You are on page 1of 12

TWELVE YEARS EXPERIENCE IN GAS PRODUCTION ON

THE MOLVE, KALINOVAC A N D STAR1 GRADAC FIELDS


Z. Mlinaric and M. Zelic, Croatia.

Abstract. The article covers the production technology as well as the Molve, Kalinovac and Stari Gradac gas
fields completion.
Specified are the upgrading phases and methods of well completion, from the standpoint of production
process optimization and safety, with special accent on the selection of adequate high-alloy steel grades for
prevention of the corrosion processes.
Experience achieved in the past twelve years has shown that the choice was correct, considering the applied
materials as weil as the sealing components and the gas-tight thread joints. No evident damage due to corrosion
or any other cause was detected in the past period and we hope that in the majority of cases this will be
maintained during the gas wells production life.

1. INTRODUCTION duction completion as well as to conceive the most


rational gathering system. We should also .stress the
The Molve Gas Field was discovered twenty years
fact that, just recently, the total production of the
ago. Further reservoir engineering was effected seven
said three fields amounted to ten billion cubic meters
years later due to extremely severe natural conditions
of gas and over two million tons of condensates.
(see Fig. 1).
Such conditions were a great challenge at the time,
2. GEOLOGY
not only for our company, but also for international
experts and technologists, and particularly for sub- The Molve, Kalinovac and Stari Gradac gas fields
surface and surface well equipment material manu- are located in the north-western part of Croatia,
facturers. some 120 km from the capital-Zagreb. Morphologi-
The first two production wells on the Molve field cally speaking, it is a low-lying region of the Drava
were equipped and put to production in 1980, after Valley, with an average height of 120 m above sea-
which both reservoir engineering and well construc- level. The ‘Molve’ structure is an asymmetrical anti-
tion were intensified, resulting in the completion of cline cut through its northern part by three reverse
the total of 21 wells presently in production, yielding fractures. The fluid bearing rocks are from the
of 200000 to 500000 cubic meters of gas per well Miocene and pre-Tertiary period, with different lith-
daily. ological content. The reservoir rocks opened for pro-
The development of the Kalinovac Gas Field duction are Paleozoic and Mesozoic conglomeritic
began in 1984, and today, there are 14 wells in pro- Phyllites and quartzites, Mesozoic carbonates
duction, yielding 100000 to 200000 cubic meters of (dolomites of the boundstone type), and Miocene
gas per well daily, together with about 120-180 cubic carbonates.
meters of condensate. The ‘Kalinovac’ structure is also an asymmetrical
As can be seen from Table 1, it is a gas-condensate anticline cut through its northern part by four
field with extremely severe natural conditions. reverse fractures and two normal fractures on the
The Stari Gradac field is the last one in the engin- southern edge of the structure, of north-west try
eering sequence, covering only 6 completed wells, 3 south-east direction. The hydrogen accumulation has
of them currently in production yielding 50000 to occurred in the natural reservoir characterized by the
100000 cubic meters of gas per well daily and 45-85 presence of three main chromostratigraphic wholes :
cubic meters of condensate. Permo-Triassic, Mesozoic and marine Miocene,
Considering the high reservoir pressures, and, separated by transgressive borders. The carbonate
especially, high reservoir temperatures, it was neces- conglomeritic Phyllites and quartzites, Mesozoic car-
sary to choose the most rational and the safest pro- bonates (dolomites) and Miocene carbonates (sandy
483
484 NEW EVALUATION TOOLS AND METHODOLOGIES

--
- I
MUDGfiAOIEANT(èad1Om)
ITHOLOGY WELL COMPLETION PRODUCTIONEQUIPMENT
- PORE GRADIEANT(barl1On
1.1 1.2 1.3 1.4 1.5 1.6
GRAVEL TUBING HANGER
7
\
\
\
CLAY CLAYSTONE HYDRAULIC \
CONTROL LINE
SAND CLAY
FLOW COUPLING
\
I
I
CLAY - CASING l
1
COAL I
TUBING RETRIEVABLE
I
SUBSURFACE SAFETY VALVE
I
SANDY I
CLAYSTONE I
I
FLOW COUPLING 1
COARSE 1
SANDSTONE I
I
I
CLAY MARL TUBING, PREMIUM THREAD I
I
COAL 1
I
SLIDING SIDE DOOR
I
l
I
I
COAL I
MARL I
STRAIGHT SLOT LOCATOR I
I
PERMA-DRILL PRODUCTION

