You are on page 1of 13

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/274869321

Risk identification and assessment of modular construction utilizing fuzzy


analytic hierarchy process (AHP) and simulation

Article  in  Canadian Journal of Civil Engineering · December 2013


DOI: 10.1139/cjce-2013-0013

CITATIONS READS

57 1,618

4 authors, including:

Hong Xian Li Mohamed Al-Hussein


Deakin University University of Alberta
55 PUBLICATIONS   345 CITATIONS    301 PUBLICATIONS   2,434 CITATIONS   

SEE PROFILE SEE PROFILE

Zhen Lei
University of New Brunswick
32 PUBLICATIONS   261 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Fort McMurray Stony Mountain Plaza View project

Structural Insulated Panel System (SIPs) for Residential and Commercial Projects View project

All content following this page was uploaded by Zhen Lei on 04 October 2015.

The user has requested enhancement of the downloaded file.


1184

ARTICLE
Risk identification and assessment of modular construction utilizing
fuzzy analytic hierarchy process (AHP) and simulation
Hong Xian Li, Mohamed Al-Hussein, Zhen Lei, and Ziad Ajweh

Abstract: Modular construction brings improved safety and mitigates risks of hazard and injury. However, modular construc-
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

tion technology is also challenged with a degree of uncertainty resulting from such internal and external factors as engineering,
occupational, cultural, socio-economic, and financial. Since modular construction is by nature distinct from conventional
construction, existing risk management research for onsite construction cannot be directly applied to modular construction.
This paper describes research on the risk management associated with modular construction, focusing on: (1) identifying risk
factors and (2) assessing the impacts of the identified risk factors on project cost and duration. The primary risk factors associated
with modular construction are identified, and fuzzy analytic hierarchy process (AHP) is utilized to rank these factors; simulation
techniques are employed to assess the risks of projects. The risk identification and ranking are evaluated by a focus group of
experts from the modular construction industry; t-distribution and chi-squared distribution are applied to analyze the results.
The case of a project in Edmonton, Canada is presented to illustrate application of the proposed methodology.

Key words: modular construction, risk management, AHP, fuzzy logic, simulation.

Résumé : La construction modulaire améliore la sécurité et atténue les risques de dangers et de blessures. Toutefois, la
technologie de construction modulaire présente également un certain niveau d’incertitude découlant de facteurs internes et
externes tels que les aspects d’ingénierie, d’usage, de culture, socioéconomiques et financiers. La construction modulaire étant
For personal use only.

par nature différente de la construction conventionnelle, la recherche existante sur la gestion des risques pour la construction
sur place ne peut être directement appliquée à la construction modulaire. Le présent article décrit la recherche sur la gestion des
risques associés à la construction modulaire, plus particulièrement : (1) l’identification des facteurs de risques et (2) l’évaluation
des impacts des facteurs de risque identifiés sur le coût et la durée d’un projet. Les principaux facteurs de risque associés à la
construction modulaire sont identifiés. La méthode de hiérarchie multicritère floue (AHP) est utilisée pour classer ces facteurs et
des techniques de simulation sont utilisées pour évaluer les risques des projets. L’identification et le classement des risques sont
évalués par un groupe de consultation composé d’experts provenant de l’industrie de la construction modulaire. La loi de
Student et la distribution chi carré sont utilisées pour analyser les résultats. Le cas d’un projet à Edmonton, en Alberta, Canada,
est présenté afin d’illustrer l’utilisation de la méthode proposée. [Traduit par la Rédaction]

Mots-clés : construction modulaire, gestion des risques, méthode de hiérarchie multicritère (AHP), logique floue, simulation.

1. Introduction risks. The PMI methodology also designs a blueprint for project
Modular construction is widely accepted as an efficient con- risk management, which will be utilized in this research. The
struction method, particularly in North America for residential Construction Industry Institute (2012) (CII), meanwhile, has out-
building construction. Processes such as offsite module prefabri- lined a three-level risk analysis process: identification, determin-
cation, shipping of modules to the site, and onsite installation are istic, and probabilistic. Based on risk identification, probabilities
involved in modular construction, making it distinct from con- and consequences are utilized for second-level risk analysis,
ventional onsite construction. The significant offsite work of whereas advanced analytical techniques, such as simulation mod-
modular construction results in considerable construction time elling, are utilized for third-level analysis. Most of the other re-
reduction, quality control, waste reduction, safety improvement, search on construction risk has focused on the current practice of
and hazard and injury mitigation; however, modular construc- onsite construction projects. Tah et al. (1993) applied fuzzy set
tion also entails a degree of risk. A systematic risk management theory to assess risk for contingency allocation; the relevant risk
approach is thus needed for modular construction so that con- factors were identified, and the risk was assessed accordingly us-
struction project stakeholders can consider project risks and plan ing fuzzy set theory for the purpose of allocating contingencies.
accordingly to avoid budget overruns and schedule delays. Other research has sought to identify construction industry risk
The Project Management Institute (2000) (PMI) has introduced a factors in a region-specific context. Tang et al. (2007) conducted a
uniform methodology for risk management in the Project Man- survey in the Chinese construction industry about the overall
agement Body of Knowledge (PMBOK), which consists of the fol- aspects of risk management from the perspectives of various proj-
lowing processes: (1) plan risk management; (2) identify risks; ect participants, including client, contractor, and superintendent.
(3) perform qualitative risk analysis; (4) perform quantitative risk The study revealed that the industry has shifted from risk transfer
analysis; (5) plan risk responses; and (6) monitor and control to risk reduction; it also underscored that the lack of a joint risk

Received 14 January 2013. Accepted 20 June 2013.


H.X. Li. Hole School of Construction Engineering, Department of Civil and Environmental Engineering, University of Alberta, Edmonton, AB T6G 2W2, Canada; Business School, Hohai
University, Nanjing 211100, PR China.
M. Al-Hussein, Z. Lei, and Z. Ajweh. Hole School of Construction Engineering, Department of Civil and Environmental Engineering, University of Alberta, Edmonton, AB T6G 2W2, Canada.
Corresponding author: Hong Xian Li (e-mail: ho8@ualberta.ca).

