Professional Documents
Culture Documents
Index: S. NO. Particulars NO
Index: S. NO. Particulars NO
INDEX
S. NO. PARTICULARS PAGE
NO.
CHAPTER-1
1. Project Background 4
CHAPTER-2
CHAPTER – 3
CHAPTER – 4
7. Detailed Methodology , 9
CHAPTER –5
16. Methodology
17. Bituminous Surfacing Course, Wearing Course, Granular Sub Base 14-15
Course (WMM)
CHAPTER – 6
CHAPTER - 7
ABBREVIATIONS
CHAPTER-1
PROJECT BACKGROUND
Ministry of Road Transport & Highways desired to convert all Level Crossings on National
Highways to ROBs/RUBs in a phased manner in time bound period. Accordingly, proposals
invited from eligible consultants for prioritization and preparation of Project Report of proposed
ROBs/RUBs. The work shall consist of all the work except submission of Detailed Design and
Working drawings. The work is divided in to 2 packages. Ministry of Railways has already
submitted the railway portion Drawings of ROBs. They have requested Ministry of Road Transport
and Highways to plan out approaches of these ROBs. Ministry of Road Transport and Highways
decided to procure the services of a Saanvi Infrastructure Private Limited to carry out feasibility
study, detailed survey/investigation, alignment option, preparation of general arrangement
drawing and engineering report for construction of proposed ROB & their approaches in
replacement of existing level crossings.
AWARD OF CONTRACT
Consultancy Services for carrying out feasibility study, Detailed Survey/Investigation, Alignment
Option, Preparation of General Arrangement Drawing & Engineering Report for Construction of
Proposed R.O.B and their approaches in Replacement of Existing Level Crossing in the State of
Assam. Package No 1, have been entrusted to SAANVI INFRASTRUCTURE PVT. LTD. vide GOI
MORT&H vide their letter no CE/STBR/14/2017-18/65 dated 27October 2017.
PRESENT TASK
The Feasibility study is for ROB & its approaches at Bijniin Replacement of Railway Level
Crossing Gate No.SK-45 at KM-268/3 on BijniRoad. During the reconnaissance Survey by us, it is
observed that
1. The speed of the vehicles is restricted due to movement of public in the habitant area.
2. The number of train crosses 120 times in 24 hrs.
3. The difficulties experienced by the public & necessity arose to build ROB for smooth move of
traffic at all the time.
4. The chances of accident will be reduced by providing ROB.
5. As per the GOVT policy, the provision of ROB is essential at every level crossing railway line.
1. 1st priority will be given to the projects which are viable on BOT mode without VGF.
2. 2nd priority will be given to the projects with VGF up to 40%.
3. The project to be taken on EPC mode.
The Scope of Services shall thus cover all steps involved in Detailed Project Report except
submission of detailed Structural Design and Working Drawings:-
CHAPTER-2
RECONNAISSANCE SURVEY
The Team of Highway Engineer along with senior survey expert visited the site & found the
following:-
a. The existing level crossing (SK-45) and proposed ROB at Lumding Yard-railway level
Crossing Gate on Road from Lumding Divisional Railway Manager office to Lumding Railway
Station South Entrance and to Railway Stadium near Horlangfur Bridge in Assam State.
b. The traffic intensity will be on higher side future coming years.
c. ROW is available 24.38 m in width on both sides of approaches from proposed ROB in the
length of survey carried out 550m approximate in length.
d. During ROB construction, the service road will be made along the existing road leading
towards ROB.
e. The existing road feature of this stretch is as under:-
9. Terrain Plain
Note:- As per Discussion held with PWD official , the ROW was PWD official and captured
during topographical survey.
The Consultant shall submit to the employer the following reports and documents after completion
of each stage of work as per TOR:-
SL. ALLOTTED
DESCRIPTION OF DELIVERABLE PERIOD
NO.
1 Submission of site plan and preliminary data 45 days
2 Submission of Draft Detailed Project Report 120 days
3 Submission of Final Detailed Project Report 180 days
NOTE: - Additional Six months will be provided for getting the approval from Railways. However,
the report shall be submitted within 180 days except approval. The work will be said to be
completed only when the approval from railway is obtained.
CHAPTER-3
Section:- Approach Road from Lumding Divisional Railway Manager office to Railway Colony. Date of Survey:
EMBA
ROA
NKME
D
PAVE NT
SIDE
MENT COND
PAVEMENT SHOULDE RIDING DRA
CHAINAGE PAVEMENT COMPOSOTION EDGE ITION Remarks
COMPOSOTION R QUALITY IN
DROP (GOO
(NE/
(MM) D/FAI
PF/F
R/PO
)
OR)
CON
RUT
DITI
CO CR PORTH (NON PATC
ON SPE QUAL RAV
FRO THI MP AC OLES E/MO HING
TO COMPO TYP (FAI ED ITY ELLI
M CKN OS KI (NO & DCRA (NO &
(m) SITION E R/P (KM/ G/F/P/ NG
(m) ESS ITI NG %/ TE/SE %/
OR/ HR) VP (%)
ON (%) 100M) VARE 100M)
FAIL
)
D)
Reconnai
ssance
survey
carried
Not out &
Rest
SURFAC Bitu mea Goo 20 to Not observed
- ricte G - - - - - -
E men sure d 40mm exist the road
d
260 d width of
Tow carriage
from
ards way is
ROB
DRM 6.80 to
Build 8.54 m
ing
BINDER
BASE
SUB-
BASE
SUBGR
ADE
Reconnai
ssance
survey
carried
out &
Not
Rest observed
SURFAC Bitu mea 20 to Not
- fair ricte G - - - - - - the road,
E men sure 40mm Exist
Tow d the width
d
ards of
260 carriage
Rail
from way is
way
ROB 6.80 to
Colo
ny 8.54 m
BINDER
BASE
SUB-
BASE
SUBGR
ADE
NOTE:-
1. The width of carriage way is 6.8 m to 8.54 m & ROW is 24.38m as intimated by PWD
official.
2. The Railway crossing exists at Gate No.SK-45 at KM-268/3 on BijniRoad.
CHAPTER-4
DETAILED METHODOLOGY
GENERAL
For successful and efficient rendering of services, the Consultant proposes to take a sound
engineering approach based on a clear understanding of the Terms of Reference and the relevant
planning and systems approach.
RECONNAISSANCE SURVEY
The Consultant has carried out a preliminary field reconnaissance of the Project site covering all
possibilities. The aim of this preliminary reconnaissance was to familiarize the Team members
with the project site.
SOIL INVESTIGATION
Sub grade Investigations- The Sub grade investigations will normally be done in the following
manner:
o Visual classification;
o In-Situ density and moisture content;
o Characterization (grain size and Atterberg’s limits);
o Laboratory density and moisture content characteristics; and,
o Laboratory CBR and swell.
For problematic soils, the testing will be more rigorous. The characteristics with regard to
permeability and consolidation will also be determined for these soils. The frequency of sampling
and testing of these soils would be finalized after the problematic soil types are identified along the
road.