SANDSTONE
'RTR' SEAL UNIT

SEAL SPACER MANDREL


SEAL BORE EXTENSION
SANDSTONE 'RTR'SEAL UNIT
MARL
'KTR' SEAL UNIT

'RTR' SEAL UNIT

MULE SHOE GUIDE


MILL-OUT EXTENSION
MARL SILTITE

LANDING NIPPLE

SANDSTONE PERFORATED TUBING

II INTERMEDIIATE
CASING NO-GO LANDING NIPPLE
COARSE
SANDSTONE 9:" L-80
47 #
MUDSTONE
WIRELINE REENTRY GUIDE
LIMESTONE
DOLOMITE

QUARTZITE

AMPHI BOLITE
SCHIST

PRODUCTION
CASING
~..
7" 32ir ~

PREMIUM

Fig. 1. Typical well completion and productionequipment for Molve field.


NEW EVALUATION TOOLS AND METHODOLOGIES 485

TABLE I
Formation and Fluid Properties

Field
Parameters Molve Kalinovac Stari Gradac

Form ation
P,, bar 480 477 505
T i , "C 179 182 195
Depth, m 3128-3480 3415-3434 3680-4072
OGR, cm3/m3 70 660 865
WGR, cm3/m3 45 146 590
k, pm2 1-36 0.2-29 0.1-0.3
Porosity, % 8.2 5 3-4
Collectors phylite, quartzite, phylite, quartzite, ciastite,
dolomite, limestone dolomite, limestone quartzite
Gas
Y8
0.8 1 0.74 0.73
Contents:
CO,, mol% 25.1-23.4 11.15-11.43 10.56-10.36
H2S, PPm 75.0-1 12 35-75 258-320
RSH, mg/m3 5.3-3.1 1.3-5.9 17.5-11.0
Hg, mg/m3 0.078 1-0.1012 O. 177-0.241 0.0026-0.0086
Condensate
Density, 15 "C kg/m3 791.3 778.3 768.53
Pour point, "C + 13-+ 14 +9 +10
Water
pH-value 4.6-5.21 5.6-6.24 5.05
Brine, g NaCl/dm3 0.1-1 1.7 12-14 2.57-4.99
Cloride, mg/dm3 O. 3 18-709 8 6824-81.5 1326-2975
Bicarbonate, mg/m3 74.44 146.4-439.0 113.5-957

wackestone and grainstone) were opened for pro- static one, as well as by extremely high temperatures,
duction. whereas the well fluid mixture contains a relatively
Stari Gradac is a massive type reservoir (horst high percentage of CO2 H2S and mercury. Some of
anticline) spreading along the border, partly belong- the reservoir and the reservoir fluids characteristics
ing to Croatia and partly to Hungary (Barcs-Nygat). are given in Table 1.
Hydrocarbon accumulation was formed in a com-
bined type trap. Collector rocks are represented by 3. PRODUCTION SYSTEM
different lithological facies-breccia conglomerates
The production system, comprising a unique
are predominant in the productive part of the M
hydrodynamic and thermodynamic 'reservoir-well-
reservoir, anhy-dolomites in the P reservoir, whereas
gathering station' system, was elaborated and
quartzites make a part of the P2 reservoir. The major
designed for all three fields in question on the basis
part of the hydrocarbon accumulation is associated
of single phase and two phase flow patterns, thereby
with pre-Tertiary rocks.
covering the follówing :
Lithological diversity within the reservoir rocks in
both the vertical and lateral sense, on all three fields, The physics of fluid flow from formation to well
was also reflected upon the layers' physical The physics of fluid flow in tubing
characteristics-from very high to very low per- The physics of fluid flow in flowline
meability and porousness. Gas and condensates are The physics of fluid flow through restrictions
contained primarily in the fracture (secondary) poro- Heat loss in tubing and flowline
sity, whereas the matrix porosity is almost negligible. Mechanical stresses in the string
All three reservoirs are characterized by reservoir Anti-corrosion protection
pressures which are much higher than the hydro- Safety system
_.

