Professional Documents
Culture Documents
INTRODUCTION
HYDROLOGY
HEAD WORK
DESIGN OF CANAL AND CANAL STRUCTURS
IRRIGATION WATER DEMAND REQUIRMENT
WATER APPLICATION METHOD
DRAINAGE
CONCLUSION AND RECOMMENDATION
1. INTRODUCTION
1.1 Back Ground of Irrigation Development in Ethiopia
Ethiopia is believed to have considerable land and water resources for agriculture, which is a
major source of food production for the population of the nation and the prime sector for food
security. Even thougth Ethiopia is endowed with water resource that could be tapped and used
for irrigation; this country is already suffering from food storage ironically, because of the
increasing population and chronic drought occurring in most part of the country.
Irrigation development in Ethiopia dates back several centuries, if not millennia, while modern
irrigation was started by the implementation of commercial irrigated sugar estate in the early
1950. Despite huge irrigation potential of the country, only a little more than 6% is yet
developed. In order to insure food security at the household level for Ethiopians fast growing
population, small, medium and large scale irrigation infra-structure needs are to be developed. In
Ethiopia about 97703ha of land is developed under medium and large scale irrigation schemes.
These schemes are constructed during 60s and they are mainly constructed in Awash valley.
According to the irrigation development plan of the country a total of 274612ha land (147474ha
under large and medium scale, 127138ha under small scale) irrigation will develop until the year
2016. [Dr.Mekonen 2005]
Development of Irrigation contributes a valuable share in the production of agricultural products
which enhances the removal of food security problem & leads the economic growth of a country
where there are sufficient water resources for this purpose.
Different study document shows, in our country, there are sufficient resources of water that can
be utilized for various purposes. But only few percent of existing water resources is
underutilization. On other side there are a number of chronically food insecure families. This
may be due to lack of good attitude, skill & budget. Nowadays, the degrees of these problems are
slightly in the stage of minimizing as per activities of past indicate because of attention given to
irrigation practices by Ethiopian government & other concerned bodies.
Similarly, Melka-Gobera Irrigation Project study has been executed to increase the agricultural
product, its operation managed by farmers of the project area. It is a small scale irrigation
project. The project is located in Amhara regional state in South Wollo zone, in Argoba special
woreda.
At the project area, agriculture is the main pillar of the economy, which depends on the annual
crops. For the production of annual crops there is insufficient & non- uniform rainfall
distribution for the production of annual crops at this project area. Therefore, the study found out
that the existence of the promise of gathering additional agricultural product by irrigation. Again,
supplementing yearly crops by irrigation can be undertaken. Hence, it is possible gather product
twice & more per year. As per this study, executing the irrigation practices during dry & wet
seasons, the livelihood of population of the project can be improved due to the registered
economic growth as a result of agriculture product increment.
Estimation of peak flood which is necessary for the design of weir at the specified
outlet point.
Assessing the demand of water requirement for the selected crops under the project.
1.5 Methodology
The study has primarily focused to preparation & collection of the secondary data required to
undertake the given assignment at required standards. Interdisciplinary team of experts has
assessed and collected necessary data both at office and field survey/investigation. After the team
has moved to the field, detail field observation and investigation has been conducted to carefully
select and decide which site will be hydraulically best and then various topographic;
geotechnical, social and environment data had been collected.
The following methods /procedures, but not the only one, have been used in the accomplishment
of this service:
Site identification:
Topographic survey:
Surveying the head work ( as part of the whole topo map ) area with sufficient
radius to u/s and d/s reaches, using Total station
Flow estimation
Physical observation on flood mark indications and local information about high
flood and base flow condition of the river Analyzing the recorded rainfall data
and use water shed inputs for further.
2.HYDROLOGY
2.1 General
The knowledge of Hydrology used in engineering is used mainly in connection with
design and operation of hydraulics structures. The magnitudes of the flood expected over
spill way, in urban storm drainage system, are among the equations calling hydraulic
studies.The collection of relevant hydrological data and analysis should be the important
task to be conduct before any hydraulic structure is designed, however; the absence of
gauging stations in the catchment may make the hydraulic analysis of the project
difficulty.
The study of hydrology of any catchment of a river proposed for construction site play crucial
role prior to any form of factors that may cause effect on the design and planning of the project.
Hydrological data for the study area were found to be very limited, however some information
from kombolcha and Bati National Meteorological station on annual daily maximum stream
flows which is adjacent to the project area and also some more information from the manuals
related to the study area.
Cultivated lands
Grass lands
Forest lands
Exposed surface
2.3.2. Climate
There are two hydro-meteorological stations these are, Kombolcha and Bati. Kombolcha
metrological stations are nearest to the watershed and it includes all components of the climate
relative to the other stations are given as follows:
2.3.2.1 Rainfall
The monthly total rainfall data record extending between 1994 to 2008 is analyzed. Out of the
total 180 monthly records, there are no months having missing data. The data source is the
National Meteorological Services Agency (NMSA).The average annual rainfall at Bati Station is
about 944.5 mm. The monthly rainfall distribution as shown in Figure 2.1with better rainfall
distribution from July to September. Nearly 60 % of the annual rainfall occurs from July to
September.
Rainfall coefficients:
Less than 0.6 represent a dry month;
Greater than 0.6 represent a rainy month;
0.6 - 0.9 represent small rain;
1.0 - 1.9 represent big rains with moderate concentration;
2.0 - 2.9 represent big rains with high concentration.
Table 2.1 Monthly Rainfall and Rainfall coefficients
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Annual
Average 33.97 24.69 75.27 91.34 34.25 38.28 182.24 217.15 146.97 33.98 40.44 19.39 945
RC (mean) 0.43 0.31 0.96 1.16 0.44 0.49 2.32 2.76 1.87 0.43 0.51 0.25
Accordingly, July and august represents big rainfall with high concentration while Moderate concentration
of rainfall is in September.
