Professional Documents
Culture Documents
P
ressure vessel is defined as the vessel The ASME UG-140 requirements and failure, Loss of air cooling, Thermal
designed above 15 psig pressure. procedures are commonly known as “Code expansion, Heat exchanger tube rupture,
When the vessel is designed per code Case 2211”. In 2008, ASME incorporated Fire case, Liquid overfill, Gas Blow by
ASME Section-VIII Division-1 (henceforth “Code Case 2211” into the body of Reactive hazard
referred as code), the requirements of the Section-VIII Division-1 as Section UG-
code are followed for design, fabrication, 140. All overpressure protection systems All the scenarios shall be evaluated with
and inspection & testing. ASME coded addressed by second or third option or a detail explanation to identify whether
vessels are marked with ASME “U” stamp on combination of second and third require the scenario is applicable and if it is
nameplate. One of the basic requirements compliance of ASME UG-140 including applicable how the pressure reached in the
of the code is to provide overpressure all approvals, responsibilities, analysis scenario is less than MAWP of pressure
protection for the vessel covered by ASME and reviews including documentation and vessel at co-incident temperature. All
Section-VIII Division-1, UG-125 through sign-offs. the relevant documents such as Piping
UG-140. and Instrumentation Diagrams (P&IDs),
Detail Requirements of UG-140 (a) Process Flow Diagrams (PFDs), Equipment
Overpressure protection for pressure and (b) General Arrangement (GA) Drawings,
vessel can be achieved by either or Per UG-140, pressure relief device is not Equipment Data Sheets, Plot Plan,
combination of following three options: required to protect a pressure vessel if the Equipment Elevation Drawings, Paving
1. Relief Device: Requirements of pressure is self-limiting and this pressure and Drainage Plans, Process Control
relief device for pressure vessel are is less than equal to MAWP of the vessel System Documentations, Instrument Data
covered by UG-125 through UG- at coincident temperature. Sheets and Material Safety Data Sheets
138. When the findings of detailed (MSDS) of chemicals involved etc. shall be
evaluation of various overpressure The major requirements of UG-140 are used to evaluate credibility of overpressure
scenarios per API Standard-521 Detail analysis of various overpressure scenarios. All the relevant documents shall
state that there are credible cases scenarios; Multidisciplinary team review; be attached as a part of documentation.
for overpressure, pressure relief Risk assessment in the event of credible
devices are provided and sized per scenarios; Manufacturer data report to 2. Multidisciplinary team review: The
applicable equations given in API state the system protected by design; and documentations shall be reviewed and
Standard-521. Documentations & signoffs. evaluated by multi-disciplinary team
of people including Process Safety
2. System Design (Inherently Safe 1. Detail analysis of various credible engineer, Process Technology Leader,
Design): This option overcomes scenarios: API Standard 521, Manufacturing Representatives,
the requirement of a relief device Pressure-Relieving and Depressuring Process Engineers and Relief Design
to protect pressure vessel. The Systems, describes “Causes of Subject Matter Experts (SME).
documentation and other specific Overpressure”. Other standards or
requirements of this option are covered recommended practices that are more 3. Risk assessment in case of credible
by UG-140(a). appropriate to the specific application overpressure scenario: For a pressure
may also be considered. The typical vessel, if a scenario is found to be
3. Safety Instrumented or High Integrity overpressure scenarios that need to credible for overpressure, then risk
Protection System (HIPS): This be analyzed are Loss of cooling water or associated with the event shall be
option can overcome the requirement cooling medium, Loss of power, Loss of judged to decide whether or not the relief
of a relief device in specific cases. steam, Loss of instrument air or electric device shall be provided. The design
The documentation and other specific supply failure, Individual control valve shall comply with local regulations and
requirements of this option are covered failure, Inadvertent valve operation, owner’s risk tolerance criteria. This
by UG-140(b). Blocked outlet, Individual equipment approach is scenario specific and if
Equipment / System Protected Pros and Cons of Relief Device, Safe Design and HIPS UG-140 (b)
D-101 (Chlorine gas knock out drum) Relief Device Inherently safe design HIPS
MAWP @ Coincident Temperature UG-140 (a) UG-140(b)
21.5 barg / FV @ 190 °C Pros Pros Pros
1. Commonly used 1. Safest way of design 1. Availability / Reliability
System Information 2. Highly reliable 2. Eliminate relief device 2. Eliminate relief device and
3. Designer feels confident and associated associated disposal system
1.1 Protected Equipment : D-101 with functionality disposal system 3. Suitable for toxic services
1.2 Fluid HandleD : Chlorine 4.Standalone Mechanical device 3. Preferred option for 4. Can eliminate overpressure
1.3 Operating Pressure / Temperature 5.Can handle runaway reactions toxic services scenarios such as runaway
: 6.5 Barg / 50°C reactions
5. Can provide protection
Description of Overpressure Scenario against excessive
1. Loss of Cooling Water or Other temperature due to process
Cooling Fluid: No cooling is supplied upsets (*)
to D-101. Hence, the case is 6. Useful when environment
not applicable. restrictions and safety
2. Loss of Power: There are no power constraints limit the venting
operated equipment associated Cons Cons Cons
with D-101. Hence, the case is not 1. Requires maintenance 1. Higher design pressures 1. Maintenance, testing and
applicable.