486 NEW EVALUATION TOOLS AND METHODOLOGIES Pl P l


Analysis and concept of the production system were the appearance of H,S corrosion is possible if
based upon the most recent correlations of single H2S partial pressure is above 0.010 bar;
phase and two phase flow not only in the reservoir, for carbonic and alloy steel grades with chro-
but also in the horizontal and vertical pipes, and cor- mium content below 13% the hardness as per
responding restrictions covering all hydrodynamic Rockwell scale should not exceed 23 H R C , and
and thermodynamic processes. for duplex materials not exceeding 28 HRC.
Besides, the correlations associated with the due to the relatively deep wells the solution
analysis and elaboration of the production system annealed tubing yield strength was supposed to
are an integral part of the ‘nodal system analysis’, be 551.7 MN/m2 (80 KSI).
‘tubing movement’ and ‘heat loss analysis’ computer
Abiding by these criteria and the MR 01-75-91
models, which have been used for the calculation of
NACE standard, the materials for the production
all relevant parameters under different conditions of
string and the production casing were selected :
both well and the entire production system exploit-
ation, as well as for the well completion. - production casing above permanent packer of con-
trolled hardness should be of carbon steel.
- production casing below the packerduplex
3.1. Anti-corrosion protection material with 25% Cr in gas wells, and 13% Cr in
gas-condensate wells.
With respect to the presence of CO,, H,S, - production tubing-high-alloy steel duplex
mercury and chloride, determination of anti-
material with 25% Cr in gas wells (Molve) and
corrosion protection methods was one of the greatest high-alloy steel with 13% Cr; hardness H R C < 23
challenges facing our experts. Two basic methods
in gas-condensate wells (Kalinovac and Stari
were considered:
Gradac) ;
(a) inhibition (continuous, batch, squeeze) - subsurface equipment (packer SCSSV . . .) made of
(b) the choice of materials resistant to corrosion Incoloy 925 material.
which was expected under such severe conditions. In principle, the thread joints of the production
In the beginning, continuous inhibition was attempt- string and production casing are gas tight premium
ed through the injection valve at a given depth, but thread with three to four sealing elements, one of
this system was not justified because very soon the them being metal to metal.
injection valve was damaged and corroded due to the
presence of certain aromates in the inhibitor. Besides, 3.2. Well completion
a part of the string below the valve remained
Initial equipping
unprotected.
Also, it is important to stress that, due to the high Well design of the first two production wells
temperature (above 180 OC), the impact of inhibitor Mol-11 and Mol-12 was executed on a geological-
failed in the deeper well layers due to its disinte- lithological column and logging measurements of the
gration. neighbouring wells, taking into account the well
After anti-corrosion protection was not effected depth, pore gradient, layer fracturing gradient and
with the inhibition it was decided to apply high-alloy ‘temperature gradient. By the standard casing pro-
steel grades to ensure resistance to different types of gramme, stresses appearing in the respective columns
corrosion under different pressure, temperature and were calculated, and the following well construction
stress conditions, i.e. resistance to: had been approved :
- CO, corrosion - conductor casing, 2 0 , J-55,94lb/ft to the depth of
- H,S corrosion (general) about 250 m for the consolidation of surface layers
- sulfide stress cracking i.e. for the protection of surface water from pol-
- chloride stress cracking lution.
- liquid metals corrosion, and so on. - 1st intermediate casing 13$”, N-80, 72 lb/ft covers
poorly consolidated layers, more shallow gas hori-
The criteria for the choice of material referred to the
zons and formations of low layer gradient.
following:
- 2nd intermediate casing, 9;“ L-80, 47 lb/ft was
(a) the appearance of CO, corrosion is possible if installed in the overpressure zone floor and was
partial pressure of CO, is above 2 bar; cemented up to the top.
i81 p1 NEW EVALUATION TOOLS AND METHODOLOGIES 487

