peg the sump alignment.
2) Hydraulic excavator or backhoe will execute excavation up to a certain depth
3) Installation of sheet piling with a vibro hammer mounted to the excavator boom
4) Hydraulic excavator will proceed excavation up to the base level
5) Bracing of sheet pile wall
6) Dewatering system shall be introduced where required to maintain the water level in
the excavation pit to a minimum.
7) Level the base and place hardcore
8) Place binding concrete
9) Laying of reinforcement bar beginning with the slab starter bar, longitudinal and
cross bar and wall starter bar. Cut and bent bar as per Bar Bending schedule will be
used.
10) Formwork for the base perimeter including wall kicker will be installed.
11) Pre concreting inspection will be carried out at this stage.
12) Concreting will be carried out with skip hoisted using a mobile crane.
B/ WALL CONSTRUCTION
Since the wall height is more than 7m we plan to construct the wall in three stages. Each
stage will have the same construction method.
C/ COVER SLAB
__________________________________________________________________________________
Page No.6 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
4) Pre concreting inspection to the reinforcement and formwork.
5) Concreting .
By satisfying the above process the construction of a pump sump structure deem to have
been completed.
The following steps will be carried out for the construction road and pavement.
1) Survey team will set out road alignment and ground level.
2) Filling and ground leveling using a backhoe and motor grader.
3) Laying of lateritic soil as subgrade to the required thickness
4) Compaction of laterite subgrade using a 12 ton vibro compactor .
5) Inspection of the compacted subgrade prior to receiving roadbase material.
6) Laying of roadbase (Crusher Run) using a backhoe and motor grader.
7) Compaction of roadbase using a 12 ton vibro compactor.
8) Inspection of the compacted roadbase prior to receiving wearing coarse material.
9) Premixing.
10) Road marking.
By satisfying the above process the construction of road and pavement deem to have been
completed.
E/ DRAINAGE
The following steps will be carried out for the construction of drainage.
By satisfying the above process the construction of the drain deem to have been
completed.
__________________________________________________________________________________
Page No.7 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
2. OPEN CUT SEWER PIPE LAYING METHOD
The following steps will be carried out for the construction of sewer pipe on open cut
methods :
The following steps will be carried out for the construction of M.S. pipes
methods :
__________________________________________________________________________________
Page No.8 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
h Place blinding concrete
i Installation of m.s pipe and jointing including pipe bedding or trust block
following the client specifications.
j Jointing of m.s. pipes either by welding method or mechanical joint.
k. Backfilling the trunk with suitable materials and compaction
l Extraction of temporary shoring
m Backfilling and compaction of the relevant pavement layers around the
excavated areas and road premix.
n Pipe testing
Please refer attached details pipe jacking methods as per specialist jacking
contractor specifications.
__________________________________________________________________________________
Page No.9 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
C. RESOURCE REQUIREMENTS
1/ MANPOWER
2/ MACHINARIES
There are two categories of machineries will be employed for this project namely:-
1/ One no of 1.8 meter diameter Slurry Pipe Jacking Machine c/w hydraulic machine
and accessories
2/ One Excavator series 250
3/ One vibro hammer
4/ One backhoe
5/ Two lorry tipper
6/ One crane
7/ Two nos of 4” Water Pump
3/ One no of smaller Water Pump cum poker vibrator
4/ One no of Genset
5/ One nos of Bar Bending Machine
6/ One nos of Bar Cutting Machine
7/ One set of Survey Equipment
8/ One nos Hand Driller
9/ One nos of Compaction Machine
10/ Two no poker vibrator
__________________________________________________________________________________
Page No.10 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
B/ AS AND WHEN REQUIRED
3/ MATERIALS
Consumables materials shall be procured from various local suppliers but the most
important materials is a Pipe Jacking Pipe will be design and supplied by approved
JPP/IWK supplier such as ALIANSA, Hume or ACPI.