Sub grade soils will be tested in the field and samples collected for laboratory testing at regular
intervals or for every change of soil type. The testing and sampling interval will be as per TOR.
o Hard stone (for crushed aggregate base, Asphalt surfacing courses and concrete);
o Sand (for concrete) and,
o Water for construction.
Potential sources for the construction material will be identified for the whole length of the
road. The testing for borrow areas for ascertaining their suitability as Sub grade and fill
materials will include:
o Identification tests (grain size and Atterberg’s Limits);
o Organic matter content (if deemed necessary);
o moisture-density characteristics); and,
o Laboratory CBR (unsoaked and 4 day soaked) and swell.
GRAVEL: - Gravel quarries will be investigated and tested in the laboratory to establish their
soundness and engineering characteristics. Each quarry located will be explored in order to
identify suitable sources of sub-base material. The testing on gravel samples will include:
o Identification (grain size and Atterberg’s Limits);
o Sand equivalent (if deemed necessary);
o Natural moisture content;
o Density - moisture content relationships (modified proctor); and, 4-day soaked CBR.
HARD STONES: - The investigations for hard stones will comprise qualitative and quantitative
assessment of potential quarries and to determine their suitability for use in:
o Graded crushed stone base and sub-base;
o Chipping's for surface dressing layers;
o Asphalt base and wearing courses; and,
o Concrete works.
The potential sources of hard stones identified on the basis of desk study of geological maps and
information collected from the reconnaissance of the area will be thoroughly investigated during
this task. The sources of hard stone in the area will be identified and sampled, as far as possible,
within the economic hauling distance.
STONE SAMPLES: - The testing of hard stone samples for ascertaining their suitability inroad
construction and concrete works will include:
o Specific gravity;
o Water absorption;
o Flakiness index (for crushed aggregates from existing crushing plants);
o Los Angeles Abrasion Value (LAV);
o Aggregate impact value (AIV));
o Bitumen affinity and stripping value;
o Chemical tests (total soluble salts, chloride content, sulphate content, alkali- silica
reaction);and,
o Sodium sulphate soundness.
SAND: - Potential sources of sand will be identified. The testing for sand samples in the laboratory
will include:
o Grain size analysis;
o Sand equivalent;
o Specific Gravity
o Deleterious Material (%)
o Chemical tests (sulphate and chloride).
Each potential borrow area and source will be assigned a unique code number for easy reference.
For potential hard stone quarries, the Consultant will also suggest quarrying method based on
engineering geology.
We shall carry out geo-technical investigations and sub-surface explorations for the proposed
structures (Road over bridges) including high embankments and any other location as necessary
for proper design of the works and conduct all relevant laboratory and field tests on soil and rock
samples as per the guidelines in IRC- 78:2000.
We shall submit the detailed proposal for geotechnical investigation after the approval of
Alignment and combined GAD submitted during the Feasibility Study. After approval of the same,
we shall start the geotechnical investigation for the bridges. Detailed Geotechnical and sub-
surface investigations conforming to the established standards and as deemed necessary, will be
carried out at all proposed bridge and high embankments locations (where required). The sub-soil
exploration investigations will also be used for span arrangement for bridges. The data of
particular importance for the design of structures include:
o Soil profile;
o Foundation stratum;
o Strength characteristics.
o Safe bearing capacity; and,
o Rock stratum.
The strength of soil layers will be evaluated in the field using SPT tests. The laboratory testing of
soil samples will normally include:
o Soil characterization (grain size distribution and Atterberg’s Limits);
o Moisture content, natural density and chemical tests;
o Shear strength parameters and
o Consolidation parameters.
The geological investigations will be preceded by a detailed study of engineering geology and also
seismological information for the area. The parameters for design will be selected after careful
consideration of the engineering strength values and geological information. The investigations for
high embankment (where required) will be carried out as per IRC special specifications No75. For
major bridges, the boreholes will be investigated under each foundation, whereas, for minor
bridges, the bore hole will be investigated as stipulated in the TOR.
All Laboratory & Field test will be conducted as per different IS codes as mentioned below:-
Field Test
Digging of exploratory bore holes
Collection of disturbed and undisturbed samples for laboratory an IS- 1892:1986.
analysis.
Visual identification of soil group and stratification
Carrying out standard penetration tests IS- 2131:1981
Observation of ground water table in each bore hole
Laboratory Test
Grain size Analysis IS: 2720 (Part-IV) –1985
Atterberg’s limits IS: 2720 (Part-V) – 1985
Specific Gravity IS: 2720 (Part-III) – 1980
Natural Moisture Content, Field out Dry Density IS : 2720 (Part-10) –1973
Unconfined compression Test on undisturbed cohesive samples IS : 2720 (Part-10) – 1991
Direct Shear Test on cohesion less Soil samples IS : 2720 (Part-13) – 1986
Axial Shear Tests in unconsolidated Un drained condition (VV IS: 2720 (Part-15) – 1986
test) on cohesive soil samples and in consolidated drained
condition (CD test) in Granular Soil sample
Consolidation test on cohesive soil samples for determination of IS : 2720 (Part-15) – 1986
settlement criteria
Void Rates in natural condition
The design standards enumerated in the Inception Report were broad based and relating these on
the ground and assessment of site conditions during field survey and investigations, have been
frozen as per relevant codes and standards. The standards adopted are given in succeeding
paragraphs. Methodologies have been stated in the Inception Report and hence not repeated in
detail again.
UTILITY SHIFTING
The detail inventory for all utilities will be collected from ground reconnaissance. After the widening
scheme is finalized, utilities shall be identified which require relocation. Subsequently a plan
showing all such utilities to be relocated shall be prepared separately for all utilities. A schedule for
relocation of utilities shall be prepared. Joint ground verification shall be conducted with respective
departments. After joint site verification of data and subsequent discussion with the respective
departments, an indicative cost estimate shall be obtained from respective departments and this
cost shall be included in the Total Project Cost (TPC).
TECHNICAL SPECIFICATIONS
The Technical Specifications in accordance with which the entire work described in Bid Document
shall be constructed and completed by the Contractor shall comprise of the following:
The Special Technical Specifications, provided in this document, shall comprise of:
i) Various amendments/modifications/additions to the "General Technical Specifications" referred
to in PART - I above and
ii) Additional Specifications for particular item of works not covered in PART-I.
The Additional Specifications comprise of specifications for particular items of works not covered
in PART-I
In the absence of any definite provisions on any particular issue in the aforesaid Specifications,
reference may be made to the latest codes and specifications of IRC, IS, BS and AASHTO in that
order. Where even these are silent, the construction and completion of the works shall conform to
sound engineering practice as approved by the Engineer and in case of any dispute arising out of
the interpretation of the above, the decision of the Engineer shall be final and binding on the
Contractor.
QUANTITIES
Based on the designs and drawings, a bill of quantities will be prepared by the Consultant
asunder:
o Preliminary and general items;
o Site clearance and earthworks;
o Sub-base, base and surfacing courses;
o Drains, culverts and protection works;
o Major structures and bridges;
o Road furniture;
o Ancillary works; and,
o Miscellaneous items of works.
