You are on page 1of 11

Risk Assessment in Bridge Construction Projects in Iran

Using Monte Carlo Simulation Technique


Hosein Naderpour 1; Ali Kheyroddin 2; and Seyedmehdi Mortazavi 3

Abstract: Risks are an inseparable part of every project, and risk management must be one of the main requirements of every project.
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

According to risk management experts, risk identification and analysis is the most important part of risk management, and can be called
the core of risk management. True identification and precise analysis of risks and implementation of risk management in a project can reduce
time and cost and improve quality and safety. This research comprehensively and systematically identified and assessed risks in the Iranian
bridge construction industry. Risks were identified during various visits and interviews and through questionnaires, risk factors were
prioritized according to statistical test results, and quantitative analysis of risks by Monte Carlo simulation was implemented on a real project
and its implications on project time and the cost were determined. Financial risk was the most crucial risk factor which negatively influenced
projects. Practical solutions for risk assessment and analysis of bridge construction projects are offered which can be utilized by contractors,
project managers, and project control engineers in bridge construction companies. DOI: 10.1061/(ASCE)SC.1943-5576.0000450. © 2019
American Society of Civil Engineers.
Author keywords: Risk analysis; Management; Monte Carlo simulation; Bridge construction.

Introduction objectives, including scopes, scheduling, quality, and cost (Naji and
Hussein Ali 2018). The project implementation risks involved
Bridges are considered as one of the most strategic developmental in the process are divided into government risk, market risk, and
products in each country. In every country, infrastructure projects project risk (Liu and Sun 2019). Project risks are of two categories,
are significantly important for economic and industrial develop- known and unknown. Known risks are recognized and can be an-
ment in order to increase the quality of life for people (Etemadinia alyzed, which makes planning and preparing response possible. It
and Tavakolan 2016). Generally, infrastructure projects are charac- is not possible to proactively unravel an unknown risk (Bahamid
terized as being large-scale, long-duration, and high-investment and Doh 2017).
(Wang and Yuan 2017). Because of the sophisticated and dynamic Developing countries should examine the risks systematically
nature of projects, a vital decision has to be made by a client and must develop a functional management model for controlling
(Choudhry 2016). Making bridges in urban or suburban areas is and responding to potential risks. In evaluating the projects, the
especially of great importance in developing countries, including absence of historical information is a disadvantage (Chang and
Iran. Smoothing urban traffic flow and facilitating and shortening Ko 2017).
road transportation can reduce cost and time in a variety of ways. It is necessary to reduce the likelihood of occurrence and the
Therefore, accelerating the time, reducing the costs, and exploiting intensity of the effects of threats in risk management (Schuyler
the projects can be of great help to the macroeconomic environment 2001). Various researchers have expressed a variety of views on
of developing countries. A construction project is a set of different risk and risk management. Akintoye and MacLeod (1997) stated
events, expected or unexpected (Asgari et al. 2018). Risks exist in that risk management is a vital necessity for reducing losses and
all projects (Choudhry et al. 2014). Uncertainties that affect the increasing profits in the construction industry. Williams et al.
project are based on two theories: probability and possibility (1997) proposed a method for observing the risk management in
(Naderpour et al. 2019). In developing countries, including Iran, the construction projects. Reilly and Brown (2004) studied the im-
risks as a bottleneck in various parts of projects have caused a great plementation of risk management processes in infrastructure and
deal of damage to the project scopes. The risks have a significant tunnels, projects which are particularly complex. Raftery (2003)
impact on the performance, efficiency, and quality of projects suggested that the use of expert information and opinions on
(Akintoye and MacLeod 1997). In many cases, risks can be defined risk identification in various projects is essential for saving time.
as uncertainties, and they also can affect at least one of the project Farooqui et al. (2007) reported that Pakistan had suffered failures
in bridge construction projects that were related to failing to take
1 risks. Choudhry and Iqbal (2013) argued that risk management was
Associate Professor, Faculty of Civil Engineering, Semnan Univ.,
Semnan 3513119111, Iran (corresponding author). ORCID: https://orcid not systematically carried out in Pakistan. Choudhry et al. (2014)
.org/0000-0002-4179-7816. Email: naderpour@semnan.ac.ir proposed a guideline for risk categories in bridge construction proj-
2
Professor, Faculty of Civil Engineering, Semnan Univ., Semnan ects in the construction industry of Pakistan.
3513119111, Iran. The risks can be evaluated from two perspectives: likelihood,
3
Ph.D. Candidate, Faculty of Civil Engineering, Semnan Univ., Semnan
and severity of effects. Risk management is the set of control
3513119111, Iran.
Note. This manuscript was submitted on January 16, 2019; approved on processes in a system that predicts the risks and shows the way of
June 12, 2019; published online on August 15, 2019. Discussion period dealing with them (Dikmen et al. 2004).
open until January 15, 2020; separate discussions must be submitted for The complexity of construction projects would cause inference
individual papers. This paper is part of the Practice Periodical on Struc- in work portfolio, and the dynamism of this space and the impact
tural Design and Construction, © ASCE, ISSN 1084-0680. of environmental factors add to this complexity, accompanied by