2.3.2.2Temperature
Temperature is an important weather element which indicates the relative degree of molecular
activity, or heat, of a substance. Several factors influence temperature of the area latitude,
altitude, distance from large water bodies, direction of prevailing wind, etc. Maximum
temperature usually occurs on day time and minimum temperature during night. Temperature is
normally decreasing with increasing altitude. Maximum temperatures during the day are
important factors to determine potential evapo-transpiration. Recording minimum temperature is
useful to identify the occurrence of frost, which damages the growth of plants. The temperature
of the project area is estimated from Bati station. Therefore, the mean, maximum, and minimum
annual temperature of the project area as shown in Table 2.2 is 21.54, 31.8, and 10.1oC
respectively. Maximum temperatures occur in the months May and June and minimum
temperatures September - November.
Table 2.2: Estimated Monthly Average Temperatures of Bati
Elemen Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Yearly
t Average
Tmin 12.2 13.9 15.8 16.7 18.2 18.2 17 15.8 12.6 10.4 10.1 14.4 14.61
Tmax 26.3 27.5 29.4 31.2 31.8 30.3 29 29 27.7 26.3 25 28.2 28.48
Tavg 19.25 20.7 22.6 23.95 25 24.25 23 22.4 20.15 18.35 17.55 21.3 21.54
1 1953 55.3
2 1954 54.6
3 1955 59
4 1956 41
5 1957 61.9
6 1958 53.6
7 1959 63
8 1960 41.2
9 1961 54.5
10 1962 51.4
11 1963 51.2
12 1964 76
13 1965 34.2
14 1966 41
15 1967 65
16 1968 53.5
17 1969 47.6
18 1970 59.5
19 1971 45.1
20 1972 43.4
21 1973 15
22 1974 58.1
23 1975 94.5
24 1976 39.5
25 1977 60.7
26 1978 48.9
27 1979 56.4
28 1980 38
29 1981 62.3
30 1982 58
31 1983 82.8
32 1984 49.6
33 1985 62.4
34 1986 42.8
35 1987 50.5
36 1988 67.9
37 1989 74.8
38 1990 59
39 1991 42.2
40 1992 52.4
41 1993 52.4
42 1994 58.5
43 1995 33.8
44 1996 42.7
45 1997 54.3
46 1998 68.4
47 1999 61.2
48 2000 50.6
49 2001 71.6
50 2002 64.4
51 2003 60.9
52 2004 46.8
53 2005 70.4
54 2006 64.8
∑Y
∑ Y =93.19 mm Ym= =1.726 ∑ ( Y −Ym )2=0.7676 ∑ ( Y −Ym )3=−0.1540
N
2
N ∑ ( Y −Ym )3 54∗(−0.1540)
Sy=
√
∑ ( Y −Ym )
¿−1.731
( N −1 )
=0.1203 Cs= =
( N −1 )( N −2 ) Sy ( 54−1 )∗ (54−2 )∗0.12033
3
The lowest recorded daily heaviest rain fall data is 15 mm in the 1973 which is less than the
threshold value of lower outliers. Hence the daily heaviest rain fall data recorded in 1973, 15mm,
departs significantly from the threshold value of low outliers.
Table 2.9: Revised data of daily heaviest rainfall (after outlier tests)
Heaviest
S/n Rainfall Descendin Y=logX
Year (Y-Ym)^2 (Y-Ym)^3 (Xi-Xm)^2
o (mm/day)=X g order i
i
1 1953 55.3 94.5 1.975 0.05727 0.013704 0.183
2 1954 54.6 82.8 1.918 0.03309 0.006019 1.273
3 1955 59 76 1.881 0.02093 0.003029 10.704
4 1956 41 74.8 1.874 0.01898 0.002615 216.923
5 1957 61.9 71.6 1.855 0.01411 0.001676 38.090
6 1958 53.6 70.4 1.848 0.01242 0.001384 4.530
7 1959 63 68.4 1.835 0.00979 0.000968 52.878
8 1960 41.2 67.9 1.832 0.00917 0.000878 211.072
9 1961 54.5 65 1.813 0.00590 0.000453 1.509
10 1962 51.4 64.8 1.812 0.00569 0.000429 18.734
11 1963 51.2 64.4 1.809 0.00529 0.000385 20.506
12 1964 76 63 1.799 0.00400 0.000253 410.942
13 1965 34.2 62.4 1.795 0.00349 0.000206 463.468
14 1966 41 62.3 1.794 0.00341 0.000199 216.923
15 1967 65 61.9 1.792 0.00309 0.000172 85.964
16 1968 53.5 61.2 1.787 0.00256 0.000130 4.965
17 1969 47.6 60.9 1.785 0.00235 0.000114 66.069
18 1970 59.5 60.7 1.783 0.00221 0.000104 14.226
19 1971 45.1 59.5 1.775 0.00147 0.000057 112.961
20 1972 43.4 59 1.771 0.00121 0.000042 151.987
21 1974 58.1 59 1.771 0.00121 0.000042 5.625
22 1975 94.5 58.5 1.767 0.00096 0.000030 1503.245
23 1976 39.5 58.1 1.764 0.00079 0.000022 263.358
24 1977 60.7 58 1.763 0.00075 0.000020 24.718
25 1978 48.9 56.4 1.751 0.00023 0.000003 46.626
26 1979 56.4 55.3 1.743 0.00004 0.000000 0.451
27 1980 38 54.6 1.737 0.00000 0.000000 314.293
28 1981 62.3 54.5 1.736 0.00000 0.000000 43.187
29 1982 58 54.3 1.735 0.00000 0.000000 5.161
30 1983 82.8 53.6 1.729 0.00005 0.000000 732.877
31 1984 49.6 53.5 1.728 0.00006 0.000000 37.556
32 1985 62.4 52.4 1.719 0.00028 -0.000005 44.512
33 1986 42.8 52.4 1.719 0.00028 -0.000005 167.141
34 1987 50.5 51.4 1.711 0.00063 -0.000016 27.335
35 1988 67.9 51.2 1.709 0.00072 -0.000019 148.150
36 1989 74.8 50.6 1.704 0.00102 -0.000033 363.730
37 1990 59 50.5 1.703 0.00108 -0.000035 10.704
38 1991 42.2 49.6 1.695 0.00165 -0.000067 183.015
39 1992 52.4 48.9 1.689 0.00219 -0.000103 11.078