- production casing 7”, 32 lb/ft, L-80 was installed - despite pre-stressing of the production casing, the
down to the well bottom, whereas, in the perfor- entire well head was lifted for about 120 mm;
ation (packer seat) zone, a 13% Cr column was - after squeezing the inhibitor, the production index
installed. Thread joints are, as we have already dropped.
mentioned, gas tight, while the column is cemented
By a major increase of the Molve field reserves, as
to the depth of 2.000 m from the head, and its free
well as by the discovery a new Kalinovac Gas-
part stretched in order to compensate for tem-
Condensate Field, the second phase of the Podravina
perature dilatations.
Project development was started, expected to solve
Estimating that in the gas, next to CO,, there is no the observed deficiencies, and to pay particular atten-
major quantity of H,S, a tubing of 3f” in diameter, tion to anti-corrosion protection, regarding the pres-
N-80, (13% Cr), 9.2 lb/ft was installed in the wells, ence of C O , , H,S, chlorides and mercury. On the
with gas tight premium thread, a permanent packer basis of information and professional experience
with latch system, two side pocket mandrels (one for from other fields in Europe and the States with
killing and one for inhibition), extension joints and similar characteristics, the conclusion has been
subsurface safety valve (SCSSV). The sealing of the reached that the chosen construction was not an
wellhead and the christmas tree was performed by optimal one, particularly with respect to anti-
elastomeric seals. The christmas tree, having a corrosion protection.
working pressure of 690 bar was made of the AIS1 On this basis, the well design and production
410 (13% Cr) material, with manually operated equipment construction were chosen which, during
master gate valve and hydraulically operated upper its life time will require a minimum number of work-
master gate valve. overs, whereas the corrosion process shall be reduced
Test production was started towards the end of to minimum through selection of adequate material,
1980, and, with numerous difficulties, went on for appreciating the aforementioned criteria prescribed
several days. During that period, the existence of a by the NACE standard.
considerable quantity of H,S in the natural gas was The well completion design (Fig. 1) did not
established. In order to prevent the corrosion undergo any major changes except in production
process, we replaced a major part of the production string material-carbon steel with controlled hard-
equipment. The N-80 tubing was replaced by a new ness. (HRc< 23).
one of L-80 quality, and a new type of packer was The production casing thread is premium thread
installed enabling free movement of the tubing. and cementation was performed in one stage-up to
Packer and tubing sealing was enabled by sealing the well head.
units with V seals in the following combination: This kind of cementation with additional circula-
ryton-teflon-ryton (R-T-R) and kalrez-teflon-ryton tion of hot drilling mud in order to make the cement
(K-T-R). Parts of the christmas tree were replaced by binding as uniform as possible and the shift of the
new monolithic parts without welded joints, whereas production casing due to temperature be minimum,
tubing hanger sealing was enabled by high tem- demanded the production casing seat to be placed in
perature elastomers activated by sticks. It was the well head, with a mandrel system.
decided that the corrosion problem caused by H,S is The production string (Fig. 2) and the christmas
to be solved by injecting a 20% inhibitor solution in tree (Fig. 3) underwent more substantial changes,
diesel oil into the layer. especially with respect to the choice of material:
A few months of performance of the said wells
(1) Considering the presence of CO2, H,S chlorides,
revealed the following difficulties:
the duplex stainless steel material was chosen for
- tubing hanger and christmas tree sealing elements tubing (50% austenite-50% ferrite), solution
made of high temperature elastomers (204 O C ) annealed, with a minimum yield strength of
proved completely inappropriate for high dynamic 80-KSI. As yield strength of this material is con-
temperatures (120 OC) and other fluid properties. siderably reduced under high temperatures, the
After four months, not even the additional activa- string was tapered.
tion of the elastomer seals was enough to reach (2) Other parts of the equipment: packer, sliding
tightness; side-door, subsurface safety valve, was made of a
- lack of tightness of the subsurface safety valve was more superior material: Incoloy 925.
observed (with a number of elastic seals) at each (3) Due to the presence of aggressive gases and
well shut-down; amines, for sealing units within the packer, the
488 NEW EVALUATION TOOLS AND METHODOLOGIES [81P l

KI L

KI1.L LINE

LEGEND:
GATE VALVE (LOWER MASTER)
HANDWHEEL OPERATED
GATE VALVE (UPPER MASTER)
ADAPTED FOR HYDRAULICACTUATOR
GATE VALVE (WING)
ADAPTED FOR HYDRAULIC ACTUATOR

ADAPTED FOR ELECTRIC ACTUATOR

Fig. 2. Wellhead and Xmas tree.