© ASCE 04019026-1 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Start

Identify and collect common


and essential risks

Financial Contractual Design Safety Management Construction External Environmental Post-exploitation


risks risks risks risks risks risks risks risks risks

Field research
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

End
Identify participants in the study
Introducing research and risk
Analysis and
presentation of solutions Distribute and send the questionnaires Name of the company, the name of person,
for the bridge and explanations in person and phone qualification and work experience
construction projects
9 headlines of risk along with 46 risk factors
Yes Statistical analysis by SPSS-17

No Risk analysis using


accepted?
PertmasterV8

Fig. 1. Flowchart of the research.

various risks and uncertainties. Having several factors affecting projects due to the lack of systematic risk management and its
the goal of an engineering problem, would make it difficult to implications.
be solved by traditional methods (Naderpour et al. 2018; This study identifies comprehensively the risks influencing the
Naderpour and Mirrashid 2018). Construction projects are very bridge construction projects, illustrates how risks affect the time
complicated because they involve a large number of activities and and cost of a running project using Monte Carlo simulation method,
workers (Choudhry et al. 2014). Time control is the most impor- and proposes an application guide for project managers in Iran. The
tant determinant of a successful project (Pall et al. 2016). risk issue is related to variables such as culture, economics, politics,
The critical path method (CPM) has been widely used and management capabilities of each country, and can be a perspec-
for project scheduling (Paz et al. 2018), and various methods have tive for the assessment of success in any country, which means that
been developed by researchers for risk analysis. The project evalu- the lower the number and the likelihood of risks, the more disci-
ation and review technique (PERT) technique, proposed in 1985 by plined and stable is law and management in that country. System-
the US Maritime Academy, is a risk assessment tool (Choudhry atic risk management is not implemented in most projects in Iran,
et al. 2014). Risk management is an essential process to reduce and many traditional managers are indifferent in these cases, and
the time and cost and to increase the profit of a project. The ad- thus, unfortunately, projects suffer from many types of risks, and
vanced programmatic risk analysis model (APRAM) is a useful this leads to lower productivity and low quality, and increases costs
tool for risk management (Dillon and Pate-Cornell 2001). Risk out of the norm of the projects.
assessment involves qualitative and quantitative types. Qualitative
risk assessment is generally based on expert experience, and
quantitative evaluation is based on the impact of risks on time Materials and Methods
and cost. The analytical model of construction scheduling risks
evaluates construction activities under uncertainty when the op- This study is a systematic investigation of risks in the bridge con-
eration time and the risk factors are correlated with each other struction projects and construction workshops, and benefited from
(Ökmen and Öztaş 2008). Improper estimations of project targets the literature. The principle of this research was based on workshop
performed without detailed risk assessment can cause serious and field observations, distribution of questionnaires, face-to-face
problems in projects (Artan Ilter and Bakioglu 2018). interviews, and telephone interviews (Fig. 1). The stages included
The experiences of managers and of people in the project in identifying and collecting common and essential risks, field
some cases may reduce the risks locally, but cannot eliminate research, identifying participants, distributing the questionnaires,
risks in future activities, but they should be carefully scrutinized to statistical analysis, risk analysis, and presentation of solutions for
provide an appropriate response. In project evaluation, a lack of the bridge construction projects.
historical information on risks is more of a norm than an exception For this study, a questionnaire based on previous studies
(Chang and Ko 2017). (Etemadinia and Tavakolan 2016) and workshop observations
As a developing country, Iran has a great deal of construction, was prepared (Fig. 2). The questionnaire consisted of three parts.
with a massive budget spent annually on the construction and repair In Part 1, the research purpose and the fundamentals of risk were
of bridges. Many projects are subject to successive risks, leading to introduced. The second part asked the name and details of the per-
damage and even closures. Unfortunately, there are many losses to son answering the questionnaire, and their experience. The third

© ASCE 04019026-2 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


section included 9 types of risk along with 46 risk factors. The risks Before distributing the questionnaires, a meeting was held for re-
included in the questionnaire were financial, contractual, design, view with six experts in bridge construction, each of whom had more
safety, management, construction, external, environmental, and than 20 years of experience in building and managing bridge con-
postexploitation risks. struction projects, and the questionnaire was reviewed and corrected.
Financial risks included lack of budget, inflation, material price The responses were based on a five-point Likert scale including
growth, delays in financial payments, contractor bankruptcy, and insignificant, minor, moderate, major, and catastrophic (Boone and
economic losses. Contractual risks included changes in the scope Boone 2012). The respondents were selected from contractors
of work and agendas, contract contradictions, claims and disputes and workshop administrators. The questionnaires were distributed
with the contractor, and incorrect estimation of time and cost. De- by email, fax, and attendance at bridge construction workshops. A
sign changes, incomplete designs, and insufficient inspections on total of 112 questionnaires were distributed, and 105 respondents
the project site were considered in design risks. Safety risks in- answered; 7 people did not respond to the questionnaires. Pitman
cluded accidents, damage to property, and death. Inadequate project (2018) stated that a 20% response rate is convincing. Black et al.
planning, low expertise, poor coordination, poor site monitoring (2000) noted that a 30% response rate is appropriate for construc-
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

