Professional Documents
Culture Documents
Project Advisor
Dr. Nader Bagheri
Team Members:
Elliot Ballard
Erin Bloom
Marco Levario
Jose (Mario) Rodriquez
Eric Sprecher
i
Abstract
This engine heat balance laboratory will make a lasting impact on the school campus and increase the
learning opportunities for both Mechanical Engineering (ME) and Engineering Technology (ET)
departments. Our Primary objective is to develop a lab that will demonstrate the thermodynamic
principles of engines. Students will be able to turn on the unit, run the engine with different fuels at
varying loads, and take data in order to conduct their own thermal balance calculations. The demonstrator
will be safe, practical, inexpensive, and have a lifespan of at least five years.
To accomplish this goal, it became our imperative to couple a 3-cylinder Kubota D902-ET03 diesel engine
to a Mecc-Alte AC03 120/240 Volt generator, implement existing instrumentation from a previous
generator project, display all the necessary engine temperatures to perform a thermal balance, provide
laboratory procedures, and provide a means of engine control for the operator/student.
Much effort was put forth by the team to create the laboratory, several key components were not
completed. The servo control for the engine was unable to operate, and how power was dissipated to the
Merlin Simplex resistor bank was not completed in time. It can be seen that our efforts, with the help of
various professors, a viable engine test bed will be created, and benefit the cadets of the California State
ii
Assembled Lab Setup
iii
iv
Contents
Abstract ......................................................................................................................................................... ii
Introduction .................................................................................................................................................. 1
Pairwise Comparison............................................................................................................................. 9
Identify Constraints................................................................................................................................. 15
v
Portable Generator Set ....................................................................................................................... 21
Instrumentation ...................................................................................................................................... 40
Thermocouples: .................................................................................................................................. 40
Rotameters.......................................................................................................................................... 45
Fuel ...................................................................................................................................................... 47
Electrical .............................................................................................................................................. 49
Paneling............................................................................................................................................... 50
vi
Fabrication .......................................................................................................................................... 54
Summary ..................................................................................................................................................... 60
Conclusion ................................................................................................................................................... 61
Recommendations ...................................................................................................................................... 62
Project Summary..................................................................................................................................... 90
Background ............................................................................................................................................. 91
vii
Gannt Chart ............................................................................................................................................. 99
viii
Table of Figures
Figure 4: Small Engine Test Bed and Data Display for Small Engine Test Bed .............................................. 3
Figure 5: Entire Schedule from Project Selection to Delivery of Final Hardware ......................................... 4
ix
Figure 24: Engine Mounted......................................................................................................................... 38
Figure 28: Calibration of Temperature Display with Power Supply and Voltage Divider ........................... 43
Figure 29: Drilled and Tapped Thermocouple Fitting for Heat Exchanger Cooling Water ......................... 44
x
Figure 48: Advisor Sheet March 3rd ........................................................................................................... 86
xi
List of Tables
xii
Introduction
The Engineering Departments (Mechanical Engineering (ME) and Engineering Technology (ET)) need a
practical thermodynamics laboratory to supplement the theoretical knowledge taught in the curriculum.
Currently, no lab specifically addresses a thermodynamic heat balance. The Power Lab has amazing
potential but is severely underused. Current updates include the new diesel simulator and the wind tunnel
for the senior design project group competing in the Department of Energy Collegiate Wind Power
Competition. Though these new additions to the Power Lab are a start to modernizing the educational
opportunities of the Power Lab, much of the lab continues to feel like a museum of interesting engineering
In order to achieve the stated goals, it was proposed to use a Kubota D902-E203 engine from the Training
Ship Golden Bear and purchase a Mecc-Alte AC03 50/60 Hz generator set that will pair with it. The
generator will provide electrical power to Simplex Merlin 200 resistive load that exists within the power
lab location on campus. A frame made out of steel was welded out of material purchased from Alco Steel,
and from material found in the machine shop at CMA. A concentric tube heat exchanger made of copper
was designed in order obtain the mass flow rate of the exhaust gasses. K-type thermocouples were used
from an existing project to obtain various temperatures from engine components. These signals were
then sent to a channel box that is calibrated to display the correct temperature. It was decided that it was
simpler to use analog data acquisition with the channel box and physical flow meters instead of using a
LabView program. A simple control panel was also designed with a key ignition to allow the user to control
the heat exchanger pump, starter circuit of the engine, the thermocouple channel box, the fuel system,
With this test bed, the student will be able to analyze the operation of the engine at different loads.
Specific data will be displayed to the operators in order for them to conduct their own energy balance
1
calculations. With the knowledge of the design team, advisement from faculty, and sponsorship from
companies this lab will provide much needed practical application to the ME and ET departments.
The idea for this project was sparked by an existing senior design project completed back in 2004. The old
design project focused on coupling the 3126B Caterpillar Marine Diesel Engine to a 60Hz, 440V Baylor
generator. The power generated was sent to a resistor bank to be dissipated, and all the pertinent
thermodynamic information was displayed. A picture of this existing setup is shown in the following figure.
This engine generator setup is currently in the Power Lab and not being used. It has been out of use
because the generator is not sized properly to the engine and is unable to be loaded up in order to perform
There is also an existing small engine test bed (Figure 2) in the Fluid Mechanics Lab that was used at one
point during the school’s history. The dates of operation are unknown.
2
Figure 4: Small Engine Test Bed and Data Display for Small Engine Test Bed
This smaller engine is rated for 2.5 – 7.5 kW at 5,000 rpm. There is an instrumentation panel that
accompanies the test bed and displays data for a thermal balance analysis. This data display is shown in
The engine instrumentation panel displays operating instructions, RPM, torque (Nm), exhaust
temperature, and a fluid flow meter. Our finalized data display for our project will be modeled after the
During the first couple weeks of the Spring semester, Randy Thomas pointed us in the direction of several
engines that could potentially be donated to us from the ET department. Elliot Ballard then attended a
faculty meeting in which it was made known that there was a Kubota engine that could be used for our
design. It was a crucial moment in our project to decide on whether to obtain the engine and start building
a test bed from scratch, or to hold out and continue looking for a construction generator to be donated.
We had been looking for months, and we felt impelled to follow through with where the momentum was
taking us. We received the Kubota engine on January 15th and the rest is history.
3
With proper instrumentation and data acquisition the engine can be analyzed through all loading
conditions. The lab must also be aesthetically pleasing and display the data well enough to be easily
recorded by students. Once data is obtained, the student will complete the lab by calculating engine
efficiencies and the amount of waste heat able to be recovered. This project will provide us the
opportunity to create something that modernizes the Power Lab and benefits future students.
Project Schedule
A Gantt chart is used to show a schedule of all the tasks and when they should be performed. Certain
tasks require others to finish before they can start, and the time for each task was determined using
conservative estimates. The schedule is very fast paced, and will be challenging to complete before the
4
Problem Definition Phase
The lab has been designed to benefit future students in the engineering programs at CSU Maritime
Academy. Our main customers were identified as the students, faculty of both the ME and ET
departments, and the personnel associated with taking care of the facilities. An important goal of our
project was ensuring that it would be used for the next five years. A well-made list of objectives must be
A detailed list of objectives, constraints, and functions was made during a serious brainstorming session.
The needs of the students, faculty, and others who will come in contact with the project were considered.
1. Thermodynamics Lab
5
a. Heat in
i. Mass flow of fuel
ii. Heating value for fuel
b. Work out
i. Break horsepower
1. Voltage
2. Current
3. Generator Efficiency
ii. Parasitic Loads
c. Heat out
i. Charge Air
1. Temperature
2. Flow
ii. Exhaust
1. Temperature
2. Flow
iii. Cooling
1. Lubrication oil
a. Flow
b. Inlet temperature of cooler
c. Outlet Temperature of cooler
2. Jacket water
a. Flow
b. Inlet temperature of cooler
c. Outlet temperature of cooler
iii. Compatible w/Multiple Fuel Types
iv. Display
b. Longevity
i. Minimum 5 year Life
ii. Easy to Operate
iii. Safe
iv. Low Maintenance
v. It will be used
c. Cost
i. Minimal/Effective
ii. Low Maintenance
iii. Receiving Funding
1. Donations
2. Funds from Engineering Depts.
3. Cal Maritime Fund
iv. Marketing Strategies
1. Make a team pamphlet
2. Talk with potential donors
d. Manageable size
i. Dimensions less than 6ft x 6ft x 6ft
ii. Power between 20-50 kW
6
The previous list is then taken and pruned explicitly for objectives. This guides the design by leaving only
the necessary requirements. The pruned objective list is shown in the following table.
