You are on page 1of 5

Rajiv Gandhi Sealink—Mumbai, India

Max Meyer, VSL Technical Centre Manager - Asia/Australia, Singapore; Devendra Sharma, Project Chief Engineer; Hindustan
Construction Company, Mumbai, India; Dinesh Paradkar, Design Executive, Hindustan Construction Company, Mumbai, India.
Contact: max.meyer@vsl.com
DOI: 10.2749/101686611X12910257102677

Abstract by bound enabling the completion of as inverted Y and transversely as a


the southbound carriageway ahead of diamond (Fig. 2).
Rajiv Gandhi Sealink in Mumbai, the northbound carriageway to gener-
India, is an eight-lane, 4,7 km long off- ate early revenue from tolls. Hence, This sealink represents an intelligent
shore road bridge, West of the Mumbai after construction had already started, bridge with state-of-the-art systems
Peninsula, which provides an alterna- major design changes had to be car- for traffic monitoring, instrumentation
tive connection across the Mahim Bay ried out: design of the second navi- and emergency support. It features a
between the districts of Bandra in the gation span as a cable-stayed bridge modern toll plaza at Bandra with 16
North and Worli in the South. To cre- called the Worli cable-stayed bridge, lanes equipped with automated toll
ate a landmark structure, a symmetri- and redesign of the Bandra cable- collection systems.
cal cable stayed bridge with a single stayed bridge. The original twin-deck
pylon was chosen to bridge the two 250 structure of the Bandra cable-stayed Design Aspects
m wide navigation spans. bridge was replaced by independent
This project forms first phase of the stayed bridges for each bound, whose The link is made up of two indepen-
Western Freeway sealink project in single pylons are made up of four dent twin bridges with four traffic lanes
Mumbai, which will be, once com- slender legs arranged longitudinally each. The bridge deck is composed of
pleted, an offshore bypass all the
way down to Nariman Point at the
Southern tip of the Mumbai penin-
sula. The southbound carriageway was
opened to traffic in July 2009, followed
by the northbound carriageway in
March 2010.
This paper focuses on the design and
construction aspects of the offshore
bridge, whose deck is almost entirely
made up of pre-cast box-girder seg-
ments. The construction faced many
challenges mainly due to late design
changes and the annual monsoon sea-
sons. Because of rough sea conditions Fig. 1: Bandra cable-stayed land mark bridge
prevailing at this location, construction
over water had to be stopped every
year during the four-and-half-month
long monsoon season.
Keywords: Rajiv Gandhi Sealink; pre-
cast segmental viaduct; match cast
technology; span-by-span construction;
overhead gantry; cable stayed bridge;
lifting frame with strand lifting units.

Introduction
This project was awarded to the main
contractor in 2000. Due to the local
fishing community’s demands, the
owner had to add, after award of work
and start of construction, a second 150
m wide navigation span to the origi-
nal design and had to shift the bridge
alignment 150 m into the sea near
the Worli connector. In addition, the
owner decided to get the Bandra cable
stayed landmark bridge (Fig. 1) rede-
signed, so that it could be built bound Fig. 2: The 126-m tall pylons of the two Bandra cable-stayed bridges