Can. J. Civ. Eng. 40: 1184–1195 (2013) dx.doi.org/10.1139/cjce-2013-0013 Published at www.nrcresearchpress.com/cjce on 21 June 2013.
Li et al. 1185

management mechanism is a key barrier to the application of risk erally, the following distinct risks are encountered in modular
management. Choudhry and Iqbal (2013) carried out an empirical construction: (1) engineering: modular construction increases re-
survey-based study on risk management in the construction in- liance on the use of machinery, automated design and drafting,
dustry in Pakistan. The resulting analysis supported the notion and production line, since most tasks are completed in a factory
that the industry generally tries to avoid or transfer financial and setting; (2) occupational and cultural: due to the nature of factory-
economic risk. Subramanyan et al. (2012) conducted an empirical based construction and the tasks involved, the demographic com-
research study in India, based on surveys of contractors, owners, position of the workforce varies from conventional construction
and project management experts. The research identified the risk in that it could include to a greater extent women, older adults,
factors and proposed a risk assessment model for risk manage- and in some cases persons with physically disabilities; (3) socio-
ment within the context of the construction industry in India. economic: modular construction is affected by the degree of
Naderi (2008) studied risk management systematically utilizing acceptance among consumers of this type of construction;
fuzzy logic, where the severity of risk was computed by multiply- (4) financial: construction process and payment schedules which
ing the likelihood with the impact. More recently, computer tech- differ from conventional construction introduce financial issues
nology has been applied to construction risk management. An to builders. Furthermore, some factors have impacts on modular
integrated methodology for planning construction projects under versus conventional construction to varying degrees: e.g., the
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

uncertainty has been developed, which is incorporated into a weather affects conventional construction more than it does mod-
computer-supported risk management system for risk identifica- ular construction. In summary, while a number of studies have
tion, analysis, and quantification (Schatteman et al. 2008). Imbeah investigated risk management for conventional construction,
and Guikema (2009) utilized an advanced programmatic risk anal- there is a lack of scholarship examining the associated risks for
ysis and management model (APRAM) for managing scheduling modular construction.
and cost and quality risks in the construction industry. A modified
APRAM was proposed that considers potential risks during the 2. Research objective and methodology
entire project life cycle to support decision making in the housing The aim of this research is to address risk management for
industry (Zeynalian et al. 2013). Karakas et al. (2013) developed a modular construction within the context of project cost and du-
multi-agent system (MAS) to simulate risk allocation and the cost ration. The risk management procedure introduced in the PMI
sharing process in construction projects. Among risk manage- PMBOK has been adopted in this research, and the main compo-
ment methodologies, analytic hierarchy process (AHP) and fuzzy nents of the PMBOK risk management procedure — the risk factor
logic are often implemented for quantification. Thomas L. Saaty identification and risk assessment — are the focus of this paper.
(1977) developed AHP, which has been extensively applied and Other components, such as risk responses, monitoring, and con-
For personal use only.

studied for decision making; AHP is a traditional approach to trol, can be addressed based on the identified risk factors and
comparing and ranking elements, and is often used in risk assess- their impacts. The research objective involves: (1) identifying and
ment. In addition, Zadeh (1965) developed fuzzy set theory, which ranking risk factors in the context of project duration and cost,
was introduced as an extension of classical set theory. For the based on the characteristics of modular construction; (2) quanti-
purpose of expressing fuzziness and uncertainty of difference, fying risk factor variations and their impact on projects; and
fuzzy set theory is combined with AHP. Liu et al. (2011) used AHP (3) assessing the cost and duration risks for a modular construc-
and fuzzy logic to evaluate the geological hazard susceptibility of tion project. To achieve the objective, the research methodology is
pipelines. Cao et al. (2011) implemented uncertain AHP on a mul- proposed as Fig. 1., in which the input of parameters include:
tistage synthesis fuzzy assessment of a pipeline using the princi- (1) modular construction processes and characteristics, which de-
ple of uncertain judgment. Liou and Wang (1992) proposed a termine the risk factors; (2) expert opinions about risk factor rank-
method of ranking fuzzy numbers with integral values, which ing and the variation of factors for a project; (3) project baseline
serves to convert each fuzzy number to a crisp number consider- information, including the precedence relationship, and the cost
ing ␣-cut and optimistic and pessimistic views. Fuzzy AHP has also and duration of each process; and (4) project variation informa-
been implemented in other industries; for example, Khorasani tion, which is described in terms of risk factors for a specific
and Bafruei (2011) proposed a fuzzy AHP approach to evaluating project. In this paper, it should be noted, “experts” refers to pro-
and selecting suppliers in the pharmaceutical industry. Although fessional engineers, plant or site managers, superintendents, and
there are many existing studies in risk management for conven- academic staff who have acquired sufficient engineering experi-
tional construction, a gap exists in the scholarship with regard to ence to evaluate the identified risks. Expert opinions were col-
risk management for modular construction in specific. lected from experts who attended the 2012 Modular and Offsite
Unlike conventional onsite construction, modular construction Construction (MOC) Summit in Edmonton, Alberta, and from per-
technology involves prefabricating modules offsite and shipping sonnel from the authors' industry partners in the modular and
them to the site for installation. Murtaza et al. (1993) addressed panelized construction sector in Alberta, Canada.
the advantages of modular construction, including time savings, The main process follows four steps:
cost savings, and the learning-curve benefit; and a decision-making
methodology was proposed to determine whether or not to utilize (1) Identify risk factors in the context of project cost and dura-
modular construction for a specific project. Lawson et al. (2012) tion for modular construction, and classify these risk factors
demonstrated the application of modular construction for high- into qualitative and quantitative factors: risk factor identifi-
rise buildings, and also indicated the benefits in terms of both cation is based on existing research and construction industry
economics and sustainability. Furthermore, a number of research experience.
initiatives have incorporated virtual construction automation for (2) Determine risk factor weightings on project cost and dura-
modular construction operations. Olearczyk et al. (2009) proposed tion. The expert opinions and fuzzy AHP are implemented
a methodology to optimize the crane selection process for onsite during this phase to rank the identified risk factors. Tradi-
erecting of five three-storey modular buildings using 4 D model- tional AHP uses crisp numbers (1, 3, 5, 7, and 9) to distinguish
ling. Lu and Korman (2010) discussed the benefits and challenges between two elements; however, it is challenging to express
of implementation of BIM in modular construction. ambiguity to account for the difference between two ele-
Despite the many advantages of modular construction outlined ments. To express the fuzziness of the difference, fuzzy logic
in the literature, modular construction still involves risks, and is combined with traditional AHP. Based on the theories of
these risks differ from those for conventional project delivery due AHP and fuzzy logic, a fuzzy scale of fuzzy AHP, shown in
to the unique activities that modular construction involves. Gen- Table 1, is proposed to determine the weights of risk factors.

Published by NRC Research Press


1186 Can. J. Civ. Eng. Vol. 40, 2013

Fig. 1. Research methodology.


Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

Table 1. Fuzzy AHP ranking scale. on reviews of related research, the primary risk factors for mod-
Linguistic variable Fuzzy number Fuzzy number scale ular construction have been identified and categorized into three
types: (1) general risk factors: these are the risk factors typical of
Identical 1 (1, 1, 1) most construction projects, whether onsite or offsite; (2) in-plant
For personal use only.

A little more important 3 (2, 3, 4) risk factors: these are the factors associated with offsite prefabri-
More important 6 (5, 6, 7)
cation of modules and panels; and (3) onsite risk factors: these
Much more important 9 (8, 9, 10)
factors have an impact on onsite preparation and installation. The
A little less important 1/3 (1/2, 1/3, 1/4)
Less important 1/6 (1/5, 1/6, 1/7) detailed items for each category are listed in Table 2. It is noted
Much less important 1/9 (1/8, 1/9, 1/10) that the factors listed in Table 2 are subjective and may vary for
different experts; however, it is the factors which are most com-
monly identified by experts that are regarded as primary. Each
factor listed in Table 2 has a different impact on project duration
Following the fuzzy ranking, the method proposed by Liou
and cost; in this paper, these impacts are measured and ranked
and Wang (1992) is used to convert fuzzy numbers to crisp
using expert opinions. The collected data are processed using
numbers, considering ␣-cut and optimistic or pessimistic views
subject to the precision of the paired comparison. fuzzy AHP to obtain the weightings of risk factors as follows:
(3) For a specific project, quantify risk factor variations and im- (1) The minimum value (L), the maximum value (U), and the
pacts on a project using function fitting and expert opinions. mean value (M) of the expert opinions are calculated satisfy-
(4) Develop a simulation model of project cost and duration ing eqs. (1), (2), and (3), respectively, using the method pro-
based on the project baseline information and related quan- posed by Buckley (1985); the calculation results are listed in
tification: as a modelling and analytical tool, simulation has Table 3.
been utilized by the construction industry for operation and
process improvement (AbouRizk and Halpin 1990; AbouRizk (1) Lij ⫽ min(Bijk)
et al. 2011). In this research, a simulation tool, Simphony.
NET4.0, is utilized as a risk simulation and quantification

冪兿
n
method.
(2) Mij ⫽ n Bijk
The proposed methodology is subject to the following criteria: 1

triangular fuzzy membership function, trapezoidal function,


(3) Uij ⫽ max(Bijk)
t-distribution, and chi-squared distribution, of which t-distribution
and chi-squared distribution are used for output analysis. The
output involves the project cost and duration profiles, and the where Lij is the minimum value of expert opinions for the
quantified project cost and duration risks for specific project cost element at row i and column j; Mij is the mean value of expert
and duration expectations. Based on the risk factor weightings in opinions for the element at row i and column j; Uij is the
terms of project cost and duration, the primary risk factors will be maximum value of expert opinions for the element at row i
monitored subsequently; the simulated project cost and duration and column j; and Bijk is the relative importance of factor i
profiles serve as the base line for project risk monitoring and compared to factor j from the view of expert k.
control. The empty cells in Table 3 have been left blank since their
values are simply the reciprocals of the values in the symmet-
3. Risk factor identification and ranking rically corresponding cells in the same table. For instance, in
The primary risk factors, which have a major impact on project Table 3, “economic condition” has a stronger impact on proj-
cost and duration, will be analyzed in this research. Based both on ect cost than does “political & social condition”. The mini-
interviews with plant managers and other industry personnel and mum value (L) in the cross-cell of row “economic condition”

Published by NRC Research Press


Li et al. 1187

Table 2. Risk factors and explanations.


Risk category Risk factor Explanation Notation
General risk factors Economic condition Economic boom in terms of construction GDP contribution, EC
which affects both construction cost and productivity
Political & social condition Change of government policies, change of political support due to PSC
change in political environment, and worker strike etc.
Construction planning Project planning for construction CP
Construction coordination & control Project coordination and control during construction CCC
Change in design or scope of work Change of project design or scope CDS
In-plant risk factors Drawings supply time Supply time of shop drawings to plant DST
Drawings quality Errors and clarity of shop drawings DQ
Material supply time Material supply on time to plant MST
Material quality Quality and type of material MQ
Labour availability Labour quantity available for plant LA
Labour skills Skills and experiences of labour LS
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

Fabrication equipment condition Production line condition in factory FEC


Onsite risk factors Temperature Temperature degree, which affects the productivity of onsite T
construction, especially in winter
Wind speed Wind speed, which affects the productivity of onsite erection, and WS
can cause construction cancellations
Site condition Ground condition and neighbourhood environment SC
Construction equipment condition Heavy equipment (mainly crane) condition for lifting and installation CEC

and column “political & social condition” is 2; correspond- are usually measured as percent change from the original scope.
ingly, the minimum value (L) in the cross-cell of row “political Temperature and wind speed can be measured using different
& social condition” and column “economic condition” is the indices, since they are considered quantitative factors. Factors
reciprocal of 2, which is 0.5. After the data processing, the that cannot be measured as quantitative data, such as “construc-
maximum eigenvalue is calculated to test the consistency of tion planning”, “construction coordination & control”, “supply of
For personal use only.

the expert opinions. drawings”, “supply of labour & material”, “fabrication equipment
(2) Once the minimum, mean, and maximum fuzzy values have condition”, “site condition”, and “construction equipment condi-
been calculated, the method proposed by Liou and Wang tion”, are considered qualitative factors.
(1992) is employed to convert the fuzzy number to a crisp For a specific project, each of the factors listed above has a
number using a triangular fuzzy membership function as il- potential variation which can be described as a change range, and
lustrated in Fig. 2. In our research, with a moderate value of the variation will have a resultant impact on the project. To quan-
0.5 applied for ␣ and ␤, eq. (4) is used to convert fuzzy num- tify these variations and impacts, various quantitative methods
bers in Table 3 into crisp numbers; then conventional AHP is are applied to the quantitative factors, and expert opinion is used
used to generate the weightings in Table 4. to analyze the qualitative factors.