40 1993 52.4 47.6 1.678 0.00342 -0.000200 11.078
41 1994 58.5 46.8 1.670 0.00434 -0.000286 7.682
42 1995 33.8 45.1 1.654 0.00672 -0.000550 480.850
43 1996 42.7 43.4 1.637 0.00973 -0.000960 169.737
44 1997 54.3 42.8 1.631 0.01096 -0.001147 2.040
45 1998 68.4 42.7 1.630 0.01117 -0.001181 160.572
46 1999 61.2 42.2 1.625 0.01228 -0.001361 29.939
47 2000 50.6 41.2 1.615 0.01470 -0.001782 26.299
48 2001 71.6 41 1.613 0.01521 -0.001876 251.911
49 2002 64.4 41 1.613 0.01521 -0.001876 75.198
50 2003 60.9 39.5 1.597 0.01947 -0.002716 26.746
51 2004 46.8 38 1.580 0.02444 -0.003822 79.715
52 2005 70.4 34.2 1.534 0.04084 -0.008255 215.259
53 2006 64.8 33.8 1.529 0.04294 -0.008897 82.296
2
N √
∑ X =2953.6 mm , Xm= ∑ X =55.73 , ∑ ( X− Xm )2=7655.99 , σn−1= ∑ ( X−Xm ) =12.13
( N −1 )
∑Y
∑ Y =92.01 mm , Ym= =1.736 , ∑ ( Y −Ym )2=0.4598 3
∑ ( Y −Ym ) =−0.00226
N
2
N ∑ ( Y −Ym )3 53∗(−0.00226)
Sy=
√
∑ ( Y −Ym )
¿−0.054
( N −1 )
=0.094 Cs= =
( N −1 )( N −2 ) Sy ( 53−1 )∗( 53−2 )∗0.094 3
3
T 50
YT=-(ln (ln( ) ¿) =-(ln (ln ( ¿ ¿ ¿=3.9
(T −1) 50−1
YT −Yn 3.9−0.5497
KT = = =2.8738
Sn 1.1658
The maximum probable point rain fall of 50 years return period is 90.589mm.
III. Log Normal distribution method
XT =Ym+ KT∗Sy , where: KT=frequency factor
2.51557+0.01033 w 2
KT =w−
1+1.143279 w+ 0.1992 w2 +0.00131 w3
1
w=(ln (1/ pr 2))0.5=2.797 where , pr= Where: Pr=probability
50
XT =Ym+ KT∗Sy=1.736+ 2.054∗0.094=1.929
XT=101.929=84.93mm
The maximum probable point rain fall of 50 years return period is 84.93mm.
IV. Log Pearson Type III Distribution Method.
In this method the Varity is first transformed into logarithmic form ( base 10 ) and the
transformed data is then analyzed . If X is the Varity of random hydrologic series then
the series of Y varieties where:
Y = log X are obtained, for this Y series for any recurrence interval T.
YT =Ym+ KT∗Sy
Where: KT = a frequency factor which is a function of T and the coefficient of skew ness, CS.
2
Sy=
√ ∑ ( Y −Ym )
( N −1 )
= standard deviation of the Y verity sample
N ∑ ( Y −Ym )3
Cs= =¿-0.054,
( N −1 )( N −2 ) Sy 3
Where: Ym =mean of the value ,N = sample size
The variation of KT =f (CS, T) is given in ----------- the annex -------.
For recurrence interval T=50
KT =f (CS, T) =f (-0.054, 50) =2.02484
YT =Ym+ KT∗Sy=1.736+2.02484∗0.094=1.926
1.926
XT=10 =84.4mm
The maximum probable point rain fall of 50 years return period is 84.4mm.
VI. Pearson Type III Distribution Method.
For the Pearson type III, the same procedure applies like log Pearson type III except that if Y is
the log series it have to be changed in to X variables, and their mean and standard deviation
XT =Xm + KT∗σn−1=55.73+ 2.02484∗12.13=80.29mm.
2.4.2.1 Selection of Distribution (Testing For Goodness of Fit)
The validity of probability distribution function proposed to fit the empirical frequency
distribution of a given sample may be tested analytically by D-index test. The D-index tests for
the comparison of the fit of various distributions in the upper tail are given by:
D-index = (1/x) ∑Abs (xi-ẍ)
Where xi and ẍ are the ith highest observed and computed values for the distribution respectively.
The distribution giving the least D-index is considered to be the best fit distribution
Table 2.12
176.19
D-index= =3.16
55.73
2. Log normal Distribution
Table 2.14
Rank Yi p=(m/n+1) Kt ẍ Abs(Yi- ẍ)
1 1.975 0.019 3.665 2.32 0.34
2 1.918 0.038 2.898 2.19 0.27
3 1.881 0.057 2.435 2.11 0.23
4 1.874 0.075 2.097 2.07 0.20
5 1.855 0.094 1.828 2.03 0.17
6 1.848 0.113 1.602 2.00 0.15
Total 1.37
1
|(Yi− ẍ)|
Ym ∑
D-index=
1.37
D-index= =0.79
1.736
3. Log Pearson Type III
The difference from Log normal distribution is only the value of Kt.
Kt=Z+(Z^2-1)k+1/3(z^3-6*Z)K^2-(Z-1)k^3+ZK^4+1/3K^5
Where K=Cs/6 =-0.05095
Z=W-(2.51557+0.01033W^2)/(1+1.143279W+0.1992W^2+0.00131W^3)
Where W= (ln(1/pr)^2)^0.5
Table 2.15
Rank Yi p=(m/n+1) Kt ẍ Abs(Yi- ẍ)
1 1.975 0.019 3.553 2.31 0.33
2 1.918 0.038 2.832 2.18 0.27
3 1.881 0.057 2.391 2.11 0.22
4 1.874 0.075 2.066 2.07 0.19
5 1.855 0.094 1.807 2.02 0.17
6 1.848 0.113 1.588 2.00 0.15
Total 1.34
1
|(Yi− ẍ)|
Ym ∑
D-index=
1.34
D-index= =0.77
1.736
4. Person type III
Table 2.16
Rank Xi p=(m/n+1) Kt ẍ Abs(xi- ẍ)
1 94.5 0.019 3.553 137.60 43.10
2 82.8 0.038 2.832 117.15 34.35
3 76 0.057 2.391 105.00 29.00
4 74.8 0.075 2.066 99.86 25.06
5 71.6 0.094 1.807 93.51 21.91
6 70.4 0.113 1.588 89.66 19.26
Total 172.69
The difference from normal distribution is the value of Kt found as Log Pearson Type III.