CONSTRUCTION COSTS
The costs for construction of the Project Road will be worked out on the basis of design proposals.
The item-wise construction costs will be computed using the bill of quantities derived from the
designs, drawings and specifications and the unit rates worked out. The construction costs will
also include the costs of ancillary works, costs for shifting of utilities and provisions for traffic
management and diversion works necessary for traffic movement during the construction of works.
BID DOCUMENTS
The tender documents will be prepared as stipulated in the TOR.
The first stage will cover the commercial documentation including:
o Instruction to bidders;
o General conditions of contract;
o Special conditions of contract;
o Outline of BOQ; and
o Schedule for additional information like formats for bank guarantee, contract agreement
etc.
The second stage will cover the technical documentation including:
o Technical specifications;
o Bill of Quantities; and Drawings;
CHAPTER -5
DESIGN STANDARDS
Road Design and Specifications Covering Road Design, Pavement Design, Masonry Works.
GENERAL
The project involves ROB cum approaches on Road at Railway Level Crossing Gate No.SK-45 at
KM-268/3 on BijniIn Chirang district in Assam State. For design of flexible pavement provision as
per IRC: 37-2012 have been adopted for new pavement construction.
METHODOLOGY
The principal method for pavement design for new construction is based on IRC: 37-2012. The
analysis and design of the pavements have been done using MS-Excel spread sheets.
While designing the pavement following factors will be considered:
CBR of existing soil on approaches to be found out.
Minimum CBR ≥ 5% and minimum thickness of sub grade should be 500 mm to be kept.
Pavement design based on CBR of > 5% and traffic intensity on by Approaches with 12
msa or more for surfacing for 10 years duration and design life 15 years.
Renewal coat of BC/ DBM/BM shall be considered after 5 years based on condition of
surface.
Pavement design is based on IRC 37-2012 with CBR > 5% for sub grade soil.
Land acquisition as right of way (ROW)
Base course with WMM material.
Surfacing with bituminous material as per IRC- 37
Composition of layers as per IRC-37-2012 is sub base, base course and surfacing
course.
CBR of borrow area selected > 5.00%
Design life period considered 15 years with 2 years construction period.
Traffic survey to be carried out.
WEARING COURSE
This is the layer in direct contact with traffic loads. It is meant to take the brunt of traffic wear and
can be removed and replaced as it gets worn. The wearing course can be rehabilitated before
distress propagates into the underlying intermediate/binder course.
The surfacing layer as mention below to be executed as per specification and procedure mention
against each Bituminous surfacing course: -
The sub base generally consists of lower quality materials than the base course but better than the
sub grade soils. A sub base course is not always needed or used. For example, a pavement
constructed over a high quality, stiff sub grade may not need the additional features offered by a
sub base course so it may be omitted from design. However, a pavement constructed over a low
quality soil such as swelling clay may require the additional load distribution characteristic that a
sub base course can offer. In this scenario the sub base course may consist of high quality fill
used to replace poor quality sub grade (over excavation).
IRC 37-2012
The method of design recommended is a modification of the CBR method incorporating
mechanistic approach.
For design of heavily trafficked roads carrying traffic exceeding 10 msa over the design life, it
gives design catalogue giving standard pavement compositions. The design relates to CBR values
ranging from 2 % to 10% and separate levels of design traffic 0 to 10 MSA and 10 to 150 MSA.
The design catalogues are available for MSA 10, 20, 30, 50, 100 and 150. The design pavement
DESIGN STANDARDS
GENERAL
The design standard is primarily based on IRC publication as described in MORT&H specification
and relevant recommendation of international standards. Where the design standard are silent, the
consultant has based the design on their past experience and sound engineering practices
geometric embankment, e.g. pavement structure, drainage, drawings, traffic safety and materials
etc.
CODES/SPECIFICATIONS
Sl.
Description Design code
No
(i) IRC :38-1992 Guidelines for design of horizontal curves
(ii) IRC :SP:23-1993 Vertical curves for Highways
(iii) IRC:39-1986 Standards for road rail level crossings
IRC:54:1974-Lateral &vertical clearances at underpasses for
(iv)
vehicular traffic
Geometric (v) IRC:64-1990 Capacity of road in rural areas
1 Design (vi) IRC:66-1976 Sight distance on Rural Highways
standard IRC :73-1980 Geometric design standard for Rural (Non-
(vii)
urban )Highway
(viii) IRC :75-2015 Guidelines for design of Highway Embankment
IRC :86:1983- Geometric design standard for urban road in
(ix)
plains
IRC: 106:1990- Guidelines on capacity of urban road in plain
(x)
areas
(i) IRC :37-2012 Guidelines for design of Flexible Pavement
Design of (ii) IRC :58-2015-Guidelines for Design of Rigid Pavement
2
pavement IRC:81-1997-Guidelines for strengthening of flexible
(iii)
pavement
(i) IRC:65-1976 Traffic Rotaries
(ii) IRC:92-1985-Guidelines for Design of interchanges
Junction
IRC:93-1985-Guidelines on Design &Installation of Road
3 intersection / (iii)
traffic signals
interchanges
Design of junctions based on type design of Intersection on
(iv)
NH published by MOSRT&H - 1995
Kilometer (i) IRC:8-1980-Type of design for Highway kilometers stones
stones 200m (ii) IRC:26:1967-Type design for 200 m stones
4
stones and
(iii) IRC:25:1967- Type design for boundary stones
boundary pillar
5 Traffic signs (i) IRC:31:1969-Route marker signs for state routes
(ii) IRC:67:2012- Code of practice for road signs
(iii) IRC:79:1979-Recommended practice for Road traffic signs
Sl.
Description Design code
No
(iv) IRC: SP:31-Road Traffic sign
IRC :35-2015 Code of Practice for Road marking, road
6 Road Marking (i)
delineators
Design of IRC: SP: 13-2004 Guidelines for design of small bridge and
7 culverts and (i) culvert Standard design of CD work and small bridge based
small bridges on MOST&H has been considered.
(i) IRC :SP:42-2014 Guidelines on Road Drainage
8 Drainage
(ii) IRC:SP:50-2013 Guidelines on urban drainage
(i) IRC :103-2012 Guidelines for pedestrian facilities
Safety
9 (ii) IRC:SP:44-2017 Highway safety Code
Measures
(iii) IRC:SP:55:2014 Guidelines for safety in construction zones
The specification included in the Final DPR broadly conforms to MORT&H Specifications for Road
and Bridgeworks (Fourth Revision).