and management, robbery and strike of workers, addicted workers, tion projects. More than 80% of the subjects who completed
and poor-quality second-class contractors were considered as man- questionnaires had more than 10 years of experience in bridge
agement risks. Construction risks included delays in construction, construction projects. About 10% of them were consultants and
defective work and quality control, technology shortage, low labor employers, and 90% of the questionnaires were completed by con-
productivity, excess inspection, absent transparency of project tractor engineers. All respondents had at least a bachelor’s degree in
scope, unpredictable site conditions, climatic conditions, work in- civil engineering, and 30% had graduate degrees.
terruptions, and lack of space. Political instability, change in the The data were analyzed by SPSS version 17 software using pre-
behavior of government officials, management change, sanctions, liminary analysis, consistency analysis, and Pearson correlation.
and delay in budget priorities were categorized as external Furthermore, a case study of a bridge project illustrated the impact
risks. Environmental risks included infecting air and soil/water of risk on time and cost. The researcher was assisted by a specialist
sources of the project site. Explosion, fire, flood, earthquake, ex- workshop for doing this, and Monte Carlo simulation techniques
treme deformity, unpredictable subsidence, and excessive fatigue were used to analyze the risks in the case study. The most com-
were classified as postexploitation risks. monly used quantitative risk assessment method for decision

Fig. 2. Details of the distributed questionnaire (main part, including questions).

© ASCE 04019026-3 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


making is the use of a decision tree and the Monte Carlo simulation Table 1. Cronbach’s alpha measurement
technique (Liu et al. 2017). This expert team consisted of five mem- Quality Measure
bers (project manager, project control manager, construction and
Excellent 0.9 ≤ α
implementation manager, head of the workshop, and head of the
Good 0.8 ≤ α < 0.9
technical office). All team members had over 20 years of experi- Acceptable 0.7 ≤ α < 0.8
ence in bridge construction. The risks in this project and their im- Questionable 0.6 ≤ α < 0.7
pact on time and cost were determined by the team and applied as Weak 0.5 ≤ α < 0.6
percentages. Probability was determined as optimistic, probable, Unacceptable α < 0.5
and pessimistic activities. This type of possible time and cost al-
lowed the use of the beta distribution function in Pertmaster version
8. Many of the program details and inputs were proposed by the
expert team. in accordance with the Friedman test using SPSS version 17
(Arbuckle 2008) software as follows: (1) financial risks, (2) safety
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

