You are on page 1of 4

CEW Features

Application of UG-140 for Overpressure Protection


It’s a common understanding that for a pressure vessel, pressure relief device is required to protect against
overpressure scenario. In the event of credible overpressure scenario, the device is sized for the scenario.
However, if there are no credible overpressure scenarios, a practice of providing a “token valve” sized arbitrarily
is generally followed. This article addresses the question on whether the relief device is required when there are
no credible scenario and how to meet the code requirements even without providing the pressure relief device.

P
ressure vessel is defined as the vessel The ASME UG-140 requirements and failure, Loss of air cooling, Thermal
designed above 15 psig pressure. procedures are commonly known as “Code expansion, Heat exchanger tube rupture,
When the vessel is designed per code Case 2211”. In 2008, ASME incorporated Fire case, Liquid overfill, Gas Blow by
ASME Section-VIII Division-1 (henceforth “Code Case 2211” into the body of Reactive hazard
referred as code), the requirements of the Section-VIII Division-1 as Section UG-
code are followed for design, fabrication, 140. All overpressure protection systems All the scenarios shall be evaluated with
and inspection & testing. ASME coded addressed by second or third option or a detail explanation to identify whether
vessels are marked with ASME “U” stamp on combination of second and third require the scenario is applicable and if it is
nameplate. One of the basic requirements compliance of ASME UG-140 including applicable how the pressure reached in the
of the code is to provide overpressure all approvals, responsibilities, analysis scenario is less than MAWP of pressure
protection for the vessel covered by ASME and reviews including documentation and vessel at co-incident temperature. All
Section-VIII Division-1, UG-125 through sign-offs. the relevant documents such as Piping
UG-140. and Instrumentation Diagrams (P&IDs),
Detail Requirements of UG-140 (a) Process Flow Diagrams (PFDs), Equipment
Overpressure protection for pressure and (b) General Arrangement (GA) Drawings,
vessel can be achieved by either or Per UG-140, pressure relief device is not Equipment Data Sheets, Plot Plan,
combination of following three options: required to protect a pressure vessel if the Equipment Elevation Drawings, Paving
1. Relief Device: Requirements of pressure is self-limiting and this pressure and Drainage Plans, Process Control
relief device for pressure vessel are is less than equal to MAWP of the vessel System Documentations, Instrument Data
covered by UG-125 through UG- at coincident temperature. Sheets and Material Safety Data Sheets
138. When the findings of detailed (MSDS) of chemicals involved etc. shall be
evaluation of various overpressure The major requirements of UG-140 are used to evaluate credibility of overpressure
scenarios per API Standard-521 Detail analysis of various overpressure scenarios. All the relevant documents shall
state that there are credible cases scenarios; Multidisciplinary team review; be attached as a part of documentation.
for overpressure, pressure relief Risk assessment in the event of credible
devices are provided and sized per scenarios; Manufacturer data report to 2. Multidisciplinary team review: The
applicable equations given in API state the system protected by design; and documentations shall be reviewed and
Standard-521. Documentations & signoffs. evaluated by multi-disciplinary team
of people including Process Safety
2. System Design (Inherently Safe 1. Detail analysis of various credible engineer, Process Technology Leader,
Design): This option overcomes scenarios: API Standard 521, Manufacturing Representatives,
the requirement of a relief device Pressure-Relieving and Depressuring Process Engineers and Relief Design
to protect pressure vessel. The Systems, describes “Causes of Subject Matter Experts (SME).
documentation and other specific Overpressure”. Other standards or
requirements of this option are covered recommended practices that are more 3. Risk assessment in case of credible
by UG-140(a). appropriate to the specific application overpressure scenario: For a pressure
may also be considered. The typical vessel, if a scenario is found to be
3. Safety Instrumented or High Integrity overpressure scenarios that need to credible for overpressure, then risk
Protection System (HIPS): This be analyzed are Loss of cooling water or associated with the event shall be
option can overcome the requirement cooling medium, Loss of power, Loss of judged to decide whether or not the relief
of a relief device in specific cases. steam, Loss of instrument air or electric device shall be provided. The design
The documentation and other specific supply failure, Individual control valve shall comply with local regulations and
requirements of this option are covered failure, Inadvertent valve operation, owner’s risk tolerance criteria. This
by UG-140(b). Blocked outlet, Individual equipment approach is scenario specific and if