94 Technical Report Structural Engineering International 1/2011


pre-cast concrete segments. A typical The viaducts were designed to be built deck and connected near the top end
segment is 18,1 m respectively, if sus- span by span with construction joints by a cross beam. The stays are over-
pended from stays, 22,7 m wide, 3,0 m at the front face of the leading pier lapped through solid pylon legs (Fig. 5).
deep and about 3 m long (Fig. 3). It has segment. Longitudinal pre-stressing
For all cable-stayed bridges, deck
three cells and a curved “fish belly” (PT) is internal and consists of para-
is monolitically tied into the pylon.
underside and weighs between 80 bolic cables located in the inner ver-
Parallel wire cables are used as stays.
and 140 t. For durability, high-perfor- tical webs and overlapped over pier
mance concrete with a cube strength segments, bottom cables running in the As typical for other pre-cast segmen-
of 60 MPa, with microsilica and flyash, bottom slab and top capping tendons tal bridges, the technical challenge for
was used. Deck slab is transversely placed in the deck slab. this project was not so much with the
pre-stressed. basic analysis of the structure, but more
Each of the two Bandra cable-stayed
so with selection of structural details,
The Rajiv Gandhi Sealink consists of bridges has two 250 m long main spans
which allowed the advantages of pre-
viaduct modules (north approach, link suspended from a pylon made up of
cast production to be fully exploited
viaduct between cable-stayed bridges, four solid legs and two end spans called
both with regard to quality of the final
south approach) that are continuous transition spans, each 50 m at either
product and with regard to ease of con-
over 4 to 6 spans, have typical spans end. Each bridge has two inclined
struction. For these projects, consider-
of 50 m, sit on disc and pot bearings, planes of stays in a semi-fan arrange-
able efforts were made to fine-tune
and cable-stayed bridges. The cable ment anchored to the edges of the deck
the deck segmentation and the deck’s
stayed bridges are the Bandra cable at 6 m spacing. Top anchorages of stays
cross section. The initial idea was to
stayed and the Worli cable stayed twin are located inside a stressing chamber
have only one wet joint per span. This
bridges. In addition, there is a 4-lane in the upper vertical part of pylon.
concept was changed in favour of an
link bridge at the southern end provid-
Each of the two Worli cable-stayed arrangment with two wet joints per span
ing connection to the mainland. This
bridges has a 150 m cable supported between the field segments and the two
link bridge is composed of pre-cast
main span flanked by two 50 m con- pier segments. This change resulted
beams of 24 m spans and segmental
ventional approach spans at either end. in several advantages. There was no
bridge decks of 30 m spans. Figure 4
Two pylons support the deck by means need to match-cast pier and expansion
shows the general bridge arrangement.
of four vertical planes of stay cables joint (EJ) segments, which due to their
Foundations and piers: All foundations in a semi-fan arrangement. The cable complexities needed to be produced
are made up of bore piles, cast in situ spacing is 6,0 m along the bridge deck. in special casting moulds, against field
pile caps and pier shafts. Diameters The pylon consists of a pair of solid segments. This completely decoupled
of bore piles are 1,5 m for viaduct legs. These legs are outwardly inclined the respective acitivites and greatly
modules and 2,0 m for the cable-stayed below the deck, tied together through simplified the production of pier and
bridges and the link bridge. the deck, inwardly inclined above the EJ segments. Geometry control during
erection was made easier, as geometri-
cal inaccuracies could be absorbed at
both ends of span being erected, even
22,7 m 22,7 m though the erection gantry’s front sup-
15 m 15 m port was standing on top of the leading
of SB of SB pier segment. The length of field seg-
ments was orignially only 2,5 and 2,0
CAD-O
CAD-O CAD-O
CAD-O
m, which would have required blisters
for bottom PT to straddle over two seg-
3m

3m

ments in order to achieve minimum


straight length and minimum radius of
Fig. 3: Typical cross-section of twin bridges for the cable-stayed portion curvature for the PT tendons behind

600 m
Bandra cable stayed bridge link viaduct 350 m
North approach viaduct 500 m Worli cable stayed South approach viaduct
16 × 50 = 800 m Precast segmental 4 × 50 = 200 m bridge 28 × 50 = 1400 m
Precast segmental (balanced cantilever) 150 m
(span-by-span) Precast segmental (span-by-span)
Bandra (span-by-span) P19 Precast segmental Worli
(forward cantilever)
A1 P6 P12 P17 P21 P25 P32 P39 P45 P50 P55 P60
Ba

Bandra worli sea link—elevation


nd
ra
A

54 ach za
pp oll p

R29
&

Worli
6 m ro
ro la
t

Link bridge
ad

811 m

A1

R12
N
or

R1 R4
th

80
ap

0 m ch v
pr
oa

P60
P17 P21 P25 P32
ia

P19
du
ct

600 m 200 m 350 m 1400 m


Bandra cable stayed bridge Worli cable stayed bridge South approach viaduct
Bandra worli sea link viaduct—plan alignment