risks, (3) external risks, (4) contractual risks, (5) management risks,
Results and Analysis (6) design risks, (7) environmental risks, (8) construction risks, and
(9) postexploitation risks.
Competency Assessment for Factor Analysis Risk prioritization is a type of qualitative analysis that allows the
employer and the contractor to be informed of the risks to which
The Kaiser-Mayer-Olkin (KMO) test and Bartlett’s sphericity tests they are exposed.
were used to guarantee the competency of factor analysis (Ye et al. Financial risks were at the top of the list. Financial risks mean
2013). The KMO test measures the adequacy of the sample size to that liquidity is not allocated to the projects correctly and at the
determine if the questions of the questionnaire can be categorized right time. It is considered to be a concern for all projects. Financial
into subfactors. Typically, the acceptable value should be higher risks regarding contracts, financing, and time progress of a project
than 0.5 (George 2011). The sampling adequacy index of the KMO cause much damage to the project and endanger project success.
test is specifically for exploratory factor analysis and shows if data Safety risks were in second place, reflecting the importance
are adequate for sampling adequacy analysis calculations or not. of this category for the respondents. Unfortunately, safety in Iran
The value of KMO must be greater than 0.5; some believe that is not taken into account, and many projects have suffered from
the KMO value must be greater than 0.9. Some texts mention that material and life losses due to absent safety factors. Injuries and
if KMO is greater than 0.9 it is excellent and if it is less than 0.5 it is deaths of the workforce have been reported in most bridge con-
not acceptable. Others believe that if the value of this parameter is struction workshops because of nonobservance of safety. Through
greater than 0.7, existing correlations are well suited for factor familiarization with bridge construction projects, the researcher
analysis; if it is between 0.5 and 0.69, the researcher must be care- noted several deaths (workers, engineers, and heads of workshops)
ful; and if it is less than 0.5 it is not suitable for factor analysis. in different work periods in various projects.
The questions of a questionnaire must be correlated with each External risks ranked third. These types of risks are more likely
other to some determined extent, and too much correlation may to be found in countries with national and international tensions.
result in multicollinearity, which will stop deriving independent
According to many experts, sanctions have hurt all domestic
factors. On the other hand, if correlation between questions of ques-
and international labor relations.
tionnaires is less than a specific amount, an identity matrix issue
Contractual risks were in fourth place. Contractual problems in
will be encountered. In order to test this, Bartlett’s test of sphericity
many projects have caused unwanted legal incidents. Several suit-
is used. Significance of the Bartlett’s test of sphericity indicates that
able contract patterns can be determined due to the variety of bridge
the material matrix has enough correlation for continuing factor
construction and different conditions.
analysis (Cerny and Kaiser 1977). The Bartlett’s sphericity test cre-
Management risks ranked fifth. This reflects the fact that the
ates a matrix union so that sufficient correlation must exist in the
respondent personnel were optimistic about the management of the
matrix for further factor analysis.
workshop and the organization, and there were no particular man-
The result of the KMO test was 0.843, and the result of Bartlett’s
agement problems in these projects.
sphericity test was 1,568,932.
Design risks ranked sixth. This rating reflects the relative famili-
arity of the designers with the problems of project implementation.
Internal Consistency Analysis Often, however, deficiencies in the plans are identified during
The internal consistency was calculated for all items to ensure the execution, which are solved by the consultant team.
reliability of the Cronbach’s alpha (CA) coefficient (Carmines and Environmental risk was ranked seventh. This rating indicates
Zeller 1979). CA is a statistic that gauges the internal consistency that risks of this type do not affect projects negatively.
of survey questions that load into the same factors (Table 1). Ideal Construction risk was in eighth place. This position for
uses for CA involve measuring the internal consistency among sur- construction risks represents the standardization of most of the ac-
vey questions (Gliem and Gliem 2003). tivities of the units in the bridge construction. The dominance of
This calculation was done for the 9 main factors and 47 risk managers and engineers in the construction and execution proc-
factors, and ranged between 0.719 and 0.948, so all were higher esses makes the training of the units fully operational.
than 0.7, indicating that the questionnaire was reliable (Ghosh Postexploitation risks were ranked ninth, suggesting that
and Jintanapakanont 2004). According to the calculations, the the respondents did not deal with such issues in their work
Cronbach’s alpha coefficient was 0.878. experience or that these issues were very restricted in their work
experience.
These results and rankings of factors can be compared between
Prioritization
Iran and Pakistan. According to a study in Pakistan (Choudhry et al.
After distributing the questionnaire among the respondents, risk 2014), the order of risks from the greatest to the least was as
prioritization is one of the most critical tasks, and was performed follows: financial risks, external risks, engineering (design) risks,

© ASCE 04019026-4 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Table 2. Pearson product-moment correlation of risk factor categories
Category Financial Contractual Design Safety Management Construction External Environmental Postexploitation
Financial 1 — — — — — — — —
Contractual 0.593 1 — — — — — — —
Design 0.399 0.535 1 — — — — — —
Safety 0.506 0.341 0.279 1 — — — — —
Management 0.493 0.502 0.547 0.633 1 — — — —
Construction 0.511 0.602 0.574 0.629 0.775 1 — — —
External 0.511 0.638 0.574 0.306 0.558 0.58 1 — —
Environmental 0.306 0.268 0.284 0.435 0.679 0.521 0.377 1 —
Postexploitation 0.437 0.397 0.489 0.55 0.448 0.527 0.596 0.363 1
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

managerial risks, construction risks, contractual risks, and safety to construction and management risks, highlighting that manage-
risks. ment and construction risks are changed directly by altering each
other, and the rate of this change is relatively steady. Another
Pearson correlation coefficient with a high value was related to
Pearson Correlation management and environment risks (r ¼ 0.679), underlining a
The Pearson correlation indicates a linear relationship between two strong correlation between these two risks. A different correlation
variables. It is not difficult to determine the correlation coefficient coefficient, which was ranked next, was related to external and con-
using statistical software. This coefficient is usually between þ1 tractual risks (r ¼ 0.638), indicating direct changes between these
and −1. The sign reveals the direction of the correlation between two risks. The next rank for the magnitude of the correlation co-
these variables. A positive coefficient means that if a variable is efficient was related to safety and management risks (r ¼ 0.633),
increased, the other variable also will increase. A negative coeffi- which reflects the value of management discussion following
cient means that if the first variable is decreased, the other variable changes in safety risks.
will increase. A larger number indicates a stronger correlation; for
example, r ¼ 0.6 indicates a stronger correlation than r ¼ 0.5.
The correlation coefficient r ¼ 0 indicates a lack of linear correla- Case Study of Bridge Construction Project
tion between the two variables, and coefficients r ¼ þ1 and −1
represent a complete linear correlation (Field 2000). The project under investigation is a concrete bridge near the city
Pearson correlations were calculated for the risk factors of Tehran. This project is under construction to improve traffic
(Table 2). The most significant correlation (r ¼ 0.775) was related and access to surrounding streets. The bridge construction method

Fig. 3. Images of bridge case study. (Images by Seyedmehdi Mortazavi.)

