交通洞纵剖面图 1:2500

LONGITUDINAL SECTION OF ACCESS TUNNEL

强风化下限
弱风化下限
lower limit of intense weathering
lower limit of moderate weathering

900 900
断层
推测水位线 fault
guessed water level

subsection of pipe roof


850 850
FCM

end of pipe roof


截水沟

J0+060.00

管 棚 截 止 处

J0+030.00

管 棚 分 段 处
drainage ditch

套拱见另图
main powerhouse cover arch refer to other drawing
access tunnel
主厂房 进厂交通洞
800 主变洞 本次出图界线 地面开关站 800
main boundary line of this drawing
Switch station

775
transformer

1:0.2
780.90 780.00
cavern
i=1.9%
769.40 J1 60 176
结构缝 结构缝 J0
J2 结构缝
structure joint structure joint structure joint
750 42153 12000 2700 3800
750
1470 60653 3000 3000
平底段 斜坡段 slope segment 平底段
flat segment 68123 flat segment

enter point
J0+666.64
J0+681.34

J0+060.00

J0+000.00

进 洞 点
700 700

650 650

轴线控制点 J2 J1 J0
control points of axis
J0+681.34

J0+232.66

J0+030.00

J0+000.00

J0-000.60
J0-017.10
J0+245.03

J0+098.01

J0+060.00
J0+125.01

J0+117.88
J0+666.64

stakes 桩号(m)
(沿洞轴线)
through tunnel axis

沿轴线长度(m) 14.70 433.98 114.78 57.88 30 30


length

围岩类别
Ⅲ Ⅳ Ⅴ
ROCK TYPE
断面型式
A B C D
TUNNEL SECTION TYPE
小导管段 管棚段2 管棚段1 地面开关站
说明 notes leading condulet pipe roof pipe roof Switch station
section section 2 section 1

NOTES:

  1、This set of drawings are the modified layout and structure for access tunnel,totally 4 pieces with drawing NO.413E63-02-07-01R1~04R1. If the dimension and scope of each lining type is different from drawing NO.413E63-02-07-01~04, the value should be taken from
this drawing. Related excavation and support drawing refer to NO.413E63-02-06-02R1~05R1. The control points are the same with those in excavation drawing.

  2、Stakes in the drawings are along the tunnel axis. The range of this set of drawings is from stake J0+000.00 to J0+681.34. Refer to other drawings for the rest segments structure and lining detail of access tunnel.
Refer to other drawings for access tunnel lining reinforcement.

  3、According to the existed geological data, access tunnel lining type include type A, B, C, and D, correspond to those in excavation drawings. When geological flaw such as fault and karst be met, supporting and lining type may need adjusting according to
EPC总承包商: 中国水利电力对外公司
actual geological condition.
EPC: CHINA INTERNATIONAL WATER & ELECTRIC CORP.
  4、Permanent structure joints should be set along access tunnel where tunnel axis turns or class of surrounding rock changes. The structure of joints is shown in detail in the drawing. Structure joints should be set by actual geological condition besides those noted
in the drawing.
设计方: 长江勘测规划设计研究有限责任公司
  5、Tunnel lining should be construted by segments which length be about 10m (no mored than 12m). A construction should be set between tunnel segments. Longitudinal construction joints should be set at about 1/3 height of side wall. The structure of construction joints
DESIGN:CHANGJIANG SURVEY, PLANNING, DESIGN AND RESEARCH CO., LTD.
is shown in detail in the drawing.
核准 APPROVED 秘鲁圣加旺Ⅲ水电站 施工详图 设计
  6、30cm's thick (minimum thickness) concrete baseboard should be set in tunnel segments with no lining. A surface cross slope of 2% should be set in the baseboard from tunnel center to two sides. A longitudinal construction joints could be set long tunnel center line.
CONSTRUCTION DESIGN
Space of transverse construction joints should be no more than 10m. A expansion joint should be set each 40m along tunnel axis. 核定 VERIFIED PERU San Gabán Ⅲ
水 工 部分
  7、Backfill grouting should be implemented after lining concrete strenth be over 70% design value, and consolidation grouting shoud be implemented after backfill grouting finish for 7 days. Effective grout stop measure should be taken at the end of tunnel segment 审查 EXAMINED HYDROPOWER PROJECT HYDRAULIC SECTION

befor grouting. Technological process and material for grouting must meet the request in related criteria and bidding document. 校核 CHECKED
  8、The pressure of backfill grouting chould be 0.2~0.3 MPa, and the pressure of consolidation grouting chould be 0.5 MPa. In order to confirm grouting parameters, a test on site should be done before grouting. 设计 DESIGNED
进厂交通洞结构布置修改图(2/4)
  9、Stakes, elevations are in meter, dimensions are in cm, diameters of holes and anchor bolts are in mm. 制图 DRAWN MODIFIED LAYOUT AND STRUCTURE FOR ACCESS TUNNEL

日期 DATE 2018.11 比例 SCALE 如图 AS NOTED


  10、Other affairs not mentioned should follow the bidding documents and related criteria.