Fig. 4: General bridge arrangement

Structural Engineering International 1/2011 Technical Report 95


on field segments with more than 400
t during launching and had to allow
for delivery of segments from below
(delivery by barge) or from behind
over the already erected part of via-
duct (by trailers). Furthermore, options
had to be provided to relocate the
pier bracket either by barge crane or
by the gantry itself. This requirement,
together with the fish belly shaped
outer segment geometry, excluded the
use of an underslung gantry. Hence,
Fig. 5: Worli cable-stayed bridges an overhead gantry with a single main
truss (MT) was selected. With segments
delivered from behind, the field seg-
their anchorages. Such a situation was the viaduct segments and four dedi- ments of a span had to be suspended
not desirable, specifically as the deck cated casting moulds for the main span in two levels to allow the feeding-in of
had a tight curvature in plan. The con- segments. To maximise available space, the last segments (Fig. 6).
sultant approved the contractor’s pro- casting moulds were located beside the
The working principles of these gan-
posal to replace the sixteen 2,5 m and two storage bays. The casting moulds’s
tries are illustrated in Fig. 7. The gan-
four 2,0 m long field segments of typical transfer carts were used to move seg-
try’s MT was supported during the
internal span with fifteen 3,175 m long ments from casting moulds to storage
span erection on the front pylon (FP)
segments allowing the confinement bays.
and rear pylon (RP), which stand on
of all PT blisters within the segment
A special feature of the casting moulds top of the pier segments (step A). After
length. This change further reduced the
on this project was use of dedicated having completed span between pier N
number of field segments by 25%.
bulkheads for different cross sections. and pier N + 1, the pier segment or the
Thickening of the internal vertical One of the critical areas, when produc- pair of EJ segments for pier N + 2 were
webs in the triple-cell box girder was ing pre-cast segments by match cast parked on completed span (step B).
orignially defined symmetrically on the technology, is the joints. Cells need to The MT was then launched in step C
inner and outer faces. As external cells be properly detailed, such that when by half-span length forward, until the
were already rather small and housed seperating a conjugate segment from a front support leg (FSL) could be acti-
lifting holes and blisters for temporary new segment by rotation of the conju- vated on the bracket attached to the
PT, the cross section was changed by gate segment, no shear keys are dam- front of pier N + 2. The pair of EJ seg-
varying the web thickness on the inner aged. Therefore, apart from checking ments (or the pier segment) parked on
side only. Hence geometry of exter- properly the kinematics for this opera- the completed span was then placed on
nal cells became typical for all field tion to ensure that such rotations are pier N + 2. FPs and RPs were subse-
segments, which cut down the casting possible without obstructions within quently relocated in several steps, until
mould modifications. Fewer modifica- keys, it is important that the buklhead’s they were standing on the pair of EJ
tions of casting moulds not only meant skin is basically free from any steps segments (or the pier segment) on pier
higher productivity but, more impor- that may prevent segment separation N + 2 respectively on the pier segment
tantly, also resulted in better quality of along the theoretical joint face. The on pier N + 1 utilizing FSL, rear support
segments. 15 field segments of a typical internal leg (RSL) and centre leg (CL) (steps C
span had three different cross sections to F). The last step was to launch MT by
due to variation of thickness of inter- another half span length forward, until
Construction
nal vertical webs. Hence, when produc- it was symmetrically standing over the
For the foundation work, five jack-up ing the 15 field segments of a span in a next span to be erected.
barges were used. After construction casting mould, the bulkhead had to be A remarkable operation was required
of piles, steel cofferdams, pre-assem- modified four times. Instead of adding to relocate the two overhead gantries,
bled on land, were placed to allow in on panels to make up the web varia- which weighed 1200 t each, around
situ construction of the pile cap and tions, dedicated bulkheads were fabri- the Bandra cable stay bridges, with a
pier shaft. For construction of founda- cated that could be quickly swapped 1600 t capacity floating sheerleg crane
tion in the intertidal zone just south of whenever cross section needed to be from Singapore, one of the biggest of
the Worli cable-stayed bridge, a tem- changed. With this innovation, not only its kind in the world (Fig. 8). The main
porary bridge had to be built. the cycle time was reduced but, more challenges for this operation were
importantly, the bulkhead was per- the shallow waters and the rough sea
For production of the pre-cast deck fectly smooth and free of steps for any
segments, the main contractor estab- conditions.
type of cross section.
lished a casting yard near the north- To accelerate the construction, the
ern abutment of the project. Segments The viaduct decks, whose typical 50 m main contractor commissioned a third
were produced using the match cast span weigh 1800 t, were erected span by gantry specifically for erection of the
short line technology. The minimum span, with two overhead gantries oper- 12 pre-cast segmental spans of the
radius in plan was as small as 245 m and ating from north to south. Performance link bridge. For that purpose, an exist-
crossfall went up to 6%. To produce specifications called for a gantry that ing gantry, which had previously been
the 2342 segments, the main contractor needed to be supported centrically used for construction of Humin Road
installed four field-casting moulds and over piers during span erection, which Viaduct in Shanghai, was bought and
one special pier/EJ casting mould for could not load the newly erected deck recommissioned.