© ASCE 04019026-5 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Table 3. Probability at start of project
Activity Baseline start P80 start P100 start Actual
Site preparation September 22, 2017 September 22, 2017 September 22, 2017 September 22, 2017
Phase 1 (piers) October 22, 2017 October 24, 2018 October 28, 2018 September 18, 2018
Phase 2 (slab, and so forth) May 30, 2018 June 24, 2018 August 25, 2018 —

Table 4. Probability at the end of the project


Activity Baseline finish P80 finish P100 finish Actual
Site preparation October 21, 2017 October 21, 2017 October 27, 2017 October 21, 2017
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

Phase 1 (piers) June 18, 2018 July 19, 2018 September 15, 2018 July 20, 2018
Phase 2 (slab, : : : ) December 03, 2018 January 06, 2019 March 17, 2019 —

Table 5. Project possible costs (IRR) To check the scheduling, initially the schedule was calculated
Activity Baseline cost P80 cost P100 cost Actual cost without taking into account the risks with probabilistic time and
beta distribution function. The estimated values were as follows
Site preparation 2.42 × 1010 2.49 × 1010 2.61 × 1010 2.58 × 1010
(Fig. 4). The minimum time to complete the project was 388 days.
Phase 1 (piers) 2.93 × 1011 3.05 × 1011 3.27 × 1011 3.18 × 1011
Phase 2 2.21 × 1011 2.32 × 1011 2.55 × 1011 — The maximum time to complete the project was 542 days. The most
(slab, and so forth) probable time to complete the project was 452 days, with a prob-
ability of 80% that the project would be completed in 472 days.
Similarly, there was a probability of 50% that the project would
be completed in 450 days. There was a probability of 30% that
is top-down. The concrete deck slab length is 350 m. The deck the project would be completed in 437 days. According to the site
slab area is 11,500 m2 . The traffic lane width is composed of schedule approved by the consultant and the employer, the total
two 11-m lanes. Furthermore, 750 piles with diameters of 1.1 m time of the project is considered to be 438 days.
to 1.2 m and heights of 20–32 m were used. Fig. 3 shows photos Concerning the possible project costs, the calculated items in
of the project. Fig. 4 were as follows (Fig. 5). The maximum estimated cost
After the necessary examinations, the project schedule was pre- for the project was IRR 590 billion (USD 16.8 million). The mini-
pared. Then the project team, including project manager, site man- mum estimated cost for the project was IRR 494 (USD 14.11 mil-
ager, technical office manager, project planning control manager, lion). The most likely estimated cost for the project was IRR
and site inspector, were selected. Following various meetings with 542 billion (USD 15.5 million). There was a probability of 48%
the project team and explaining the research objectives and the that the project would cost IRR 541 billion (USD 15.4 million).
topic of risk analysis with the help of the project team, the time There was a probability of 50% that the project would cost IRR
and cost of (optimistic, probable, and pessimistic) activities were 543 billion USD 15.51 million). There was a probability of
determined. Subsequently, the most critical risks were selected 80% that the project would cost IRR 557 billion (USD 15.91 mil-
by the project team according to the qualitative assessment and risk lion). According to the project schedule, the final cost of the project
prioritization, prepared as questionnaires. After this stage, the prob- will be IRR 541 billion.
ability of risks and their effects on the activities were examined
during the meeting, and the necessary steps were taken to record Quantitative Analysis of Risk
the numbers proposed by the project team in Pertmaster. Input data
to the program included risk numbering, threat-opportunity, risk As explained previously, the project team selected the most criti-
explanation, probability of risk, correlation of risk and activity, cal risks for the project. The selective risks included (1) lack
distribution type of time, and risk type (time-cost). of budget, (2) inflation, (3) incorrect estimated time and cost,
The quantitative analysis of the risks was performed in Pertmas- (4) claims, (5) incomplete design, (6) accidents, (7) incomplete
ter using the Monte Carlo simulation method (Williams 2012). planning, (8) poor-quality second-class contractors, (9) low exper-
This method provides approximate answers for quantitative tise, (10) delays in construction, (11) low labor productivity,
problems by statistical sampling. In general, it is a simulation that (12) sanctions, and (13) delays in financial payments.
explicitly and quantitatively represents uncertainties; thus the After selecting the preceding risks, the probability of risks and
whole system is simulated a large number of times (e.g., 1,000). the effect of time-cost with the uniform distribution function were
Each simulation is called a realization of the system. For each reali- assigned to the selected activities, and Pertmaster recalculated the
zation, all the uncertain parameters are sampled. Then the system is time and cost. The results of the calculations are as follows.
simulated over time so that the system performance can be calcu- The minimum probable project completion time was 484 days
lated. This leads to a large number of independent and separate (Figs. 6 and 7). The maximum probable project completion time
results, each of which represents a possible future for the system was 788 days. However, the most probably project completion
(Castro-Santos and Diaz-Casas 2015). The results of the autono- time was 608 days. There was a probability of less than 1% that
mous system realizations are in the form of probability distributions the project would be completed in 438 days (March 21, 2018).
of possible outputs. Hence, the outputs are not single, but proba- There was a probability of 50% that, the project would be
bility distributions (Tables 3, 4 and 5). completed in 608 days (May 22, 2019). There was a probability

© ASCE 04019026-6 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

Fig. 4. Pert technique (duration).

