You are on page 1of 9

Management, Procurement and Law Proceedings of the Institution of Civil Engineers

Volume 169 Issue MP5 Management, Procurement and Law 169 October 2016 Issue MP5
Pages 199–207 http://dx.doi.org/10.1680/jmapl.15.00038
Strategies to minimise the effects of Paper 1500038
Received 22/07/2015 Accepted 15/06/2016
delayed payments
Published online 18/07/2016
Francis, Ramachandra and Rotimi Keyword: contracting/contracts & law/developing countries

ice | proceedings ICE Publishing: All rights reserved

Strategies to minimise the


effects of delayed payments
Mathusha Francis BSc James Olabode Bamidele Rotimi BSc, MSc, PhD
Lecturer, Department of Building Economics, University of Moratuwa, Senior Lecturer, Auckland University of Technology, Auckland, New
Moratuwa, Sri Lanka (corresponding author: mathushaf@yahoo.com) Zealand
Thanuja Ramachandra BSc, MPhil, PhD
Senior Lecturer, University of Moratuwa, Moratuwa, Sri Lanka

Delayed payments to parties in the construction supply chain are due to cash-flow difficulties of upper-tier parties.
The phenomenon is common in the construction industry, and in Sri Lanka most government-funded large-scale
projects experience payment delays. This research therefore investigates the effects of delayed payments and
possible strategies that could help minimise their effects. A survey approach was adopted where an equal sample
(N = 10) of contractors and subcontractors, drawn through purposive sampling, were interviewed. The sample is
justified through ‘saturation’, which determines the credibility of research findings in qualitative research. Solicited
views were grouped under themes, with NVivo 10 software used to organise the responses. The research found that
over 60% of main contractors and subcontractors have experienced the effects of cash-flow difficulties and project
delays. They are generally affected by irregular progress payments. Contractors and subcontractors strategise, other
than by using contractual provisions, to help maintain their business relationships with upper-tier parties and to
survive industry competition. Main contractors (70%) depend on bank loans, while subcontractors (40%) tend to
negotiate feasible payment plans and use fund transfer mechanisms in delayed payment situations. The research
suggests proactive actions that will ensure the effective implementation of contractual provisions.

1. Introduction payment problems are generally widespread in both developing


In construction contracts, project owners and contractors are and developed countries. Ye and Rahman (2010) therefore
legally bound by terms and conditions where payment is concluded that payment issues are endemic in construction
considered as a reward for the work performed (Balamuralithara industries and need to be recognised explicitly as they recur
et al., 2011). Payment here refers to the sum of money paid to project after project.
contractors upon the successful completion of certain works, to
which both parties to a contract have agreed (Ansah, 2011). Delayed and non-payment issues affect other parties to
Survival of construction parties, particularly subcontractors, is construction contracts: client, contractor and consultant. Reeves
contingent on the timely receipt of the amount agreed between (2003) found that delayed payments are usually due to incorrect
parties to the contract. Contractors and subcontractors are claims submitted by contractors, including payment applications
reimbursed the money expended on materials, labour, plant, from contractors without adequate supporting documents,
subcontractors’ services, preliminaries and general overheads inaccurate quantities and failure to follow the right procedures for
during the progress of works (Frics and Smith, 2012). preparation and submission of claims. This requires contractors to
resubmit their payment claims and hence delay in payment by
Payment malpractices, particularly by upper-tier parties, cause ill project owners. On a different note, Hasmori et al. (2012) stated
effects within the construction industry. It is not uncommon to that a major cause of delayed payments is the paymasters’ poor
find financial claims by contractors and subcontractors withheld financial management.
unreasonably, partially settled or completely unpaid. Therefore,
payment issues are present in the form of delayed, incomplete and Amoako (2011) suggested that payment delays result in higher
non-payment of amounts owed to lower-tier parties (Ye and cost of capital from banks, delayed completion of projects, lower
Rahman, 2010). Hasmori et al. (2012) suggested that contractors quality of works, an increase in project cost, disputes, bankruptcy
experience payment issues not only on government-funded of construction firms and loss of productivity. On a similar note,
projects but also on privately funded projects. Similarly, the Kaka et al. (2003) were of the opinion that many construction
National Construction Association of Sri Lanka (2009) has found companies have negative net cash flows due to improper payment
that contractors experience unsatisfactory payment practices practices and become bankrupt due to the lack of liquidity for
regardless of whether issues arose from contracts financed by the supporting their day-to-day activities. The practice of inefficient
government, the World Bank, the Asian Development Bank or and untimely payment in construction projects is a major factor
any other organisation. Further, Hou et al. (2011) explained that contributing to unsuccessful projects (Danuri et al., 2012).

