Professional Documents
Culture Documents
TABLE OF CONTENT
1. BACKGROUND.....................................................................................................................................3
2. OBJECTIVES.........................................................................................................................................3
Project Delivery Method: Public-Private Partnership (PPP)........................................................4
Contract Type: Fixed-Price Contract...........................................................................................4
3. SCOPE..................................................................................................................................................5
4. CONSTRAINTS......................................................................................................................................7
Time Constraint:.........................................................................................................................7
Production-Service Constraints:.................................................................................................8
Sub-contractor Constraints.........................................................................................................8
5. ASSUMPTIONS.....................................................................................................................................9
6. RISKS....................................................................................................................................................9
6.1. Risk Management Strategies...............................................................................................9
6.1.1. Exceeding Estimated Duration, Risk and Time Management......................................10
6.1.2. Negotiation Management...........................................................................................10
7. DELIVERY PARTS...............................................................................................................................11
8. RESOURCES.......................................................................................................................................11
8. ADAPTING PROJECT MANAGEMENT PRINCIPLES TO THE PROJECT..............................................12
Project Integration Management.............................................................................................................12
Project Scope Management.....................................................................................................................13
Steps for Defining the Scope of a Project.....................................................................................13
Project Time Management......................................................................................................................16
Project Cost Management.......................................................................................................................17
Project Quality Management...................................................................................................................18
Project Human Resources Management..................................................................................................18
Project Communication Management.....................................................................................................19
Project Risk Management........................................................................................................................19
Project Procurement Management.........................................................................................................20
9.REFERENCES......................................................................................................................................21
1. BACKGROUND
This project covers the rough works of Urla State Hospital Annex Building. As a result of the
insufficient hospital capacity, such a structure was needed. The most important constraint in
this project is time. In the project, a 2-storey structure is planned as the ground floor and the
first floor. The construction area is 600 m2 and the construction site is state land (Table.1).
Construction area and necessary permits are provided by the state. It is a project carried out in
cooperation with the state. As a result of the tender with the state, a contract was made with
2. OBJECTIVES
PPPs are a cooperative between government and the private sector, they are an
implemented in multiple countries, are primarily used for infrastructure projects, such
as the building and equipping of schools, hospitals, transport systems, and water and
sewerage systems [1]. This method is the most suitable method as it is a hospital project
Fixed-Price Contract means that the seller has agreed to deliver work for a fixed
The contract covers only rough works. The project has been defined as the Start Building -
Rough Work and Completion of Structural Works as the main task (Table.3). As a sub-task is
- Mobilization
- Excavation
- Foundation
- Basement
- 1st Floor
4. CONSTRAINTS
Time Constraint:
While the work plan is being prepared, one is defined to start as soon as possible the
work is finished. In addition, 3 milestones have been determined in order to follow the
studies and reach the desired target in terms of time. These are included in Table 6.
Production-Service Constraints:
Payments are created per unit business or unit service. Employees and mobile cranes
are charged per hour and materials are charged per unit (Table 7).
Sub-contractor Constraints:
It has been agreed with the Batıbeton for concrete as a fee per m3. The requested order
will be fully prepared if it is notified the day before the required day. Batıbeton has
been preferred because it is the closest concrete producer to the construction site. It is
considered that there is no problem in setting time of the concrete. With the steel sub-
contractor, it was decided that delivery will be made at the discretion of placing an
Since it is a project made with the cooperation of the state, permits etc. will be
The subcontractor agreed for the excavation was determined 1 day before the delivery
date in the contract made with the subcontractor in case it could not perform its duty
Shareholders equity will be used and it is foreseen that there will be no financial
problems. It is included in the contract that the project payment from the state will be
6. RISKS
The day specified in the MS Project is the same day in the contract. It is planned that
There may be complaints as the annexed building is located on the side of the hospital.
organized and economical use of resources to mitigate, track, and regulate the threat or
techniques usually include minimizing the danger, decreasing the danger's negative impact
or likelihood, moving all or part of the threat to another group, and even maintaining some
The most important constraint in the business plan is time, and the biggest risk was taken
over time. The budget will be financed from the company equity, but payment is
scheduled per day of delay. The biggest advantage in this regard is the high financial
power. In addition, contracts have been agreed with sub-contractor at a fixed dollar rate.