Fig. 5. Pert technique (cost).

© ASCE 04019026-7 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

Fig. 6. Monte Carlo simulation result.

of 80% that the project would be completed in 660 days (July 21, The researcher’s suggestion is to create a risk management
2019). option (RMO) in contractor companies and state agencies and
The calculation of the project cost was verified by taking to submit monthly codified risk analysis reports to upstream
into account the risk (Fig. 8). The maximum estimated cost managers.
for the project was IRR 691 billion (USD 19.7 million). The mini- 2. Abandoning unprofessional timetables—in some of the work-
mum estimated cost for the project was IRR 510 billion (USD shop meetings and observations, it was found that the timeline
14.57 million). The most likely estimated cost for the project was often unrealistic, and the project significantly deviated from
was IRR 614 billion (USD 17.54 million). There was a proba- the schedule. This is a severe risk to a project. Improper plan-
bility of 4% that the project would cost IRR 541 billion (USD ning and mismatching of activities with time will cause inaccu-
15.45 million). There was a probability of 50% that the project rate estimates in the macroscale of the project, and the risks
would cost IRR 620 billion (USD 17.71 million). There was a involved in the project at random times will cause severe
probability of 80% that the project would cost IRR 642 billion damage to the project.
(USD 18.34 million). 3. The correct estimation of the risk effects on the activities and the
project—failure to accurately estimate the impacts and probabil-
ities of risks can lead to significant mistakes in project manage-
Important Strategies for Risk Analysis
ment. Incorrect estimates will directly affect the time and cost of
By considering the scientific and practical research in the discus- the project, may cause waste of project resources, and may lead
sion of risk analysis in the bridge construction, the following issues to further decisions with many problems. It is recommended to
were investigated: use expert groups in this field.
1. The knowledge of bridge construction companies regarding the 4. Utilization of standard risk simulation techniques—there are
concepts of risk analysis—field studies, project site observa- many techniques for quantitative analysis of the risks, but the
tions, and attendance at various bridge construction workshops, Monte Carlo simulation method is one of the easiest and
should consider that the risk category is not explored in a stan- best techniques, and Pertmaster software with a professional
dardized and systematic manner in contracting companies in and appropriate structure can provide a proper analysis to
Iran, and management teams are working to create a contract project decision makers.
and implement the project with a limited knowledge of the 5. Description of the output tables of Pertmaster—one of the
nature and categorization of risks and their consequences, so most critical parts of risk analysis is the use of multiple charts
that in many cases the project experiences various problems. in Pertmaster. With the application of the correct interpretation

© ASCE 04019026-8 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

Fig. 7. Monte Carlo simulation finish date.

of the various types of graphs (time, cost, sensitivity, scatter, and cases mentioned in this research. Regarding data tables and
so forth), a comprehensive assessment of the project can be calculations which were based on project scheduling, based on
made that which would be effective in decision making process expert’s ideas, projects risks and their quantities were entered in
of projects. Pertmaster 8; considering time and cost calculations, the following
estimates are presented. In project schedules, range of time change
risk for minimum probability regarding the project completion
Conclusion would increase the project time by 24%, and in an extreme case
increased project time by 45%; the most probable project comple-
Because of the strategic importance of bridges in suburban and
tion time increased the project time by 34%. The calculation of risk
urban roads and the specific conditions of Iran, politically and
economically, risk assessments were conducted. Identification effects on project costs indicated that a range of 3%–17% in the
and prioritization of risks were based on questionnaires in bridge most probable state will increase project costs by 13%.
construction workshops and on the opinion of engineers and Project managers, contractors, and anyone involved in project
experts in bridge construction in various interviews and meetings risk management must note that risks and their impacts should
using statistical software, resulting in prioritization of risks as be assessed in different phases of a project and the risk management
follows: (1) financial risks, (2) safety risks, (3) external risks, team should constantly audit risks and report their impacts to man-
(4) contractual risks, (5) management risks, (6) design risks, agers. In most projects in Iran, the identified framework can solve
(7) environmental risks, (8) construction risks, and (9) postexploi- the problems of and help the plans for bridge construction projects.
tation risks. A case study investigated the effect of risks and their Modeling and exploiting the experiences from past projects can in-
quantitative analysis using workshop schedules, expert opinions, crease the potential for project success, resulting in more accurate
the Monte Carlo simulation method, and Pertmaster software; es- and transparent forecasts for the future of the project, more efficient
sential tables regarding the impact of risks on time and cost were use of existing resources, and reduction in the losses. The results of
calculated, and general and specific solutions were presented that, this study can help project managers to enter projects with open
according to the researcher, can be implemented in bridge construc- eyes and celebrate the successful opening of the project. This is
tion projects in Iran. The researcher attempted to compile a com- probably the only real and systematic research on the risks involved
prehensive framework for information on existing risks in the in bridge construction projects in Iran, the trends and outcomes of
present circumstances of Iran, but a specific project at a particular which can be considered suitable technical and managerial guide-
site may be defined for specific purposes without evaluating all the lines for bridge construction companies.