(4) g␣,␤(ãij) ⫽ [␤ × f␣(Lij) ⫹ (1 ⫺ ␤)f␣(Uij)], 0 ≤ ␣, ␤ ≤ 1 4.1. Quantitative factors

where ãij is the element at row i and column j in the fuzzy 4.1.1. Economic condition
matrix; g␣,␤共ãij兲 is the crisp value for the cell at row i and Construction GDP as an indicator of the construction economy
column j in the ã fuzzy matrix with ␣ and ␤-cut value; ␣ is the reflects both productivity and construction prices. As a result, the
left-end ␣-cut value for element ãij; ␤ is the left-end ␤-cut value variation of construction GDP entails certain risks in terms of
for element ãij; Lij is the minimum value of expert opinions for project duration and cost. Meanwhile, according to industry prac-
the element at row i and column j; Uij is the maximum value of tice, construction productivity will decrease during an economic
expert opinions for the element at row i and column j; f␣(Lij) is boom, since fewer skilled workers are available and there is less
the left function of the triangular membership function in competition in the labour market. As a result, construction prices
Fig. 2; f␣(Uij) is the right function of the triangular member- increase along with lower productivity during economic boom
ship function in Fig. 2. For example, expert opinion about the times, in turn resulting in higher costs and a longer duration.
impact of “political & social” vs. “economic” conditions on proj- In this paper, the variation in construction GDP is measured as
ect cost is calculated as follows: the minimum is 2, the average is a range of potential change percentage compared to the baseline
3, and the maximum is 4; the crisp number corresponding to the GDP, which is the initial construction GDP for a project, satisfying
fuzzy set is calculated as 0.5 × [(3−2) × 0.5 + 2] + 0.5 × [4−(3−2) × eq. (5). To measure the impact of economic variation on a project,
0.5] = 3. a linear function is applied to correspond symmetrically to the
(3) These converted crisp numbers are processed using conven- fitting function; however, the accuracy of the impact may be im-
tional AHP, and the results are listed in Table 4. paired. The impact of the economic situation, denoted as Fe, can
be calculated satisfying eq. (6).
4. Risk factors’ variation and impact quantification
In Table 2, such risk factors as “economic condition”, “change
in design or scope of work”, “temperature”, and “wind speed” can
(5) Ve ⫽ 共 MinB⫺ B, Max ⫺ B
B 兲
be measured quantitatively. In this paper, economic condition is
measured in terms of the construction industry's contribution to where Ve is the economic variation; Min is the minimum construc-
GPD (referred to subsequently in this paper as “construction tion GDP during the construction period of a project; Max is the
GDP”), since construction GDP is regarded as the key indicator of maximum construction GDP during the construction period of a
the construction economy. Changes to the design or scope of work project; and B is the baseline GDP.

Published by NRC Research Press


1188
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

Table 3. Fuzzy AHP ranking of risk factors on project cost and duration.
EC PSC CP CCC CDS DST DQ MST MQ LA LS FEC T WS SC CEC
L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U L M U
EC 1 1 1 2 3 4 4 5 6 4 5 6 4 5 6 4 5 6 4 5 6 4 5 6 4 5 6 4 5 6 4 5 6 6 7 8 7 8 9 8 9 10 5 6 7 5 6 7
1 1 1 1 2 3 0.2 0.3 0.4 0.3 0.4 0.5 0.1 0.2 0.3 0.1 0.2 0.3 0.2 0.3 0.4 0.1 0.2 0.3 0.2 0.3 0.4 0.1 0.2 0.3 0.2 0.3 0.4 0.4 0.5 0.6 0.7 0.8 0.9 0.7 0.8 0.9 0.3 0.4 0.5 0.3 0.4 0.5
PSC 1 1 1 2 3 4 2 3 4 2 3 4 2 3 4 2 3 4 4 5 6 4 5 6 4 5 6 4 5 6 2 3 4 4 5 6 7 8 9 2 3 4 4 5 6
1 1 1 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 2 3 4 4 5 6 5 6 7 2 3 4 4 5 6
CP 1 1 1 1 2 3 1 2 3 1 2 3 5 6 7 4 5 6 5 6 7 4 5 6 5 6 7 4 5 6 4 5 6 5 6 7 5 6 7 5 6 7
1 1 1 1 2 3 3 4 5 1 2 3 3 4 5 1 2 3 3 4 5 1 2 3 3 4 5 5 6 7 5 6 7 5 6 7 5 6 7 5 6 7
CCC 1 1 1 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 4 5 6 4 5 6 5 6 7 6 7 8 6 7 8
1 1 1 2 3 4 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 1 2 3 5 6 7 5 6 7 2 3 4 2 3 4
CDS 1 1 1 4 5 6 3 4 5 4 5 6 3 4 5 4 5 6 3 4 5 3 4 5 4 5 6 5 6 7 4 5 6 4 5 6
1 1 1 1 1 1 2 3 4 1 2 3 2 3 4 1 2 3 2 3 4 2 3 4 6 7 8 6 7 8 4 5 6 4 5 6
For personal use only.

DST 1 1 1 1 1 1 1 2 3 1 2 3 1 2 3 1 2 3 0.7 0.8 0.9 4 5 6 5 6 7 4 5 6 4 5 6


1 1 1 2 3 4 1 2 3 3 4 5 1 2 3 3 4 5 2 3 4 5 6 7 5 6 7 4 5 6 4 5 6
DQ 1 1 1 2 3 4 1 2 3 2 3 4 1 2 3 1 2 3 4 5 6 5 6 7 2 3 4 2 3 4
1 1 1 0.6 0.7 0.8 1 2 3 0.6 0.7 0.8 1 2 3 1 2 3 5 6 7 5 6 7 2 3 4 2 3 4
MST 1 1 1 0.7 0.8 0.9 1 1 1 0.7 0.8 0.9 0.7 0.8 0.9 4 5 6 5 6 7 3 4 5 3 4 5
1 1 1 3 4 5 1 1 1 3 4 5 3 4 5 5 6 7 5 6 7 3 4 5 3 4 5
MQ 1 1 1 1 2 3 1 1 1 3 4 5 4 5 6 5 6 7 1 2 3 1 2 3
1 1 1 0.4 0.5 0.6 1 1 1 3 4 5 5 6 7 5 6 7 1 2 3 1 2 3
LA 1 1 1 0.7 0.8 0.9 0.7 0.8 0.9 4 5 6 5 6 7 3 4 5 3 4 5
1 1 1 3 4 5 3 4 5 5 6 7 7 8 9 3 4 5 3 4 5
LS 1 1 1 3 4 5 4 5 6 5 6 7 1 2 3 1 2 3
1 1 1 3 4 5 5 6 7 5 6 7 1 2 3 1 2 3
FEC 1 1 1 2 3 4 3 4 5 1 2 3 1 2 3
1 1 1 5 6 7 4 5 6 0.7 0.8 0.9 0.7 0.8 0.9
T 1 1 1 1 2 3 0.7 0.8 0.9 0.7 0.8 0.9
1 1 1 1 2 3 0.7 0.8 0.9 0.7 0.8 0.9
WS 1 1 1 0.7 0.8 0.9 0.7 0.8 0.9
1 1 1 0.6 0.7 0.8 0.6 0.7 0.8
SC 1 1 1 3 4 5
1 1 1 3 4 5
CEC 1 1 1
Published by NRC Research Press

