REACH -3 AMBAZARI -

DHARAMPET STATION - BOX GIRDER -01


DATE OF COMMENCEMENT: 18.01.2021 PROGRESS AS ON 1
SL.NO ACTIVITIES WEIGHTAGE GIVEN % OF PROGRESS
1 Shop drawing 3% 50%
2 Material procurement 10% 50%
a) Steel plates
b) Fastners/studs/bolts
c) Paints
3 Cutting and budding/fitment 10% 50%
4 Welding 30% 50%
a)First stage
b)Second/final stage
c)Inspection
5 Inspection and testing of weldings 5% 50%
6 Trail fitment 5% 50%
7 Sand blasting 2% 50%
8 Painting 8% 50%
9 Transportation/ dispatch 10% 50%
10 Erection of girder 12% 50%
28 Miscellaneous Work & Handing Over 5% 50%
TOTAL 100% 50.00
OVERALL PROGRESS (in %age) up to 19.01.2021
AMBAZARI - FOB

STATION - BOX GIRDER -01


PROGRESS AS ON 19.01.2021
REMARKS
REACH -3 AMBAZARI -

DHARAMPET STATION - BOX GIRDER -02


DATE OF COMMENCEMENT: 18.01.2021 PROGRESS AS ON 1
SL.NO ACTIVITIES WEIGHTAGE GIVEN % OF PROGRESS
1 Shop drawing 3% 50%
2 Material procurement 10% 50%
a) Steel plates
b) Fastners/studs/bolts
c) Paints
3 Cutting and budding/fitment 10% 50%
4 Welding 30% 50%
a)First stage
b)Second/final stage
c)Inspection
5 Inspection and testing of weldings 5% 50%
6 Trail fitment 5% 50%
7 Sand blasting 2% 50%
8 Painting 8% 50%
9 Transportation/ dispatch 10% 50%
10 Erection of girder 12% 50%
28 Miscellaneous Work & Handing Over 5% 50%
TOTAL 100% 50.00
OVERALL PROGRESS (in %age) up to 19.01.2021
AMBAZARI - FOB

STATION - BOX GIRDER -02


PROGRESS AS ON 19.01.2021
REMARKS