96 Technical Report Structural Engineering International 1/2011


Construction of Bandra cable-stayed
bridges: After construction of the
lower pylon legs below deck level with
conventional formwork, an exten-
sive falsework system standing on the
pylon’s pile cap was erected to support
the pre-cast segments making up the
69 m long pier table. Interface between
the deck and the pylon is formed by
massive in situ cast crossbeams. Upon
completion of the pier table, the upper
part of the pylon was built with four
sets of self-climbing formwork. Due to
their slenderness, the four legs form-
ing a pylon had to be stabilized during
construction by an elaborate tempo-
rary strutting system made of large-
diameter steel pipes.
A temporary bridge was built con-
necting the already completed viaduct
north of the main span with the pylon’s
pile cap to allow delivery of reinforce-
ment and concrete for construction
of pylons even during the monsoon
Fig. 6: Details of span-by-span erection of viaducts with segments delivered over season.
completed part of viaduct on trailers
Transition spans were erected with the
MI overhead gantries, whereas the stay
suspended part of the main spans was
built by cantilevering with segment lift-
FSL CL RP FP FSL
ing frames (Fig. 9). These frames were
equipped with strand lifting units to
(a)
lift barge-delivered segments up to the
final position. A buffer element was
developed that was made up of 2-m
long slings installed between the lifting
beam and the segment. This device was
very effective to lift segments off the
(b) barges in choppy waters without dam-
aging the lifting frame or segments.
Construction of Worli cable-stayed
bridges: After the construction of
pylons with the self-climbing form-
work, side spans were erected with
(c) the two overhead gantries. To launch
PIER N PIER N + 1 PIER N + 2

MT these gantries over the Worli cable-


stayed bridge’s main span of 150 m,
two temporary piers per carriageway
FSL CL
RP
FP FSL were built. The main span decks were
subsequently erected with similar lift-
(d) ing frames as used for Bandra cable-
stayed bridges.
A special challenge faced when casting
the upper pylon legs for all the cable-
stayed bridges was the requirement for
very fine architectural surface grooves.
(e)
The need for heavy equipment nor-
mally associated with installation of
parallel wire stay cables was greatly
reduced by utilizing movable wheel-
based decoilers and strand pulling
technologies rather than pulling rods
(f) PIER N PIER N + 1 PIER N + 2
for drawing cables through the pylon’s
Fig. 7: Gantry kinematics and deck’s guide pipes (Fig. 10).

Structural Engineering International 1/2011 Technical Report 97


Conclusion
Construction of the Rajiv Gandhi
Sealink faced great technical and logis-
tical challenges, mainly due to major
design changes made after the award of
contract and start of construction and
as well as the adverse sea conditions,
which prevented the main contractor
from carrying out any work over water
for one-third of a calendar year. The
use of pre-assembled steel cofferdams
for construction of pile caps and pier
shafts, resegmention of viaducts, com-
missioning of quality match cast short
line cells with dedicated bulkheads for
production of deck segments, use of
overhead gantries that were completely
self-launching and could receive either
segments delivered from sea or from
behind, good climbform systems for
pylon leg construction, use of strand
lifting technology for installation of the
Fig. 8: Relocation of overhead gantry around Bandra cable-stayed bridges with a 1600-t parallel wire stays and detailed con-
capacity floating shear leg crane
struction stage analysis and geometry
control during tower leg and deck can-
tilever erection of cable-stayed bridge’s
main spans helped greatly to overcome
the technical challenges in the con-
struction of this very visible new land-
mark structure in Mumbai.

SEI
EI Data Block

Owner:
Maharashtra State Road Development
Corporation
Consultant:
Overall concept (alignment,
cross section): Jacobs Engineering
Group—Svedrup Asia Ltd (India)
Bandra cable stayed bridge:
Original design (single bridge with
single pylon): Jacobs Engineering
Group—Svedrup Asia Ltd (India)
in association with HNTB, USA
Redesign (twin bridges): Dar
Al-Handasah, London, UK
Fig. 9: Details of deck erection for Bandra cable-stayed bridges with lifting frames Worli cable stay bridge: Dar Al-
Handasah, London, UK
Main contractor:
Hindustan Construction Company
(HCC)
Specialist contractor for prestressing
and erection of stay cable bridge decks:
VSL India
Construction engineering:
VSL Technical Centre Asia/Australia,
Singapore; P. Klein and A. Faessler,
Switzerland
Bridge deck area: 143 700 m2
Estimated Cost
(USD million): 300
Service Date: July 2009/ March 2010
Fig. 10: Installation of parallel wire cables—use of strands and movable decoilers

98 Technical Report Structural Engineering International 1/2011

You might also like