NEW EVALUATION TOOLS AND METHODOLOGIES 489

-- __- - -- __
__ - __-
__-._.- -. --
Tubing retrievable
suríace controlled

DOWN SYSTEM

Fig. 3. Wellhead safety (control) system.

combination R-T-R and K-T-R was chosen, (2) The clad material of the Christmas tree was
whereas the DSV sealing materials were made of replaced by the F6NM (13% Cr) forged material.
Ryton, Aflas or Kalrez.
A clad material was chosen for the christmas tree,
3.3. Safety system
whereas the gate seat and stems were made from
Inconel 625. The safety/shut-down/system consists of two
For sealing of the Christmas tree, a metal to metal hydraulically operated gate valves : the upper main
sealing was chosen, ensuring high sealing safety and the wing surface controlled subsurface safety
even at temperatures above 135 OC. valve and an electrical hydraulic unit. The criteria for
shut-down of the wing valve is either high or low
With the discovery of the Stari Gradac Gas-
pressure in the gas flowline, whereas all three valves
Condensate Field (200-300 ppm H,S) and the exten-
are closed only in the case of low pressure of the
sion of the Kalinovac field, the third phase of the
Christmas tree.
production system design was practically started. On
Remote control shut-down of the well is also pos-
the basis of the experience gained, the correctness of
sible from the control room in the central gas station,
the well construction, i.e. of the subsurface and
where other well performance parameters are moni-
surface equipment, was confirmed, since it completely tored as well,: pressures, temperatures, production,
satisfied the criteria set for safe operation of the well. etc. The gas flowline is made of plain carbon steel,
Therefore, for new wells of the Kalinovac and the
whereas the anticorrosion protection is performed by
Stari Gradac fields, the changes in the choice of sub- continuous inhibition at the inlet of the gas flowline.
surface and surface materials were only partial:
(1) Aware of the fact that we were dealing with gas- 3.4. Well killing
condensate reservoirs, the AIS1 420 (13% Cr)
material was chosen for tubing, maximum hard- For cases of unpredicted accidents and leakage of
ness below 23 HRC,although it does not entirely production equipment, a killing system was con-
meet the criteria set by the NACE Standard; structed. Brine water was chosen for well killing and
NEW EVALUATION TOOLS AND METHODOLOGIES
490
-

LEGEND
- Gas Line
_ _ _ _Condensate
____ Line
_.

-
..-.-.--
Salt Water line
Process Feed Line ('Etan')
Distribution Line
Fig. 4. Gathering system of Molve-Kalinovac-Stari
Gradac.
GTP Gas Treatment Plant
SGS Satellite Gas Station
PP SGS Pilot Plant Satellite Gas Station

is prepared in a plant located next to the central gas The gas from all gas fields is directed to the Molve
station. In every gas station, there is a reservoir with GTP where non-hydrocarbon components are
a 120 cubic meter volume, containing brine water separated from the gas mixture, the gas is dehydrated
which is, when necessary, transported to each indi- and prepared for transport. Within the scope of the
vidual well through a pipeline. central gas treatment plant there is an H,S purifi-
Due to the proven characteristics of formation on cation unit and an ethane yielding plant.
all three fields, the well killing was performed by The water from all gas stations is transported by
direct pumping of the corresponding fluid into the pipeline to Molve, where it is injected into the wells.
formation. If that is not possible, there is yet another
possibility: the opening of the sliding side-door or
perforation of tubing immediately above the packer,
4. PRACTICAL EXPERIENCE AND
thus providing for fluid circulation.
OPERATIONAL PROBLEMS
All devices and equipment, as well as the team for
well killing, are located in the immediate vicinity of 4.1. Corrosion
the central gas station. The time elapsed between the
The corrosion process is monitored in several
sounding of the accident on one of the wells and the
ways:
preparation for starting operation is not to surpass
two hours. (a) by measuring the iron content in water
(b) by measuring the inhibitor content in conden-
sates
3.5. Gathering system
(c) by measuring atomic hydrogen-hydrogen probes
The gathering system consists of one satellite gas (d) measuring by electro-resistant probes
station on the Stari Gradac field, three satellite gas (e) coupon testing
stations and a plant for condensate stabilization on (f) measuring of the inner tubing wall with a micro-
the Kalinovac field and one satellite gas station and caliper
three gas treatment plants on the Molve field (Fig. 4). (g) ultrasonic wall thickness measurement
The satellite gas stations perform first of all the
Experience has shown the following:
separation of liquid and gaseous phase, whereas the
condensate from the fields of Kalinovac and Stari (1) On particular wells of the Molve field where a
Gradac is stabilized on Kalinovac, from which it is 13% Cr tubing was used and the anti-corrosion
forwarded for transport. protection carried out by injecting the inhibitor
NEW EVALUATION TOOLS AND METHODOLOGIES 491