36 • September 2013 Chemical Engineering World

new Daelim.indd 36 01-10-2013 21:37:09


CEW Features
it can be justified that having a relief
device does not benefit then one can go
without having a relief device even when
the case is credible for overpressure. To
illustrate, examples can be as follows:
• If fire scenario is applicable to a
pressure vessel operating in gas
service, pressure relief device is of
no help in protecting the vessel as the
vessel ruptures due to overheating
before the pressure reaches the set
pressure of relief device.
• The pressure vessel is empty and fire
case is applicable, relief device is of Figure1: Example of System Architecture for HIPS
little help for the same reasons.
• Pump Seal pots: Consider 5 gallon U High Integrity Pressure Protection Integrity Protection System) used to
stamped seal pot is provided for API System (HIPS) limit the system pressure, including the
pump and fire case is applicable. During a Industrial use of HIPS is to reduce the identification of all truly independent
fire, the seal pot will likely fail, regardless pressure relief device’s size for specific redundancies and a reliability evaluation
of whether it has a PSV, and regardless scenarios. It is not intended to drive the (qualitative and quantitative) of the
of that PSV’s size. For vessel size being complete removal of pressure relief devices. overall safety system shall be provided
that small, a fire-sized PSV will quickly However, in specific cases, use of HIPS as part of UG-140 documentation.
result in the seal pot being emptied can lead to elimination of relief device. HIPS finds its use in complex process
of liquid. Once the liquid is gone the The documentation and other specific applications. For example, the application
vessel will fail due to excessive heating
requirements of this option are covered by of HIPS is for a reactor o perating at high
(excessive wall temperature). Thus, a
UG-140(b). temperature and pressure conditions
PSV can’t adequately prevent this vessel
where coolant is circulated to remove
from failing during a sustained pool fire.
HIPS typically involve an arrangement exothermicity of reaction and loss of
of instruments, final control elements coolant would lead to high temperature
One can go with UG-140 documentation
(e.g. valves, switches, etc.), and logic rise leading to runaway reaction or boil
for such cases.
solvers configured in a manner designed up of coolant. In such application, HIPS
4. Documentation and Sign off: All to avoid overpressure incidents by is used to cut off the feed once coolant
the involved parties shall sign off the removing the source of overpressure flow is stopped.
document to conclude and certify that or by reducing the probability of an
the vessel is protected by system design overpressure contingency to such a low The table (on the next page) can be used as
and in no credible event the pressure will level that it is no longer considered to reference when making a choice between
exceed MAWP at coincident temperature. be a credible case. With appropriate the options to be followed for overpressure
5. Manufacturer’s data report to state levels of redundancy, a HIPS can be protection of pressure vessel while meeting
the system protected by design: designed to achieve a level of availability code requirements.
Annexure-W of ASME Section- equal to or greater than a mechanical
VIII Division-1 provides details of relief device. Example of Pressure Protection of a
Manufacturing Data reports. UG-140 Pressure Vessel Operating in Chlorine
requires that manufacturing data report A detailed description of any safety Service by System Design (UG-140 (a)) (See
shall mention that the vessel is protected critical instrumentation (HIPS-High Figure 2 below)
by system design. Typically, vessel
manufacture provides data report and
this requirement is mentioned in the
notes section of the report. To the data
report, a U-1 or U-1A form is enclosed.
Typically, U-1 or U-1A form should say
“Overpressure protection is provided
by others per UG-140 (a) or (b). OSHA
inspector is likely to see this form to
check for overpressure protection of the
vessel when the ASME code stamped
vessel is not provided with a pressure
relief device. Figure 2: D-101 Schematic