© ASCE 04019026-9 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

Fig. 8. Monte Carlo simulation cost result.

Data Availability Statement Castro-Santos, L., and V. Diaz-Casas. 2015. “Sensitivity analysis of float-
ing offshore wind farms.” Energy Convers. Manage. 101: 271–277.
All data, models, and code generated or used during the study https://doi.org/10.1016/j.enconman.2015.05.032.
appear in the paper. Cerny, B. A., and H. F. Kaiser. 1977. “A study of a measure of sampling
adequacy for factor-analytic correlation matrices.” Multivariate Behav.
Res. 12 (1): 43–47. https://doi.org/10.1207/s15327906mbr1201_3.
Chang, C.-Y., and J.-W. Ko. 2017. “New approach to estimating the stan-
References
dard deviations of lognormal cost variables in the Monte Carlo analysis
Akintoye, A. S., and M. J. MacLeod. 1997. “Risk analysis and management of construction risks.” J. Constr. Eng. Manage. 143 (1): 06016006.
in construction.” Int. J. Project Manage. 15 (1): 31–38. https://doi.org https://doi.org/10.1061/(ASCE)CO.1943-7862.0001207.
/10.1016/S0263-7863(96)00035-X. Choudhry, R. M. 2016. “Appointing the design consultant as supervision
Arbuckle, J. 2008. Amos 17.0 user’s guide. Chicago: SPSS Inc. consultant on construction projects.” J. Leg. Aff. Dispute Resolut. Eng.
Artan Ilter, D., and G. Bakioglu. 2018. “Modeling the relationship between Constr. 8 (4): 04516005. https://doi.org/10.1061/(ASCE)LA.1943-41
risk and dispute in subcontractor contracts.” J. Leg. Aff. Dispute Res- 70.0000195.
olut. Eng. Constr. 10 (1): 04517022. https://doi.org/10.1061/(ASCE) Choudhry, R. M., M. A. Aslam, J. W. Hinze, and F. M. Arain. 2014.
LA.1943-4170.0000246. “Cost and schedule risk analysis of bridge construction in Pakistan:
Asgari, M., A. Kheyroddin, and H. Naderpour. 2018. “Evaluation of project Establishing risk guidelines.” J. Constr. Eng. Manage. 140 (7):
critical success factors for key construction players and objectives.” Int. 04014020. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000857.
J. Eng. 31 (2): 228–240. Choudhry, R. M., and K. Iqbal. 2013. “Identification of risk management
Bahamid, R. A., and S. I. Doh. 2017. “A review of risk management system in construction industry in Pakistan.” J. Manage. Eng. 29 (1):
process in construction projects of developing countries.” Mater. Sci. 42–49. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000122.
Eng. 271 (1): 012042. Dikmen, I., M. T. Birgonul, and A. E. Arikan. 2004. “A critical review of
Black, C., A. Akintoye, and E. Fitzgerald. 2000. “An analysis of success risk management support tools.” In Proc., 20th Annual Conf. of Asso-
factors and benefits of partnering in construction.” Int. J. Project Man- ciation of Researchers in Construction Management (ARCOM), 1–3.
age. 18 (6): 423–434. https://doi.org/10.1016/S0263-7863(99)00046-0. Chennai, India: ARCOM.
Boone, H. N., and D. A. Boone. 2012. “Analyzing Likert data.” J. Exten- Dillon, R. L., and M. E. Pate-Cornell. 2001. “APRAM: An advanced
sion 50 (2): 1–5. programmatic risk analysis method.” Int. J. Technol. Policy Manage.
Carmines, E. G., and R. A. Zeller. 1979. Reliability and validity assess- 1 (1): 47–65. https://doi.org/10.1504/IJTPM.2001.001744.
ment: Quantitative applications in the social sciences. Thousand Oaks, Etemadinia, H., and M. Tavakolan. 2016. “Fuzzy weighted interpretive
CA: SAGE. structural modeling: A new method for risks path identification of