solution into the layer (first portion: 4 cubic stream, or the high percentage of amines in the con-
meters, 50% of the inhibitor; second portion: densate.
10-20% of the inhibitor), even after eight months, The subsurface safety valve sealing elements made
the content of the inhibitor in the condensate was of ryton, aflas, kalrez and peek, have also satisfied all
above 100 ppm. Chemical, mechanical and metal- production criteria, whereas only at a production
lurgical tests performed on the same tubing after shut-down and cooling of the well there has been
eight years of performance have shown satisfac- some occasional gas leakage. By restarting (heating)
tory results. Namely, the results of microstruc- it, a full tightness was achieved. The Christmas tree
tural tests pointed to the existence of pitting sealing elements made of elastomers has proven non-
corrosion caused by CO2 and C1- with the great- functional at the initial equipping of wells due to
est depth of 0.035 inches. high dynamic fluid temperatures (> 135 OC), so that,
On other wells of the Molve field, where a duplex after four months of operation, tightness could not
material tubing was used (25% Cr), by measuring be achieved even by additional activation. Therefore,
the iron content in the water, and by measuring the Christmas tree and the tubing hanger sealing
the inner tubing walls by means of a micro- system at such temperatures have to be metal to
caliper, even in the wells with an increased water metal. Practice has shown that sealing of the pro-
content, it was shown that there is no major cor- duction casing may be performed by elastomers due
rosion presence. The same satisfactory results to a significant thermal drop between the tubing and
(regardless of a high H2S content) were obtained the outer part of the production casing.
on the Kalinovac and Stari Grad fields wells,
where a 13% Cr tubing was used, due to a con-
siderable quantity of condensates acting as a 4.3. Other experiences regarding the
natural inhibitor. production equipment
The appearance of erosion more than corrosion
- After a long performance of the well, it was no
has been spotted on the lock mandrels of the wire
longer possible to open the sliding side-door. This
line safety valve made of 9% Cr 1 Mo material,
was caused by diesel oil cracking (with inhibitor),
and on the outlets of the adjustable chokes and
by which the brine water in the well was replaced
control discs that were not coated with hard
before the perforation (through production
material. The same phenomenon was registered
equipment).
by measuring the wall thickness of the elbows of
- Fracturing of a well through production
the gas flowline loops.
equipment caused major damage regardless of the
The anti-corrosion protection of all surface pipe-
protective measures that were undertaken.
lines by inhibitor application has proven most
- The percentage of the damage of thread joints
appropriate. By a long-standing practice, we have
during workover operations amounted to 10-30%,
established that, on the Molve field, for the pro-
whereas the break up torque was 3-4 times higher
tection of the flowline, the dosage of one phase
than the make up torque.
inhibitor in the amount of 0.016 ppm per cubic
- The safety (shut-down) system has to be tested ‘at
meter of gas suffices. On the Kalinovac and Stari
the spot’ at least after each six months of oper-
Gradac gas-condensate fields, the continuous
ation. While doing so, care has to be taken of the
dosage of a ‘three phase’ inhibitor in the amount
hydraulic oil quality (viscosity) for the operating
of 0.026-0.064 ppm per cubic meter of gas was
conditions of - 35 OC to + 50 OC.
maintained. Inhibition is also performed in the
forwarding salt water pipelines-10-20 ppm per
cubic meter of water.
4.4. Difficulties encountered in the
We have given up the corrosion monitoring by
production process
means of hydrogen probes.
An extremely significant problem in the pro-
duction of Kalinovac and Stari Gradac fields is the
4.2 Sealing components
disposal of scales in the near well zone and a part of
The combination of R-T-R and K-T-R sealing the production string below the packer. This pheno-
components has ensured full tightness of the packer menon has been spotted when there were very high
seal assembly, regardless of the high temperature and dynamic pressure pulsations on some of the wells,
the presence of aggressive components in the gas whereas, at the same time, production rates were
-