1
|( xi−ẍ )|
Xm ∑
D-index=
172.69
D-index= =3.1
55.73
5. Gamble Distribution
ẍ =Xi+Kt*σn-1
Kt= 0.7801*(0.5772+ln(ln(T/(T-1))))
Table2.17
Rank Xi p=(m/n+1) Kt ẍ Abs(xi- ẍ)
1 94.5 0.019 2.639533 126.52 32.0
2 82.8 0.038 2.091271 108.17 25.4
3 76 0.057 1.767306 97.44 21.4
4 74.8 0.075 1.535095 93.42 18.6
5 71.6 0.094 1.353097 88.01 16.4
6 70.4 0.113 1.202806 84.99 14.6
Total 128.4
1
|( xi−ẍ )|
Xm ∑
D-index=
128.4
D-index= =2.3
55.73
Comparing the value of D-index for the above calculation, we get the least value for Log Pearson
type III; this indicates that Log Pearson type III distribution is the best fit probability distribution
to the data. But the rain fall obtained by Gamble distribution is greater than that of log Pearson
type III distribution so to be more safe take Gambles distribution, in addition Gambles is the
most common used method of distribution for practical work. Hence peak daily point rainfall of
50 years return period is 90.59mm.
2.4.3 Design flood estimation
2.4.3.1 Estimating Time of Concentration
The time of concentration Tc is defined as the time required for a drop of water falling on the
most remote part of the drainage basin to reach the basin outlet.
To calculate the time of concentration the water course is divided according to its slope .The
longest water course is divided into different intervals and the time of concentration is computed
using Kirpich formula.
L3 0.385
Tc=∑Tci ,Where Tci=0.948( )
∆H
Where: L=water course (stream) length in km
∆H=elevation difference
Tci= Time of concentration for each divided stream length
Tc= total time of concentration
From the total catchments area starting remotest water shed point to the out let the time of
concentration is calculated as follow.
Table 2.18: Time of concentration computation
Time of
Elevati
concentration in
Length on
(hr)=
(km.) Differen 3 0.385
ce in m 0.948( L )
∆H
0.000 0.00 0.000
0.291 5.86 0.115
0.134 9.88 0.039
0.581 14.01 0.183
0.327 59.06 0.054
0.186 36.10 0.034
0.636 112.09 0.091
0.650 39.29 0.140
0.093 24.47 0.018
0.867 59.84 0.166
0.171 10.15 0.051
1.123 73.84 0.207
0.979 5.93 0.466
0.090 18.86 0.019
0.130 9.98 0.037
0.090 0.60 0.072
0.519 6.44 0.217
0.183 13.11 0.049
0.332 8.40 0.117
0.131 0.40 0.129
0.089 3.12 0.038
0.649 18.85 0.186
0.911 26.99 0.239
0.257 7.96 0.089
0.182 0.01 0.687
0.130 11.51 0.035
0.410 15.43 0.118
0.273 0.92 0.218
0.259 6.27 0.098
0.726 20.93 0.203
0.388 9.32 0.135
0.183 6.15 0.066
0.130 0.96 0.091
0.274 4.59 0.118
0.387 12.37 0.120
0.183 4.21 0.077
0.517 5.52 0.229
0.364 9.55 0.124
0.129 6.08 0.044
0.456 9.16 0.163
0.330 7.46 0.122
0.205 3.02 0.099
0.545 11.70 0.183
0.130 3.18 0.057
1.184 26.91 0.324
0.111 3.52 0.046
0.002 4.49 0.000
16.918 6.116
The total time of concentration Tc=6.116hr is greater than 3hr.Hence the recommended
minimum practical time increment is one hour (1hr).
Rainfall Profile.
Rainfall profile is the distribution of the proportion of design rainfall during every incremental
time on the watershed area during the 24 hours duration. Well-developed models are needed to
determine such an event for the selected basin area. But there are no sufficient modeling studies
in the vicinity and adaptation of standard curves has been taken as the only option. Designer of
this project has adopted the standard curve from Design Guidelines for Small Scale Irrigation
Projects in Ethiopia. With the aid of rainfall profile versus duration curve the percentages of
design rainfall distribution on the catchment area are computed for the first most intensive storm
duration from the graph as follows:
Figure: 2.2
The areal to point rainfall is found from the table for the given catchment area 73.02956Km
square and duration by the interpolation which is found between 50 and 75.
Table 2.19
Areal Rainfall
As the area of the catchment gets larger, coincidence of all hydrological incidences becomes
less and less. This can be optimized by changing the calculated point rainfall to aerial rainfall.
The conversion factor is taken from standard table that relate directly with the size of watershed
area and type of the gauging station. (IDD manual).
For the case of Sewer3 irrigation project, Total
watershed area = 73.02956 Km2
Type of gauging station = Daily rainfall (24 hr.)
Aerial to point Rainfall ratio (%) is found from the above table for the given catchment area and
duration by interpolation.
Rainfall profile in (mm) =Rainfall profile (%) x Daily point rainfall (mm)
Area rainfall (mm) =Areal to point rainfall ratio (%) x rainfall profile (mm).
Table 2.20: Design rain fall arrangement for design rain fall, p=90.59mm
Daily Rainfall Rain Arial to Area Increme Descen Re
point rain profile fall point R.F rain fall ntal ding arranged
Duratio fall (mm) (%) profile ratio (%) (mm) Rain fall order order
n (mm) (mm)
Hr Mm % Mm Mm Mm mm Mm
0-1hr 45 40.77 67.31 27.44 27.44 1 6
1-2hr 58 52.54 75.24 39.53 12.09 2 4
2-3hr 67 60.70 79.24 48.09 8.56 3 3
90.59
3-4hr 72 65.22 82.16 53.59 5.49 4 1
4-5hr 76 68.85 84.08 57.89 4.30 5 2
5-6hr 79 71.57 83.31 59.62 1.73 6 5
The curve number of the catchment was determined based on the guide prepared by the US Soil
Conservation service. Based on the hydrologic soil group, land cover, antecedent moisture
content and treatment of the catchment the curve number was determined for different plots. The
results of the curve number assigned for each plot and the corresponding catchment
characteristics are presented in the watershed study report of this project. Accordingly the curve
number was found to be 92.115.