199
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

Further, the chain-payment culture within the construction and the strategies adopted by construction parties to minimise
industry, where payment flows from upper tiers to lower tiers, their effects.
makes payment to lower tiers dependent on the upper tiers
(Khosrowshahi, 2000). Therefore, when there is a payment delay 2. Literature review
to the upper tier, it cascades down to the lower tiers. Several publications have identified the different ill effects of
unfair payment practices on construction projects to contractors
Researchers have explored ways of minimising payment problems and subcontractors. Some solutions have also been suggested by
in different countries. For example, Ramachandra and Rotimi these publications. Table 1 provides a summary of the effects of
(2011) found that strategies used to minimise payment problems delayed payments as collated from different authors.
in New Zealand include placing of charging orders and registering
caveatable interest over properties, lodging bankruptcy and As observed from Table 1, cash-flow difficulties are the primary
liquidation proceedings, holding money in trust accounts and concern of many authors, as it is considered the lifeblood of
direct payment by sureties. In support of this, Amoako (2011) construction projects. In this sense, cash flow is described as the
found that the ‘right to lien’, to take and hold or sell a property of inflow of cash to the contractor from clients and also the outflow
a debtor as security for a debt until payment is made, is being of cash to suppliers and subcontractors, and is used for procuring
practised in countries such as the UK and Canada to minimise resource inputs. Generally, many construction projects have
the effects of payment problems. On a different note, a study negative net cash flow until the very end of construction activities,
conducted in Malaysia revealed that contractual provisions in the when the final payment is received. Unless an advance payment
standard forms of a contract, including the right to regular is received before the project’s start, the cash-flow situation will
periodic payments, the right to a defined time frame for payments most probably be negative until project completion. Any delay
and the right to a speedy dispute resolution mechanism, could in monthly progress payments could exacerbate the cash-flow
minimise payment issues to a certain extent (Danuri et al., 2012). pressure, since most contractors rely on progress payments to
However, despite these efforts, construction organisations still procure their resource inputs. This means that irregular payments
experience payment problems on construction projects. will impact directly on the contractor’s cash flow.

The National Construction Association of Sri Lanka (2009) Many authors opined that irregular cash flow within construction
viewed payment delay to contractors as one of the most projects causes a chain reaction down the supply chain. Longer
significant concerns of Sri Lankan contractors. Uninterrupted payment periods result in other participants in the downstream
progress payments could enable contractors to maintain their supply chain becoming cash starved, forcing their greater reliance
cash flow and thereby ensure the smooth running of projects on borrowings. Usually, upstream main contractors will seek to
(Jayalath, 2013). Yet uninterrupted payments are becoming a impose longer payment periods on downstream subcontractors
mirage. Despite significant concerns with delayed payments and suppliers (who have limited financial capacities). Therefore,
within the Sri Lankan construction industry, there is little credible payment issues have relatively more impact on parties down the
research that could provide evidence for the necessary supply chain. Contractors are expected to manage their financial
performance improvements. Therefore, this research addresses this affairs, knowing that they may need to pay a subcontractor prior
knowledge gap by investigating the effects of delayed payments to receiving payment for work done from owners. However,

Effects of delayed payments Authors

Cash-flow difficulties Atout et al. (2008); Danuri et al. (2012); Hou et al. (2011); Sambasivan
and Soon (2007); Ye and Rahman (2010)
Negative chain effects down the supply chain Ang (2006); Balatbat and Carmichael (2010); Brand and Uher (2008);
Khosrowshahi (2000); Pettigrew (2003); Tran and Carmichael (2012)
Delays in completion of projects Atout et al. (2008); Bibi et al. (2011); Mohammed and Isah (2012);
Sambasivan and Soon (2007)
Disturbance in day-to-day construction activity Atout et al. (2008); Sambasivan and Soon (2007)
Increase in contractor’s creditability, additional cost Wilder (2007)
incurred for interest paid for bank loans
Abandonment of projects, unsuccessful projects Amoako (2011); Ansah (2011); Danuri et al. (2012); Wilder (2007)
Disputes among parties Amoako (2011)
Insolvency of contractors Amoako (2011); Ang (2006); Ansah (2011); Odeyinka and Kaka (2005)