The objectives from the objective list are then used to create the objective tree. The objectives are placed
into a hierarchal structure and are used to better understand their relationship to one another. The
7
Figure 6: Objective Tree
8
The major design requirements, the main branches of the tree, are shown in the following table.
Pairwise Comparison
Each objective in the tree is organized in relation to its parent objective, but that does not readily display
the importance of each objective. A pairwise comparison is used to find a weighting number. Only
objectives within the same tier and the same parent will be compared.
A comparison table was made for each set of objectives that were being compared. The group voted on
which objective was more important and the winner was assigned a value of “1” while the loser received
a “0”. The results of each comparison were added up. An addition of one point to each sum prevents any
individual objective from receiving a score of zero. The tables can be seen below.
9
Table 3: Pairwise comparison
10
Weighted Objective Tree
The results of the pairwise comparison can be seen in the weighted objective tree in the following Table
3. Demonstrating thermodynamics principles was determined to be the most important objective, with
safety at a close second. The rest of the objectives are ranked in a color scheme with red being of high
11
Figure 7: Weighted Objective Tree
12
Work Breakdown Structure (WBS)
Now that the objectives have been weighted a schedule can be created that will be used to plan a timeline
of events in order to complete the project. It is now necessary to construct a work breakdown structure.
Tasks were further broken down and placed in order of logical completion. A full WBS is shown in
Figure 7.
13
Figure 9: Work Breakdown Structure
14
Identify Constraints
Identifying constraints was done in the same manner as identifying objectives. Information was gathered
on the physical limitations of the power lab, federal emission regulations, and the group’s personal
experience working with engines. A list of these constraints is shown below in Figure 8.
There are definite requirements to be met with the Environmental Protection Agency (EPA), building and
fire codes, and the California Air Resources Board (CARB). The size of the demonstrator cannot be too
large or bulky as it will have to fit in the power lab. Student safety is of a paramount importance, and will
15
Identify Functions
In order to realize our design objectives, it is necessary to identify the functions that our design must
accomplish. There are many functions that have to do with the actual operation of the engine and
generator. Those that pertain to the Lab demonstrator itself are in bold. An entire list of functions is
shown below.
16
● Lube Oil Outlet from Heat Exchanger
● Jacket Water Inlet to Heat Exchanger
● Jacket Water Outlet from Heat Exchanger
▪ Voltage from Generator
▪ Current from Generator
▪ Analyze Exhaust Gases
o Interpret Electrical Signals (Computer)
Box diagrams show the relationships between each function and their desired outputs. A black box
diagram is created to strictly show what are the inputs and outputs of the design. This is shown in Figure
9.
After the black box diagram is completed, a clear box diagram is created showing the distinct paths in
order to obtain each output. Figure 10 shows the flow of material (in blue) and signal information (in red).
17
Figure 12: Functional Block Diagram
It is necessary to have many sensors in order to calculate a thermal balance of the engine. It is anticipated
that the sensors which will measure flow, temperature, electrical load, and exhaust gas composition will
be needed to achieve the goals of this project. The data acquisition (DAQ) device will take in upwards of
12 inputs and output voltage signals to a computer. The black box diagram does not show how the
computer will take in the sensor information and conduct calculations before displaying the data. A main
artery of the project is deciding on what kind of instrumentation to use, how the DAQ will be set up, and
how the information is displayed. The rest of the block diagram is determined by which type of generator
18
Quality Function Deployment (QFD)
Measurable design parameters must be set in place in order to know if an objective has been
accomplished. These metrics should be quantifiable and be set on educated target values. A quality
function deployment is used to establish these values. Customer requirements are determined and
identified in the left hand column. Each of the requirements must have an associated metric in order to
drive the design team’s focus as the project matures. Listed in the horizontal direction are engineering
characteristics that can be used to measure the relative success of each requirements. Cumulative scores
for each metric are tallied by factoring in results from the weighted objected tree. Results of the QFD are
19
Table 4: Quality Function Deployment (QFD)
20
Conceptual Design Phase
Our initial interest in the project was spurred by the old design project, so it made sense to use that for
the new lab demonstration. Keir Moorhead, a graduate from of the CSUMA Mechanical Engineering
program and ET professor, worked on this generator set for his senior design project. He also has immense
knowledge in the realm of control systems and automation, and has provided helpful guidance in how to
accomplish this project. The old CAT generator set was a good choice because it would not require
spending time acquiring equipment. The facilities in the Power Lab were already in place for its use, and
instrumentation was already installed on the engine. The existing instrumentation may or may not be
There were several downsides to using the existing setup that were highlighted by Mr. Moorhead. It is not
known when the engine was last operated, and it will not pass current air pollution standards. The engine
is coupled to a generator that is too small to properly load up the engine. Essentially, the generator would
be maxed out while the engine was only operating at 20% load. The exhaust is not vented out of the
Mr. Moorhead recommended that we attempt to find a construction generator that was already coupled
to a motor, easily moved, and might have a higher chance of being donated. This design choice became
There are many generator rental agencies that might have a set with high hours, and does not make sense
for them to have in their fleet. These sets are ideal because the engine is already sized for the generator,
21
and has the controls to provide constant power. They are also a good size (10KW – 50KW) for heat
The problem with this option is that instrumentation would have to be installed that can provide sufficient
information for a full heat balance to be accomplished. This instrumentation will cost a good amount of
money, and if a generator unit is not donated, then budgeting will become a serious problem.
Finding a construction generator set became the team’s top priority, and several approaches have been
attempted. A marketing pamphlet comprised of the team’s picture, a summary of the project, and contact
information was disseminated amongst several generator rental companies in Benicia, CA. A few vendors
expressed interest, such as Hertz and Aggreko, but nothing has materialized since the first meeting. An
older gentleman with warehouses full of old automobiles, and naval artifacts was willing to donate an old
8KW Volvo generator. The generator looked like it needed work, and it was determined that the team was
not desperate enough to accept the offer. This might change as spring semester starts and there is still no
generator in sight.
22
Gas Turbine
There is currently a gas turbine that is installed and already used in power generation labs. This would be
a good option because it is an existing installation, and is in operating condition. No effort has been made
towards determining if the turbine is a viable option for the project. A picture of the installation is shown
below.
23
Purchasing an Engine for the Existing 150 KW Generator
Buying an engine that will better match the generator is one of the final options to consider. An engine is
cheaper to purchase than a generator yet existing equipment will still be used. The issues with this option
is that the engine will have to be coupled to the generator, engine controls and instrumentation will have
to be fully installed, and the money to support such a purchase may not be in the budget. An engine
mount will also have to be designed to support the installation. The group has spoken to Mr. Strange
about possible funding sources, and Mr. Moorhead has mentioned that he would donate a Mercedes
engine to the cause. This option was determined to be the most difficult to implement, and was not
explored further.
As was stated, this project is a re-development project based upon a past senior project which was, for
the most part, a thoroughly designed project. The Caterpillar Gen-set project included an advanced data
acquisition system and significantly more robust components when compared to the Kubota diesel gen-
set – the current project. However, the setback to the former project was that a 450HP engine was
coupled to a 201HP generator. They ended up with an engine thermal balance lab that could not develop
enough heat off of the engine. Of course, due to this extreme over-powering of the generator from the
engine – the engine could not be sufficiently loaded in order to effectively map the heat flux. That was a
primary goal for the current project. The power transmission system for this project had to be properly
matched.
24
Kubota Diesel Engine
Mechanical Load: Mecc-Alte ACO3 Generator, 15kW (rated power) / 18kW (Peak power)
25
General Specifications:
Number of Cylinders: 3
26
Incorporation into Project Design:
The Kubota D902-ET03 diesel engine was donated to the engine thermal balance project by the California
Purchasing a similar engine would have issued the cost of roughly $3,000-$4,000 (Based upon current
The engine provided an initial design basis to work from as well as a cost-effective means of conducting
the project. In addition to the donated D902 engine, the engineering technology department provided 3
other engines to explore and salvage from. These engines included the Kubota ZB600-C, the Z400-B, and
It was initially assumed that the engines were all in working order. In later discussions with the
Engineering Department, it was determined that these engines were deemed “Out of Commision” and
were therefore rendered unusable as options for prime-movers. With the elimination of the said engines
as viable options, another option was introduced – the D902 diesel engine.