2.4.3.3 Estimation of direct runoff
25400 25400
S= −254= −254=21.7423
CN 92.115
Substituting the value of “S” in the above equation,
( I −0.2∗S)2 (I −0.2∗21.74 )2 (I −4.348)2
Q= = =
( I + 0.8∗S) ( I +0.8∗21.74) (I +17.392)
Where: S=Maximum potential difference b/n rain fall and runoff (mm)
Q= Direct surface runoff (mm)
I=Accumulated design rain fall (mm)
Table2.21: Direct runoff corresponding to incremental rain fall
Time Rearranged Incremental Accumulative
order Design Rain Rain fall (mm) Direct runoff (mm)
fall (mm) Accumulative Incremental
Tp=Time to peak.
120
Discharge (m^3/s)
100
80
60
40
20
0
0 2 4 6 8 10 12 14 16 18
Time(hr)
Q1 Q2 Q3 Q4 Q5 Q6 QTOTAL
The depth of approach head (weir height/head of water above the crest i.e. h/Hd) and
submergence need to be checked whether a correction factor needs to be applied for the assumed
coefficient of discharge or not.
Check based on approach depth
Q=CdLHe3/2 C=2.225
He= (Qd/CdL) 2/3 = (137.174/2.225*17.36)^2/3
He=2.328 m
Q
The approach velocity, Va= …………………………………………………… 1
L(Hd+ p)
Va2 Va2
where, Hd=He- => =He-Hd………………………………………2
2g 2g
Q 137.174
But Va= = by subistuting velocity head in equation(2) we get:
L ( Hd+ p ) 17.36 ( Hd+0.5 )
2
137.174
( ) ∗1
17.36 ( Hd +0.5 )
=He−Hd
2∗9.81
-Hd^3+1.328Hd^2+2.078Hd-2.6=0
By trial and error, Hd will be 1.129m.
Cd Q L Hd Ha=(Q/L*(P+Hd))^2/(2*g) He-Hd h/Hd
2.225 137.174 17.36 1.129 1.225 1.199 2.126
h
Since =2.126>1.33, C=2.225 is correct based on approach depth condition.
Hd
Check based on d/s apron and submergence effect
U/s HFL = U/s bed level +weir height+Hd
=1189.8+2.4+1.129=1193.329
U/s TEL =U/s HFL +approach velocity head
=1193.329+1.225=1194.554m
D/s HFL=River bed +Tail water depth…………1
Tail water depth= D/s HFL- River bed, where D/s HFL=1192.105 which
is given.
=1192.105-1189.8=2.305
D/s TEL=D/sHFL+V2/2g, where, the velocity head is Computed in the
above table which is 1.225m.
D/sTEL=1192.105+ 1.225=1193.33m
hd=U/S TEL-D/S HFL=1194.554-1192.105=2.449
(hd+d)/He= (2.449+2.305)/2.328=2.042,
where, d=Tail water depth=2.305m
Hence 2.042>1.7, the d/s apron interference for Cd is negligible effect.
Afflux=U/s TEL-D/S TEL
Afflux =1194.554-1193.33m =1.224m, so it is safe.
4.
x Y
0.0000 0.000
-0.1000 0.011
-0.2000 0.051
-0.2646 0.123
Downstream Profile
The x and y coordinates of the curved surface of the downstream profile of the weir was
determined by the following formula (US Corps of Arms-for vertical weir).
X1.85=2*Hd0.85*Y…………..2
According to the US Corps of Arms the downstream profile needs to be constructed up to the
point where dy/dx of the above equation results the slope of the tangent profile which is usually
taken as 1 for construction simplicity and stability. To have efficient curvature, it is better to
determine the tangent point.
dy/dx=v/h=dy/dx=1/1
dy/dx=1.85*X^(1.85-1)/2Hd^0.85/1
X0.85=2.217/1.85, X= (2.217/1.85)^0.85
X=1.237
y=0.669
This point was found to be (1.237, 0.669m). The full downstream profile determined by the
above equation is presented in the table below using 0.10m interval in the x direction. The
downstream tangent profile extends from the point (1.237, 0.669m) where the curved profile
ends to the point h/8 above the toe of the weir (determined to be 0.30m). h is the height of the
weir. It has a slope of 1:1 (H: V).The foot curve (circular curve) profile needs to be made from
the end of the tangent profile to the point tangent to the weir toe level with a radius of 0.60m
(h/4).
Table 4.6: Coordinates of the d/s weir profile with respect to the weir crest level
X Y=X1.85/2*Hd0.85
0.000 0.000
0.100 0.00637
0.200 0.02297
0.300 0.04863
0.400 0.08280
0.500 0.12512
0.600 0.17531
0.700 0.23317
0.800 0.29850
0.900 0.37118
1.000 0.45106
1.1000 0.53804
1.200 0.63200
1.237 0.66900
Figure 3.2: Weir profile
3.8 Hydraulic Jump Computation
In the determination of pre and post jump depths the basic energy equation between upstream
face of the weir and the point where the hydraulic jump starts to form (where depth y 1is
achieved). The head loss between these two points due to friction is assumed to be zero. This is
described in fig 4.5 below.
Accordingly: h + He = Y1 + Hv
h + He = Y1 + (q2/2gy12)……………………..……………………………1
Where: h = Weir height
He = Head over the crest including the velocity head (m)
Hv = Velocity head at the point where hydraulic jump starts to be formed (m) at Y1
= (q2/2gy12)
q = Discharge intensity (m3/sm)=Qd/L
g = acceleration due to gravity=9.81m2/s
From equation 1 above the value of Y1 was determined for different values of q as in table
4.7.The value of Y2 was determined by the following formula:
Y1
Y 2= ∗¿………………………………………………….2
2
q
where: f = where: f=Froude number
√ gy 13
To illustrate for the peak discharge assume the river bed lowered by about 0.4m from the original
river bed due to retrogression i.e. 1189.8-0.4=1189.4. Hence neglecting the minor loss and
Appling equation 1 above the value of y1 is determined as follow by iteration.