1 1 1

Can. J. Civ. Eng. Vol. 40, 2013


Notes: The numbers in empty cells are the reciprocals of the corresponding symmetrical cells in the same table. For each factor in one row, the number in the cell above is for cost, and in the one below is for duration.
Li et al. 1189

Fig. 2. Triangular fuzzy membership function. 4.1.3. Temperature


Within the possible temperature (°C) range for construction
activities there is a range of preferable temperatures within
which construction productivity peaks; outside of the range, pro-
ductivity decreases to some extent. In this paper, a trapezoidal
function is used to account for temperature such that the function
f(x) represents the preferable degree of temperature. The differ-
ence between the actual and the preferable temperature is calcu-
lated as ⌬Ft, satisfying eq. (9) (see Fig. 3). Assuming the impact to
the preference degree difference is linear, the impact of temper-
ature (Ft) is calculated satisfying eq. (10) and shown in Fig. 3b.

再 冎
(x ⫺ a)
1⫺ a≤x≤b
(b ⫺ a)
(9) ⌬Ft ⫽ 1 ⫺ f(x) ⫽ 0 b≤x≤c
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

(d ⫺ x)
1⫺ c≤x≤d
Table 4. Risk factor weights on cost and duration. (d ⫺ c)
Risk factors Cost weight Duration weight
where ⌬Ft is the preference degree difference between a specific
Economic condition 0.214 0.030
Political & social condition 0.135 0.115 temperature and the preference one; f(x) is the preference degree
Construction planning 0.105 0.142 function; x is the temperature value; a is the lower-bound value of
Construction coordination & control 0.081 0.096 temperature; d is the upper-bound value of temperature; b is the
Change in design or scope of work 0.102 0.095 lower-bound value of preference temperature; and c is the upper-
Drawings supply time 0.054 0.101 bound value of preference temperature.

再 冎
Drawings quality 0.056 0.057
Material supply time 0.038 0.082 1 ⫹ (1 ⫺ f(x)) ⫽ 2 ⫺ f(x) a ≤ x ≤ b
Material quality 0.043 0.048 (10) Ft ⫽ 1 ⫹ ⌬Ft ⫽ 1 b≤x≤c
Labour availability 0.038 0.079 1 ⫹ (1 ⫺ f(x)) ⫽ 2 ⫺ f(x) c ≤ x ≤ d
Labour skills 0.042 0.047
For personal use only.

Fabrication equipment condition 0.030 0.031


Temperature 0.014 0.015 where Ft is the impact of temperature; f(x) is the preference degree
Wind speed 0.011 0.013 function; x is the temperature value; a is the lower-bound value
Site condition 0.021 0.028 of temperature, –25° in this research; d is the upper-bound value of
Construction equipment condition 0.016 0.022 temperature, 35° in this research; b is the lower-bound value of
Total 1 1 preference temperature, 22° in this research; and c is the upper-
bound value of preference temperature, 25° in this research.

4.1.4. Wind speed


(6) Fe ⫽ 1 ⫹ Ve Wind speed affects onsite erecting in modular construction in
the following manner: the lower the wind speed, the higher the
where Fe is the impact index of the economy and Ve is the eco- productivity. In this paper, the semi-trapezoidal function is em-
nomic variation. ployed to account for wind speed, in which the function f(x) rep-
resents the preference degree of wind. The preference degree
difference between the actual and the preference wind speed is
4.1.2. Change in design or scope of work
calculated as ⌬Fw, satisfying eq. (11) (see Fig. 4). Assuming the
Project design or scope variation is usually measured by percent
impact is linear to the preference degree difference, the impact of
change in project quantity. Theoretically the uniform measure of wind (Fw) is calculated satisfying eq. (12) (see Fig. 4b).
project change is project cost; however, after considering the im-

再 冎
pact on project duration, a general project quantity is found to be 0 0≤x≤a
more versatile. This allows for the use of building floor area, for (11) ⌬Fw ⫽ 1 ⫺ f(x) ⫽ (b ⫺ x)
example, to be input as the measure of project percent change, 1⫺ a≤x≤b
(b ⫺ a)
which may be more useful for some projects. The project change
variation is quantified satisfying eq. (7); assuming the impact is
linear to the variation, the impact of project change, denoted as where ⌬Fw is the preference degree difference between actual and
Fc, can be calculated satisfying eq. (8). preference wind speed; f(x) is the preference degree function; x is
the wind speed; a is the turning point of wind speed, 36 km/h in

共 Min WW ⫺ W, 兲
Max W ⫺ W this research; and b is the construction cancellation point of wind
(7) Vc ⫽ speed, 50 km/h in this research.
W

where Vc is the project change variation; Min W is the minimum


work of a project; Max W is the maximum work of a project; and
(12) Fw ⫽ 1 ⫹ ⌬Fw ⫽ 再 1
2⫺
(b ⫺ x)
(b ⫺ a)
0≤x≤a
a≤x≤b 冎
W is the Initial work of a project.

(8) Fc ⫽ 1 ⫹ Vc where Fw is the impact of wind speed; ⌬Fw is the preference degree
difference between actual and preference wind speed; x is the
wind speed; a is the turning point of wind speed, 36 km/h in this
where Fc is the impact index of change and Vc is the change vari- research; and b is the construction cancellation point of wind
ation. speed, 50 km/h in this research.

Published by NRC Research Press


1190 Can. J. Civ. Eng. Vol. 40, 2013

Fig. 3. Trapezoidal function fitting.


Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

Fig. 4. Semi-trapezoidal function fitting.


For personal use only.

4.2. Qualitative factors the impact indices and weights of risk factors, satisfying eqs. (13)
For qualitative risk factors, including “construction planning”, to (18). However, RC and RD cannot be calculated directly, since the
“construction coordination & control”, “supply of drawings”, impact index of each factor (Fi) is a range; simulation is applied to
“supply of labour & material”, “fabrication equipment condition”, address this problem. The modelling and simulation tool, Sim-
“site condition”, and “construction equipment condition”, the phony.NET4.0, is utilized in this research, and the mean value
variations cannot be predicted directly as quantitative ranges. and the variance of the simulation results are analyzed using
Thus, the expert opinion method is necessary to quantify the t-distribution and chi-squared distribution, satisfying eqs. (19) and
variations. In this paper, “good”, “ordinary”, and “poor” are ad- (20).
opted to describe the variation, corresponding to quantified num-
k

兺F × w
ber ranges: [0.8, 1], [0.6, 0.8], and [0.5, 0.6]. Furthermore, all of the
qualitative risk factors have reverse impacts on the project cost (13) RC ⫽ i
C
i
i⫽1
and duration compared to the variations. Taking “political and
social condition” as the example, the project cost and duration k
tend to be lower and shorter if the political and social conditions
are promising. The impact index of each qualitative risk factor is
(14) RD ⫽ 兺F × w
i⫽1
i
D
i

thus calculated in this paper as the reciprocal of the variation.


m
5. Cost and duration risk simulation
Theoretically, project cost and duration (C and D, respectively)
(15) C⫽ 兺C × R
j⫽1
j
0
C

can be calculated by combining cost and duration baselines with


their risk indices (RC and RD, respectively), which are derived from (16) D ⫽ T m ⫹ Dm
0 × R
D

Published by NRC Research Press


Li et al. 1191

Fig. 5. Compassion House 3D model.


Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

(17) T s ⫽ Max共T r ⫹ Dr0 × RD兲 and that there is sufficient workforce to accomplish parallel ac-
tivities, the project is scheduled as presented in Table 5. The con-
(18) T0 ⫽ 0 struction process involved in this project is illustrated in Fig. 6,
and Table 6 lists the risk factors with their corresponding base-
lines and quantified variations. The estimated amount without
where RC is the project cost risk index; RD is the project duration contingency is $1 043 900, as shown in Table 6, and the total ex-
risk index; Fi is the impact index of risk factor i; wiC is the cost pected budget is $1 180 000; the target project duration for this
weight of risk factor i; wiD is the duration weight of risk factor i; C project is 60 days.
is the project cost; D is the project duration; Cj0 is the cost baseline
of activity j; Dm m
0 is the duration baseline of last activity m; T is start
6.2. Simulation model and results
For personal use only.

s
time of last activity; T is the start time of any activity in the
The modular construction process (as shown in Fig. 6) is simu-
project; Tr is the start time of predecessor r of any activity s; Dr0 is
lated using Simphony.NET, a simulation environment developed
the duration baseline of predecessor r of any activity s; T0 is the
at the Hole School of Construction, University of Alberta. The
start time of first activity; i is the risk factor number; j is the
activity number; k is the number of risk factors; and m is built simulation model is presented in Fig. 7; in this model, two
the number of activities. production lines are considered. The simulation model incorpo-
rates the risk factor weights, risk factor variations, and cost and
S duration baselines as inputs, and the results are presented in
(19) Y ⫽ X ± t(n⫺1),(1⫺(␣/2)) terms of probability density function (PDF) and cumulative distri-
兹n bution function (CDF).
The cost and duration variations, which are quantified using
where Y is the confidence interval of mean value with a 95% con- function fitting or expert opinions, are listed in Table 6. Based on
fidence level; X is the mean value of project cost/duration of the proposed methodology, the simulation results show that the
simulation results; t is the value of t-distribution with the corre- mean project cost is $1 148 891 (see Fig. 8), and the mean project
sponding confidence interval and simulation times; S is the stan- duration is 59 days (similar to Fig. 8). The 95% confidence level
dard deviation of project cost/duration of simulation results; and interval of mean project cost is [$1 148 553, $1 149 228], and the
n is the simulation running times. confidence interval of variance within the same confidence level
is [288779072, 305241598]. The 95% confidence level interval of
(20) Z⫽ 冋 (n ⫺ 1)S2 (n ⫺ 1)S2
␹(1⫺(
2
, 2
␣/2)),(n⫺1) ␹(␣/2),(n⫺1)
册 mean project duration is [59.36, 59.38], and the confidence inter-
val of variance within the same confidence level is [0.15, 0.16]. The
simulation results indicate that the probability of completing the
project within a budget of $1 180 000 is about 92%, and the prob-
where Z is the confidence interval of variance with a 95% confi- ability of completing the project within 60 days is about 95%.
dence level; ␹2 is the value of chi-squared distribution with the According to the results, it is demonstrated that in addition to
corresponding confidence interval and simulation times; S is the “economic condition” and “political & social condition”, such fac-
standard deviation of project cost/duration in simulation results; tors as “construction planning”, “project change”, and “construc-
and n is the simulation running times. tion coordination & control” are primary controllable risk factors
for project cost; also “drawing supply time” is an important factor
6. Case study with respect to project duration. Due to their effect on project cost
6.1. Project information and duration, these primary factors are given particular attention
The proposed methodology is demonstrated in a case project, in terms of monitoring and control during the construction pro-
Compassion House in Edmonton, Alberta, Canada, which in- cess. The simulation results (cost and duration profiles) in turn
volves the expansion and renovation of an existing building; the can be used as the benchmarks for project cost and duration
expansion floor area is 855.36 m2, while the existing floor area is control during the monitoring and control process.
695.57 m2. The stakeholders in this case were interested in imple-
menting a modular construction approach to build this project; 7. Conclusions
the corresponding 3 D model for the project and the modules are Although applications of modular construction result in improved
presented in Fig. 5. Based on the assumptions that there are two safety and mitigated hazards and injury, modular construction tech-
independent production lines in the module fabrication plant, nology is still challenged with the degree of associated uncertainties.

Published by NRC Research Press


1192 Can. J. Civ. Eng. Vol. 40, 2013

Table 5. Compassion House project information.


Task Task Duration Cost
No. name (Days) Predecessors (Dollars)
I Module fabrication
1 Module-1 for 1st floor 21 None 42 600
2 Module-2 for 1st floor 23 Module-1 of 1st floor (SS = 2 days) 84 000
3 Module-3 for 1st floor 22 Module-2 of 1st floor (SS = 2 days) 85 000
4 Module-4 for 1st floor 22 Module-3 of 1st floor (SS = 2 days) 82 500
5 Module-5 for 1st floor 16 Module-4 of 1st floor (SS = 8 days) 26 500
6 Module-6 for 1st floor 12 Module-5 of 1st floor (SS = 6 days) 15 600
7 Roof manufacturing 18 Module-6 for 1st floor (SS = 2 days) 15 000
8 Module-1 for 2nd floor 21 None 42 600
9 Module-2 for 2nd floor 23 Module-1 for 2nd floor (SS = 2 days) 84 000
10 Module-3 for 2nd floor 22 Module-2 for 2nd floor (SS = 2 days) 85 000
11 Module-4 for 2nd floor 22 Module-3 for 2nd floor (SS = 2 days) 82 500
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

12 Module-5 for 2nd floor 16 Module-4 for 2nd floor (SS = 8 days) 26 500
13 Module-6 for 2nd floor 12 Module-5 for 2nd floor (SS = 6 days) 15 600
II Panels fabrication
14 Lift pit & Basement wall fabrication 6 Module-1 of 1st floor (SS = 15 days) 38 000
III Site preparation and footing
15 Mobilization 1 Module-1 of 1st floor (SS = 20 days) 15 000
16 Demolishing existing house 4 Mobilization 10 000
17 Excavation 2 Demolishing existing house 6 500
18 Footing casting 2 Excavation 10 000
19 Backfilling and compaction 1 Footing casting 4 000
20 Utility connections (including trenching 4 Backfilling and compaction 8 000
and backfilling)
IV Module shipping
21 Lift pit & Basement wall shipping 1 Lift pit & Basement walls fabrication 10 000
22 Module shipping for 1st floor 1 Module fabrication for 1st floor 9 000
For personal use only.