Table 1. Summary of the effects of delayed payments

200
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

experience shows that some contractors delay subcontractors’ In this study, interviews were conducted with ten main contractors
payments to improve their own cash flow, particularly when and subcontractors. However, a saturation point had been reached
payments from the owner are late or incomplete. Payments to a after eight interviews. Sandelowski (2007) had recommended ten
subcontractor are, therefore, not only subjected to a contractor’s interviews when purposive sampling techniques are used for
payment behaviour but are also affected by the owner’s payment participant selection. Sandelowski (2007) suggested that the
behaviour. Moreover, subcontractors’ financial and professional adequacy of sampling in qualitative research is relative, a matter of
resource limitations may mean they are unable to recover judging a sample whether small or large. Further, Guest et al.
payment claims through formal dispute resolution mechanisms. (2006) indicated that data saturation guides the sample size for
Therefore, subcontractors are exposed to more financial risks interviewees selected using purposive sampling. Solicited views
associated with payment uncertainties. were organised under subthemes on effects of delayed payments and
strategies by using the NVivo 10 software program. NVivo results
As observed in Table 1, uneven flow of cash within construction were used to compute the descriptive statistics of the findings.
projects can have a major impact on a project’s progress.
Construction work involves huge amounts of money, and
4. Research findings
most contractors find it very difficult to manage day-to-day
construction expenses when payments are delayed. Work can 4.1 Profile of research participants
be delayed because there is inadequate cash flow to support The semi-structured interviews sought the participant’s profile,
construction expenses, particularly for those contractors who are which included the position of the interviewee in the organisation,
not financially well resourced. Many authors are of the opinion years of experience, the nature of the work performed by the
that disruptions to work in progress would ultimately cause delay organisation and the Institute for Construction Training and
in project completion. Development (Ictad) grading of the contracting and subcontracting
organisations interviewed. Table 2 provides a summary of the
Delayed payments indirectly increase contractors’ debt burden interviewees’ profile information. Participants in the research were
as indicated in Table 1. Contractors tend to borrow additional selected from major industry groups: main contractors and
capital to improve cash flow in late or non-payment situations. domestic and nominated subcontractors who have experienced
This could create an unfavourable situation and put pressure on payment issues in the Sri Lankan construction industry.
contractors. Also, there will be additional costs in the form of
interest on borrowings. Payment problems result in disputes As observed from Table 2, by profession all participants are
among key construction parties. A construction dispute resolution quantity surveyors and hold different positions in the organisation.
process can become prolonged, leading to cost and time overruns Sixty per cent (12 out of 20) of the participants hold the positions
and eventually abandonment of projects. At particular thresholds, of quantity surveyor and project manager, who handle payment
the capacity to absorb payment irregularities is eroded, and unless claims with clients and contractors. The remaining 40% are
funds are injected into a project, it runs the risk of being directors, general managers and owners of construction companies.
abandoned. Worse still, contractors may go into liquidation due to The selected organisations are involved in both buildings and
failure on their part to honour trade creditors such as bankers, civil engineering construction works for public and private clients.
subcontractors and suppliers. The contracting organisations that have an Ictad grading of C1
to C9 were considered for this research by selecting at least
The insolvency of upper-tier parties in the payment chain could one participant from each organisation. The contractors and
cause severe impacts on parties down the chain. The main subcontractors are graded by the Ictad based on their financial
contractor at the apex of the procurement structure is the conduit capability; technical ability with the staff, plant and machinery;
for significant sums of money. Where this is not forthcoming, and experience in relevant fields. Accordingly, contractors who
then other parties in the project chain become insolvent. undertake work in building construction, highways, bridges, water
supply and drainage, irrigation and land drainage, dredging and
3. Research methodology reclamation, storm water drainage, groynes and revetments and
The current study undertook an investigation into strategies that reclamation are graded as C1 to C10. Trade contractors, those
could minimise the effects of delayed payments within the involved in electrical and mechanical services and specialised
Sri Lankan construction industry. This study adopted an construction such as aluminium fabrication, waterproofing and
interview-based survey approach to investigate the effects of finishes, are given grades of EM1 to EM5 and SP1 to SP5. In
delayed payments on main contractors and subcontractors and the terms of experience, 40% (eight out of 20) of the participants have
strategies used to minimise those effects. The research sought the more than 20 years of experience, while the remaining 60% have
views of participants (main contractors and subcontractors) who 10–15 years of experience in the relevant field. The research
have experienced construction payment issues on their projects. collated the views of different subtrades: aluminium fabrication,
The survey approach employed enables researchers to collect data plumbing, fire, electrical installation, glazing, waterproofing and lift
by using interviews, questionnaires or a combination of both installation. All representatives of the subcontracting organisations
(Kothari, 2004). interviewed have more than 10 years of work experience. These

201
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

Interviewee Position/profession Years of Nature of the work provided by the Ictad


code experience organisation grade

Main contractors (MC)


MC-I01 Chief quantity surveyor 21 Construction of buildings and infrastructure C1
projects
MC-I02 Chief quantity surveyor 20 Construction of buildings and infrastructure C1
projects
MC-I03 Project manager/quantity 23 Construction of infrastructure projects C2
surveyor
MC-I04 General manager/quantity 42 Construction of infrastructure facilities C3
surveyor
MC-I05 Director/quantity surveyor 20 Construction of infrastructure projects C4
MC-I06 Director/quantity surveyor 20 Construction of building projects C5
MC-I07 Owner/quantity surveyor 10 Construction of building projects C6
MC-I08 Owner/quantity surveyor 10 Construction of building projects C7
MC-I09 Owner/quantity surveyor 12 Construction of building, roads and culverts C8
MC-I10 Owner/quantity surveyor 10 Construction of roads and culverts C9
Domestic subcontractors (DSC)
DSC-I01 Project manager/quantity 15 Aluminium fabrication and installation F1
surveyor
DSC-I02 Senior quantity surveyor 10 Plumbing, fire, electrical works EM1
DSC-I03 Senior quantity surveyor 10 Electrical installation EM1
DSC-I04 Senior quantity surveyor 35 Construction of infrastructure facilities —
DSC-I05 Senior quantity surveyor 20 Waterproofing SP-2
Nominated subcontractors (NSC)
NSC-I06 Director/quantity surveyor 14 Glazing —
NSC-I07 Senior quantity surveyor 12 Plumbing, fire, electrical works EM1
NSC-I08 Senior quantity surveyor 10 Electrical installation EM1
NSC-I09 Senior quantity surveyor 10 Waterproofing SP-2
NSC-I10 Senior quantity surveyor 15 Lift installation EM1