2.4+2.328+0.4=y1+v12/2*g
5.128=y1+(q/y1)2/2*g where q=Q/L= 137.174/17.36=7.90
19.62y13-100.61136y12+62.41=0, by trial and error or by using iteration y1=0.864
y1 19.62y13-100.61136y12+62.41=0 Remark
Figure 3.3: Energy equations between upstream face of the weir and the point where the
hydraulic jump starts to form.
3.9 The relation b/n tail water and sequent jump depth curve
and its Implications
The relation of the tail water and jump depths for different discharges determines the scouring
effect of the flow on the river bed and bank. The tail water depth is lower than the jump depth for
higher discharges and is lower for low discharges. This implies the jump depth will have a
velocity that will scour the bed and banks of the river unless sloping apron with cutting of the
river bed is provided. The maximum difference between the jump and tail water depths at the
design discharge is 1.392m and the calculated jump depth is 3.697m. Therefore excavating the
bed of the river for a length of 15m with a depth of 1.392m should be done up to which the jump
is going to occur.
3.10 Design of impervious and pervious apron
3.10.1 Determination of cutoff (scour depth)
Depth of scour below high flood level
1 /3
q2
R=1.35( ) , f=1.76√ d=1.76*√ 18.74=7.62, where, d is average particle size in (mm)
f
2 1/ 3
7.9
R=1.35(
7.62 )
=2.72
When a hydraulic jump forms in the basin under the maximum flow condition (case (b)) the
thickness of concrete is determined from:
4 Hr
t= ( ), where, H r = u/s HFL-cistern level-y1
3 G−1
=is the uplift head at the point of the hydraulic jump on the stilling basin
Point G Hw Lp L Hr t
A 2.3 3.31 6.7 30 2.57 2.64
B 2.3 3.31 11.53 30 2.04 2.092
C 2.3 3.31 16.53 30 1.49 1.528
D 2.3 3.31 21.53 30 0.93 0.953
The concrete thickness to be adopted for the structure is the greater of the two cases. Hence,
maximum flow condition is adopted, that means the second case.
3.10.4.2 Check for the exit gradient
b=Total length of impervious apron, assume b= 20.5
d2=d/s cutoff depth=3.00m, Hw=3.31
Hw
∗1 1
GE= d 2 ………………………………1 Where: λ= (1+ √ 1+α 2)
2
π∗√ λ
b 20.5
α= = =6.83
d2 3
1
λ= ( 1+ √ 1+ 6.832 )=3.95
2
3.31/3∗1
GE= =0.1767
π∗√ 3.95
The maximum permissible exit gradient for mixture of gravel, boulder, cobble and sand is less
than1/4 or 0.25 and Lanes creep coefficient is 2.5 to3.0. Which is greater than the GE=0.1767
then the structure is safe against piping.
3.10.4.3 Checking the thickness of the impervious floor by khoslas
Pressure at key points of u/s cutoff
1 b 20.5
λ= ( 1+ √ 1+ α 2 ), where: α = = =20.5
2 d1 1
1
= ¿
2
100 λ−2
фC1=100- фE, Where фE= cos−1 ( ¿ )¿
π λ
=100-19.722
100
=80.278% = ∗35.5
180
=19.722%
100 λ−1
фD1=100- фD, Where фD= cos−1 ( ¿ )¿=
180 λ
=100-13.833
100
=86.167% = ∗24.9
180
=13.833%
Ct=correction for thickness фC1
= ( фD 1−ф
d1
C1
)∗t=
86.17−80.28
1
∗0.5=2.94where 0.5 is the nominal thickness of u/s apron.
d +D D
Cif=19*(
b
)¿
√
b'
3
=19*¿)¿
√ 20
=1.436
Corrected фC1=80.28-2.94-1.436
= 75.897%
The residual pressure head at C1=Hw* Corrected фC1
=3.31*0.759=2.51229
2.51229
Floor thickness at point c1= =1.9325 m where 2.3=G
2.3−1
From practical point of view, the u/s apron (impervious floor) mostly covered by river deposit,
one thickness cover of the structure, and uplift pressure is also counter balanced by the weight of
the standing water. Hence provide nominal thickness of 0.5m.
Pressure at key points of d/s cutoff
1( b 20.5
λ= 1+ √ 1+ α 2 ), where α = = =6.83
2 d2 3
1
= ¿
2
100 −1 λ−2 100
фE= cos ( ¿ )¿ = ∗60.4 ==33.56
π λ 180
100 λ−1 100
ф D= cos−1 ( ¿ )¿ = ∗41.67 =23.13
180 λ 180
Ct=correction for thickness фE
= ( фE−ф
d2
D
)∗t= 33.56−23.15
3
∗0.78=2.705
Corrected фE=33.56+2.705+0.829
= 40.15%
The residual pressure head at E=Hw* Corrected фE
=3.83*0.4015=1.538
1.538
Floor thickness at the E1= =1.18 m
2.3−1
By assuming the uplift pressure is usually varying linearly from u/s to the d/s the pressure head
(uplift) at intermediate are calculated in the table below.
Table 4.8 Thickness correction
These are the forces acting on the weir due to the reservoir created upstream of the overflow
section, tail water, and the dynamic pressure created at the toe due to change in the momentum
of the flow. The external water pressure on the upstream face of the weir is calculated for sever
case i.e. for the design discharge level. The water pressure that could be exerted on the weir body
due to a change in momentum as the water flows over the curved toe surface was also calculated
and incorporated in the analysis. This is calculated based on the basic momentum formula as
shown in table 4.9. These two forces are labeled as Pwdv and Pwdh.
Uplift pressure
The sub surface flow (seepage) may build up uplift pressure under the foundation especially on
pervious foundation. This effect is also considered in the stability analysis of the structure.
Silt pressure
As a result of the weir construction the water surface of the flow will be substantially reduced
which will enhance deposition of silts and soils as well as cobles and stones. This will produce
pressure on the upstream section of the weir. This effect is considered in the stability analysis.