23 Module shipping for 2nd floor 1 Module fabrication for 2nd floor 9 000
24 Roof shipping 1 Module shipping for 2nd floor, Roof manufacturing 6 000
V On-site construction
25 Lift pit & Basement wall installation 2 Lift pit & Basement wall shipping, 10 000
Utility connections floor cast
26 Module installation for 1st floor 1 Lift pit & Basement installation, 4 000
Module shipping for 1st floor
27 Module installation for 2nd floor 1 Module installation for 1st floor, 4 000
Module shipping for 2nd floor
28 Roof installation 1 Roof shipping, Module installation 8 000
for 2nd floor
29 Basement floor casting 3 Roof installation 20 000
VI Finishing
30 Interior finishing 6 Roof installation 30 000
31 Exterior finishing 8 Roof installation 45 000
VII Renovation
32 Existing house renovation 4 Exterior finishing 35 000
33 Opening 1 Existing house renovation 15 000
VIII Landscaping
34 Landscaping 5 Exterior finishing 60 000
Total 1 043 900

Fig. 6. Modular construction processes.

Published by NRC Research Press


Li et al. 1193

Table 6. Risk factor variation and impact quantification.


Risk factor Project construction condition Quantified variation Impact on project
Economic condition Ordinary (Baseline point is $73 467M*) [$72 000M, $75 000M] [0.98, 1.02]
Political & social condition Good [0.8, 1] [1, 1.25]
Construction planning Good [0.8, 1] [1, 1.25]
Construction coordination & control Good [0.8, 1] [1, 1.25]
Change in design or scope of work Small [−1.5%, 1.5%] [0.985, 1.015]
Drawings supply time Good [0.8, 1] [1, 1.25]
Drawings quality Good [0.8, 1] [1, 1.25]
Material supply time Good [0.8, 1] [1, 1.25]
Material quality Good [0.8, 1] [1, 1.25]
Labour availability Good [0.8, 1] [1, 1.25]
Labour skills Good [0.8, 1] [1, 1.25]
Fabrication equipment condition Good [0.8, 1] [1, 1.25]
Temperature [25 °C, 30 °C] [0.5, 1] [1, 1.5]
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

Wind speed [0, 30 km/h] [1, 1] [1, 1]


Site condition Poor [0.5, 0.6] [1.67, 2]
Construction equipment condition Good [0.8, 1] [1, 1.25]
*http://www.statcan.gc.ca/tables-tableaux/sum-som/l01/cst01/econ41-eng.htm.

Fig. 7. Simulation modeling.


For personal use only.

Previous research related to risk management has mainly focused on risk factors on project cost and duration. For specific modular
conventional onsite construction technology, which cannot be di- construction projects, function fitting and expert opinions have
rectly applied to modular construction. A generic method for risk been employed to quantify risk factor variations and their im-
management of modular construction has thus been presented in pacts on the given project. Subsequently, simulation (Simphony.
this research. NET) has been implemented as a modelling and computation ap-
As an initial step, risk factors associated with the modular con- proach to calculate project risks. The case of a building project in
struction process were identified as follows: (1) General risk fac- Edmonton, Alberta, Canada, Compassion House, has been consid-
tors: these are the common risk factors that affect both onsite and ered to illustrate the application of the proposed methodology. In
offsite construction, including economic conditions, political & terms of verification and validation of this research, the expert
social conditions, construction planning, construction coordina- opinions and the mutual confirmation provided the validation for
tion & control, changes in the design and scope of the work. the risk identification. For the risk quantification, the simulation
(2) In-plant risk factors: these are the factors involved in offsite tool was utilized to quantify the project risks and generate the
prefabrication of modules and panels, including drawings supply project cost and duration profiles; the results can be compared
time, drawings quality, material supply time, material quality, with the daily risk management as validation of the proposed
labour availability, labour skills, and fabrication equipment con- methodology.
dition. (3) Onsite risk factors: these are the factors that have an This research has proposed a generic risk management frame-
impact on onsite preparation and installation, including temper- work for modular construction; the innovative contribution of
ature, wind speed, site condition, and construction equipment this paper comprises two aspects: (1) the specific risk factors are
condition. Based on the risk factor identification, expert opinions identified based on the unique activities involved in modular con-
and fuzzy AHP have been utilized to determine the weightings of struction, accommodating both offsite and onsite construction

Published by NRC Research Press


1194 Can. J. Civ. Eng. Vol. 40, 2013

Fig. 8. Simulation result (Cost).


Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15

environments; and (2) the method of quantifying the risk factors' Cao, T., Zhang, H., Xiang, X., Dai, L., Zheng, H., and Liu, Y. 2011. Risk assessment
variation and impacts is generic; the quantification results assist of city gas pipeline based on uncertain analytic hierarchy process. In Proceed-
ings of the International Conference on Pipelines and Trenchless Technol-
in subsequently controlling and mitigating risk. In addition, this ogy, Beijing, China, 26–29 October 2011. American Society of Civil Engineers,
research has proposed a unique and reasonable fuzzy AHP rank- New York, pp. 1648–1656.
ing scale. This research has been conducted with the assistance of Choudhry, R.M., and Iqbal, K. 2013. Identification of risk management system in
a residential builder operating in Edmonton, Alberta, Canada, construction industry in Pakistan. Journal of Management in Engineering,
29(1): 42–49. doi:10.1061/(ASCE)ME.1943-5479.0000122.
which has adopted modularization as their main construction
Construction Industry Institute. 2012. Applying probabilistic risk management
method, and the identified risks are based on the daily experience
For personal use only.