The risk in business deliveries is reduced to a minimum as it will work with proven
subcontractors. It is planned to agree with an insurance company for natural disasters that
understandably aim to achieve the best possible result for their position in any
disagreement
[4]
.
Since the project is located near the hospital, it is thought that patients and hospital
management may complain about it. This situation can be prevented by negotiation
management. Patients in the current hospital can complain about dust and noise. The
project manager must meet such a situation with understanding and not follow that must
follow a savvy path. In addition, the N100 mask will be provided by the company free of
3 milestones have been assigned to follow the regular progress of the project. Project
reporting will be made on these 3 milestones. This report will be prepared by the project
manager. The report will be shared with all the engineers in the project, especially the
company partners. In case of any delay with the engineers, they will be shared to find
8. RESOURCES
In this part of the report, there is an adaptation of the information about 9 pm knowledge areas
to the project. The project prepared with theoretical knowledge for project management has
been reconsidered.
Without good teamwork, proper integration of the project is not possible. You should
have the resources which know their role and responsibilities to be successful. It is the
duty of project managers to explain project priorities and efficiently manage the
The project was carried out using the BOSCAR project identification method.
According to the BOSCAR project identification method work plan was defined under
six main headings such as; background, objectives, scope, constraints, assumptions,
risks and resources. To successfully complete the project, project started date, targeted
project finished date, estimated project cost, fee requested, targeted project time and
the profit from the project were determined and reported before the project (Table.9).
Defining and recording all of the research is handled within reach. The management
manager will know what the outcomes are, and what issues the management is trying
to fix. All of this makes it easier for members of the team to accomplish the targets
and lets clients know what to expect from the projects [5].
The project has been defined as the main tasks (Table.3) and the sub-tasks (Table.4)
associated with it. In this way, a more regular operation is aimed. Project end date has
been determined and project planning has been arranged for this target (Table.9). In
o Project Objectives:
Objectives belonging to the project were created before the project started as
given in the Table 10 below. See page 3 and 4 for detailed information.
The goal of the project is to complete the rough work of the Urla State Hospital
o Sub-phases
The project is divided into sub-phases to reach the main goal. Work Break
created. This, sub-works were facilitated. For detailed information, see Table
o Tasks
o Resources
The resources were created using the MS Project program before the project,
o Budget
Estimated project cost has been determined as 949,360.00 TRY (Table 2), fee
o Schedule
Necessary plans are explained with the information and tables at the top of the
For project managers one of the biggest challenges is completing projects on time.
Most of the programs they oversee fail to finish before the deadline. There are six sub-
processes associated with the information field of project time management which
- Estimate the time required: Required time is determined as 75 days by using Ms project
program.
- Develop a schedule: WBS and OBS created with the MS project program.
- Control schedule: Milestones have been added to follow the progress of the project.
Project Cost Management
Cost management can make a difference between a project success and a project loss. Due
to budget constraints many projects are abandoned. If you don't want this to happen to
your projects, then you should learn the art of efficient cost management of the project
[5]
and complete the projects within the budgets . Here are three main sub-processes
- Estimate costs: A general cost calculation was made for the foreseeable costs before the
project started. The cost is determined as 949,360.00 TRY (Table.9). This estimate
includes the cost of services and materials that were generally determined at the
- Determine budget: It was thought that there might be unexpected expenses during the
project. For these unexpected expenses and for profit, the fee is determined as
1,200,000.00 TRY requested. Thus, the profit share is 26.40% (Table.9). In order not
to exceed the budget, attention should be paid to the budget and expenditures. The
project manager should pay attention to the cost method from the very beginning. To
keep project costs under control, every dollar and where it is spent should be tracked.
For this reason, the agreements made were made at a fixed dollar rate.
Project Quality Management
No matter how you define quality, a high-quality project is one that satisfies the needs
of the customer and does not contain any deficiencies or defects. To achieve the
highest project quality, project managers and their team should focus on initially
gathered customer requirements, try to know what the customer wants and which
The prototype of the project was prepared in the best way and this was presented in
the agreement with the state. It has been agreed by the government for the necessary
management and management of project teams. It's how you treat the company's most
important asset, i.e. men. Project managers should have a clear strategy when it comes
to hiring and staffing people and inducing them into project teams, in order to succeed.
Hiring the right people can make your chances of success even greater [5].
