ETAP Page: 1
12.6.0H
Location: Date: 07-04-2020
Contract: SN:
Engineer: Study Case: MOYOTA Filename: TEMA2
Revision: Base
Frequency: 60,0
Revision: Base
System Data:
Soil Data:
Conductor & Rod Copper-clad steel wire 1 40.0 0.00378 245.0 1084.0 4.40 3.85
Rod Data:
Grid Configuration:
Cost:
Conductor Rod
Total Total Length Cost Total Total Length Cost Total Cost
No. ft $ No. ft $ $
11 550.35 1816.16 18 141.66 1800.00 3616.16
Project:
ETAP Page: 3
12.6.0H
Location: Date: 07-04-2020
Contract: SN:
Engineer: Study Case: MOYOTA Filename: TEMA2
Revision: Base
Rg GPR
Touch Potential Step Potential
Ground Ground
Resistance Potential Rise Tolerable Calculated Calculated Tolerable Calculated Calculated
ohm Volts Volts Volts % Volts Volts %
0.624 2382.3 1069.7 320.6 30.0 3612.9 311.2 8.6
Maximum Grid Current: 3.816 kA Surface Layer Derating Factor (Cs): 0.848