Table 2. Profile of research participants

participants’ information profiles, taken altogether, affirm the respondents (90%) disclosed that the government does not have
reliability and validity of the findings. enough money in the treasury and there is a long procedure to be
followed in making payments to contractors. Understandably,
4.2 Nature of main contractors’ payment issues 70% of the interviewees opined that private clients are good
The views of the participants were collected on the nature of paymasters compared with local governments. MC-I02 and MC-
payment issues: types of payment issues, clients, payments and I06 indicated that corporate clients are financially stable and
types of industry groups. The majority of the respondents (95%) establish proper budgets at the outset. Private project owners
were of the opinion that payment delays occur much more source funding prior to initiating projects, while individual clients
often than losses and non-payment. One interviewee (MC-I03) entering into contracts do so with partially arranged funding.
indicated that contractors experience loss of payments in variation
works, and disagreements about variations are resolved in the Seventy-five per cent of the participants agreed that there are
final payment certificate. According to 90% of the participants, delays in interim payments, which are increasingly delayed as the
non-payment is experienced rarely within the Sri Lankan work progresses, due to the cash-flow difficulties of clients.
construction industry. Therefore, subsequent research focused Interviewee MC-I04 stated that many trades are involved during
mainly on delayed payments. project execution. Therefore, the value of interim payments
increases considerably during project execution. Sixty per cent
All participants representing contracting organisations, except of the main contractors’ representatives experienced delays in
MC-I03, indicated that payment delays mostly exist in projects interim payments when a project moves towards the later stages.
fully funded by the local government. The majority of the Ninety per cent of the interviewees experienced delays in final

202
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

payment. Final payment applications include variations and all the


disputed quantities that were not sorted out in previous claims.
Therefore, the opinion is that final payments are more likely to be
delayed than other types of payments.

Fifty per cent of the main contractors agreed that subcontractors


are affected the worst by payment delays as they are financially
less stable. The next section of the research explored the
nature of subcontractors’ payment issues by interviewing the
subcontractors.

4.3 Nature of subcontractors’ payment issues


Subcontractors’ payment issues are categorised into two: domestic Figure 1. Effects of delayed payments to main contractors
and nominated subcontractors. All of the representatives of
domestic subcontracting businesses confirmed that payment cash flow arranged as per the payment schedule provided by
delays occur frequently, while two of the interviewees (NSC-I03 the client. When the payment is delayed by the client, it will
and NSC-I04) felt that losses of payments occur particularly disrupt the cash flow, which in turn is reflected in the construction
in variations. The majority of the participants from domestic programme. All the domestic subcontractors stressed that they
subcontractors opined that final payment is more frequently are affected badly by delayed payments from main contractors.
delayed than interim payments and there are much fewer DSC-01 pointed out that the subcontractors’ cash flow depends
problems with advance payments and retention money. However, primarily on interim payments and that materials purchase also
interviewee DSC-I05 stressed that retention money is frequently becomes delayed because of late payments. All the nominated
delayed, as the work is already completed and the main contractor subcontractors other than NSC-06 indicated that there are few
takes undue advantage without paying. payment problems, as payments often come directly from the
client.
The nominated subcontractors are generally of the view that they
are not experiencing the same payment problems as domestic Delay in the completion of projects is identified as a critical effect
subcontractors. The representatives of domestic subcontractors of delayed payments to 30% of main contractors and 35% of
are in agreement with the nominated subcontractors’ opinion. subcontractors surveyed. An interviewee (MC-I05) pointed out
Nominated subcontractor payments come directly from the client that the contractor is entitled to claim extension of time (EOT)
and sometimes through the main contractor, as per NSC-I06 when the contractor has followed the contractual provisions for
and NSC-I07. If the main contractor delays a nominated delayed payment. The client has to pay for additional charges
subcontractor’s payment, the client should make the payment only if EOT is approved. Otherwise, the contractor has to bear
directly and deduct that amount from the main contractor’s any additional expenses for the delay. However, the situation is
payment, according to the conditions of contract. Therefore, a different for subcontractors. Most of the subcontractors (90%)
nominated subcontractor’s payments will flow smoothly and found no EOT clause in their contract document. Therefore, the
domestic subcontractors’ payments are at risk in the construction subcontractor is expected to accept the situation and bear the
industry. additional cost incurred for the delay in construction period due to
payment delays. Thus, the subcontractors’ creditability increases
4.4 Effects of delayed payments
The research participants were asked to indicate their opinion on
the effects they experienced due to delayed payment from their
respective paymasters of clients or main contractors in construction
projects. The effects were drawn from the participants’ views by
using NVivo 10. Figures 1 and 2 indicate the effects of delayed
payment to contractors and subcontractors, respectively, with their
respective frequencies.