38 • September 2013 Chemical Engineering World

new Daelim.indd 38 01-10-2013 21:37:09


CEW Features

Equipment / System Protected Pros and Cons of Relief Device, Safe Design and HIPS UG-140 (b)
D-101 (Chlorine gas knock out drum) Relief Device Inherently safe design HIPS
MAWP @ Coincident Temperature UG-140 (a) UG-140(b)
21.5 barg / FV @ 190 °C Pros Pros Pros
1. Commonly used 1. Safest way of design 1. Availability / Reliability
System Information 2. Highly reliable 2. Eliminate relief device 2. Eliminate relief device and
3. Designer feels confident and associated associated disposal system
1.1 Protected Equipment : D-101 with functionality disposal system 3. Suitable for toxic services
1.2 Fluid HandleD : Chlorine 4.Standalone Mechanical device 3. Preferred option for 4. Can eliminate overpressure
1.3 Operating Pressure / Temperature 5.Can handle runaway reactions toxic services scenarios such as runaway
: 6.5 Barg / 50°C reactions
5. Can provide protection
Description of Overpressure Scenario against excessive
1. Loss of Cooling Water or Other temperature due to process
Cooling Fluid: No cooling is supplied upsets (*)
to D-101. Hence, the case is 6. Useful when environment
not applicable. restrictions and safety
2. Loss of Power: There are no power constraints limit the venting
operated equipment associated Cons Cons Cons
with D-101. Hence, the case is not 1. Requires maintenance 1. Higher design pressures 1. Maintenance, testing and
applicable.
2. Can plug in heavy service 2. HIPS needs to be used inspection
3. Steam Failure: No steam is associated
3. Requires disposal system in combination to handle 2. Complex systems
with D-101. Hence, the case is
downstream for safe handling runaway reactions 3. Expensive systems
not applicable.
4. When not used in and protection against
4. Instrument Air / Electrical Supply Failure: In
combination of HIPS, may excessive temperature
the event of instrument air failure, following
require bigger disposal 3. Designer needs to
valves shall close as failure position being
Fail Closed. [Inlet of D-101 - 1. EBV-01: system such as large flare meet requirement of
Closure of the valve shall lead to loss of headers and scrubbers UG-140 by way of
chlorine gas flow to D-101. Hence, there 5. Not desirable in toxic services documentations, reviews
shall be no overpressure. Outlet of D-101 - 6. Cannot provide protection and sign-offs
1. FCV-01 / EBV-02: Closure of the valves against excessive temperature
shall not lead to overpressure as chlorine Table1: Comparison of Options for Overpressure Protection , (*) Fire case is not considered as a process upset scenario.
gas flow to D-101 shall be lost due to
closure of EBV-01.] 10. Gas Blow Through:The case is activities. However, maximum operating
5. Individual Control Valve Failure: Failure not applicable. pressure of LP Nitrogen is 7 barg which
Opening of FCV-01: The valve is located 11. External Fire: Per Equipment GA is less than MAWP of D-101. Hence,
on vent outlet of D-101. The case of drawing, the equipment is located above overpressure is not credible.
failure opening of control valve shall fire height of 7.6m. Hence, overpressure
result in no overpressure to D-101 as is not credible. Safety Critical Instrumentation And
the valve shall provide open path to 12. Exchanger Tube Rupture: D-101 is Reliability Evaluation
downstream system. not connected to any heat exchanger. For D-101, no safety critical instrumentation is
6. Inadvertent Valve Operation: Failure Hence, the case is not applicable. used for purpose of overpressure protection.
closure of FCV-01: Failure closure of 13. Liquid Overfill: D-101 is operating in Hence, this section is not applicable. As
the valve shall not result in overpressure gas service. Hence, the case is not detailed evaluation of possible overpressure
as MAWP of D-101 is higher than the applicable. scenarios suggests that in no case the
maximum pressure of chlorine gas at 14. Thermal Expansion: D-101 is operating pressure can exceed MAWP of D-101, it
battery limit which is 9 barg. in gas service. Hence, the case is can be concluded that pressure is self-
7. Individual Equipment Failure: There are not applicable. limiting and D-101 is protected by system
no mechanical equipment associated with 15. Vacuum: D-101 is designed for full design. Hence, no relief device is required
D-101. Hence, the case is not applicable. vacuum. Hence, the case is not deemed to for overpressure protection.
8. Loss of Air Cooling :No air cooling be credible.
is provided for inlet and outlet 16. Runaway Reactions (Reactive Hazards): No Conclusion
streams of D-101. Hence, the case is reactive hazard is associated with D-101. In certain services, having Pressure relief
not applicable. Hence, the case is not applicable. devices adds to issues related to leaking
9. Blocked Outlet: Refer to Case 6. 17. Any Other: Low pressure nitrogen can be and maintenance due to plugging. If it
No overpressure. hooked up to D-101 during maintenance can be justified that the pressure vessel