DESIGN CONSIDERATIONS
GENERAL
The design comprises geometric design i.e. the horizontal alignment and the vertical profile, and
the design of appurtenances and structures and other pedestrian facilities. The geometric design
consists of the following features:
I. Design of horizontal alignment, vertical profile, intersections and junctions and other
features for upgrading the existing intermediate lane to required lane configuration by
widening, strengthening and/or reconstruction;
II. Avoiding obstructions, trees, utilities and structures as far as possible;
III. Designing drains and footpaths in built-up areas to minimize land acquisition;
IV. The geometric design is subject to available right of way (ROW) and shall conform to the
standards, set out as minimum, as far as possible;
V. The uniformity of design standards is maintained throughout the length of the Project road,
as far as possible;
VI. Wherever the existing road geometrics are deficient, due importance to improvement of
these sections will be provided;
VII. Existing horizontal curves, which are found deficient in radius need to be corrected to meet
the design requirement subject to ROW constraints;
VIII. Any deficiencies in the vertical profile in respect of grades layout and sight distance shall
need to be corrected to meet the minimum standard requirements;
IX. Design of road side appurtenances shall be in accordance with relevant codes of IRC, BIS,
or other international standards and should meet minimum requirements set forth in the
MORT&H Specifications for Road and Bridge Works;
X. The design of cross drainage works shall be in accordance with the relevant IRC Codes.
The road alignment design shall take into account the location of the cross drainage (CD)
works, bridges and other structures. In case of major bridges (above 60 m), the design
alignment shall give precedence to the bridge location.
Road carriageway:
Shoulder
Camber or cross fall.
The above element clubbed together constitutes a Road cross section. Adoption of various
elements with appropriate manner in accordance with IRC codes for safe movement of traffic is a
major design requirement and discussed in the following paragraph.
Sl.
Description Design code
No
Geometric Design Standard for rural (Non-Urban)
1 IRC :73-1980
Highways
2 IRC :86-1990 Geometric Design Standard for Urban Roads in plains
3 IRC :106-1990 Guidelines for capacity of Urban Roads in plain areas
4 IRC :64-1990 Guidelines for capacity of Roads in Rural areas
The following IRC codes and standard have been referred for finalizing the design of cross
sectional element:-
Although the IRC codes provided indicative standard for state Highway but these could
apply to only new roads proposal.
The IRC Code 73-1980 lays down formation width guidelines for 2 lane multilane
carriageway configuration as under:
Sl.
Lane Configuration Roadway width (m) Remarks
No
Carriage way -7.0 m Shoulder
1 2-Lane 12
-2x2.5 m
Carriage way -2x7.25 m
4- Lane divided
2 22 Shoulder -2x2.5 m Median-
Carriageway
1x2.50
WIDTH OF SHOULDER
The width of shoulder for NH/SH with 9 m formation width and 5.5 m road carriageway width
works out to 1.75 m on either side and the width of shoulder for a NH/SH with 12 m formation
width and 7 m road carriageway width works out to 2.5m either side. The shoulder shall be
unpaved but with soil CBR not less than 8%.The width of shoulder in stretch having divided
carriageway is restricted to 1.0 m minimum, considering the ROW constrain.
INTRODUCTION
GENERAL
As per the requirements of IRC: 73:1980, the following guidelines will be followed during the
design:
Uniformity of design standards;
Horizontal alignment should be fluent and blend well with the surrounding topography;
Limit the damage to the existing environment including preservation of natural crops and plant
growth and conservation of existing features
The horizontal alignment should be designed in consideration of the longitudinal profile and
vice versa; and
Location of bridges and their approaches are to be properly co-ordinate keeping in view the
overall technical feasibility, economy, fluency in alignment and aesthetics. The geometric design
shall also be undertaken so as to minimize impact on trees, utilities, houses, shops and avoid
extending beyond the existing right of way (ROW).
HORIZONTAL CURVES
Lengths for different speeds and curve radii are given below:
GENERAL
In general horizontal curves consist of a circular curve portion flanked by a spiral transition on both
ends. Design speed, super elevation and coefficient of side friction affect the design of circular
curves. Length of transition curve is determined on the basis of rate of change of centrifugal
acceleration or the rate of change of super elevation.
SUPER ELEVATION – This is required on horizontal curves and is calculated from the following
formula:
e= V2
225R
Radius of Horizontal Curves – These shall correspond to the ruling minimum and absolute
minimum design speeds and the maximum permissible values of super elevation. These are as
per IRC: 73:1980.
Transition Curves - Transition curves are necessary for a vehicle to have smooth entry from a
straight section into a circular curve. The transition curves also improve aesthetic appearance of
the road besides permitting gradual application of the super elevation and extra widening of
carriageway needed at the horizontal curves. Spiral curves are proposed for this purpose.
The minimum length of the transition curve is determined from the following two considerations
and the larger of the two values adopted for design:
(i) Rate of change of centrifugal acceleration; and
(ii) Rate of change of super elevation.
Widening is effected by increasing the width at an approximately uniform rate along the transition
curve. Extra width is continued over the full length of the circular curve. On curves having no
transition, widening shall be achieved in the same way as super elevation. Extra widening is
provided on the inside of the curves.
Design Speed - Based on IRC: 73:1980, the design speeds adopted for design of horizontal
curves, depending upon the terrain is shown below.
Ruling Minimum
Plain 100 80
Rolling 80 65
Super elevation – Although super elevation is designed in accordance with the formulae
described above it is limited to 7% in plain and roiling terrain as per IRC codes although this has
been further amended to 5%.
When the value of super elevation, obtained, as above, is less than the road camber, the normal
cambered section has been followed on the curved portion without providing any super elevation.
For 3% camber rate, shows the radii of horizontal curves beyond which super elevation is not
required.
Radius at Which Camber is not required
Design Speed (Km/h)
40 50 65 80 100
Radius for camber of 3 % 240 370 620 950 1500
(meters)
These are indicative design speeds. Due to constraints in ROW, large scale easing of sub-
standard curves is not feasible. Wherever, improvement of curves from design speed
considerations is not possible, speed limitation shall need to be resorted to.
Radii of Horizontal Curves - The minimum radii of horizontal curves for different terrain
conditions is shown below:
Based on above methodology, the horizontal alignment has been designed using MX Road
software.
Sight Distance
Safe stopping sight distance both in the vertical and horizontal directions will apply in design. The
sight distance values as per IRC recommendation are as follows:
VERTICAL ALIGNMENT
The vertical alignment is proposed to provide for a smooth longitudinal profile consistent with
category of the road and layout of the terrain and use of land. Too frequent grade changes cause
kinks and visual discontinuities in the profile. There should not be change in grade within a
distance of 150 m.
The existing road profile is to be followed as far as possible, if the Project road improvement is
limited to widening and strengthening of the existing road. In case of reconstruction of the
pavement, if the existing pavement has disintegrated and in sections which are prone to
submergence, the design road level is to be fixed taking into consideration the HFL.
Decks of small cross-drainage structures will conform to the profile of the new road section in case
of new construction / reconstruction. Where existing structures are retained, the profile of the road
has been suitably adjusted to avoid loading the existing deck with overburden.
DESIGN FEATURES
Gradients - Grades have been selected carefully keeping in view the design speed, terrain
conditions and nature of traffic on the road. Recommended gradients for different classes of terrain
are given below, as per IRC: SP: 23-1983.