As observed from Figures 1 and 2, 90% of the main contractors


and 70% of the subcontractors expressed their opinion that the
major repercussion of delayed payment is cash-flow difficulties.
Contractors’ cash flow is the major concern in the construction
industry, as without it contractors are not able to proceed with
the project. An interviewee (MC-I01) explained further that Figure 2. Effects of delayed payments to subcontractors
contractors plan the future activities of the project according to

203
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

and their properties remain with the banks longer than the as labourers, supervisors and staff who connect directly with the
expected period (DSC-I02). However, there is no penalty to the construction works, this would reflect on their performance.
payer, the main party of contracts. Finally, this could lead to an unsuccessful project (MC-I01). The
worst effect of payment delay is that the contractor becomes
Payment delays could cause considerable effects on day-to-day bankrupt. According to DSC-I02, there is much evidence of
construction activities to the majority of the subcontractors, bankruptcy in the small and medium enterprises (SME) sector,
according to 70% of participants. Few of the main contractors which primarily includes subcontracting firms. Large contractors
(20%) concur with this opinion. It seems that the subcontractors have their own strategies to tackle delayed payment situations and
rely primarily on the progressive payments to procure material, thus avoid bankruptcy. However, the SME sector is less financially
labour and plant for the upcoming construction activities. As per stable and fails to have adequate strategies.
interviewees MC-I03 and MC-I04, when payment is delayed, the
contractor has to find other ways to source money to purchase To maintain the reputation of the industry, contractors very rarely
materials and carry out day-to-day construction activities. Therefore, practise dispute resolution methods. However, one interviewee (MC-
the supply of materials for construction activities will be delayed. I05) specified that some contractors choose arbitration without being
The domestic subcontractor (DSC-I01) is of a similar opinion as aware of other contractual provisions for delayed payments. Some of
that of MC-I03 and MC-I04. Interviewee MC-I06 indicated that the subcontractors (DSC-I05, NSC-I06 and NSC-I09) are of the
lower-grade contractors are not capable of handling the risk of similar opinion that effects of payment delays could damage the
delayed payments. In such a situation, the project will not move reputation of the firm. In cases of delayed payment, the subcontractor
further until payment can be made. On this note, DSC-I01 said that could even tend to reduce the quality of work (DSC-I04). This again
when there is a delay in purchasing materials, it slows down the stressed that the project could end up being unsuccessful in terms of
project’s progress. quality, time and cost due to delayed payments.

An equal percentage (20%) of main contractors and subcontractors 4.5 Strategies to minimise the effects of delayed
identified negative impact down the supply chain as another payments
significant effect of delayed payment. MC-I01 agreed that payment The research participants were required to indicate the strategies
delays from a client could lead to delay in a subcontractor’s that they had used as main contractors and subcontractors to
payment. The upper tier follows a back-to-back arrangement minimise the effects of delayed payments. The findings from the
in payment practices to the lower tier. Forty per cent of the interviews indicate that both main contractors and subcontractors
subcontractor representatives (DSC-I01, DSC-I02, DSC-I03 and use two major approaches – the use of contractual provisions and
DSC-I04) agreed that they delay payment to their suppliers, staff other strategies – to handle delayed payment situations. By using
and labourers when there is a delay in payments from the main NVivo 10 to analyse the responses, the strategies identified, with
contractor. Thus, the payment problem reflects up to the last entity their respective frequencies, are presented in Figures 3 and 4.
in the supply chain.
As observed in Figures 3 and 4, 80% (eight out of ten) of the main
Some of the participants were of the opinion that delayed payment contractors sought bank loan facilities to mitigate the effects of
leads to increased contractor’s creditability. They explained that delayed payments. Although this would result in additional costs, a
contractors generally do not keep excess money in hand. Delayed few of the subcontractors (three out of ten) employed this strategy
payments drive contractors to source additional funding from
banks or any other financial institutions irrespective of their
financial capacity reflected by the Ictad grading. If the contractor
has excess money, it is more profitable to invest in another project
than utilise the money in the same project (MC-I02). Another
interviewee (MC-I04) expressed the opinion that contractors,
except C1 and C2 (Ictad grade), purchased materials on credit.
Therefore, the contractors depend heavily on timely payment for
the progress of work to honour their creditors. The situation
remains the same with the domestic subcontractors.