The manpower to work in the project has been determined at the beginning of the
project. Estimated labor rate calculation was made (Fig.1). The agreement was made
so that the payments were made per unit hour (Table.7). The necessary plan for each
Poor communication with a project can wreak havoc on the progress of your project.
This can also take your project to failure. And if you want to successfully complete the
tasks, all members of the team will be on the same page. They will also work as a
situation. Within the scope of occupational health and safety training, a training on
the project:
Most project managers regard risk management as the most significant factor in
important part in preventing failure of your projects. Project managers who disregard
minor risks will suffer from project failure because such minor risks can turn into
major risks, which if left unattended, can lead to a project catastrophe [5]. The risks that
1. The day specified in the MS Project is the same day in the contract. It is
and noise.
Risk strategies have been developed to minimize these risks. Risk management
techniques usually include minimizing the danger, decreasing the danger's negative
impact or likelihood, moving all or part of the threat to another group, and even
maintaining some or all of the possible or real effects of a specific risks. Risk & Time
Management and Negotiation Management strategies were used to reduce these risks.
The knowledge area of Project Procurement Management covers all aspects relating to
the purchase and acquisition of the products and services needed to effectively
Planning has been made for material supply. For example, an agreement was signed
with firm Batıbeton for the supply of ready-mixed concrete. In this context, the
requested order will be fully prepared if it is notified the day before the required day.
Batıbeton has been preferred because it is the closest concrete producer to the
concrete. With the steel sub-contractor, it was decided that delivery will be made at the
[1] Public–private partnership. (2020, June 04). Retrieved June 04, 2020, from
https://en.wikipedia.org/wiki/Public%E2%80%93private_partnership
[2] Fixed-Price Contract. (n.d.). Retrieved June 04, 2020, from https://project-management-
knowledge.com/definitions/f/fixed-price-contract/
[3] Risk management. (2020, June 07). Retrieved June 24, 2020, from
https://en.wikipedia.org/wiki/Risk_management
[4] 2011-2020, (. (n.d.). What is Negotiation? Retrieved June 24, 2020, from
https://www.skillsyouneed.com/ips/negotiation.html
[5] Hasan, S. (2019, August 08). PMBoK Knowledge Areas: 9 Must Know Aspects Related
to PM. Retrieved June 24, 2020, from https://blog.taskque.com/pmbok-knowledge-
areas/
Haziran 2020
Pazartesi Salı Çarşamba Perşembe Cuma Cumartesi Pazar
1 2 3 4 5 6 7
8 9 10 11 12 13 14
Mobilization; 10
gün
15 16 17 18 19 20 21
Mobilization; 10 Excavatio n; 10 gün
gün
22 23 24 25 26 27 28
Excavatio n; 10 gün Lean Concrete; 2
gün
29 30
Lean Concrete; 2 Ste 5 gün
gün
el; rk; 5 gün
Form
wo
Temmuz 2020
Pazartesi Salı Çarşamba Perşembe Cuma Cumartesi Pazar
1 2 3 4 5
Ste 5 gün
el; rk; 5 gün
Form
wo
6 7 8 9 10 11 12
Steel; 5 gün Concret e; 2 gün Steel; 3 gün
Formwork; 5
gün
13 14 15 16 17 18 19
Steel; 3 gün Formwork; 3 gün Concrete; 2 gün
20 21 22 23 24 25 26
Concrete; 2 gün Staffoldin g; 4 gün
MS1: Completion of
B
27 28 29 30 31
Fromwor k; 4 gün Steel; 5 gün
Ağustos 2020
Pazartesi Salı Çarşamba Perşembe Cuma Cumartesi Pazar
1 2
Steel; 5 gün
3 4 5 6 7 8 9
Steel; 5 gün Concrete; 2 gün
10 11 12 13 14 15 16
Concrete; 2 gün Formwork; 3 gün
MS2: Completion of
B Steel; 3 gün
17 18 19 20 21 22 23
Formwor k; 3 gün Concret e; 2 gün
MS3: Completion of
1
Staffolding; 4 gün
24 25 26 27 28 29 30
Fromwo rk; 4 gün
Staffolding; 4 gün
31
Fromwor k; 4 gün
Eylül 2020
Pazartesi Salı Çarşamba Perşembe Cuma Cumartesi Pazar
1 2 3 4 5 6
Fromwor k; 4 gün Steel; 5 gün
7 8 9 10 11 12 13
Steel; 5 gün Concret e; 2 gün
Completion of
Structu
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30