The worst condition, silt level at the crest level, is considered in the analysis. An average value
of 10.84KN/m3 was used for the submerged unit weight of the silt and 300 for internal angle of
friction. The silt pressure is computed using the widely used Rankin’s formula.
Psilt= gs *h2*(1-sinФ)/(1+sinФ))/2
Where: Psilt= Silt pressure
gs = the unit weight of the silt
h= the height of the silt to be deposited= weir height
Ф=angle of internal friction
The stability analysis of the weir against all disturbing forces is checked for two critical
conditions, i.e. for maximum flood condition and for no tail water condition.
a. Maximum flood condition
Consider summation of momentum around counter clock wise direction is +ve and clock wise
direction is –ve and unit weight of concrete is 23KN/M^2 and water is 10KN/M^2.
Magnitude of forces
(KN) Lever arm Moment at "o"(KN.M)
Force designation Vertical Horizontal in m Resisting Disturbing
Weight of weir
and impervious
apron
W1 5.75 24.25 139.44
W2 54.05 22.15 1197.21
W3 44.85 22.80 1022.58
W4 272.09 17.42 4738.45
W5 219.65 12.50 2745.63
W6 154.10 7.50 1155.75
W7 138.00 2.50 345.00
W8 26.45 0.25 6.61
W1' 20.98 23.04 483.29
W2' 20.61 22.64 466.57
W3' 17.94 22.24 398.99
W4' 14.44 21.84 315.46
W5' 10.76 21.44 230.78
W6' 7.18 21.04 150.98
W7' 3.50 20.64 72.16
W8' 0.28 20.24 5.59
W1'' 0.51 23.11 11.69
W2'' 0.69 22.57 15.58
W3'' 1.33 22.17 29.58
W4'' 1.79 21.77 39.06
W5'' 1.79 21.37 38.34
W6'' 1.79 20.97 37.63
W7'' 1.79 20.57 36.91
W8'' 1.61 20.17 32.48
W9'' 0.07 19.90 1.37
Hydrostatic
Pressure
Pw2 -28.80 1.98 57.02
Silt pressure
Psilt -10.40 1.98 20.58
Hydrodynamic
pressure
Weight of water
Ww1 43.94 23.85 1047.97
Weight of silt
Ws 33.82 23.85 806.63
Uplift pressure
Pu1 -284.52 12.25 3485.31
Pu2 -148.85 16.40 2441.00
sum 666.41 39.20 15571.70 6003.92
Checking for sliding Checking for overturning
∑ Fv 666.41 ∑MR 15571.70
Fs=μ = =10.2>1.5 OK Fo= = =2.6>1.5 OK
∑ FH 39.20 ∑ MD 6003.92
Checking for tension development
B ∑ MR−∑ MD 15571.70−6003.92
e= −x where : x= = =14.36
2 ∑ FV 666.41
B 24.5 B 24.5
e= −x = −14.36=−2.11< = =4.08 … … … … . OK
2 2 6 6
Checking for bearing capacity
Maximum base pressure=ΣV/B*(1+6*e/B)
=1099.77/24.5* (1+6*7.31/24.5)
=124.9 KN/m2<200KN/m2 so it is safe.
B 2 B 2
e= −x = −0.96=0.04 < = =0.33 ……….OK
2 2 6 6
3.12.2 Scouring sluice
Souring sluice openings (a size 1.4x 1.00 meters) have been provided in the body of the
diversion weir close and adjacent to the head regulator. The provision of this opening would
allow the silt laden lower layer of water to pass out, reduces silt entry into the canal, passes low
floods, guide the lean flow to the head regulator, and passes also normal floods there by reducing
the afflux and subsequently slightly lowering the highest flood level. The discharge passing
through the under sluice is determined by the discharge formula:
Q=Cd∗A∗√ 2∗g∗he ………………………………..1
Where: Cd= Coefficient of discharge=0.60 for broad crested weir
L= Crest length=1m
H=gate height=1.4m,where:A=1*1.4=1.4m^2
he=head causing flow=Crest level-center of opening
= 1192.20-(1189.8+1+0.7), sill level =1m above the river bed level,FB=0.7
= 0.7m
Q=0.60*1.4*(2*9.81*0.7) ^0.5=3.11m3/s
Therefore the cross section and discharge that can pass through the under sluice is computed to
be 1.4m2 and 3.11m3/s respectively. It is believed in different irrigation literatures that the
discharge passing the under sluices need to be at least 5 times the dry base flow of the river.
Compared to the base flow during the dry periods the discharge that can pass through the
assumed under sluice opening is found to be 5 times more the dry period’s base flow (which is
(5*150/1000)=0.75m3/s). Therefore the assumed under sluice opening which is 1.4mX1m was
accepted.
3.12.2.1 Design of under sluice gate
The gate of the under sluice is to be vertical sheet metal of 1.4m x 1.00m for the closure of the
opening space. Providing some extra dimensions for groove insertion. Gross area of sheet metals
for the under sluice gate will be 1.45m x 1.1m (allowing 5cm insertion for grooves). The grooves
are to be provided on the walls using angle iron frames at the two sides of the gate openings. The
gate (sheet metals) is provided with stiffening angle irons. A vertical raised gate is designed for
the under sluice. These gates simply raised by farmers without spindle.
3.12.2.2 Design of under sluice gate thickness
Hydrostatic water pressure, Pa=1.4*10=14KN/m2
Hydro Static water Pressure for head of 1.4m at the bottom of the gate=14kN/m2=1.4N/cm2
The allowable tensile and bending stress of the steel during wet conditionδ =0.45*300=135
K∗P∗a2
N/mm2=13500N/cm2.Hence bending stress in flat plate should be, δ =
100∗S2
Where S=thickness of the sheet metal (cm)
P=Hydrostatic pressure (N/Cm)=1.4N/cm2
K=Non-dimensional factor
a =minor support length which related with K
1.4
For b /a= =1 , K=45.06 from the table for different supporting condition.
1
K∗P∗a2 0.5 45.06∗1.4∗1002 0.5
S=( ) =( ) =0. 68 cm
100∗δ 100∗13500
Hence considering incoming boulders and transported materials, take S=6.8 mm
Weight of gate= gsteel *s*a*b, Where s=thickness (m) =0.0068 m
h=gate height (m)=1.4m ,b=width=1m ,gs=Density of steel =7800kg/m3
Weight of gate=7800*0.0068*1*1.4=74.3kg.