Gradients for Roads in Different Terrain
Sl. No. Terrain Ruling Gradients Limiting Gradient Exceptional
Gradient
1. Plain/rolling 3.3% 5% 6.7%
(1 in 30) (1 in 20) (1 in 5)
Gradients up to the maximum design values are used unless some factor limits this. “Limiting
gradients” are proposed where site issues such as excessively steep gradients. In such cases, the
length of continuous grade steeper than the maximum design gradient is proposed to be as short
as possible. “Exceptional gradients” are meant to be adopted only in very difficult situations for
short lengths not exceeding 100 m.
Minimum Gradient for Drainage - On uncurbed pavements, near level grades may be acceptable
when the pavement has sufficient camber to drain the storm water laterally. However, in cut
sections, or roads at ground level, or where the pavement is provided with kerbs, it is necessary to
provide some gradient for efficient drainage. Recommended minimum gradient for this purpose is
0.5% if side drains are lined and 1.0%, if these are unlined.
Vertical Curves - These are introduced for smooth transition at grade changes. There are two
types:
summit curves or convex vertical curves or hog curves; and
Valley curves or concave vertical curves or sag curves.
Both of the above are designed as square parabola. Length of these curves is controlled by sight
distance requirement, but curves with greater length are aesthetically better. Minimum lengths of
vertical curves are as per IRC: 73-1980 and shown below:
Length of summit curves is governed by the choice of sight distance. Length of the valley curves
should be such that for night travel, the head light beam distance is equal to the stopping sight
distance. The lengths of the valley curves are worked out as per the guidelines and formula given
in the IRC: 73-1980.
The degree of curvature is proposed in proper balance with the gradient. Vertical curvature
superimposed upon horizontal curvature gives a pleasing effect. Vertical and horizontal curves
should coincide as far as possible and their length should be more or less equal. If not feasible,
the horizontal curve should be somewhat longer than the vertical curve. Sharp horizontal curves
are avoided at or near the apex of pronounced summit/sag vertical curves from safety
considerations. These guidelines are however, feasible under ideal conditions for new road
alignment.
REINFORCING ELEMENT
The reinforcing element shall be of Geotextile, aluminum alloy strip, copper strip, carbon steel
strip, mats of metal or synthetic grids, or any other proprietary material which may be approved by
the Engineer and indicated on the drawings.
GEOTEXTILE
The material shall conform to Clause 701.2.6.
Aluminum alloy strip shall comply with BS: 1470 quality 5454 in the H 24 condition.
Copper strip shall comply with BS: 2870 quality C 101 or C 102 in the 1/2 H condition and shall
have 0.2 per cent proof stress of not less than 180 N/mm2.
Carbon steel strip which shall be galvanized shall comply with BS: 1449 (Part 1), either quality
KHR 34/20 P or quality 50/35 P, each having a silicon content of not less than 0.25 per cent and
not more than 0.40 per cent. The fabricated element shall be galvanized in accordance with BS:
729 and the average zinc coating weight for any individual test area shall not be less than 1000
gm/sqm.
Stainless steel strip shall comply with BS: 1449 (Part 2) quality 316 S 31 or 3/6 S 33 except that
the Material shall be cold rolled to provide a 0.2 per cent proof stress of not less than 400 N/sq.
mm and the tensile strength shall not be less than 540 N/sq. m.
All metallic components buried in soil shall be of electrolytic ally compatible materials.
GEOGRIDS
The supply of geogrids shall carry a certification of BIS or ISO 9002 for all works. While the
reinforcing element for wall or slope portion shall be with mono oriented Geogrids, there
enforcement for the foundation of a reinforced earth wall or slope shall be with bi-directionally
oriented Geogrids. For mono oriented Geogrids, the characteristic design tensile strength at a
strain not exceeding 10 per cent in 100 years shall be at least 40 kN/m when measured as per
GRI: GG3. The strength for bi directionally oriented Geogrids in the longitudinal direction shall be
at least 40 Min at a maximum elongation of 15 per cent. The Geogrids shall be inert to all naturally
occurring chemicals, minerals and salts found in soil.
EARTH FILL
The fill material for reinforced earth structures shall have an angle of interface friction between the
compacted fill and the reinforcing element of not less than 25O C, measured in accordance with IS:
13326 (Part 1). The soil should be predominantly coarse grained; not more than 10 per cent of the
particles shall pass 75-micron sieve. The soil should have properties such that the salts in the soil
should not react chemically or electrically with the reinforcing elements in an adverse manner.
FACIA MATERIAL
The facing shall comprise of one of following:
Reinforced concrete (Cast in situ or precast) slabs
Plain cement concrete form fill hollow block (precast)
Masonry construction, Rubble facia.
Other proprietary and patented proven system.
The facing shall be sufficiently flexible to withstand any deformation of the fill.
Facia, unit joint should be durable, resistant to the effect of air pollution and water/saline water.
Bedding material shall consist of either cement mortar or a durable gasket seating such as resin
bonded cork strip. Connection between the facia and the reinforcing element shall be by using
polyethylene strips/rods, fiberglass dowels or any other material shown in the drawing. Any other
material used shall be tested to provide 100 per cent joint strength as of parent element in
continuity. Overlapping in principal reinforcement or in the joint shall ensure load transfer through
joints, perpendicular to the direction of lying.
CONSTRUCTION DETAILS
The plan area of the reinforced earth structure shall be excavated to provide a nominally level
base which may be stepped at the back as required to receive the horizontal reinforcing element
grid. The depth of the foundation below the finished ground level at the foot of the slope or wall
shall not be less am 1000 mm. Additional strip footing, trough guide made of concrete or anchor
keypad shall be provided at founding level to receive the facia or the bottom most reinforcement
connection. This shall have adequate sod cover against erosion and scour in particular cases.
ORIENTATION
The reinforcing elements shall be placed at right angles to the face of the wall, with greater cross
sectional dimension in the horizontal plane. The placement of the elements including their
vertical/horizontal spacing and length shall be as in the drawing.
FACING BATTER
It may be necessary to set facing unit at an additional batter than as provided in the drawing as
there is a tendency for initially positioned units of facia, to lean outward as the fill material is placed
and compacted. Care and caution shall be taken to rectify this phenomenon.
DRAINAGE
Drainage shall be provided as per drawing given in detail. The retained fill shall have a suitably
designed drainage bay to allow free draining of the reinforced fill.
All construction plant having a mass exceeding 1000 kg shall be kept at least 1.5 in away from the
fact of slope or wall. In this area (up to 1.5 in from the face of slope or wall), following compaction
plant shall be used:
Vibratory roller having a weight per meter width of roll not exceeding 1300kg with total weight not
exceeding 10,000 kg. Vibratory plate compactor of maximum weight 1000 kg. Vibro tamper having
a weight not exceeding 75 kg.
Compaction by any other method like using dozer or back blade compaction by dozer or excavator
bucket shall be permitted with due approval from the Engineer after ascertaining the level of
compaction so achieved.
During construction of reinforced fill, the retained material beyond the reinforcement at the rear or
the structure shall be maintained at the same level as reinforced fill.
The compacted layer shall not be more than 200 mm, to achieve compaction of 95 per cent of
maximum laboratory density where measured as per IS: 2720 (Part 8). Temporary formwork shall
be used to support the construction as per specified details given in the drawing. The forms,
scaffolding and props shall be sufficient in numbers to allow taking up of a sectorial construction
schedule specified in the design.