492 NEW EVALUATION TOOLS AND METHODOLOGIES 181P l

lowering, which finally resulted in complete pro- damage nor single intervention due to damage
duction shut-down. Believing that it was a blockage caused by corrosion.
caused by the liquid phase forming in the near well Sealing elements as well as premium thread joints
zone, a subsurface choke was installed in one of the have completely justified their purpose and there
wells in order to improve the two phase flow. After a were no major problems in this respect.
few days of operation, the well stopped producing Due to high pressure and high temperature, the
once again, and, when the subsurface choke was Joule-Thomson coefficient has relatively small sig-
taken out, it was observed that it is completely nificance (in perforations it comes close to the
plugged with scales. inversion point), so that the cooling effect in the
By chemical analysis of the sample, it was estab- tubing is smaller, i.e. the fluid comes to the surface
lished that the scales consisted of about 90% of under relatively high temperature (120-135 OC),
calcium sulphate and about 10% of calcium carbon- which caused the rational conception of the gath-
ate. Its formation was explained by the mixing of ering system.
incompatible waters, in our case, the CaBr, solution The safety system, conceived with three safety
and layer water containing sulphate ion, as well as by valves (SCSSV, upper main and wing automati-
the change of pressure and temperature. cally operated) has also proven efficient under
The problem was solved by injecting 20 cubic such severe conditions of gas production.
meters of 8% Na EDTA solution in the reservoir. Intensive formation of scales and its disposal in
Such interventions have been performed only on the perforation area and the lower part of the well
some wells and they have given good results, while has so far been successfully taken care of by
the time elapsed until the new treatment amounted chemical means through periodical injecting of the
to 6-8 months. EDTA solution into the formation (twice a year).
It was also observed that, by longer production,
i.e. after two to three treatments regarding the
removal of calcium sulphate using Na, EDTA, the APPENDIX A
formation of calcium carbonate was increased, which
was only to be expected of the basis of the layer Basic fluid f l o w equations
water analysis. The disposal of calcium carbonate
was solved very simply by injecting a 10% acetic acid Jones-Blount-Blaze equation (2) is used for fluid
solution. flow from formation into well:
The problem of scales is still being studied, both
with respect to the establishment of its genesis, type al - P 2 = A%, + &,e (A- 1)
and conditions of formation, and with respect to the
establishment of an efficient solution and/or inhibi-
tion which would prevent its formation at such high
(
A = 15.40 kh T)[ln
j
(0.472 rJr,,,) + S ] (A-2)

temperatures. 4.734 x 10-19 yTzp


B= 64-31
a
(2) Fluid flow in tubing based on correlations for
5. CONCLUSION single (gas fields) and two-phase flow (gas-con-
densate fields) (4):
On the basis of the afore presented the following
can be concluded : (a) for single phase flow (gas)
1. The choice of well completion equipment has
proven to be fully justified, both from the pro- qse = 3.378 x lo9
(pif- pw,, - e")D:6/3
duction process standpoint as well as from the yE L ,
standpoint of safety. 0.5

2. The choice of material in order to lower the corro- e"-1


sion process i.e. of high-alloy steel grades with
13% Cr and 25% Cr (which, at the time, was (b) for two-phase flow pressure gradient
among the first to be used in practice under such
conditions) has shown, after 10-12 years, to be
completely justified, since there was no single
P l p1 NEW EVALUATION TOOLS AND METHODOLOGIES 493

2.1. Terminal critical velocity of the droplet in (5) Fluid heat loss based on equations (4):
tubing based on Turner's et al. equation (2): (a) in tubing

Vcr =
C[(pJ16) - 0.0405 pwJ0.25 -
('4-6)
(0.0405 *
C = 1.62-for water
c = 1.23-for condensate
Minimum flow rate of gas for continuous
X [GT-
%bwf

x ( i - e-0L)
Lt
-Pw&

-1
9
- CP
(A-14)
liquid removal :
(b) in pipeline
(qse)min= 24.64 x At P
lo6 u gi-.? (A-7) TL= To + (T,- T o ) ë U L
2.2. Erosional velocity (1):
0