As observed in Figure 1, unsuccessful projects and bankruptcy are


also identified as adverse effects due to delayed payments. When
the main contractor’s payment is delayed, the main contractor will
face cash-flow difficulties that are then transferred to subcontractors
and suppliers. Consequently, parties in the payment chain will Figure 3. Strategies practised by main contractors to minimise
be affected and their performance will diminish. As the payment effects of delayed payments
problem transferred to the final entities in the supply chain such

204
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

delay in certification of payment claims by project consultants, the


consultants suggest an on-account payment. In such a case, on-
account payment is made for at least 75% of the claim amount.

A few of the main contractors and subcontractors have used self-


financing as a mechanism to compensate for delayed-payment
effects. In case of payment delays, the main contractors and
subcontractors use their own funds to procure materials, pay for
workers and pay the supply chain. Generally, the financial
backgrounds of main contractors and subcontractors are less
stable and depend on credit from financing organisations.
However, contractors with C1 grade (according to Ictad), MC-I01
and MC-I02, confirmed that they use their own money in the case
of tolerable amounts that are delayed. Other grades of contractors
generally do not have similar access to funds. MC-I01 and MC-
Figure 4. Strategies practised by subcontractors to minimise
I02 further agreed that they prefer bank loan facilities in situations
effects of delayed payments
where considerably large amounts of payment are being delayed.
This would further endanger the situation by hindering contractors
to handle delayed payment situations. Fifty per cent of the main from undertaking new projects and widening their business. One
contractors confirmed that negotiating with clients on a feasible of the subcontractors (DSC-I02) opined that they use self-finance
payment plan is a better way of handling any delayed payment. where there is a ‘back-to-back’ payment arrangement from the
Forty per cent of the subcontractors are of a similar opinion. Most upper tier. However, if a main contractor deliberately delays,
of the main contractors and subcontractors believe that working subcontractors would blacklist the main contractor and avoid
for trustworthy clients, having mutual understanding and proper working with them in future.
coordination would minimise the effects, rather than working in
accordance with contractual provisions. DSC-I02 pointed out that Within contractual provisions, C1-grade contractors claim interest
the projects they are involved in are mainly on the grounds of as a means of minimising the effects of delayed payments. Other
relationships maintained with main contractors, and, therefore, grades of contractors fail to utilise this payment provision so as to
mitigating problems by way of negotiation was preferred by their maintain their relationship with the client. MC-I01 and MC-I02
organisation. This secures their survival in the industry. indicated that contractors used to include the interest claim in the
final bill, not with interim payment applications. The majority of
Most of the main contractors (70%) indicated that a slowdown in the contractors consider that claiming interest with each interim
work pace is experienced when payments are delayed. DSC-I03 payment application would damage their relationship with the
(in the subcontracting business) also agreed with this view. client. This would result in contractors losing future business
DSC-I03 explained further that they usually divert purchased opportunities with the same client. The majority of subcontractors
materials and labour on other ongoing projects to augment their (90%) were of a similar opinion as the main contractors (except C1
cash flow on a project. An equal percentage (40%) of main grade). They do not charge interest for delayed payments,
contractors and subcontractors identified fund transfer from other preferring a continued smooth relationship with project parties. Two
projects as a mechanism to minimise the effects of delayed of the subcontracting firms interviewed, DSC-I01 and DSC-I02, are
payments. According to the interviewees, both main contractors and of the opinion that delayed payments are inevitable. Therefore, they
subcontractors practise a fund transfer mechanism, where funds are provision for a marginal increase in prices while tendering.
transferred from projects that are at their starting stages (advance
payments) to projects experiencing delayed payment. 5. Discussion
From the current research findings, it would seem that payment
Use of on-account payment is seen as a strategy to minimise delays are mostly experienced on construction projects that are
delayed payments by 60% of the participants representing main fully funded by local governments, since this arm of government
contractors. The contractors who possess an Ictad grading lower usually fails to secure adequate funds prior to the start of their
than C5 seem to be unaware of the provision for requesting projects in Sri Lanka. This is also associated with the lengthy
on-account payment from clients. One interviewee (MC-I03) procedures required for processing payment claims in the Sri
indicated that on-account payments are made when the client Lankan government sector. By comparison, contractors that deal
faces cash-flow difficulties. This strategy would improve the cash with private sector clients are less vulnerable to delayed payment
flow of clients, main contractors and the rest of the supply chain. problems because their clients have more secure project funds.
Only one of the subcontractors (DSC-I04) received on-account Thus, it is safe to conclude that payment delays vary depending on
payments from a main contractor because that subcontractor is a the type of clients, although Hasmori et al. (2012) confirmed that
leading firm and responsible for 95% of the work. When there is a delayed-payment situations were common in government-funded