__________________________________________________________________________________
Page No.11 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
D. WORK PROGRAMME
Upon receiving the letter of acceptance from the Government ( Employer ) we will
mobilized our project team to carry out the following:-
1/ ADMINISTRATION TEAM
The administration team will have the task to arrange all preliminary requirement of the
contract. Performance Bonds will be procured through our Bank Facilities. It is expected
the bank will issue Bank Guarantee on the Performance Bond within a month after Letter
Acceptance date. Contractor’s All Risk and Workmen Compensation Insurance will be
negotiated with our insurance agents. We expect the cover note will be issued within one
week and the policy will be submitted to the employer within a month.
The administration team will also procure items needs to be supply to the superintending
officer stipulated in the contract. The items will be handed over to the Superintending
Officer within one month from site possession.
The team will have a challenging role to scout for subcontractors and material and
equipment suppliers. They will cooperate with the design team and give feedbacks on
market response to facilitate optimum design. A procurement programme and planning
will be table and a cashflow programme will be issued.
During the construction stage the team task will be appointing subcontractors and
suppliers. They will have to liaise with the site team to coordinate the supply of
construction material, labor, machineries and equipments.
3/ DESIGN TEAM
The design team will again review of all data available. New data such as current original
ground survey, Soil Investigation data (mackintosh probes) will be gathered and
analyzed.
Upon receiving data from surveyor and soil investigation contractor the team will
commence their detail design. We expect submission to authorities within two months.
__________________________________________________________________________________
Page No.12 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
All in all the Construction Drawing will be ready within five months from the date of site
possession.
The design team will also acquire data from various authorities to check flood conditions
And history of the area.
4/ PROJECT TEAM
The project team will be station at site. They will be headed by an experienced Project
Manager. Their first task is to get all the preliminary works at site executed smoothly.
They will work together and supervise the survey team and soil investigation
subcontractor. Hoarding, access road and site clearing will be under their responsibility.
The Project Manager will then liaise with authorities to arrange for water supply and
power supply.
Superintending Officer site office, contractor site office , workers accommodation shall
be erected with the approval of Local Authority. We expect all this building will be
completed within one month from the date of site possession. The project Sign board
will be erected at a location approved by the Superintending Officer.
The Project Manager should maintain a number of daily workers to help him to do petty
works such as pumping water, site clearing, grass cutting, survey control, pegging and so
on. Site security and watching will also be under his supervision.
Safety and Hazard sign are crucial at this project since most of the works involved deep
excavation and construction on the road. The sign shall be advertised at strategic location
to remind fellow workers and public of the safety requirement to enhance a safe working
environment.
The execution of works at site should strictly follow the work programme approved by
the Employer. As part of a preparatory works the Project Manager will liaise with the
Procurement team to get all construction materials to be tested and samples to be
submitted for the Superintending Officer approval. Suppliers of concrete need to submit
their propose design mix and arrange for trial mix to be tested and witness by the
Superintending Officer.
Once the Construction Drawing issued we will start excavation works for the pump
station follows by others structure works, Meanwhile Barbenders will start fabricating
reinforcement and Carpenters will proceed with the fabrication of formworks. Upon
completion of the excavation work the structural constructions will take place. There are
three separate teams working on this three separate site.
While the construction of the pump station in progress the same process of excavation,
and construction of sewer line will be in place. We will have three teams working
concurrently on the open cut sewer line and two teams on pipe jacking works.
__________________________________________________________________________________
Page No.13 of 14
GENERAL METHOD STATEMENTS FOR SEWAGE TREATMENT PLANT
UPGRADING WORK
Feedbacks of the work progress will be reported to the head office to update
information to the procurement teams for their further actions. Mechanical and Electrical
Equipment shall be procured to suit staggered completion of the structures.
Prior to delivery all equipments that need factory testing shall be witness tested at the
factory by the Superintending Officer. Mechanical and Electrical Equipment will then be
installed at site to suit staggered completion of the pump stations.
__________________________________________________________________________________
Page No.14 of 14