2. Can plug in heavy service 2. HIPS needs to be used inspection
3. Steam Failure: No steam is associated
3. Requires disposal system in combination to handle 2. Complex systems
with D-101. Hence, the case is
downstream for safe handling runaway reactions 3. Expensive systems
not applicable.
4. When not used in and protection against
4. Instrument Air / Electrical Supply Failure: In
combination of HIPS, may excessive temperature
the event of instrument air failure, following
require bigger disposal 3. Designer needs to
valves shall close as failure position being
Fail Closed. [Inlet of D-101 - 1. EBV-01: system such as large flare meet requirement of
Closure of the valve shall lead to loss of headers and scrubbers UG-140 by way of
chlorine gas flow to D-101. Hence, there 5. Not desirable in toxic services documentations, reviews
shall be no overpressure. Outlet of D-101 - 6. Cannot provide protection and sign-offs
1. FCV-01 / EBV-02: Closure of the valves against excessive temperature
shall not lead to overpressure as chlorine Table1: Comparison of Options for Overpressure Protection , (*) Fire case is not considered as a process upset scenario.
gas flow to D-101 shall be lost due to
closure of EBV-01.] 10. Gas Blow Through:The case is activities. However, maximum operating
5. Individual Control Valve Failure: Failure not applicable. pressure of LP Nitrogen is 7 barg which
Opening of FCV-01: The valve is located 11. External Fire: Per Equipment GA is less than MAWP of D-101. Hence,
on vent outlet of D-101. The case of drawing, the equipment is located above overpressure is not credible.
failure opening of control valve shall fire height of 7.6m. Hence, overpressure
result in no overpressure to D-101 as is not credible. Safety Critical Instrumentation And
the valve shall provide open path to 12. Exchanger Tube Rupture: D-101 is Reliability Evaluation
downstream system. not connected to any heat exchanger. For D-101, no safety critical instrumentation is
6. Inadvertent Valve Operation: Failure Hence, the case is not applicable. used for purpose of overpressure protection.
closure of FCV-01: Failure closure of 13. Liquid Overfill: D-101 is operating in Hence, this section is not applicable. As
the valve shall not result in overpressure gas service. Hence, the case is not detailed evaluation of possible overpressure
as MAWP of D-101 is higher than the applicable. scenarios suggests that in no case the
maximum pressure of chlorine gas at 14. Thermal Expansion: D-101 is operating pressure can exceed MAWP of D-101, it
battery limit which is 9 barg. in gas service. Hence, the case is can be concluded that pressure is self-
7. Individual Equipment Failure: There are not applicable. limiting and D-101 is protected by system
no mechanical equipment associated with 15. Vacuum: D-101 is designed for full design. Hence, no relief device is required
D-101. Hence, the case is not applicable. vacuum. Hence, the case is not deemed to for overpressure protection.
8. Loss of Air Cooling :No air cooling be credible.
is provided for inlet and outlet 16. Runaway Reactions (Reactive Hazards): No Conclusion
streams of D-101. Hence, the case is reactive hazard is associated with D-101. In certain services, having Pressure relief
not applicable. Hence, the case is not applicable. devices adds to issues related to leaking
9. Blocked Outlet: Refer to Case 6. 17. Any Other: Low pressure nitrogen can be and maintenance due to plugging. If it
No overpressure. hooked up to D-101 during maintenance can be justified that the pressure vessel
Thank you,
Regards,
Mi�ravinda Ranjan
Editor
Author’s Details
Sushant G Labhasetwar (P.E)
Jasubhai Media Pvt Ltd
Assistant Manager - Process Engineering Team Tel: +91 22 4037 3636 (Dir: 4037 3615)
Daelim Industrial Corporation, Seoul Korea E-mail: mi�ra_ranjan@jasubhai.com
Email: sushant@daelim.co.kr