205
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

and in privately funded projects. Conclusively, untimely payments completion of projects and disturbances to day-to-day construction
and latter-stage payment delays occur because individual clients activities.
start their projects without securing enough funds.
In terms of strategies to minimise the effects of payment problems,
In line with accepted views, this study found that the most critical contractors are more inclined to use contractual provisions, while
effect of delayed payments is the contractor’s cash-flow difficulties. subcontractors are more willing to use strategies other than
Compared with the effects on main contractors, the effects of contractual provisions. Subcontractors need to be facilitated with a
delayed payment on day-to-day activities of subcontractors are simplified standard form of contract for subcontracted works.
found to be more severe. This is due to subcontractors’ primary Although contractual provisions exist, the industry is reluctant to
reliance on progressive payments for managing their projects. Thus, implement strictly such provisions in consideration of the working
the risk of delay to project completion is high for subcontractors. relationship between project participants. For example, the
suspension of work provision in the standard form of contract
In terms of solutions, subcontractors seem to be less aware of entitles the contractor to suspend the work until the payment is
stipulated dispute resolution processes. The provisions for dispute made. However, contractors seldom exercise the provision.
resolution are absent from most subcontractor contracts. Domestic Therefore, it is recommended that professional bodies and
subcontractors are financially less stable and have less protection in government agencies in Sri Lanka need to take actions to protect
terms of contractual provisions. Subcontractors and their workers and promote a balanced allocation of risk and fair contracts to all
are the people who carry out most work at site level. When they parties in construction contracts. The subcontractors suggest that
are cash starved, it is ultimately reflected in the quality of the the allocation of contingency for the risk of payment problems
project. could mitigate the effects to a certain extent.

This research found that Sri Lankan contractors use contractual The research further recommends that a security from the paymaster
provisions to secure delayed payments by slowing down the through the bank in the form of a ‘payment bond’ could improve
work, claiming interest, suspending the work and using dispute the payment situation in Sri Lanka. This would be beneficial to all
resolution mechanisms. Most main contractors tend to slow down parties: the client could receive a return on investment without any
work progress until they are paid. This strategy forces the clients delays because of payment problems and contractors could encash
to source alternative funds, since clients are keen on early or the money through a bank; thereby, this could minimise the effects
timely completion of projects. Although there are provisions of payment problems down the supply chain. The study further
available in construction contracts, contractors tend to avoid suggests that the use of a schedule of payments as part of the
exercising dispute resolution mechanisms to maintain their contract could ensure regular payment to contractors.
continued and long-lasting relationship with clients. Subcontractors
seldom use contractual provisions. REFERENCES
Amoako KB (2011) The Effect of Delayed Payment on Cash Flow
Financially stable contractors in grade C1 and C2 categories have Forecasting of Ghanaian Road Contractors. Undergraduate
access to bank loans to compensate for any delayed payment. dissertation, Kwame Nkrumah University of Science and
Unlike contractors in other countries, Sri Lankan contractors Technology, Kumasi, Ghana.
exercise an on-account payment strategy where 75% of the claimed Ang T (2006) Payment Issues – the Present Dilemmas of the
amount is paid to contractors in case of delays in the certification Malaysian Construction Industry. MSc thesis, University of
of their payment claims. Few subcontractors use fund transfer from Technology, Johor Bahru, Malaysia.
other projects, particularly advance payments received for new Ansah SK (2011) Causes and effects of delayed payments by
projects, to be able to proceed with ongoing projects. The use of clients on construction projects in Ghana. Journal of
these strategies enables subcontractors to mitigate payment risks Construction Project Management and Innovation 1(1):
and survive better in a competitive industry. 27–45, http://dx.doi.org/10.1108/02635571111182782.
Atout M, Jones J and Ren Z (2008) Root causes of construction
6. Conclusions and practical implications project delays in Dubai. In Proceedings of 24th Annual
The primary focus of the current study is on two aspects: the ARCOM Conference, Cardiff, UK, pp. 749–757.
effects of delayed payments to main contractors and subcontractors Balamuralithara B, Chong HY and Chong SC (2011)
and the strategies used to minimise those effects. As a departure Construction contract administration in Malaysia using DFD:
from the existing literature, the current study determined the effects a conceptual model. Industrial Management and Data Systems
of delayed payment from the perspective of main contractors and 111(9): 1449–1464, http://dx.doi.org/10.1108/
subcontractors. According to main contractors, the top three most 02635571111182782.
significant effects of delayed payments are cash-flow difficulties Balatbat MCA and Carmichael DG (2010) A contractor’s analysis
(80%), delays in completion of projects (60%) and negative of the likelihood of payment of claims. Financial Management
chain effects on other parties down the supply chain (40%). For of Property and Construction 15(2): 102–117, http://dx.doi.
subcontractors, the effects are cash-flow difficulties, delays in org/10.1108/13664381011063412.

