Our Project Plan


Shown as a Gantt Box Chart
31-May 14-Jun 28-Jun 12-Jul 26-Jul 9-Aug 23-Aug 6-Sep

Project Kickoff

Gather Requirements

Design Module 1

Design Module 2

Develop

Test

Implement

Task Start Best Case Realistic Worst Case BC


Project Kickoff 1-Jun-10 5-Jun-10 9-Jun-10 14-Jun-10 4
Gather Requirements 6-Jun-10 13-Jun-10 18-Jun-10 23-Jun-10 7
Design Module 1 11-Jun-10 17-Jun-10 20-Jun-10 27-Jun-10 6
Design Module 2 11-Jun-10 16-Jun-10 19-Jun-10 26-Jun-10 5
Develop 20-Jun-10 29-Jun-10 15-Jul-10 22-Jul-10 9
Test 21-Jul-10 27-Jul-10 29-Jul-10 5-Aug-10 6
Implement 8-Aug-10 14-Aug-10 16-Aug-10 23-Aug-10 6
Chandoo.org

How to use this?

1) Set up your project plan using the


table in row 6
2) Just enter first 5 columns of dates
9-Aug 23-Aug 6-Sep 3) Last 3 columns are calculated. Do not
mess with them.
4) If you have Excel 2007 or above, the
calculated columns should
automatically update when you add
new rows to the table.
6) The chart now shows the project
plan as a Gantt Box Chart
7) Adjust horizontal / date axis scaling
and major units to see dates clearly.

For more info. visit:

http://chandoo.org/wp/2010/07/09/ga
ntt-box-chart-proposal/