Flexible pavement is being proposed for bypass construction. Design inputs required for the
pavement design are established based on the pavement investigation.
Flexible Pavement Design
Flexible pavement design has been done using IRC: 37-2012 guide lines for new construction and
widening
IRC 37-2012
The method of design recommended is a modification of the CBR method incorporating
mechanistic approach.
For design of heavily trafficked roads carrying traffic exceeding 10 msa over the design life, it
gives design catalogue giving standard pavement compositions. The design relates to CBR values
ranging from 2% to 10% and separate levels of design traffic 0 MSA to 10 MSA and 10 MSA to
150 MSA. The design catalogues are available for MSA 10, 20, 30, 50, 100 and 150.
The design pavement composition specified in these catalogues is relevant to Indian conditions,
materials and specifications.
For intermediate traffic ranges, the pavement layer thickness could be interpolated linearly. For
traffic exceeding 150 million standard axles, extrapolation of design thickness is not
recommended.
To use the recommended method an estimate of the cumulative number of standard axles to be
carried by the pavement during the design life is required. For this following inputs are made.
i) Traffic intensity in terms of commercial vehicles per day
ii) Traffic growth rate
iii) Design life
iv) Vehicle damage factor (VDF)
v) Soaked CBR(% )for sub grade soil
,
vi) Cumulative MSA for the design period
TRAFFIC INTENSITY
For the purpose of structural design, only the number of commercial vehicles of laden weight of 3
tons or more and their axle loading is considered. The traffic is considered in both directions in the
case of two lanes and below. Annual Average Daily Traffic (AADT) in terms of commercial
vehicles for the project road to be considered. Traffic Study shall be carried out on acceptance of
GAD ROB.
The depth of boring will be conducted as per provision in IRC: 78-2014, MORTH specification.
The Depth of bore-Logs is based on expected type of foundation. As per the preliminary survey it
seems deep foundation shall be suitable. In case of open foundation, the bore hole will be done
as per IRC: 78 i.e. 1.5 times the width of the foundation below the proposed foundation level. The
depth of drilling/ boring shall be 5.0m in soft rock & 3.0m in hard rock.
For any deviation (s), if any, by the DPR Consultants from the scheme presented above will be
got approved by client.
However, where a study of geo-technical reports and information available from adjacent
crossings over the same waterway (existing highway and railway bridges) indicates that
subsurface variability is such that boring at the suggested spacing will be insufficient to
adequately define the conditions for design purposes, the Consultants will review and finalize the
bore hole locations in consultation with the concerned officers.
The scheme for the borings locations and the depth of boring will be prepared by the Consultants
and submitted to the client for approval. These may be finalized in consultation with concern
department.
Sub-soil exploration and testing will be carried out through the Geo-technical Consultants who
have done Geo-technical investigation work in similar project. If outsourcing of Geo-Technical
Investigation will be desired, the firm selected by the DPR Consultant for this purpose will also be
got approved from client before start of such works. The soil testing reports will be furnished in
the format prescribed in relevant IRC Codes.
Ours is the elevated viaduct for all the three animal corridors, so locations, numbers and depth of
bore hole will be decided in close consultation with PWD officials depending upon the type of
foundation anticipated. Prima facia tentative type of foundations will be Pile foundations and
subsequently depth of bore hole will be in the range of 30 to 40m depending of type of strata
encountered.
Material Investigations
Sources of all materials (including use of fly-ash/ slag), quarry sites and borrow areas shall be
identified and field and laboratory testing of the materials to determine their suitability for various
components of the work and establish quality and quantity of various construction materials shall
be undertaken and their use on the basis of techno-economic principles shall be recommended.
A mass haul diagram for haulage purposes giving quarry charts indicating the location of selected
borrow areas, quarries and the respective estimated quantities shall be prepared.
It shall be ensured that no material will be used from the right-of-way except by way of leveling the
ground as required from the construction point of view or for landscaping and planting of trees etc.
or from the cutting of existing ground for obtaining the required formation levels.
Environmental restrictions, if any, and feasibility of availability of these sites to prospective civil
works contractors, will be duly taken into account while selecting new quarry locations.
Suitable recommendations shall be made regarding making good borrow and quarry areas after
the exploitation of materials for construction of works.
The Material Investigation aspect shall include preparation and testing of bituminous mixes for
various layers and concrete mixes of different design mix grades using suitable materials
(binders, aggregates, sand filler etc.) as identified during Material Investigation to conform to
latest MORT&H specification.
26 IRC: SP:13-2004 Guidelines for the Design of Small Bridges and Culverts
29 IRC: SP:69 – 2011 Guidelines & Specifications for Expansion Joints (First Revision)
30 IRC: SP:70 – 2005 Guidelines for the Use of High Performance Concrete in Bridges
(A) For any item not covered by A & B, above the relevant provisions from B.S. and AASHTO
codes of Practice.
(B) For items not covered by any of the above Standards and Specifications sound
Engineering practice and provisions in the Departmental design and provisions of relevant
codes of other nation shall be referred.
Structural Detail
DPR Consultant will prepare General Arrangement Drawing (GAD) and Alignment Plan
showing the salient features of the structures proposed to be constructed / reconstructed along
the road sections covered under the Study. These salient features such as alignment, overall
length, span arrangement, cross section, deck level, founding level, type of bridge components
(superstructure, substructure, foundations, bearings, expansion joint, return walls etc.) shall be
finalized based upon hydraulic and geo-technical studies, cost effectiveness and ease of
construction. The GAD will be supplemented by Preliminary designs. In respect of span
arrangement and type of bridge a few alternatives with cost-benefit implications will be
submitted to enable client to approve the best alternative.
For existing structures having inadequate carriageway width will be widened / reconstructed in
part or fully as per the latest MoRT&H guidelines. DPR Consultant will furnish the detailed
design and drawings for carrying out the above improvements.
In case land available is not adequate for embankment slope, suitable design for RCC retaining
wall will be furnished. However, RES wall may also be considered depending upon techno-
economic suitability to be approved by PWD NH Works/MORT&H
Width of Structures
The typical cross-section of proposed bridges will be Given Below
STEEL REINFORCEMENT
Reinforcement bars of grade 500D (minimum) conforming to IS: 1786 will be adopted. MS bars, if
required, shall conform to IS 432.
Minimum yielding strength or 0.2% proof stress of steel reinforcement is considered equal to 500
MPa and Young modulus equal to 200000 MPa.
The following diameters can be used [in mm]: 8, 10, 12, 16, 20, 25 & 32, with a maximum length
for a single rebar of 12 m. Lapping arrangement shall be as per chapter 15 of IRC: 112. Welding
shall be avoided, however if unavoidable, shall be provided as per the Cl. 15.2.5.2 of IRC: 112.
Moderate exposure condition has been considered as per IRC: 112. 20 mm aggregate shall be
used. Concrete cover for the different components shall be.