The California Maritime Academy’s engineering department had a number of Kubota diesel engines which
were donated for the use of education while underway on cruise. Though most of these engines were
severely out of working order – one engine was set aside. This was the engine that was donated to the
cause of the project. The engine was in top working condition and showed no signs of educational
tampering.
The ZB600, Z400, and S2800 still played a very important role in the engine thermal balance project as
they included radiators, cooling hoses, electrical harnesses, key-switches, and many other associated
components. That being said, the three said diesel engines provided extremely economic means of
acquiring necessary engine components – so long as they were compatible with the D902. For the most
27
Kubota Mini-Series Stub Shaft Assembly
The Kubota Mini Series Stub Shaft Assembly was donated by the Hayes Manufacturing Company out of
Neenah, Wisconsin. This system component was priced at $641.00, however, through its donation, the
product only had project cost of $29.99 for shipping and handling.
This component was selected after many hours of research and consulting with various companies. Other
design alternatives included flexible lock jaw type couplings, flexible flywheel flange type couplings, spring
and rubber assembly couplings, universal joint type couplings, bent space-frame type couplings, and
28
The stub shaft assembly falls under the category of a tapered stub coupling – very similar to the tapered
connections used on a precision mill. The tapering feature of the coupling provided the most viable
characteristic for the coupling: no mechanical misalignment, as long as the torque specifications were
met.
This was not the only reason why this coupling was chosen for the design. It was also chosen on the basis
of mating with a specific generator – a generator with a SAE J609a B-type flange. Coincidently, a generator
was found which would effectively serve the purpose of completely loading the Kubota D902 diesel engine
throughout its operating range. Further details on this generator has been provided in the generator
General Specifications:
29
Power Output: 15kW (Rated) / 18kw (Peak)
Voltage: 120/240VAC
Pole: 2-Pole
Phase: 1φ
The Mecc-Alte ACO3 generator was chosen due to its availability in a J609a B-type mating feature and
As was stated, if a generator was found which enabled a J609a B-type mating feature it would introduce
an avenue which incorporated no mechanical misalignment (This was because of the tapered stub shaft
coupling). Having the ability to coupling a generator which included no mechanical misaligned with the
generator would not only simplify the project at hand but it would ensure further longevity into the
project – a project which is intended to leave a lasting legacy in the engineering curriculum at the
An addition reason why this generator was chosen was because of its economic viability. The generator
was found on EBay; it was originally priced at $1000.00 but was on sale at price of $600.00 with free
That being said, the combination which was found had a significant impact on the project. As was stated,
it greatly simplified the project mechanically, it reduced the overall cost of the project – enabling an
overall price of $630.00 ($600.00 for the generator and $29.99 for the shipping and handling of the
30
generator drive). If expedited measures were not taken, or if timing was not in the project group’s favor,
these components would have issued a gross cost of $1671.00 ($1000.00 for the generator, $641.00 for
Without a doubt, these two components of the power transmission system proved to be the most difficult
aspects for the project’s mechanical buildup and acquisition stage. It started with many attempts at
finding a coupling which incorporated a 15/16” 6-Splined connection; this would enable direct coupling
to the engine as it was given. The following picture depicts the 6-Splined connecting which was bolted to
It was found that any coupling which incorporated a 15/16” 6-Splined connection could not be
affixed to a generator which was compatible with D902. As was stated, various coupling types were
explored, however none were readily available which could enable a drive train meeting the project’s
design requirements. This dilemma is what lead to the final solution of the project’s final drive train
mechanism.
31
Engine Test Bed and Frame
The initial thought process and inspiration for the test bed came from the Caterpillar Gen Set. Since our
project budget was limited, we originally set out a plan to salvage as much material from the existing
frame in order to incorporate it into our design. The benefits of this option were to minimize the
fabrication time by simply cutting sections down to fit the dimensional requirements of our engine and
generator. The Figure below illustrates an early rendering of the modification that would have been a
viable option. Not only would this option minimize cost and fab time, the design had incorporated
isolation mounts to mitigate the vibration inherent with any running engine.
After exploring this option with the Engineering Technology department, we were unable to pursue this
plan due to the logistics of storing and transporting the original gen set following disassembly for
material salvaging. Consequently, we began exploring a complete redesign of the test bed that would
32
attempt to build upon the success of the original design while incorporating feedback from the ET
department.
One of the ideas that was brought to attention while speaking with the ET department was to
incorporate mobility into the design of the project. Understandably so, the original project did not
consider this due to the shear mass of the equipment. Our project differed from the original due to the
ultimate selection of equipment that was significantly smaller and more accommodating to mobility To
do so, we sought to minimize the weight of the overall structure without compromising the structural
integrity. We chose 3/16th in angle steel to form the base structure composed of stanchions and upper
and lower rectangular rings. This particular cut was selected due to the availability of material, stability
under heavy loads, and cost. Unlike the square tubing used for the existing gen set on campus, angle
steel would significantly reduce the weight of the structure. A conceptual design with is presented
below in the following figure. The model was analyzed given the weight of the selected Kubota Engine
33
Figure 20: Structural Analysis of the Frame
The results above predict a more than sufficient structural design for supporting the most significant
components. In addition, the total weight based on the solid model and referenced material properties
is approximately 180lbs. Altogether, the frame and gen set was predicted to weigh approximately
450lbs. This estimate does not include the weight of additional structural supports and subsystems but
represents the most significant contributor to the overall weight. This estimate was used to select a set
of casters that were to provide the mobility goal. The casters selected were acquired on campus from
Randy Thomas. The exact specification on the casters is unknown, but based on similar models and sizes
found online the capacity of each one should easily exceed 500lbs. Once the engine and generator were
mounted, the caster selection proved to be successful by the relative ease in rolling the gen set around
34
There was plenty of material at our disposal in the machine shop so it was decided to build the frame out
of steel, and weld most of the connections instead of using hardware. Welding provides a very strong
bond, prevents noise when vibrating, and is a good skill to learn. All those who partook in building the
frame learned quite a bit about the welding process and how to prevent heat warpage of metal parts. The
engine test bed started with a simple CREO design shown in the following figure.
This preliminary design allowed us to make estimates on how much material would be needed to
accomplish the build. Appendix A shows several other angles of the test bed, and Appendix B shows the
This first iteration of the test bed only contains the engine, generator, gas tank, and battery. It does not
contain information on the heat exchanger system, control panel, electrical breaker box, and fuel system.
This as a good base to go off of, and it was decided to go ahead with construction, and then accommodate
our design to the framework of the frame. An initial stage of the frame construction procedure is shown
35
Figure 22: Engine Test Bed Takes Shape
A level was used to make sure that the legs were as straight as possible in order to transmit weight
effectively. At this point in the project it was unknown how much weight was going to be placed on the
skid, so thicker metal and an increased amount of welds were necessary. Mario, a.k.a. the fabricator,
stands over the completed basic frame on casters. It was at this point that work could be done on
36
Figure 23: El Fabricante with Basic Engine Skid
37
Mounting of the Kubota Engine
The next step in the test bed process was to mount the engine, and then adjust the generator mounting
as needed for the coupling procedure. Vibration became a concern for us and it became our prerogative
to mount the engine on rubber shock mounts. Four arms were manufactured out of square steel tubing,
welded, and affixed to the frame via these shock mounts. The engine with the mounting arms can be seen
38
Mecc-Alte Generator Mounting
Being able to adjust the generator as much as possible was desired in order to accomplish the coupling
procedure. The initial design called for using solid rectangular plate, but that did not provide the rigidity
that was required. Channel-type steel beams were used because of their increased stiffness properties.
These beams were tacked into place, and drilled with the mounting pattern on the underside of the
generator. Height adjustment was brought about through using stock all thread, washers and bolts. Each
support leg could then be adjusted in order to get the right level. The following figure shows the generator
in the air with chain falls, and the adjustable mountings on the frame.
The Hayes tapered cone generator end, too much of the quess-work out of the shaft alignment, as the
gen-set would be rigidly mounted to the power end of the engine. The finished coupling process can be
39
Figure 26: Completed Coupling Process
It was at this point that other mission critical aspects of the project could be mounted.
Instrumentation
Thermocouples:
All of the thermocouples used were pulled off the of the Caterpillar engine. Based on the wire colours of
red and yellow, it was determined that all the thermocouples were K type. A standard K type
thermocouple table was used to verify that all thermocouples output a voltage in the range of what was
expected at known temperatures. The initial test was in ice water and boiling water because the
temperature of those two states is fixed and known. This setup can be seen below in the figure.
