Management Science

I. Learning Outcomes
At the end of the activity, you will be able to:
a. convert the new program with correct slack variables;
b. set up the initial table correctly;
c. compute the value of Zj, Cj – Zj correctly;
d. make decision on the values of the optimum solution.

II. Enhancement Activity

Find the value of the unknown variables and the maximum profit
using the simplex method.
Maximize Z: 6x1 + 5x2
Subject to: 1) 2x1 + x2 = 12
2) 2x1 + 3x2 ≤ 24
3) 2x1 + 9x2 ≥ 36
III. Procedures
1. Set up the new programs with slack variables.
2. Make the initial table and enter the needed data.
3. Compute the Zj values.
4. Compute the Cj – Zj values.
5. Identify the optimum column.
6. Determine the pivotal row.
7. Construct the table II with the replacing row.
8. Complete the table entries indicating the optimum
solution and pivotal row.
9. Construct table III replacing row and complete the
entries by providing the necessary data to complete
the table.
10.Continue the process until you reach the optimum
table/solution.
11.Make a decision from the optimum table.
The new program with slack variable will be:
Maximize Z: 6x1 + 5x2 + 0s1 + 0s2 + 0s3
Subject to: 1) 2x1 + x2 + s1 = 12
2) 2x1 + 3x2 + s2 = 24
3) -2x1 - 9x2 + s3 = -36

Table 1
Cj 6 5 0 0 0
Prod Qty X1 X2 S1 S2 S3
0 S1 12 2 1 1 0 0
0 S2 24 2 3 0 1 0
0 S3 -36 -2 -9 0 0 1
Zj 0 0 0 0 0 0
Cj - Zj 6 5 0 0 0

Table 2
Cj 6 5 0 0 0
Prod Qty X1 X2 S1 S2 S3
6 X1 6 1 ½ ½ 0 0
0 S2 12 0 2 -1 1 0
0 S3 -24 0 -8 1 0 1
Zj 36 6 3 3 0 0
Cj - Zj 0 2 -3 0 0

Table 3
Cj 6 5 0 0 0
Prod Qty X1 X2 S1 S2 S3
6 X1 3 1 0 3/4 -1/4 0
5 X2 6 0 1 -1/2 1/2 0
0 S3 24 0 0 -3 4 1
Zj 48 6 5 2 1 0
Cj - Zj 0 0 -2 -1 0

Decision: X1 = 3 units
X2 = 6 units
Max Z = P 48.00