OWNER:
NATIONAL AUTHORITY FOR TUNNEL
CONSULTANT:
ENGINEERING CONSULTANT’S CONSORTIUM
MAIN CONTRACTORS:
AHPC CONSORTIUM
SPECIALIZED CONTRACTOR:
TUNNEL & SLIPFORM DEPARTMENT – THE ARAB CONTRACTORS
THE ARAB CONTRACTORS
الموقع العام OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Figure 2-1
The project is the greater Cairo metro line 4, which is considered the best
route to connect 6th of October City with the center of the capital and its
DESCRIPTION
other parties to the metro network and provides passenger trANDport service
PROJECT
and connects it to areas with high population densities in the pyramid, Faisal,
Omraneya and Giza. The Greater Cairo Metro Line 4 shall be
approximately 18.8km in length.
The greater Cairo metro line 4 phase new CP401 consists of 12 stations from
Hadaek El- Ashgar station to El- Mesaha square with 13.60 km in length.
Figure 2-1 shows the tunnel alignment of greater Cairo metro line 4,
including Phase New CP401.
THE ARAB CONTRACTORS
مكونات المشروع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
overview
PROJECT
The station understudy is Al-Ahram station. Figure 3-1 shows the location
of Al-Ahram station on map. Al-Ahram stations are considered
underground station with dimensions approximately 17.70m x 192.4m X
32m as in Figures 3-1 and 3-2. The station shall be executed by the topdown
method with a permanent diaphragm wall supported with horizontal
slabs as in Figure 3-3.
THE ARAB CONTRACTORS
مكونات المشروع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
overview
PROJECT
The station understudy is Al-Ahram station. Figure 3-1 shows the location
of Al-Ahram station on map. Al-Ahram stations are considered
underground station with dimensions approximately 17.70m x 192.4m X
32m as in Figures 3-1 and 3-2. The station shall be executed by the topdown
method with a permanent diaphragm wall supported with horizontal
slabs as in Figure 3-3.
THE ARAB CONTRACTORS
مكونات المشروع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Figure 3-4: Section of the diaphragm wall with slabs at Al-Ahram station
(Top- down construction method)
overview
PROJECT
The station understudy is Al-Ahram station. Figure 3-1 shows the location
of Al-Ahram station on map. Al-Ahram stations are considered
underground station with dimensions approximately 17.70m x 192.4m X
32m as in Figures 3-1 and 3-2. The station shall be executed by the topdown
method with a permanent diaphragm wall supported with horizontal
slabs as in Figure 3-3.
TUNNELS AND SLIPFORMS DEPARTMENT
SCOPE
THE ARAB CONTRACTORS
نطاق العمل OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
نطاق العمل OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
نطاق العمل OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
الجدول الزمني للمشروع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
CRITICAL
PANEL
THE ARAB CONTRACTORS
نطاق العمل OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
REFERENCE GEOTECHNICAL DATA
THE ARAB CONTRACTORS
تقرير التربة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
GEOTECHNICAL
The geotechnical data needed as a reference in the execution of the diaphragm
works at Al- Ahram station is concluded from the tender document volume 6. The
DATA
reference geotechnical data shall be the performed boreholes and the idealized soil
parameters. Figure 6-1 shows the geological sections of the soil at Al-Ahram
station. The logs for the two preformed boreholes BHDD27-BH65 are in Annex A.
BC 40
SchlitzwandfräseTrench Cutter
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أجزاء الماكينة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
PROCEDURES OF EXECUTION
(Diaphram walls and slurry walls)
THE ARAB CONTRACTORS
خطوات التنفيذ التفصيلية OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
خطوات التنفيذ التفصيلية OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
خطوات التنفيذ التفصيلية OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
ملخص مراحل التنفيذ OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
PROBLEM OCCURRENCE
(2021/11/09)
THE ARAB CONTRACTORS
بداية المشكلة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
DURING EXCAVATION WORKS IN PANEL (13) IN (2021/11/09) AT (15:23) ,THE DESANDER UNIT STOPPED
WORKING AND THE CUTTER OF THE MACHINE STUCK BENEATH THE SOIL LAYERS AT THE DEPTH OF
(43 M) AND THE CABLES OF THE MACHINE WAS UNABLE TO LIFT THE CUTTER FROM THE SOIL .
THE ARAB CONTRACTORS
أسباب المشكلة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Steps of Rescue.
1. Move main hydrofraise away from the
trench, so rescue one can be vertical to the
panel
2. Make rescue panel Infront of the main
panel using secondary hydrofraise till depth
= 50 meter from current ground level .(as-
shown in drawings)
3. Remove the Cutter of secondary hydrofraise
& install air lift pipe ,through main panel
and start to pump air through the air lifter
4. Any filled soil above cutter shall be moved
to the rescue panel, Meanwhile the main
hydrofraise lift up the Stuck cutter from the
panel smoothly (low rate)
5. After lifting cutter & air lift pipe, the two
panels shall be concreting using sand
immediately .
THE ARAB CONTRACTORS
نتائج المحاولة األولى OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Steps of Rescue.
1. Move the main hydrofraise away from the
trench, so the rescue one can be vertical to
the main panel
2. Make excavation for two rescue panels at the
two sides using secondary hydrofraise till
depth = 50 meter from current ground level .
3. Install air lift pipe through the main panel
and start to pump air through the air lifter
4. Any filled soil layers above the cutter shall be
removed to the rescue panel, Meanwhile the
main hydrofraise lift the trapped cutter from
the panel smoothly (low rate)
5. After lifting cutter & air lift pipe, the three
panels shall be concreting using stabilized
sand immediately .
THE ARAB CONTRACTORS
نتائج المحاولة الثانية OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Steps of Rescue.
Steps of Rescue.
1. Evacuate the Road surrounding the panel
for (6 hours period).
2. Start the excavation works for the new
rescue panel behind the main panel
3. Install the new frame to lift the cutter at
the center of the main panel
4. Start the process of lifting the stuck cutter
using the hydrofraise and the Cable wires
attached to the crawler crane which
installed by Divers and the additional
installed Truss frame.
THE ARAB CONTRACTORS
الرسومات التنفيذية للهيكل المعدنى OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
ELEVATION - VIEW
SIDE-VIEW
TOP-VIEW
THE ARAB CONTRACTORS
نتائج المحاولة النهائية OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
The method Managed to lift the cutter up from the soil layers successfully IN (2022 / 1 / 3)
PROCEDURES OF FINAL TRIAL
THE ARAB CONTRACTORS
اجراءات إخالء الطريق OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
تصنيع الهيكل المعدنى بالورش OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
نقل الهيكل المعدنى الى الموقع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
تركيب الهيكل المعدنى بالموقع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
عملية تحضير معدات الغطس و التأكد من األمن و السالمة OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
عملية إنزال الغطاسين OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
عملية إنزال الغطاسين OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
عملية إنزال الغطاسين OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
تجهيز المعدات لعملية السحب OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
أثناء عملية السحب OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
بداية ظهور القاطع أثناء عملية السحب OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
)2022-01-03( خروج الجسم الكلى للقاطع OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
THE ARAB CONTRACTORS
OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
إعداد
الوحدة الھندسية بإدارة األنفاق و الشدات المنزلقة
ENGINEERING UNIT - TUNNEL & SLIPFORM DEPARTMENT
م – محمد نبيل عبد الفتاح )(ENG – MOHAMED NABIL ENG – AHMED A . NASSER
THE ARAB CONTRACTORS
OSMAN AHMED OSMAN & CO.
TUNNELS AND SLIPFORMS DEPARTMENT
Thank you