40
Figure 27: Thermocouple Operational Check
It was determined that all thermocouples did output a voltage that corresponded to the table, but all had
an offset. This offset was determined to be from the copper connection to the thermocouple leads. This
second connection of dissimilar metals created another thermocouple that induced a voltage offset.
Data Acquisition
The next step was to figure out how to convert the thermocouple output voltage to a relevant
temperature reading. A DAQ was first considered because of prior experience, but with that DAQ, we
would need a computer to run LabView. The only available computer to do this was in the power lab and
would need to be shared with the wind turbine group. This was determined not to be a good solution
because on presentation day the computer would have to be shared between the two groups. This would
cause time delays and would lead to potential technical difficulties. It was then determined that a direct
conversion box that would read the thermocouple output and display a temperature would be the best
41
option. This would keep the Lab completely self-contained and be much less complicated having an
analog readout verses a large set of data. The heat exchanger lab that is currently used, is set up the same
way with an analog readout that the user writes down. The idea was that the experiment was to be run
at a steady state. Therefore, the temperatures being recorded would be relatively constant.
With the decision made to use an analog display of temperatures the next step was to source and
purchase a device that would be useful for the lab. The initial search was for a digital thermocouple
temperature display and a selection knob. Upon further research an Omega Instrumentation product was
found that would display the temperature that the thermocouples were reading and had a built in selector
switch for ten thermocouples. This product is the Omega DP460-T digital thermometer for thermocouples
and resistive temperature devices (RTD). Buying a new DP460-T at $280+ was not in our budget, and after
some searching, a used DP460-T digital thermometer was found being sold as lab equipment surplus from
a terminated experiment for $50. More research was done to make sure that this product is what we
needed and could be used. The manual was located online that included instructions on how to configure
the DP460-T setup to read thermocouples ranging from K to E type, RTDs, and calibration of the
temperature display. It was determined that we would be able to configure this product to our needs and
Upon arrival the DP460-T was tested with the K type thermocouples on all ten channels. It was
determined that all channels were functioning and could be used in our experiment. Upon a closer look,
the factory plate was labeled for reading T type thermocouples. The front panel was taken off, and sure
enough the selector was set to “T” meaning that it would display a temperature that corresponded to the
voltage output of a T type thermocouple. The selector was simply switched to K. It was also noted that a
jumper wire inside the housing of the instrumentation was a piece of T type thermocouple wire. The wire
was replaced with a piece of K type thermocouple wire. The calibration was of the DP460-T was then
42
In order to calibrate the DP460-T a 39.000 mVDC power source was needed. There was no power source
on campus that could output such a small voltage that precisely. With a little help from Randy Thomas
and digging back to the days of circuits class, it was determined that a voltage divider could be used to
obtain a 39.000 mVDC output. By using the simple Equation below an input voltage that could be
generated with a power supply was calculated and used to generate the required voltage.
𝑅𝑅1
𝑉𝑉𝑜𝑜𝑜𝑜𝑜𝑜 = 𝑉𝑉𝑖𝑖𝑖𝑖
𝑅𝑅𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇
Vin is the voltage from the power supply, R1 is the resistance over which the output leads are, RTotal is the
total resistance of the divider circuit, and Vout is the measured output voltage over R1. The Figure below
shows the DP460-T displaying the proper values as the multimeter is reading exactly 39.000 mVDC. Once
calibration was complete, the selector was turned to “K” for K type thermocouples.
Figure 28: Calibration of Temperature Display with Power Supply and Voltage Divider
43
Thermocouple Mounting
All of our thermocouples were taken off of an existing senior project located in the power lab. This added
a layer of difficulty to our project because all the thermocouples varied in length, diameter, and thread
type. Making these work for our installation proved to be a more difficult process than originally
envisioned. Thermocouples need to have proper immersion within the process fluid in order to send an
accurate reading. Thermocouples need to be sufficiently far enough away from the wall of a pipe to avoid
the no-slip condition some literature state that probe should reach ⅓ to ½ of the diameter of the pipe, or
Our plan called for making wet-well mounts where the thermocouple would physically sit within the
process fluid. This seemed like an easier option at the time, but would create more difficulties later on.
Different approaches were taken, and each had their respective problems. Separate fittings could be used
with the proper thread type, but would not provide the proper depth. Many fittings were made out of
plastic, but would not connect to two different hose sizes as we had coming out of the engine. It was
decided to drill and tap pipe fittings for each individual thermocouple. An example of a finished
Figure 29: Drilled and Tapped Thermocouple Fitting for Heat Exchanger Cooling Water
44
The drill and tap process is fairly simple, but requires some patience. Especially when you are unable to
find the proper drill sizes that you need to make a secure tap. These fittings looked promising, but it is
very hard to seal off leaks if the threads are not tight enough. The most troublesome fitting was the jacket
water coming out of the engine. The best way to go about mounting the thermocouples would be to
purchase dry-well mounts where the probe is not in physical contact with the medium being measured.
During the first test run of the engine with all the thermocouples in place to take measurements none of
the displayed temperatures were responding in a way that we expected. Negative numbers were being
displayed, and some channels were not changing at all, or very little. This did not draw much concern
because it was obvious to me that there must be a lead connected backwards, and I would have to figure
out which one it was. The first thing checked was to make sure all the thermocouples were connected
properly with positive leads to positive connections. This was critical because a person conventionally
thinks of the red lead as the positive, but in the case of thermocouple wire the red lead is negative. All
the thermocouples were connected properly, but there was only one other connection that could be
switched. The jumper of K type thermocouple wire needed to be connected to the connection board to
the processor box of the DP460-T. This wire was connected correctly to the processor box and an
assumption was made that the wire should be connected to the connection board in the same fashion. It
so happened that the connection board was opposite of the processor box. So, the negative lead was
connected to the positive connection, and vice versa for the positive lead. Upon making that switch the
display output correct temperatures and when thermocouples were heated the temperature rose.
Rotameters
Research was done to determine what type of instrumentation there was available to determine the flow
rate of fluids. With the initial notion of using a DAQ we were looking at turbine flow meters. Turbine flow
meters turned out to be very expensive though, and they did not span into the low flow rates that were
45
calculated to be used in the heat exchanger or the engine jacket water. When it was determined that a
DAQ would not be use, it made selection of a flow rate measuring device much easier. It was clear that a
rotameter would be ideal because the span and resolution can reach low flow rates fairly accurately. Also,
they would be easy to install, and easy to read during the experiment.
When it came to searching for the appropriate rotameters for the heat exchanger cooling water, and the
engine jacket water the heat exchanger had been designed to operate under a specific flow rate and
temperature. A rotameter with a 3.5 GPM maximum flow rate was chosen that was made of acrylic that
was rated for a maximum temperature of 130F. The rotameter for the engine jacket water was not as
easy to determine what was required because we had no idea what the radiator outlet temperature of
the water would be, and despite doing some research no conclusive estimate could be made. On top of
that, there was no way to know in what range of rate the pump on the engine would be moving the engine
jacket water. It was getting close to the build deadline and a chance was taken to order the same
rotameter as what was ordered for the heat exchanger. This would at least give us some way of measuring
the flow of the engine jacket water and gave us an idea of how much, or little, the flow was.
When it came to testing the engine, the heat exchanger rotameter worked perfectly. We were able to
throttle the flow of the cooling water and observe the measured flow increase and decrease based on
how much the valve was throttled. The rotameter for the engine jacket water on the other hand did not
move as much as we had anticipated. There was a 0.5 GPM flow measured while the engine was running
at full throttle, which is on the lower limits of the rotameter with poor resolution. Another rotameter was
46
Engine Auxiliary Systems
Fuel
In order to make calculations easier, we wanted to take measurements as a mass flow rate. Flow meters
were considered, but it was determined that they are not accurate enough to measure the small amounts
of fuel being consumed at any given time. From there on out it was determined that to keep with the
measurement of mass a scale would be used to measure the amount of fuel in a tank at the beginning
and at the end of the experiment. This idea was eventually scrapped after a lot of thought of how it would
be done with hoses hanging off of a container being weighed. From there we decided on the traditional
volume measurement with the use of a graduated cylinder. We thought this would be an easy and simple
solution. As it turned out, it was a little more involved than initially anticipated.
