Odorkor, St. Anthony, Djaman Township, Oblogo, Salaga Market, CMB Flats,
3 GROUP C Mamprobi, Soko, Taifa, Ofankor, Asofa, Alhaji, Tabora, Chantan, Israel, Fadama,
North Kaneshie, Joma, NIC Top, Seminary, Sowutuom Last Stop, Ablekuma Curve,
Russia, Sukura, Kokrobite, Bortianor, Osofo Dadzie, Datus
SCHEDULE
10th May, 11th May, 12th May, 13th May, 14th May, 15th May, 16th May, 17th May,
2021 2021 2021 2021 2021 2021 2021 2021
DAY
A C B D A C B C
(6.00am – 6.00pm)
NIGHT
B D A C B D A D
(6.00pm – 6.00am)
Other needed interruptions in power supply to enable contractors complete the different intervention projects, will be
communicated in due course.
While calling on customers to bear the inconvenience with us, we pledge our commitment to complete the projects on
time.