Cast-in-situ Deck : 40 mm;
Piers/pier cap : 50 mm;
Piers subjected to alternate drying and wetting (Nallah Portion) : 75 mm;
Footings : 75 mm;
Pile foundation/Pile cap : 75 mm;
RCC Retaining wall : 50 mm;
Stress-strain relationship for reinforcement shall be considered as per Fig. 6.2 of IRC: 112 and for
STRUCTURAL STEEL
Structural steel of Grade E250 for composite section shall be conforming to IS: 2062-2011 will be
adopted.
QUALITY/WORKMANSHIP
All materials, quality and workmanship shall conform to IRC: 112, Section -16.
Bearings
Bearing for Structures shall be designed to transmit all the loads and appropriate horizontal
forces. Pot fixed/Pot PTFE sliding bearings shall be proposed for superstructures .The design of
the POT/ PTFE bearing shall be done by the manufacturer conforming to the provisions of
material as well as design parameters stipulated in IRC: 83 (part-III). The same shall be got
approved by the engineer. The forces, movements and rotation etc shall be provided by the
designer of the project on the format given in appendix–1 of IRC: 83 (part-III). In support of quality
assurance, acceptance specification given in clause 928 of IRC: 83 (part-III) shall be followed
.wherever Large span will be proposed spherical Bearings shall be adopted for catering large
movement and rotation as per IRC:83(PART-IV)
Expansion Joints
Expansion joint shall be provided as per IRC: SP: 69-2005 depending upon the anticipated
expansion/ contraction. These shall conform to Section 2600 Technical Specification of MORTH.
Types of expansion joint based upon the length of span and movements are as given below:
The bar sizes and distance between bars shall be in accordance with section 15 of IRC: 112-
2020.
Curtailment of bars shall be as per clause 16.5.1.3 of IRC: 112-2020,
Minimum Reinforcement and Distribution reinforcement in Decks slabs, Columns shall be as
per IRC: 112-2020
Minimum shear reinforcement shall be as per IRC: 112-2020.
Minimum diameter of any reinforcement shall not be less 10mm for open foundation,
transverse ties, stirrups and all secondary reinforcement for slab.
Minimum diameter of any reinforcement shall not be less than 12 mm for pier vertical bar, pier
cap main bar.
Ductile detailing shall be done as per chapter 17 of IRC: 112-2020.
Permissible Stresses
The Permissible Stresses in the RCC and PSC members shall be as per IRC: 112. The
Permissible Stresses in the Composite members & Steel prestress structures considered in
design shall be as per IRC: 22 2015 & IRC: 24-2010, respectively. Increase in Permissible Stress
in steel and concrete due to various load combinations shall be as per IRC: 6-2017.
In house developed programs and spread sheets for checking stresses and capacity of structural
element.
Structural Analysis: STAAD.pro
to the modeling / idealization aspect and if necessary will revise our model for greater accuracy.
We have suitable software for the analysis of bridges of all types for various IRC live loading,
permanent dead loading and construction stage loading. These will be used in the analysis.
Plate Girders will be design by using STAAD Software and joint connections will be designed by
considering HSFG bolts.
Size of bolts will be used as per table as below:
(iv)
Design
of
Bearing
The loads transferred from the superstructure to the bearings shall be taken from the earlier
analysis of superstructure. Short and long term deformations shall be computed for the
temperature, shrinkage and creep of concrete.
POT cum PTFE bearings shall be designed as per IRC: 83 (Part III) for these effects design loads
and movements are to be supplied to the manufacturer to enable him to manufacture these
bearings. The manufacturer’s details & design have to be got checked to ensure compliance with
the design requirements.
(v) Design of Elements above Deck Level
The miscellaneous elements such as kerb and parapets/railing are designed as reinforced
concrete section for the loads and forces as per Cl. 209 of IRC: 6 - 2017.
Design Methodology for Substructure and Foundation
Piers
Pier will be wall/circular/Hollow type with cantilever fixed at base, which is taken as top of
foundation. The sections at various levels will be checked as sections subjected to axial thrust
and bi-axial bending. In addition to dead load and live loads from superstructure, the pier
substructure and its foundation will be designed for the loads due to seismic/wind and water
current forces as appropriate. It also suggests proposing high strength light weight plastic fiber
prefabricated / molded shuttering.
Abutment
Abutments will be of wall /spill through type with earth pressure. These shall be designed resting
on open foundations, pile foundations or well foundations as per requirement after detailed soil
exploration.
Abutments shaft shall be designed in reinforced concrete and Pier Caps and abutment caps may
be CIP or Precast for least disturbance during the execution. The stability checks shall be carried
out as per relevant IRC Codes. It also suggests proposing high strength light weight plastic fiber
prefabricated / molded shuttering.
Foundation
Foundation of proposed bridges will be conceptualized after evaluation of subsoil data such as
type of soil and its safe bearing capacity at foundation level for abutment/pier/return-wall and
footings. Thereafter suitable type of foundations will be provided with respect to soil and type of
superstructure. Adequacy of the size and depth of foundation will be ensured for the satisfactory
performance of the structure. The structural design of the foundation is to be designed as per the
latest computerized modeling. Particular attention is paid to stability checks and corresponding
safety factors.
Open Foundation
Design of isolated open foundation shall be based on complete sub soil investigations. The
allowable bearing pressure shall satisfy the provisions contained in the clause 708 and the
minimum foundation depth shall not be less than that specified in Clause 705 of IRC: 78-2014
(Revised Revision).
The selection of the appropriate type of open foundation (counter fort type or cantilever type)
depends on the magnitude and disposition of structural loads, allowable bearing capacity etc.
However, if rock strata are encountered at shallow depth, it will be preferable to adopt open
foundation to pile foundation.
Deep Foundations
In case of large scour depths and unavailability of rock at shallow depth deep foundation shall be
provided. This may be pile foundation or well foundation depending on vertical load, horizontal
load, bending moment and soil strata. Cast in-situ Pile foundation up to 1.2m -1.5m diameter may
be constructed fast and are more suitable if the total length of pile is up to deeper depths (20m –
30m), pile can also be seated on hard rock, and guidance can be taken from appendix-5 of IIRC:
78-2014 (Revised Revision). Beyond 30.0m depth of foundation, well foundation will be adopted
as they can carry large horizontal loads and bending moments compared to pile foundations.
Choice of foundation between pile and well shall depend on their relative merits and demerits with
respect to loads and soil strata.
Pile Foundation:
The various assumptions made for the pile and pile cap designs are as follows:
I. Bored cast-in-situ vertical piles have been proposed for the foundations. For pile foundations in
soil the minimum spacing between the piles shall be 3D whereas for piles in rock the minimum
spacing between the piles shall be 2D, where D is the diameter of pile.
II. The vertical capacity of piles shall be minimum of that recommended by Soil Consultants and
Initial load test of pile.
III. Initial load test (not on working pile) shall be conducted as specified in tender document.
IV. The vertical capacity of the pile shall be based on static formula given in IS: 2911 (Part-1/Section-
2) and correlated with appendix-5 of IRC: 76. The permissible increase in pile capacity for seismic
load combinations [combination (iii)] would be taken as 25% (as per cl 706.1.2 of IRC: 76.