The first step was to figure out how much fuel we would need to run the experiment long enough for
students to collect all the temperatures and flow rate, and allow enough time for fuel consumption to be
significant enough for useable data. Based on a performance chart of the engine, the break specific fuel
consumption (BSFC) could possibly be as high as 270g/kw h. Based on the BSFC and knowing that the
maximum load we would put on the engine is 15 kw it was calculated that the engine could run on 379.2
ml of fuel for five minutes on maximum load, and 758.4 ml of fuel for ten minutes. The available clear
pipe that could be ordered started at one inch nominal in two foot increments and went up in size from
there. Calculations were done for the maximum amount of fuel each a one inch two foot long schedule
40 pipe could hold considering loss in length due to fittings, and a 1 ¼ inch two foot long schedule 40 pipe.
It was determined from these calculations that a two foot section of the one inch pipe could hold 300 ml
in a length of 21.183 pipe. Increments were calculated to determine how fine of a scale could be feasibly
achieved. Five ml increments were chosen based on the ease of reading the cylinder and process time to
47
score the cylinder. The cylinder was turned on the lathe and the precise dials were used to increment the
The fuel system design used is based off of the Alterdyne gas turbine in the Power lab and any other
common fuel system. The systems consists of a root valve, a drain and an experiment measuring section
that pulls fuel from the graduated cylinder. All fittings are brass hose fittings to negate corrosion and for
safe fuel handling. A drawing of the system is shown in the following figure.
48
Electrical
The electrical system which was designed to support the lab’s operations was based upon Kubota’s D902
specific electrical systems. The following picture depicts the ideal system which was designed to support
For the purposes of this lab, however, a full redesign of the system was required. In particular,
components which were eliminated included the Key-Stop timer relay, the fuel booster pump, the
alternator (with associated “Charge” lamp), the glow plug heating system (with associated “Glow” lamp,
and Timer relay). The redesigned system has been depicted below.
49
Figure 32: Implemented Electrical Diagram
Notice in the redesigned system that a 120VAC was included. This addition enabled the use of a
temperature display box; it enabled 3W indicator lamps to be utilized in coordination with DC relays; and
it enabled direct control of the lab’s heat exchanger exhaust-gas metering system.
Paneling
The main objective of the paneling was ease of use and functionality. We wanted to make sure that the
placement of valves, push buttons, lights, and temperature displays were in a logical place and order. We
first made a cardboard drawing of rough dimensions of how big the control panels would be and what
they would look like. This more or less ended up being how the control board looking. Some paneling
50
was scrounged up and used as a base where the key, start, stop, and indicator lights were mounted. The
fuel control valves were mounted on a vertical panel from right to left as the fuel was flowing to the
engine, and above the fuel valves is the DP460-T temperature display. The temperature display was
removed from its original housing, and mounted on to the panel. The thermocouples were connected to
the temperature display with logic, ease of use, and recording data in mind.
1. Exhaust temperature
The fuel cylinder was mounted on the right side of the vertical panel for ease of viewing and access. To
support the cylinder over the entirety of its length a piece of angle iron comparable in size was used for
the cylinder to be fastened to, and for the cylinder to be fastened to the panel.
After the first run of the engine with all the control panels and instrumentation connected it was obvious
that the vertical panel needed to be harmonically isolated. The vibrations made it difficult to read the
fuel cylinder and the temperature display. It also cause concern about damaging the temperature display.
To reduce the amount of vibration, rubber was inserted on the base of the panel where it was bolted
down to the frame of the engine. Also, another support was added to the frame that the control panels
were sitting on. This significantly reduced the amount the panel vibrated on the next test run.
51
Heat Exchanger
The idea for an exhaust heat exchanger came about for two reasons. First, there was no effective way to
measure the mass flow rate of the exhaust. Second, analysis of waste heat recovery would add another
element to the learning potential of the laboratory. Using knowledge learned from heat transfer and
fluid/thermal design, a method for calculating the mass flow rate of the exhaust was determined. The
measured parameters would be the volumetric flow rate of the cooling medium, the inlet and outlet
temperatures of the cooling medium, and the exhaust inlet and outlet temperatures. Using these with the
density and specific heats of the cooling medium and the exhaust allowed the mass flow rate of the
exhaust to be calculated. Below are the equations for the exhaust mass flow rate calculations:
The cooling medium mass flow rate can be determined by multiplying the cooling medium volumetric
flow rate by the density of the cooling medium. Waste heat recovery analysis can be performed on the
engine by calculating the heat extracted from the exhaust by the cooling medium.
̇ = 𝑚𝑚̇
𝑄𝑄̇𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝑛𝑛𝑛𝑛 ∗ 𝐶𝐶𝑃𝑃,𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 ∗ (𝑇𝑇𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶,𝑜𝑜𝑜𝑜𝑜𝑜 − 𝑇𝑇𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶,𝑖𝑖𝑖𝑖 )
Several choices were made for the heat exchanger. First, the type of heat exchanger was decided. The
options included concentric tube, shell and tube, and cross flow. Because of the simple design and minimal
pressure drop, a concentric tube type heat exchanger was chosen. Next, the cooling medium was chosen
to be water because it was readily accessible and has a high heat capacity. Then, the flow pattern was
chosen to be counter flow to increase the effectiveness. After that, two assumptions were made. The first
assumption was the exhaust temperature which was assumed to be 627 degrees Celsius. The second
52
assumption was the cooling water temperature which was assumed to be 20 degrees Celsius. Another
parameter that was chosen was the inner pipe inner diameter. To minimize fluctuations in the exhaust
flow, it was decided that the inner pipe inner diameter should be as close as possible to the exhaust
manifold inner diameter of 1.5 inches. This resulted in the use of 1.5 inch type M copper tubing. Type M
copper tubing was chosen because it has the smallest wall thickness which would allow for better heat
transfer. Copper tubing was chosen because of copper’s high thermal conductivity which also aids the
transfer of heat. The exhaust mass flow rate was estimated using the performance curves of the diesel
engine. At the rated power of 16.1 kW, the break specific fuel consumption was 265 g/kW h. This resulted
in a mass flow rate of 1.185 g/s. The mass flow rate of the fuel along with other combustion parameters
were calculated using a MATLAB program (Appendix D).With these values known, design iterations to
determine the length, annulus diameter, and cooling water mass flow rate were performed. A MATLAB
program was created that output exhaust and cooling water outlet temperatures, heat transferred, and
pressure drops for various heat exchanger lengths (Appendix E). The program used equations from
William Janna’s book Design of Fluid Thermal Systems. To prevent the formation of acids in the exhaust
gas, iterations resulting in exhaust gas outlet temperatures below 200 degrees Celsius were not
considered. Based on the iterations, an annulus diameter of 2 inches was chosen. This diameter provided
the smallest flow area for the water. This increased the velocity of the water which made it more turbulent
and better at transferring heat. A volumetric flow rate of 1.5 GPM was chosen for the cooling water. This
flow rate provided the longest dwell time in the heat exchanger while still providing turbulent water to
increase heat transfer. Finally, the length of the heat exchanger was determined. Based the other
parameters, a length of 1.5 meters was chosen. At this length, the heat exchanger would not be too
cumbersome and would provide outlet reasonable outlet temperatures. Below is a table of data for the
53
Table 5: Original Heat Exchanger Design Specification
Fabrication
After the theoretical analysis, benchmarking was performed on the current heat exchanger laboratory to
determine how the annulus and the inner tube were sealed. Though compression fittings were used on
the current laboratory, it was determined that brazing would be a more effective solution for this heat
exchanger. After this, a 3D model was made in Creo Parametric. Models for the fittings were obtained
from McMaster-Carr. Next, the parts were ordered; however, there was a problem. The fittings were
drinking water tube fittings while the tubing was multi-purpose copper tubing. Because of this, the two
did not connect. McMaster-Carr does not carry fittings for multi-purpose copper tubing, so the tubing was
shipped back. New drinking water tubing was ordered that connected with the fittings. To reduce the
amount of left over material, the length of the heat exchanger was compromised. McMaster-Carr sells
54
multi-purpose tubing in 1, 3, and 6 feet lengths and drinking water tubing in 2, 5, and 10 feet lengths. The
multi-purpose tubing worked well for a 1.5 meter heat exchanger because 6 feet lengths of tubing could
be purchased. The drinking water tubing would require 10 feet tube lengths to be purchased to achieve
the 1.5 meter length. Instead, 5 feet lengths were purchased and the heat exchanger length was
With the parts purchased, fabrication began. The tubing was originally attempted to be cut with tube
cutters. However, the tubing cutter’s blade was too wobbly and a good cut could not be made. Instead,
the tubing was cut using a band saw and sanded down. Once the lengths were correct, the connections
were prepared for brazing with sand paper. To braze the heat exchanger together, a rosebud heating
torch was used to supply enough heat to copper. Brazing works by heating the tubing to the filler metal’s
melting point. Once this has been reached, the filler metal is tapped against the joint. This causes the filler
metal to melt and capillary action draws it into the tubing joint. This was fairly simple with the rosebud
55
Figure 35: Heat exchanger leak test
tip with small parts. However, when large amounts of copper were being brazed, the copper conducted
much of the heat away from the joint which made it difficult to get the filler metal to melt and flow. After
the brazing was completed, a pressure test was performed. One leak was found on one of the fittings, so
56
the heat exchanger was dried and the one joint was brazed again. This fixed the leak and allowed the
After the heat exchanger was fabricated, the cooling water system needed to be built. A pump from the
materials laboratory was repurposed to pump water into the heat exchanger. Also, an old radiator was
used to dissipate the heat absorbed by the cooling water in the heat exchanger. Hoses and hose
connections were purchased at Home Depot and Lowes to connect the system parts. A rotameter and a
valve were purchased to control the flow through the heat exchanger. Exhaust ducting was purchased at
Pepboys to route the exhaust through the heat exchanger. After everything was obtained, the system was
lined up, insulation was wrapped, and the heat exchanger was mounted underneath the engine. With the
heat exchanger mounted and the system lined up, testing could be completed.