Hence the weight of the sheet metal gate is light; we can use stiffening materials for further
safety. 3.12.3 Head Regulator
The head regulator is located on both side of the weir body. The intake sill level is fixed based on
route alignment and optimal elevation to command the possible irrigable area. Hence, the intake
sill level is fixed at 1.8m above the minimum river bed level at weir axis. The minimum river
bed level and intake levels are 1189.8 and 1191.6 m.a.s.l. respectively. The lean flow was
measured on April 20/2010 is 150 l/sec. In usual case, this time is the driest time. Hence, this
figure is the real representative of the lean flow. Therefore this figure indicates that, the river has
a good flow. Hence, the main canal on the left and the right is designed to serve an area of 50.5
and 14.5 hectares of land with a design discharge of 111.1 l/sec (0.111m^3/s)and 31.9
l/sec(0.0319m^3/s) respectively at the canal head. The maximum duty for the locality is 2.2
l/s/ha.The flow through the canal head regulator is supposed to be orifice flow, and hence the
coefficient of discharge through the head regulator, Cd=0.6. The water level (pond level) of the
canal head regulator to the weir side assumed equal to the weir crest level i.e. 1192.2 masl, and
the water level difference, he, between pond level and center half of intake slot is 0.30m. So the
discharge, Qd, through the main canal on the left and the right is determined as follows by:
Q=Cd∗A∗√ 2∗g∗he
The capacity of opening provided to the left is checked as follow;
Coefficient discharge (Cd)= 0.60
Opening area, A= 0.6X0.6= 0.36 m2
Acceleration due to gravity (g) =9.81 m2/s
Head causing flow (he) = Pond level-center of off take
=1192.2 - (1191.6+0.3) = 0.3m
Q=Cd∗A∗√ 2∗g∗he =0.6*0.36*(2*9.81*0.3)0.5=0.524m3/s>>Qd=0.111m3/sec and 0.0319
m3/sec Safe!
3.12.3.1 Design of head regulator gate
The gate of the off take canal is to be vertical sheet metal of 0.6m x 0.6m for the closure of the
opening space providing some extra dimensions for groove insertion. Gross area of sheet metals
for the off take canal gate will be 0.7m x 0.70m (allowing 5cm insertion for grooves). The
grooves are to be provided on the walls using angle iron frames at the two sides of the gate
openings. The gate (sheet metals) is provided with stiffening angle irons.
3.12.3.1.1 Design of head regulator gate thickness
Hydrostatic water pressure, Pa=0.6*10=6KN/m2
Hydro Static water Pressure for head of 0.6m at the bottom of the gate=6kN/m2=0.60N/cm2
The allowable tensile and bending stress of the steel during wet condition=0.45*300=135
N/mm2=13500N/cm2
K∗P∗a2
Hence bending stress in flat plate should be, δ =
100∗S2
Where S=thickness of the sheet metal (cm)
P=Hydrostatic pressure (N/Cm)=0.60N/cm^2
K=Non-dimensional factor
a =minor support length which related with K
b 0.6
For = =1 , K=28.7 from the table for different supporting condition.
a 0.6
K∗P∗a2 0.5 28.7∗0.6∗602 0.5
S=( ) =( ) =0.214 cm
100∗δ 100∗13500
Hence considering incoming boulders and transported materials, take 3S=6.42mm
3.12.3.2 Design of operation slab and Breast wall
To avoid spilling of water during HFL over the canal regulator gate, a R.C.C wall is provided
from the gate top level up to the HFL (i.e. known as breast wall). A vertical raised gate is
designed for the head regulator. These gates are slides over the breast wall-using spindle during
opening and closing. The thickness of the breast wall is simply determined from
recommendations (point of construction) rather than the imposed load. The thickness required
for the imposed load is less than this nominal value taken 0.2m.For the breast wall, the minimum
reinforcement area is taken as 0.15% along the respective direction. Hence
Asteel=0.0015*1000*200=300
Asteel=3.14*12^2/4*5=565.2 mm2
Therefore the actual provided steel area per meter width is 565.2 mm2/m>300 mm2/m …..Ok!
Hence, provide t = 0.20m = 20cm thickness for the breast wall work. And provide the
reinforcement bar of 12mm @200mm c/c spacing in all directions with reinforcement covers of
50mm for the breast wall.
∑ MR−∑ MD 309.25−38.07
Where: x= = =1.35
∑ FV 201.15
Check for bearing capacity
Maximum base pressure=ΣV/B*(1+6*e/B)
=201.15/2.5* (1+6*-0.1/2.5)
=61.51 KN/m2<200KN/m2 so it is safe!
Q
(m^3/s
Canal ) B(m) d(m) Fb A (m^2) Pw R=A/P m S n V(m/s)
SC-1-1 0.094 0.500 0.270 0.330 0.208 1.264 0.165 1.000 0.001 0.025 0.450
1
Q= n
AR 2 / 3 S1 /2 , Where
Q = Design discharge, m3/s
R = Hydraulic radius of the canal, m
A = Wetted cross sectional area of canal, m2
n = Manning’s roughness coefficient
S = Bed slope of the canal
The shape of the canal cross section, is trapezoidal with 1 to 1 side slope as shown below
FB
d 1
1
B
Canal Q Water
descriptio des(m^3/ Depth A R=A/ V(m/s
n s) B(m) d(m) Fb (m^2) Pw P m S n )
TC-1-1 0.017 0.300 0.130 0.320 0.056 0.668 0.084 1.000 0.001 0.025 0.290
TC -1-1-
1 0.056 0.400 0.220 0.300 0.136 1.022 0.133 1.000 0.001 0.025 0.400
TC -1-1-
2 0.038 0.400 0.18 0.300 0.104 0.909 0.115 1.000 0.001 0.025 0.360
TC -2-1 0.015 0.300 0.120 0.300 0.050 0.639 0.079 1.000 0.001 0.025 0.280
TC -2-2 0.017 0.300 0.130 0.300 0.056 0.668 0.084 1.000 0.001 0.025 0.290