in design and construction projects. Construction Industry Institute, Austin,


of practitioners from this residential builder. Although the possi- TX.
bility for some marginal regional variation in risk factors exists, it Imbeah, W., and Guikema, S. 2009. Managing construction projects using the
is reliable to apply the identified risk factors and assess risk im- advanced programmatic risk analysis and management model. Journal of
Construction Engineering and Management, 135(8): 772–781. doi:10.1061/
pact for modular construction on the basis of the experience of (ASCE)0733-9364(2009)135:8(772).
these practitioners. The proposed methodology benefits stake- Karakas, K., Dikmen, I., and Birgonul, M.T. 2013. A multi-agent system to simu-
holders by identifying the specific risk factors and quantifying late the risk allocation and cost sharing process in construction projects.
their impact on modular construction, e.g., stakeholders can ob- Journal of Computing in Civil Engineering, 27(3): 307–319. doi:10.1061/
(ASCE)CP.1943-5487.0000218.
tain better understandings of the risks involved in both offsite
Khorasani, O., and Bafruei, M.K. 2011. A fuzzy AHP approach for evaluating and
and onsite construction, apply the methodology to evaluate the selecting supplier in pharmaceutical industry. International Journal of Aca-
risk impacts, and consequently take action to avoid or mitigate demic Research, 3(1): 346–352.
those risks. The research has also laid a foundation for modular Lawson, R., Ogden, R., and Bergin, R. 2012. Application of modular construction
construction risk management upon which future researchers in high-rise buildings. Journal of Architectural Engineering, 18(2): 148–154.
doi:10.1061/(ASCE)AE.1943-5568.0000057.
can develop more complicated methodologies or algorithms for Liou, T., and Wang, M.J. 1992. Ranking fuzzy numbers with integral value. Fuzzy
modular construction risk management. The following points Sets and Systems, 50(3): 247–255. doi:10.1016/0165-0114(92)90223-Q.
should be considered in future research: (1) the assumption that Liu, L., Jia, S., Zhou, L., Feng, Q., Li, Y., and Yu, H. 2011. Evaluation of geological
the impacts of risk factors are linear to the variation, which may hazard susceptibility based on AHP and fuzzy comprehensive evaluation in
impair quantification accuracy, is one of the limitations of this Zhongwu pipeline. In Proceedings of the International Conference on Pipe-
lines and Trenchless Technology, Beijing, China, 26–29 October 2011, Amer-
research; and (2) the in-depth integration of risk management ican Society of Civil Engineers, New York, pp. 1365–1375.
processes, from risk management planning to risk monitoring Lu, N., and Korman, T. 2010. Implementation of building information modeling
and controlling for modular construction, should be considered (BIM) in modular construction: Benefits and challenges. In Proceedings of the
in future research. Construction Research Congress, Banff, Alta., 8–10 May 2010, American Soci-
ety of Civil Engineers, New York, pp. 1136–1145.
Murtaza, M., Fisher, D., and Skibniewski, M. 1993. Knowledge-based approach
Acknowledgements to modular construction design support. Journal of Construction Engineer-
The authors are grateful for support from NSERC, and to those ing and Management, 119(1): 115–130. doi:10.1061/(ASCE)0733-9364(1993)119:
who have contributed their time and resources to this research 1(115).
Naderi, M. 2008. Fuzzy logic application in risk analysis of construction man-
(Mr. Jonathan Tomalty, Dr. Gunnar Lucko, Dr. Ahmed Bouferguène, agement. M.Sc. thesis, Department of Civil and Environmental Engineering,
Mr. Gurjeet Singh, and Mr. Hexu Liu). Also, financial support from The University of Alberta, Edmonton, Alta.
the Fundamental Research Funds for the Central Universities in Olearczyk, J., Al-Hussein, M., Bouferguène, A., and Telyas, A. 2009. Virtual con-
China (No. 2011B03714) is much appreciated. struction automaton for modular assembly operations. In Proceedings of the
Construction Research Congress, Seattle, WA., 5–7 April 2009. American
Society of Civil Engineers, New York, pp. 406–415.
References Project Management Institute. 2000. A guide to the project management body of
AbouRizk, S.M., and Halpin, D.W. 1990. Probabilistic simulation studies for re- knowledge. Project Management Institute, Newtown Square, PA.
petitive construction processes. Journal of Construction Engineering and Saaty, T.L. 1977. A scaling method for priorities in hierarchical structures.
Management, 116(4): 575–594. doi:10.1061/(ASCE)0733-9364(1990)116:4(575). Journal of Mathematical Psychology, 15(3): 234–281. doi:10.1016/0022-2496(77)
AbouRizk, S.M., Halpin, D., Mohamed, Y., and Hermann, U. 2011. Research in 90033-5.
modeling and simulation for improving construction engineering opera- Schatteman, D., Herroelen, W., Van Vonder, S., and Boone, A. 2008. Methodol-
tions. Journal of Construction Engineering and Management, 137(10): 843– ogy for integrated risk management and proactive scheduling of construc-
852. doi:10.1061/(ASCE)CO.1943-7862.0000288. tion projects. Journal of Construction Engineering and Management, 134(11):
Buckley, J.J. 1985. Fuzzy hierarchical analysis. Fuzzy Sets and Systems, 17(3): 885–893. doi:10.1061/(ASCE)0733-9364(2008)134:11(885).
233–247. doi:10.1016/0165-0114(85)90090-9. Subramanyan, H., Sawant, P.H., and Bhatt, V. 2012. Construction project risk

Published by NRC Research Press


Li et al. 1195

assessment: Development of model based on investigation of opinion of ment in the Chinese construction industry. Journal of Construction Engi-
construction project experts from India. Journal of Construction Engineer- neering and Management, 133(12): 944–956. doi:10.1061/(ASCE)0733-9364
ing and Management, 138(3): 409–421. doi:10.1061/(ASCE)CO.1943-7862. (2007)133:12(944).
0000435. Zadeh, L.A. 1965. Fuzzy sets. Information and Control, 8(3): 338–353. doi:10.1016/
S0019-9958(65)90241-X.
Tah, J.H.M., Thorpe, A., and McCaffer, R. 1993. Contractor project risks contin-
Zeynalian, M., Trigunarsyah, B., and Ronagh, H.R. 2013. Modification of ad-
gency allocation using linguistic approximation. Computing Systems in En- vanced programmatic risk analysis and management model for the whole
gineering, 4(2–3): 281–293. doi:10.1016/0956-0521(93)90052-X. project life cycle's risks. Journal of Construction Engineering and Manage-
Tang, W., Qiang, M., Duffield, C.F., Young, D.M., and Lu, Y. 2007. Risk manage- ment, 139(1): 51–59. doi:10.1061/(ASCE)CO.1943-7862.0000571.
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by 52.2.249.46 on 09/09/15
For personal use only.

Published by NRC Research Press

View publication stats

You might also like