Model Testing
Testing the laboratory became an issue, as several key systems remained unfinished. The following are
Pre checks
57
Pre start
Starting
58
Experimentation
Shut Down
1. Burn all fuel left in the cylinder (refer to Experimentation number 7 and 9 for
instructions to do that)
2. When fuel is no longer visible in large amounts switch fuel sources back to
the tank
3. Press and hold the RED button until the engine stops firing
4. Remove the key
5. Close all fuel valves
6. Stop the heat exchanger cooling water pump
7. Disconnect battery
8. Turn off temperature display
9. Unplug the AC power strip
10. Open the generator breaker
59
Once data is collected then the students can either do their calculations by hand or create their own
computer program. The following figure shows an excel program that displays a thermal balance and
efficiencies.
Summary
The goal of our project was to couple a Kubota D902-ET03 to a Mecc-Alte AC03 generator end, design the
necessary support systems, and create a thermodynamics laboratory experience. We were able to
accomplish much with our time and have gotten very close to providing what we had originally promised.
A few of the components were not completed, but, with a few more iterations and testing, we could have
fixed the issues. It was just a little too late. We put in over 300 hours of work as a group over spring pause,
but there always seemed to be one more thing to work on. Other assignments started to pile up, and we
were unable to focus 100% of our effort on the “capstone” project. One of the issues was that certain
60
systems were overlooked, and left unfinished until the end. One of the components that needed more
work was the thermocouple data collection system. We experienced difficulty obtaining quality readings
due to vibration on the analog channel box. Vibration would cause the unit to become uncalibrated and
The thermocouples installation was another issue. How they were installed in their wells could vary
drastically from fitting to fitting, as It was difficult to measure how much exposure each individual
thermocouple was getting to their respective convective fluid flows. The drilled and tapped fittings ended
Since we were unable to get quality readings, a thorough thermal heat balance could not be completed.
This also means that the efficacy of the heat exchanger design could not be tested as it was installed.
Conclusion
This project ended up being much more involved than originally anticipated. The challenge only adds to
our satisfaction when certain milestones for the project were met. Getting all the major components
proved to be an endeavor that involved many hours of labor. We are very grateful to have had Randy
Thomas to provide us with many materials that we ended up using for our project. Our biggest purchase
ended up being the Mecc-Alte Generator, while the engine and coupling were donated. The engine and
generator run very well together, but we were unable to run the system under an electrical load.
The paneling for the electrical and fuel system turned out looking very good and professional. At this time
labeling of the valves and buttons still needs to be made, and the frame painted.
We would definitely look into purchasing dry wells for the thermocouple installation. There were too
many leaks to fix with the way that it was originally created. One of the better wet wells we had was
manufactured by Lawrence Northrop out of a solid piece of steel round stock. There was still the issue of
61
making sure that the thermocouples tap would not leak. More thought on how the instrumentation would
Attempting to use the Merlin Simplex resistive load bank was also delayed. It was known since the start
of the project that we were going to use the Merlin in the power lab, but no plans were put forth on how
power was going to get there. We started to think about this a little too late, and, as a result, were unable
Our biggest holdup for a satisfactory completion of this project was us waiting around to get a
construction generator donated. Getting one of those would have decreased the difficulty of the project
substantially, but we ended up building our own skid from the ground up. If we would have decided on
the harder course of action sooner we would have had enough time to run through all the kinks.
We hope that what we have built will be able to be improved upon by professors and faculty. We hope to
Recommendations
There is plenty of future work that can be done on this project. Different heat exchangers could be
designed, the use of different fuels can be incorporated, and there is the potential to build additional
systems for the test bed that we designed. Students could potentially design waste-heat recovery systems,
power other loads besides the simplex, and incorporate a turbocharger bypass system. Exhaust gas
A more robust instrumentation system is desired, and changing the thermocouple mountings to dry-wells
are a must.
62
Appendix A: Various Angles of First Iteration of the Test Bed
63
Appendix B: Bill of Materials for Test Bed
64
Appendix C: Heat Exchanger Program
clear all
close all
clc
%% Thermo Lab
%Waste Heat Recovery
%Heat Exchanger Design
%by Erin Bloom
%h = hot (Exhaust)
%c = cold (Water)
%p = inner pipe (Exhaust)
%a = annulus (Water)
%% Design Choices
%Inner Diameter Inner Pipe
%Seamless Type M Cu Tubing (1.5" nom)
IDp = 3.880/100; % m
%Length
L = [1.2192]; % m
65
T1_h = 627; % C
%Specific Heat
Cp_h = 1.2295; % kJ/kg K
%Prandtl Number
Pr_h = 0.696;
%% Water Properties
%Denisty
rho_c = 1000; % kg/m^3
%Thermal Conductivity
kf_c = 0.597/1000; % kW/m K
%Kinematic Viscosity
nu_c = 10.06e-7; % m^2/s
%Inlet Temperature
t1_c = 20; % C
%Specific Heat
Cp_c = 4.181; % kJ/kg K
%Prandtl Number
Pr_c = 7.02;
%% Flow Areas
%Inner Pipe Area
Ap = (pi*IDp^2)/4; % m^2
%Annulus Area
Aa = pi*(IDa^2-ODp^2)/4; % m^2
%% Flow Velocities
%Exhaust
Vp = mdot_h/(rho_h*Ap); % m/s
%Water
Va = mdot_c/(rho_c*Aa); % m/s
%% Reynolds Numbers
%Exhaust
Re_p = (Vp*IDp)/nu_h;
%Water
66
Re_a = (Va*De)/nu_c;
for ii = 1:1:length(L)
%% Nusselt Numbers
%Exhaust
if Re_p < 2200
%Laminar
Nu_p(ii) = 1.86*(IDp*Re_p*Pr_h/L(ii))^(1/3);
else
%Turbulent
Nu_p(ii) = 0.023*(Re_p^(4/5))*(Pr_h^0.3);
end
%Water
if Re_a < 2200
%Laminar
Nu_a(ii) = 1.86*(De*Re_a*Pr_c/L(ii))^(1/3);
else
%Turbulent
Nu_a(ii) = 0.023*(Re_a^(4/5))*(Pr_c^0.4);
end
%% Convection Coefficients
%Inner Pipe
h_i(ii) = Nu_p(ii)*kf_h/IDp; % kW/m^2 K
%Exhaust
h_p(ii) = h_i(ii)*IDp/ODp; % kW/m^2 K
%Water
h_a(ii) = Nu_a(ii)*kf_c/De; % kW/m^2 K
%% Exchanger Coefficient
%Ideal
Uo(ii) = h_p(ii)*h_a(ii)/(h_p(ii)+h_a(ii)); % kW/m^2 K
%With Fouling
Rdi = 0.002*1000; % m^2 K/kW
Rdo = 0.0004*1000; % m^2 K/kW
one_over_U(ii) = (1/Uo(ii))+Rdi+Rdo; % m^2 K/kW
U(ii) = 1/one_over_U(ii); % kW/m^2 K
67
%Log Mean Temperature Difference
LMTD(ii) = ((T1_h-t2_c(ii))-(T2_h(ii)-t1_c))/...
log(((T1_h-t2_c(ii))/(T2_h(ii)-t1_c))); % C
%% Heat Balance
%Exhaust heat tranfer
q_h(ii) = mdot_h*Cp_h*(T1_h-T2_h(ii)); % kW
%Water Heat Transfer
q_c(ii) = mdot_c*Cp_c*(t2_c(ii)-t1_c); % kW
%Overall Clean Heat Transfer
q(ii) = U(ii)*Ao(ii)*LMTD(ii); % kW
f_p = (-0.782*log(6.9/Re_p+(roughness/(3.7*IDp))^1.11))^-2;
f_a = (-0.782*log(6.9/Re_a_p+(roughness/(3.7*Dh))^1.11))^-2;
end
%% Results
68
Appendix D: Combustion Program
clear all
close all
clc
%Thermo Lab
%Combustion Program
%by Erin Bloom and Marco Levario
%% Inputs
% This section would have allowed the user to input values for a
% combination of two hydrocarbons and theoretical air. It is not used
% because the final project requires a range of theoretical air, not a
% single input.
