  PT. MAHESA KURNIA PRATAMA
  JL. Bina Marga Kav. 21, Komplek Ferry Souneville, Karangan, 
  Gunung Putri, Bogor Telp. 021 22940033
 
No: 157/H‐MKP/IX/2020                                                 Jakarta 7 September 2020   
 
Contract No: AH3‐IN‐0140‐2019   
PT ShimizuAdi Karya JO   
Asahan 3 Hydroelectric Power Project    
 
Attn           :  Bapak Yusly Lubis  
Subject          : Deep Well Construction      
 

We would  like to inform you that currently we had  been re‐drilling Deep well No‐1 up to  38.5 meter, 


however we found water loose zone at depth 30M and caused very hard to continue since not enough 
water. Additionally deepwell No‐2 that we already drilling up to 35 meter last May also found water loose 
and difficult ground zone which cause drilling had been stopped. As well as at proposed deep well no‐3 
also no water resources/supply. 

Due to all above as well as difficulties of cash flow, here with we inform you that we can’t continue to 
resume the work (3 Deep well constructions)  and we will demobilize the drilling machine within this week. 
Our drilling crew Bapak Ayub will be organized. Please help and support him. 

Again we are very sorry for this condition and thank you very much for your kind support and cooperation. 

Thank and Regards 

 
Ikomang Suandra 
Director  

  