( 4 kDon
a=- (A- 16)
mCP
c = 120
Erosional flow rate of gas : (6) Forces acting on tubing expressed by equations:
(a) external pressure
(qsc)max= 161.0 x 106At (A-9)

(3) Fluid flow in flowline based on correlations for


single and two-phase flow (4): (A-17)
(a) for single flow (gas)
2YC(DtO/6) - 11 for Dto/6 < 14
pTiPqo. 5 Po =
(D,0/@2
qse = 3.378 x lo9 D'I3
(A-18)
(A-10) (b) internal pressure

(4) Fluid flow through restrictions (1) :


(a) through choke beam (A-20)

(A-12)
4, = 225
m'
d,'CDPWh.
LIST OF SYMBOLS
(b) through subsurface safety valve
_A_ constant in Eq. (A-1)
At cross section of tubing area, m2
a parameter of heat transfer, W/(m2 K)
R
u constant in, Eq. (A-1)
(A-13) c constant in Eq. (A-6)
or CD discharge factor
c constant in Eq. (A-8)
Ap = 4.86 x 10-6(1 - /I:)4SeYTlZi cp specific heat of gas (at p = const)
Pld: G Y 2 D flowline size (ID), m
Do flowline size (OD),m
Bo = dJDt
D, tubing size (ID),m
Dto tubing size, (OD), m
y = 1 - (0.41 + 0.35E) d, choke beam diameter, mm
494 NEW EVALUATION TOOLS AND METHODOLOGIES 181p1

e Napierian logarithm base (e = 2.71828) underground temperature, K


f, two-phase friction factor bottom hole flowing temperature, K
GT geothermal gradient K/m wellhead flowing temperature, K
9 acceleration caused by gravity (g = 9.81 m/sz) upstream temperature of gas, K
h effective reservoir thickness, m critical velocity, m/s
hP perforated interval, m erosional velocity, m/s
dh elevation distance, m gas velocity, m/s
k heat transfer coefficient, W/(m2 K) mixture velocity, m/s
k effective reservoir permeability, pm2 x expansion factor
(CP) minimum yield strength, N/m2
L length of flowline, m average compressibility factor
Lt length of tubing, m Joule-Thomson coefficient, K/bar
dL distance (section) of flowline, m turbulent velocity flow coefficient
m
m'
-
mass flow rate, kg/s
tubing unit mass, kg/m
(ß = 2.33 x 10")
p o i
P average pressure, bar
internal tubing pressure, Pa ratio of borehole and tubing diameter
Pi
external tubing pressure, Pa specific gravity of gas (air = 1)
Po
- tubing wall thickness, m
Pr
PS,
average reservoir pressure, bar
separator pressure, bar gas viscosity, mPa s-
bottom hole flowing pressure, bar liquid density, kg/m3
PwJ
wellhead flowing pressure, bar mixture density, kg/m3
Pwh
surface flowing pressure downstream of choke, ratio of specific heat (IC= c,/c,)
Pwhs
bar
AP pressure drop, bar
upstream pressure, bar REFERENCES
Pi
Pz downstream pressure, bar 1. Beggs, H. D. Gas Production Operations, OGCI Pub-
gas flow rate at standard condition, m3/day lications, Tulsa, Okla., 1985.
4sc
2. Brown, K. E. The Technology of Artificial Lift Methods,
re drainage radius, m Voi. 4, PennWell Publishing Co., Tulsa, Oklahoma,
rW wellbore radius, m 1991.
S skin factor 3. Golan, M. and Whitson, C. H. Well Performance,
SF safety factor IHRDC, Boston, MA 02116,1986.
S parameter in Eq. (A-4) s = 0.06836 yLt/T,?) 4. Zeli&,M. Technology of Oil and Gas Gathering and
Preparation for Transport, INA-NAFTAPLIN,Zagreb,
average temperature, K 1987.
T, temperature at fluid entry, K 5. Technical Documentation of INA-NAFTAPLIN,
TL temperature at location L, K Zagreb.

You might also like