© ASCE 04019026-10 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026


the infrastructure projects.” In Construction Research Congress 2016, networks.” Measurement 126 (Oct): 299–308. https://doi.org/10.1016/j
2841–2850. Reston, VA: ASCE. .measurement.2018.05.051.
Farooqui, R. U., S. H. Lodi, and F. Saleem. 2007. “Risk management per- Naji, H. I., and R. Hussein Ali. 2018. “Risk response selection in construc-
ceptions and trends among construction contractors in Pakistan.” In tion projects.” Civ. Eng. J. 3 (12): 1208.
Proc., 4th Int. Conf. on Construction in the 21st Century: Accelerating Ökmen, Ö., and A. Öztaş. 2008. “Construction project network evaluation
Innovation in Engineering, Management and Technology (CITC IV with correlated schedule risk analysis model.” J. Constr. Eng. Manage.
2007), Gold Coast, Australia. 134 (1): 49–63. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:
Field, A. 2000. Discovering statistics using SPSS for Windows: Advanced 1(49).
techniques for beginners (Introducing Statistical Methods series). Pall, G. K., A. J. Bridge, M. Skitmore, and J. Gray. 2016. “Comprehensive
London: SAGE. review of delays in power transmission projects.” IET Gener. Transm.
George, D. 2011. SPSS for windows step by step: A simple study guide and Distrib. 10 (14): 3393–3404. https://doi.org/10.1049/iet-gtd.2016.0376.
reference, 17.0 update, 10/e. Chennai, India: Pearson Education India. Paz, J. C., D. Rozenboim, Á. Cuadros, S. Cano, and J. Escobar. 2018. “A
Ghosh, S., and J. Jintanapakanont. 2004. “Identifying and assessing the simulation-based scheduling methodology for construction projects
critical risk factors in an underground rail project in Thailand: A factor considering the potential impacts of delay risks.” Constr. Econ. Build.
Downloaded from ascelibrary.org by The University of Adelaide on 08/06/23. Copyright ASCE. For personal use only; all rights reserved.

analysis approach.” Int. J. Project Manage. 22 (8): 633–643. https://doi 18 (2): 41. https://doi.org/10.5130/AJCEB.v18i2.5842.
.org/10.1016/j.ijproman.2004.05.004. Pitman, E. J. G. 2018. Some basic theory for statistical inference:
Monographs on applied probability and statistics. London: Chapman
Gliem, J. A., and R. R. Gliem. 2003. “Calculating, interpreting, and report-
and Hall/CRC Press.
ing Cronbach’s alpha reliability coefficient for Likert-type scales.” In
Raftery, J. 2003. Risk analysis in project management. London: Routledge.
Midwest Research-to-Practice Conf. in Adult, Continuing, and Commu-
Reilly, J., and J. Brown. 2004. “Management and control of cost and risk
nity Education. Columbus, OH: Ohio State Univ.
for tunneling and infrastructure projects.” In Tunneling and Under-
Liu, B., and F. Sun. 2019. “Research on the risk assessment method of PPP
ground Space Technology. Underground Space for Sustainable Urban
project based on the improved matter element model.” Sci. Iranica. Ac- Development. Proc., 30th ITA-AITES World Tunnel Congress Singa-
cessed August 08, 2018. http://scientiairanica.sharif.edu/article_20820 pore, 22–27 MAY 2004. Geneva, Switzerland: ITA-AITES.
.html. Schuyler, J. R. 2001. Risk and decision analysis in projects. Newton
Liu, J., F. Jin, Q. Xie, and M. Skitmore. 2017. “Improving risk assessment Square, PA: Project Management Institute.
in financial feasibility of international engineering projects: A risk Wang, J., and H. Yuan. 2017. “System dynamics approach for investigating
driver perspective.” Int. J. Project Manage. 35 (2): 204–211. https://doi the risk effects on schedule delay in infrastructure projects.” J. Manage.
.org/10.1016/j.ijproman.2016.11.004. Eng. 33 (1): 04016029. https://doi.org/10.1061/(ASCE)ME.1943-5479
Naderpour, A., J. Majrouhi Sardroud, M. Mofid, Y. Xenidis, and T. Pour .0000472.
Rostam. 2019. “Uncertainty management in time estimation of con- Williams, D. L. 2012. Oracle primavera P6 Version 8: Project and
struction projects: A systematic literature review and new model devel- portfolio management. Packt.
opment.” Sci. Iranica 26 (2): 752–778. Williams, R. C., J. A. Walker, and A. J. Dorofee. 1997. “Putting risk man-
Naderpour, H., and M. Mirrashid. 2018. “An innovative approach for com- agement into practice.” IEEE Software 14 (3): 75–82. https://doi.org/10
pressive strength estimation of mortars having calcium inosilicate min- .1109/52.589240.
erals.” J. Build. Eng. 19 (Sep): 205–215. https://doi.org/10.1016/j.jobe Ye, K., B. Li, and L. Shen. 2013. “Key factors considered in compiling
.2018.05.012. tender prices for China’s public works projects.” J. Manage. Eng.
Naderpour, H., O. Poursaeidi, and M. Ahmadi. 2018. “Shear resistance pre- 29 (3): 206–215. https://doi.org/10.1061/(ASCE)ME.1943-5479
diction of concrete beams reinforced by FRP bars using artificial neural .0000153.

© ASCE 04019026-11 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2019, 24(4): 04019026

You might also like