%% Combustion Equation
N_O2_R = x.*(nHC+yHC./4);
N_N2_R = x.*(nHC+yHC./4).*3.76;
N_HC_R = 1;
N_CO2_P = nHC;
N_H2O_P = (yHC./2);
N_O2_P = (x-1).*(nHC+yHC./4);
N_N2_P = N_N2_R;
N_tot_R = N_O2_R+N_N2_R+N_HC_R;
N_tot_P = N_CO2_P+N_H2O_P+N_O2_P+N_N2_P;
69
%% Air Fuel Ratio
% This section calculates the Air Fuel Ratio on a mass and molar basis. It
% starts off with given molar masses and then calculates the mass of the
% reactants. Then the air fuel ratio is calculated.
M_O2 = 31.999;
M_N2 = 28.013;
M_C = 12.011;
M_H = 1.008;
M_H20 = 18.015;
M_CO2 = 44.01;
M_HC = nHC.*M_C+yHC*M_H;
m_O2_R = N_O2_R.*M_O2;
m_N2_R = N_N2_R.*M_N2;
m_HC_R = N_HC_R.*M_HC;
AFmass = (m_O2_R+m_N2_R)./m_HC_R;
AFmole = (N_O2_R+N_N2_R)./N_HC_R;
% disp('AFmole')
% disp(AFmole)
% disp(' ')
Ptot = 101.325;
PH2O = Ptot.*(N_H2O_P./N_tot_P);
70
%% Exhaust Gas Properties
%This part takes the input as a percent, then converts the percent into a
%fraction. The sum of the mole fractions is calculated along with the
%length of the vector. If the sum does not equal 1, or the length does not
%equal 4, then the program prompts the user for the correct values.
y_m = sum(y_i); %kmol/kmol
lengthY = length(y_i);
%This creates a vertical vector for temperature and calculates the length
%of the vector for use in subsequent calculations.
%SI
T = 900; % K
%ENGLISH
% T = [500:100:2500]'; % R
lengthT = length(T);
%This array contains the a, b, c, and d values from Table A-2 for N2, O2,
%CO2, and H2O.
%SI
abcd = [28.90 -0.1571e-2 0.8081e-5 -2.873e-9
25.48 1.520e-2 -0.7155e-5 1.312e-9
22.26 5.981e-2 -3.501e-5 7.469e-9
32.24 0.1923e-2 1.055e-5 -3.595e-9];
%ENGLISH
% abcd = [6.903, -0.02085e-2, 0.05957e-5, -0.1176e-9
% 6.085, 0.2017e-2, -0.05275e-5, 0.05372e-9
% 5.316, 0.79361e-2, -0.2581e-5, 0.3059e-9
% 7.7, 0.02552e-2, 0.07781e-5, -0.1472e-9];
%This nested for loop calculates Cp_i for all of the gases at all the
%temperatures in the T vector.
for kk = 1:1:4
for jj = 1:1:lengthT
CpBAR_i(jj,kk) =
abcd(kk,1)+abcd(kk,2)*T(jj)+abcd(kk,3)*T(jj)^2+abcd(kk,4)*T(jj)^3; %kJ/kmol K
end
end
%This is a vector of the Molar Masses of the gases. The mixture Molar Mass
%is also calculated.
M_i = [M_N2 M_O2 M_CO2 M_H20]; %kg/kmol
Mm = sum(y_i.*M_i); %kg/kmol
for tt = 1:1:4
71
mf_i(tt) = y_i(tt)*(M_i(tt)/Mm);
end
%This calculates the mass based specific heat from the mole based specific
%heat. The next line calculates the mass based mixture specific heat.
Cp_i = [CpBAR_i(:,1)/M_i(1), CpBAR_i(:,2)/M_i(2),
CpBAR_i(:,3)/M_i(3),CpBAR_i(:,4)/M_i(4)];
for mm = 1:1:lengthT
Cp_m(mm,1) =
mf_i(1)*Cp_i(mm,1)+mf_i(2)*Cp_i(mm,2)+mf_i(3)*Cp_i(mm,3)+mf_i(4)*Cp_i(mm,4);
end
%This for loop calculates the mixture Cp for all the temperatures in the T
%vector.
for hh = 1:1:lengthT
CpBAR_m(hh,1) =
y_i(1)*CpBAR_i(hh,1)+y_i(2)*CpBAR_i(hh,2)+y_i(3)*CpBAR_i(hh,3)+y_i(4)*CpBAR_i
(hh,4); %kJ/kmol K
end
%These next lines of code include the universal gas constant, the
%calculation for Cv from Cp, and the calculation for Km.
%SI
R_u = 8.31447; %kJ/kmol K
%ENGLISH
% R_u = 1.9858; %Btu/lbmol*R
CvBAR_m = CpBAR_m - R_u; %kJ/kmol K
k_m = CpBAR_m./CvBAR_m; %unitless
% Outputs
disp('Exhaust Specific Heat, Cp_exh, (kJ/kg K)')
disp(Cp_m)
72
Appendix E: Energy Balance Equations
𝑃𝑃𝑏𝑏 = 𝑉𝑉 ∗ 𝐼𝐼�𝜂𝜂𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔
̇ ∗ 𝜌𝜌𝐽𝐽𝐽𝐽
𝑚𝑚̇𝐽𝐽𝐽𝐽 = 𝑉𝑉𝐽𝐽𝐽𝐽
Engine Efficiency
𝑃𝑃𝑏𝑏
𝜂𝜂𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒 = �̇
𝑄𝑄𝑖𝑖𝑖𝑖
73
Break Horse Power 𝑃𝑃𝑏𝑏
Current 𝐼𝐼
Density 𝜌𝜌
Efficiency 𝜂𝜂
Exhaust 𝐸𝐸𝐸𝐸ℎ
Mass 𝑚𝑚
Temperature 𝑇𝑇
Time 𝑡𝑡
Voltage 𝑉𝑉
Volume 𝑉𝑉𝑉𝑉𝑉𝑉
74
Appendix F: Bill of Materials
75
Appendix G: Fall 2015 Advisor Report Sheets
76
Figure 39: Adviser Sheet for November 5th
77
Figure 40: Adviser Sheet for November 13th
78
Figure 41: Advisor Sheet December 3rd
79
Appendix H: Spring 2016 Advisor Report Sheets
80
Figure 43: Advisor Sheet January 28th
81
Figure 44: Advisor Sheet February 4th
82
Figure 45: Advisor Sheet February 11th
83
Figure 46: Advisor Sheet February 18th
84
Figure 47: Advisor Sheet February 26th
85
Figure 48: Advisor Sheet March 3rd
86
Figure 49: Advisor Sheet March 10th
87
Figure 50: Advisor Sheet March 24th
88
Appendix I: Initial Proposal
Project Advisor
Dr. Nader Bagheri
Team Members
Eric Sprecher
Marco Levario
Erin Bloom
Jose (Mario) Rodriquez
Elliot Ballard
Submitted: 10/29/2015
89
Project Summary
The Engineering Departments (Mechanical Engineering (ME) and Marine Engineering Technology (ET))
need a practical thermodynamics laboratory to supplement the theoretical knowledge taught in the
curriculum. Currently, no lab specifically addresses a thermodynamic heat balance. With the knowledge
of the design team, advisement from faculty, and sponsorship from companies, this lab will provide
Though an attempt at a thermodynamic lab was made and realized a good amount of success, this lab
needs to be designed from scratch to overcome the problems. A thermal heat balance analysis will be
required to obtain the data to be analyzed. The lab will be aesthetically pleasing and display the data easily
to the students participating in the lab. Once data is obtained, the student will complete the lab by
calculating engine efficiencies and the amount of waste heat able to be recovered.