40 • September 2013 Chemical Engineering World

new Daelim.indd 40 01-10-2013 21:37:09


CEW Features
is designed to withstand all credible scenarios, UG-140 comes
handy to meet the requirements of the code. In toxic services Contribute in CEW
such as phosgene, it is desirable to protect the vessel by system
design and/or by employing HIPS system. Pressure relief devices
operating in phosgene service require proper disposal system
and may create operational hazards. These devices also require
critical procedures in place for inspection and maintenance.

HIPS typically finds its application in critical process operations


handling hazardous services. On the other hand, having a relief
device on the vessel provides a kind of insurance for the vessel.
Decision to have a relief device to protect the vessel depends
upon number of factors as service it is operated with, type of
overpressure scenario and experience of engineers working with
the technology. As there are number of factors which influence Dear Readers,
the decision making to protect the vessel and the decision being
scenario specific, its users responsibility to decide the option to Chemical Engineering World (CEW), the
be followed for overpressure protection keeping in mind that the Official Organ of CHEMTECH Founda�on, is
code permits not to have a relief device by way of UG-140 provided
India's premier technology magazine for the
the detail evaluation is performed and analysis is documented to
ensure no hazardous situation would arise due to overpressure that
chemical process industry professionals. This
may lead to loss of containment or risk to operating personnel. highly reputed monthly publica�on provides
novel insights on the dynamics of Indian and
References global process industries. CEW, a niche
1. Pressure-relieving and Depressuring Systems, ANSI/API Standard publica�on with proven track record, has
521, Fifth Edition, January 2007, Addendum May 2008. been dissemina�ng authen�c informa�on on
2. ASME Boiler and Pressure Vessel Code VIII, Division 1, Rules for
process industry innova�ons for more than
Construction of Pressure Vessels, Edition 2010
four decades.
Definition of Terms
1. Design pressure: Pressure, together with the design temperature, You can contribute in the magazine with
used to determine the minimum permissible thickness or physical technical ar�cles, case studies, and product
characteristic of each component, as determined by the design rules write-ups. The length of the ar�cle should
of the pressure-design code
not exceed 1500 words with maximum three
2. MAWP: Maximum gauge pressure permissible at the top of a
completed vessel in its normal operating position at the designated
illustra�ons, images, graphs, charts, etc. All
coincident temperature specified for that pressure the images should be high-resolu�on (300
3. Overpressure: Pressure increase at the relief valve inlet above the DPI) and a�ached separately in JPEG or JPG
set pressure, when the relief valve is relieving (Overpressure is format. Have a look at our editorial calendar
expressed in pressure units or as a percentage of the set pressure.) on the website – www.cewindia.com.
4. Relief device: Device used to relieve excess pressure and/or vacuum
that has developed in a tank
To know more about Chemtech Founda�on,
5. Set pressure: The inlet gauge pressure at which pressure relief valve
is set to open under service conditions
Jasubhai Media and other publica�on and
events, please visit our website –
www.chemtech-online.com

Thank you,
Regards,
Mi�ravinda Ranjan
Editor
Author’s Details
Sushant G Labhasetwar (P.E)
Jasubhai Media Pvt Ltd
Assistant Manager - Process Engineering Team Tel: +91 22 4037 3636 (Dir: 4037 3615)
Daelim Industrial Corporation, Seoul Korea E-mail: mi�ra_ranjan@jasubhai.com
Email: sushant@daelim.co.kr

42 • September 2013 Chemical Engineering World

new Daelim.indd 42 01-10-2013 21:37:14

You might also like