V. The lateral load capacity of pile shall be evaluated by using empirical formulae given in IS:2911
(Part-1/Section-3) by limiting the lateral deflection of 1% at its tip considering it as fixed headed
pile under normal conditions. The capacity so evaluated will be used purely for the purpose of
arriving at the upper bound of lateral load capacity. This deflection limitation will not be applicable
in load combinations with seismic conditions for which the resulting stress and capacity of the
section would be the governing criterion.
VI. Soil stiffness for lateral loads shall be taken from IS: 2911 (Part-1/Section 3 Appendix b). The
vertical and lateral load capacity of the pile under fixed head condition shall be confirmed by Initial
Pile Load Test. The length of (L1+Lf) under the free head condition will be obtained from lateral
load test at site. The same length (L1+Lf) will then be correlated for Fixed Head condition after
accounting for difference in length of fixity for Free Headed Condition and Fixed Head Condition.
VII. The working load on pile for vertical and horizontal loads shall be checked by conducting routine
tests during construction. For calculating pile loads, load obtained @ pier base from analysis shall
be applied on the pile cap.
VIII. Pile cap shall be designed based on bending theory/truss analogy using the forces derived in
piles using rivet theory. No support from soil below pile cap shall be considered.
IX. The top of pile cap will be kept about 500mm below the existing ground level and weight of the
earth cover will be applied on top of pile cap when unfavorable. Indeed, the earth cover on pile
cap for any favorable effect (stability, soil horizontal capacity, pile cap design) will be neglected.
X. Pile foundations will be of M35 with minimum cement content of 400 kg/m3. The max water
cement ratio shall be 0.4 with a minimum slump of 150-200mm. Pile cap shall be of M35 grade of
concrete. A clear cover of 75mm will be provided to any reinforcement closest to concrete surface
of pile & pile cap.
XI. The structural design of pile & pile cap will be checked for maximum/minimum axial load in pile
with co-existent moment using IRC: 112.
XII. The minimum thickness of pile cap shall be 1.5 times the pile diameter.
XIII. A minimum offset of 150mm will be adopted beyond the outer face of the outermost pile in the pile
cap so as to bend the main flexural (bottom) reinforcement of pile cap for a defined minimum
radius beyond the outer edge of pile.
XIV. Liquefaction potential of soil, if any, shall be considered as per soil investigation report. The length
of liquefaction shall be ignored for vertical and lateral resistance under seismic condition. The
seismic on structure within liquefaction shall be considered.
CHAPTER-6
QUALITY ASSURANCE PLAN (QAP)
GENERAL
The prime objective of the management of Technical Consultancy Services is to provide services
in a manner, which conforms to the contractual and regulatory requirements. In order to achieve
this objective, it is the policy of CPC is to maintain and implement an efficient and effective Quality
Assurance Plan (QAP) with the full commitment of management for its ongoing vitality and
relevance. Determination and conformance of our firm’s work to requirements is verified on the
basis of objective evidence of quality.
QUALITY AUDIT
TCS shall be responsible for in-house auditing of the implementation and conformance of the
QAP. This may be done by way of periodic project audits. Spot checks, interviews with staff, or
other means as determined by the key personnel o the project team.
COLLECTION OF SAMPLES
Soil samples were collected from the sub grade of existing road, proposed widening portion,
borrow areas. Stone aggregate and sand were collected from quarries.
The following tests were conducted in the laboratory of the samples collected from the pits:-
o Gradation tests
o Atterberg’s limits
o Compaction tests (Modified AASHTO)
o CBR (un soaked and 4 days soaked)
SAND
Fine Sand is available mainly from river beds. The following tests have been carried out in the
laboratory:-
o Sieve analysis
o Fineness Modulus
o Specific gravity
o Deleterious material content (%)
Drawings
Drawings shall be prepared and reviewed specifying the characteristic elements, which, if properly
constructed, shall produce a product, which is consistent with the design objective. The Consultant
shall assign the responsibility for preparing drawings to the key personnel and shall ensure that
they have the proper information. The key personnel of the project team shall conduct frequent
review of drawings to assure that proper standards and formats are being utilized in their
preparation.
The Senior Experts shall be responsible for checking drawings for the following:
o Compliance with the design requirements and codes,
o Dimensional accuracy and consistency with design,
o Sufficient dimensions and staging for constructability,
o Material specifications referenced in design incorporated into drawings,
o Previous comments to check prints have been incorporated into completed drawing,
o Drawings incorporate design elements of the supporting engineering disciplines, etc.
The reviewer shall give the checked prints to the key personnel, who shall resolve any problems
identified in the review. The drawings shall then be revised to satisfaction of the key personnel. In
addition to periodic quality assurance reviews, TCS shall schedule at critical times during the
design and sufficiently in advance of submissions, specific quality and construct ability reviews.
These reviews shall be performed based on design level reached to ensure compliance with
design criteria and construct ability. The key personnel of the project team shall review Quality
Assurance comments.
CLIENT CHANGES
Upon receipt of CDO review comments to a submittal, SIPL shall document written comments and
comments received at review meetings. Responses to the review comments shall be formulated
and filed in the project file, “Review comments and Responses.”The Consultant shall determine
the cause by review of design criteria and minutes of meetings. Where necessary, new and
additional calculations shall be performed and plans shall be revised. When the corrected actions
have been taken, a QA review shall be performed to ensure compliance.
The review of the noncompliance shall identify the cause and, if it is found to be the result of poor
procedural practice, measures to eliminate reoccurrence of the practice such as more training
shall be developed. These revised QAP procedures shall then be issued to all the members of the
project team.
and specific Employer’s requirements. The Project Manager designated for the Project shall
interact directly with the employer, MORTH. They shall discuss the QAP with the Employer and
get the same approved after incorporation their suggestions /comments. TCS shall ensure
adherence to the approved QAP. TCS shall be responsible for all technical and administrative
aspects of the project, for establishing and maintaining the control necessary to ensure completion
of assignment on time to the satisfaction of the concerned Authority. TCS shall work closely with
the MORTH to ensure that the project goals are met. TCS shall also organize the specific
assignments in terms of sequence of contents work, the type and number of people required for
each phase, and the timing at which various tasks are to be started and completed. The key
personnel (defined in the Consultancy Contract) are the task leaders for their respective technical
and administrative aspects related to their discipline. They are responsible for the directs up
revision of all technical and administrative aspects related to address the issues, compile the
deliverable documents. TCS shall ensure that, the Sub-Consultant’s work shall be submitted with
ample time to incorporate into the contractual submissions.TCS personnel shall ensure that they
as envisaged in the contract are exercising proper checks on quality, which is over and above the
contractual obligations.
CHAPTER -7
LOCATION OF PROPOSED ROB
The proposed Location for construction of ROB & its approaches in replacement of existing level
crossing (SK-45) and proposed ROB at Railway Level Crossing Gate No.SK-45 at KM-268/3 at
Bijniis:
GOOGLE IMAGE
SITE PHOTOGRAPHS