The project will be judged on three aspects: functionality, safety, and accurate data. Functionality of the
lab includes location of the lab and ease of use. Safety will be realized by the use of alarms, shutdowns,
permissives, and proper procedures. Accurate data will be obtained through the use of high quality
sensors and proper calibration of equipment. The lab must be robust enough to remain operational for
This project will promote better use and future updates of the Power Lab. With this, faculty and students
will be able to better utilize the Power Lab to accomplish educational goals. Analysis of a running engine
will provide a modern, more relevant education to students. The California State University Maritime
Academy is known for reinforcing theoretical knowledge through practical application which is exactly the
90
Background
The idea for this project was sparked by Keir Moorhead’s senior design project which is currently in the
Power Lab and not being used. His old project consists of a Marine Power Cat engine coupled to a
generator. It has been out of use because the generator is not sized to the engine. The engine was unable
to be loaded up enough to perform a worthwhile heat balance. Our goal is to obtain an engine-generator
set that is already sized correctly. Then, the engine can be analyzed through all loading conditions. This
will provide us the opportunity to create something that modernizes the Power Lab and benefits future
students.
All members of the group have gone through the ME curriculum and realized there is not a lab
mechanical engineering and should be properly supplemented. The only lab currently in use that makes
use of some thermodynamic principles is the heat exchanger lab; however, this lab mainly focuses on
The Power Lab has amazing potential but is severely underused. Current updates include the new diesel
simulator and the wind tunnel for the senior design project group competing in the Department of Energy
Collegiate Wind Power Competition. Though these new additions to the Power Lab are a start to
modernizing the educational opportunities of the Power Lab, much of the lab continues to feel like a
museum of interesting engineering with no real benefit to the academy. This engineering space should be
91
Specific Goals
The goal of this project is to develop and integrate a real-world thermodynamics lab into the ME and MET
curriculum. This lab would be directly applicable to the following classes: ME 240, ME 440, ME 349L, EPO
322/L, ET 344, and ET 490/L. The outcomes of our project include: a sample heat balance lab report and
a working lab.
The engine will be fully instrumented in order to acquire the necessary data for determining a heat
balance. These measurements will then be displayed in a manner competitive to other engine lab
The hardware and software used shall provide a means for the students to intuitively collect the engine's
performance data. Students utilizing this lab will use their time to observe dynamic engine response, and
then to collect and analyze the associated data. This provides a highly marketable learning experience to
the students as it will additionally compliment and extended their current understand of fundamental
Of course, safety will be paramount in our design, therefore, alarms, shutdowns, operational permissives,
and proper procedures will be used to ensure the safety of the students, faculty, building, and
environment.
92
Strengths, Weaknesses, Opportunities, and Threats (SWOT) Analysis
Strengths:
The students on the team have a strong balance of skills from various disciplines and backgrounds. There
are three members specializing in mechanical system design: Eric Sprecher, Elliot Ballard, and Mario
Rodriguez. Additionally, there are two members specializing in energy system design: Marco Levario and
Erin Bloom. This combination will allow us to view design problems from multiple perspectives, which will
Eric Sprecher is a great asset to the team. He has already filled the niche of project manager by taking th
lead on using Basecamp to organize the project. He delegates tasks, sets deadlines, and motivates team
members to accomplish tasks and stay focused. As the project continues, Eric will keep the team in line
Elliot Ballard benefits the team as well. As the most fast paced, charismatic, and creative member of the
team, he has suggested numerous, novel ideas and solutions to problems. He keeps the team moving
forward onto the next step in the design process and gets work done. When the team moves into the
resource acquisitioning phase, he will play a key role in marketing our project by meeting and selling our
Mario Rodriguez brings a wealth knowledge to the design team. He already has a B.S. in Physics and has
excelled in all of his classes while at CSU Maritime Academy. As an unlicensed engineer, he has had the
opportunity to intern at Northrup Grumman where he acquired much real world design experience.
Additionally, he has much experience and knowledge working with Matlab which will greatly benefit the
team.
93
Marco Levario brings much needed realism to the team. Occasionally, ideas emerge which are too
implausible or impractical to be useful. Marco will help the team greatly by his excellence in evaluating
potential solutions. Furthermore, he is able to ensure that the solutions which may arise are realistic and
sound solutions to the problem at hand. In addition, because of his emphasis in energy system design, he
will provide much needed knowledge and advice on the thermal balance analysis.
Erin Bloom is advantageous to the team due to his interest in thermodynamics, engines, and controls. He
is especially motivated to take initiative and accomplish tasks assigned to him. As the other team member
pursuing energy system design, he brings a more in depth understanding of thermodynamic principles
which will benefit the theoretical predictions and experimental calculations required for developing the
All members of the design team have practical knowledge of diesel engines and generators from various
cruises and internships. Along with varying skills in fabrication that will benefit the installation and
Weaknesses:
We currently do not have a working engine-generator set to conduct a heat balance on, and a heavy
emphasis on instrumentation is expected. Though all team members have passed the instrumentation
class, none of us have experience installing data acquisition systems on a working diesel engine. Another
weakness is in regards to the teams experience with engine control systems and automation. The
members of the team have little knowledge of the control units and software language used by the engine.
One final weakness is the team’s lack of knowledge of computer languages to create a graphic user
interface (GUI) that will display the information from the analysis.
94
Recommendations and advice from colleagues, advisors, and professionals will be used heavily in these
areas.
Opportunities:
As the CSU Maritime Academy Mechanical Engineering Department Head, Dr. Bagheri, our daily advisor,
has the ability to bring departments together for possible funding opportunities. He is also well versed in
fluid thermal design which will be useful with the fluid thermal balance.
Keir Moorhead, a graduate from of the CSUM mechanical engineering program and MET professor, has
experience with a very similar project he completed as his senior design project. He also has immense
knowledge in the realm of control systems and automation. His advisement and help will be critical to the
Ryan Storz has also shown an interest in the project. His field of expertise is in industrial power
engineering. Also, Robert Jackson of the MET department has also given his support and consent for our
project.
We want to market ourselves to companies around the bay area, specifically those that are in construction
rentals as they are more than likely to have engines with high hours that they are more willing to donate.
Threats:
Engines, generators, instrumentation, and controls can be expensive. Though this project will benefit the
school, and the ME and MET departments are enthusiastic about it, there is only a limited amount of
funding available. If enough funding is not provided or equipment is not donated or reduced in price, this
95
Another threat is the ability to acquire the equipment necessary for the success of the project in a timely
manner. If the equipment is not obtained by the deadlines, there will be less time to complete successive
tasks which, in the end, could result in an incomplete project or, at the very least, an aesthetically
unprofessional lab.
96
Specific Resources Needed
3. Proper engine cooling, exhaust, and intake attachments for safe operation of engine
4. Instrumentation equipment
6. Diesel fuel
8. Matlab
9. LabView
97
Work Breakdown Structure
98
Gannt Chart
D
T Pre
Activity ur 1 1 1 1 1 1 1 1 2
as Activi 1 2 3 4 5 6 7 8 9 10 11
Description ati 2 3 4 5 6 7 8 9 0
k ties
on
Acquire
A 2
Generator Set
Construct testing
B A
site for engine
F
C Acquire Funds 5
A
Engine Testing
L D 3 A,B
and Analysis
L
Instrumentation
E 2 A
Research
Instrumentation
F 4 C,E
Requisition
99
Fit
G Instrumentation 3 F
to engine
H Calibrate 3 G
Neatly display
I 3 H
data
J Record data 3 G
S
K Fine tuning 4 H,I
P
Theoretical
R L 2 I
Analysis
I
Organize and
report
Make
O 2 M,L
Presentation
DELIVER FINISHED
P 1 N
PRODUCT
100
As it is shown in the Gannt chart, there is not much room for error here. There is plenty of opportunity to
move things up and start earlier on certain objectives, but there are critical bottle necks. Next semester
101
Appendix J: Fall PowerPoint Presentation
102
103
104
105