206
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Strategies to minimise the effects of
Volume 169 Issue MP5 delayed payments
Francis, Ramachandra and Rotimi

Bibi A, Dyian MU, Haseeb M, Lu X and Rabbani W (2011) ARCOM Conference, Glasgow Caledonian University,
Problems of projects and effects of delays in the construction Glasgow, UK, pp. 547–556.
industry of Pakistan. Australian Journal of Business and Kothari CR (2004) Research Methodology, 7th edn. New Age
Management Research 1(5): 41–50. International, New Delhi, India.
Brand MC and Uher TE (2008) Impact of the ‘Security of Mohammed KA and Isah AD (2012) Causes of delay in Nigeria
Payment’ Act in New South Wales on clients, contractors and construction industry. Interdisciplinary Journal of
subcontractors. In Building Resilience – Proceedings of the Contemporary Research in Business 4(2): 785–792.
CIB W89 International Conference on Building Education and National Construction Association of Sri Lanka (2009) Report on
Research (Haigh R and Amaratunga D (eds)). University of Payment Delays in Sri Lankan Construction Industry.
Salford, Salford, UK, pp. 1274–1286. See http://www.irbnet. National Construction Association of Sri Lanka,
de/daten/iconda/CIB11542.pdf (accessed 13/07/2016). Battharamulla, Sri Lanka. See http://www.ncaslsouth.com/
Danuri MSM, Munaaim MEC and Rahman HA (2012) Is late or PAYMENTS.pdf (accessed 10/05/2013).
non-payment a significant problem to Malaysian contractors? Odeyinka HA and Kaka A (2005) An evaluation of contractor’s
Design and Built Environment 3(1): 35–49. satisfaction with payment terms influencing construction cash
Frics MA and Smith MJ (2012) Payments to Contractor – Delay in flow. Journal of Financial Management of Property and
Settlement of Final Account. Wolverhampton University and Construction 10(3): 171–180, http://dx.doi.org/10.1108/
Chartered Institute of Building, Wolverhampton, UK, Report 13664380580001074.
No. 1031989. Pettigrew R (2003) The Need for Payment Controls in the
Guest G, Bunce A and Johnson L (2006) How many interviews Construction Industry. Thomas Telford, London, UK.
are enough? An experiment with data saturation and Ramachandra T and Rotimi JO (2011) The nature of payment
variability. Field Methods 18(1): 59–82, http://dx.doi.org/ problems in the New Zealand construction industry.
10.1177/1525822X05279903. Australasian Journal of Construction Economics and Building
Hasmori MF, Ismail I and Said I (2012) Issues of late and 11(2): 22–33.
non-payment among contractors in Malaysia. Proceedings of Reeves K (2003) Pay up. JUBM Construction News and Views
the 3rd International Conference on Business and Economics, 1(2003): 4–6.
Bandung, Indonesia, pp. 613–623. Sambasivan M and Soon YW (2007) Causes and effects of delays
Hou W, Liu X and Chen D (2011) Payment problems, cash flow in Malaysian construction industry. International Journal of
and profitability of construction project: a system dynamics Project Management 25(5): 517–526, http://dx.doi.org/10.
model. World Academy of Science, Engineering and 1016/j.ijproman.2006.11.007.
Technology International Journal of Social, Behavioral, Sandelowski M (2007) Sample size in qualitative research. Focus
Educational, Economic, Business and Industrial Engineering on Qualitative Method 18(2): 179–183.
5(10): 1266–1272. Tran H and Carmichael DG (2012) The likelihood of
Jayalath C (2013) Arguing Construction Claims. S. Godage & subcontractor payment: downstream progression via the owner
Brothers, Colombo, Sri Lanka. and contractor. Journal of Financial Management of Property
Kaka A, Morledge R and Odeyinka HA (2003) An evaluation of and Construction 17(2): 135–152, http://dx.doi.org/10.1108/
construction cash flow management approaches in contracting 13664381211246589.
organizations. Proceedings of the 19th Annual Association of Wilder J (2007) Guard yourself against construction risk. Hotel
Researchers in Construction Management (ARCOM) and Hotel Management 222(21): 1–12.
Conference, Brighton, UK, pp. 33–41. Ye MK and Rahman HA (2010) Risk of late payment in the
Khosrowshahi F (2000) A radical approach to risk in project Malaysian construction industry. Science, Engineering and
financial management. Proceedings of the 16th Annual Technology 65(1): 538–546.

HOW CAN YOU CONTRIBUTE?


To discuss this paper, please email up to 500 words to
the editor at journals@ice.org.uk. Your contribution
will be forwarded to the author(s) for a reply and, if
considered appropriate by the editorial board, it will be
published as discussion in a future issue of the journal.

Proceedings journals rely entirely on contributions from


the civil engineering profession (and allied disciplines).
Information about how to submit your paper online
is available at www.icevirtuallibrary.com/page/authors,
where you will also find detailed author guidelines.

207
Downloaded by [ UNIVERSITY OF THE WEST INDIES] on [20/09/19]. Copyright © ICE Publishing, all rights reserved.

You might also like