Professional Documents
Culture Documents
Topic:
Retention Money's Impact on SME Contractor Cash Flow and Project Performance
2.0 INTRODUCTION
In this chapter, the definitions and theories related to the topic of this research
will be discussed with the information collected from research papers, journals,
conference paper and e-books. The purpose of the chapter of literature review is to
sections. The first section of literature review will be discussing about the definition
of retention money, SME contractor, cash flow, project performance and PAM
Construction Contracts. The following section will be presenting the literature review
on impact of retention money practice under PAM contracts on the cash flow of SME
contractor. Meanwhile, the last section of this chapter is about the impacts on project
In the 1840s, railway construction during the time of Queen Victoria was the
first time where “retention money” is being utilized. It started because construction
companies often went broke. This caused delays and money loss for clients. The goal
was to give money protection by keeping funds aside to pay for finishing costs if the
contractor runs out of cash. This habit grew popular in building businesses and is still
an important part of papers used for agreements, guaranteeing money safety and
(Raina & Tookey, 2012)
project finish .
until later in the agreement. This is a common way in making deals where the money
held back are only given out after checking carefully to confirm that the project was
(Raina & Tookey, 2012)
finished well. .
client withheld as a guarantee; if there are problems with the building during its
defect liability period, then, these saved funds must be used to fix the problems
(Muhammed et al., 2019) Cui et al. (2010),
. According to “Retention Money” is also
defined as the sum withheld from early payments to ensure a project is finished
contractors or subcontractors until later in the contract. It acts like a promise given by
the customer, meant to handle problems during the time when they can report
defects. This way makes sure the project is done in the right time and it protects
Authors Definition
(Raina & Retention money is the sum kept from paying a contractor or
(Cui et al., Retention money is the sum withheld from early payments to
contract “JCT 98”, 5% of the contract sum, is kept back as security during work on
the project. Also, there is a set top limit for holding onto money. This means that the
most you can keep from payments in a project is 10% of the contract sum which was
(Muhammed et al., 2019)
decided during tender . In Malaysia construction industry,
the amount of retention money withheld by the client has been depicted in the
standard form of contract PAM 2018 in clause 30.5 “The Employer may retain the
percentage of the total value of the work, materials and goods referred to in clause
30.2, which is stated in the Appendix as Percentage of Certified Value Retained” (if
(PAM 2018 (With Quantities), n.d.).
none stated is 5% of the contract sum )
When it come to the release of retention money, only half of the retention
money (5% of the contract sum OR 50% of the retention money) will be released
the remaining half of the retention money (the remaining 5% of the contract sum OR
the remaining 50% of the retention money) will be released after the issuance of
(PAM 2018 (With Quantities), n.d.)
Certificate of Making Good Defects .
Recognising the global importance of the SME sector and the informal
economy, defining SMEs proves to be a tough challenge due to the various criteria
used by different countries. The different criteria that could be considered when
as the number of employees, turnover, and overall balance sheet, are frequently
(Aluko, 2016)
emphasised in the classification of SMEs .
defined a company with fewer than 50 full-time workers or making RM5 million or
(Bank Negara Malaysia, 2005)
less annually .
contractors while the contractors who are graded within the range of G4 to G5 is
Development Board (CIDB). Therefore, SME contractor can also be defined as the
contractors who are graded within the grade of G1 to G5 in the context of Malaysia
construction industry. The Contractor Registration Grades will be shown in the Table
2 below:
SME contractors often face problems that slow down their growth, like
efficiency. They also face regulatory restrictions, limited buying power and trouble
(Hisham & Ruddock, 2017)
getting into global markets . Table 3 below presents the
Authors Definition
(Bank Negara SME (Small Medium Enterprise) is defined a company with
Malaysia, 2005) fewer than 50 full-time workers or making RM5 million or less
(Mohamed et SME contractor can also be defined as the contractors who are
construction industry.
in many ways. In this research, the definition of SME contractor will be limited to
those contractors who are graded within Grade 1 to Grade 5 according to the CIDB’s
Contractor Registration Grades and able to handle projects worth up to RM5 million
Cash flow is the total amount of money that comes in and goes out on a
(Zayed & Liu, 2014)
project during a certain time . Cash flows is also defined as the
amount of money a business has and makes sure it runs well, stays safe with its
(Pavlovi et al., n.d.)
finances, can pay off debts easily and keep up good reputation .
Tarawneh et al. (2023) once said that cash flow is the backbone of the
company. In the context of construction, cash flow has been further categorized into
2 different types namely “positive cash flow” and “negative cash flow”. Positive cash
flow mainly comes from cash received every month through payment certificates. On
the other hand, negative cash flow is linked to spending on a contract. It includes
flow to fluctuate, with large outflows for labour and materials during the early stages
(Glowacki, 2015)
of the project and inflows once it is completed . The factors leading
to the variation of cash flow of a construction firm have been grouped under 5
activities of the construction industry such as paying the wages of the workers,
suppliers, and subcontractors for costs they spend during a certain construction
period. The contractors then add these costs up and the leftover amount makes a
(Koopman & Cumberlege, 2021)
fresh bill that will eventually lead to cash inflow .
within a project or business during a specified period. It represents both the incoming
financial health, security, debt management, and overall reputation of the enterprise.
Positive cash flow is primarily derived from the consistent inflow of funds received
Authors Definition
(Zayed & Liu, Cash flow is the total amount of money that comes in and goes
(Pavlović et al., Cash flows is defined as the amount of money a business has
n.d.) and makes sure it runs well, stays safe with its finances, can pay
(Odeyinka et al., -Positive cash flow mainly comes from cash received every
assessment of success in the construction industry. It's a very complex idea that is
looked at based on many criteria, like client satisfaction, the quality, safety, cost, and
(Unegbu et al., 2023) A. S. Akintoye & MacLeod (1997
time consumed . Besides, according to
the ability of construction project to meet the expectations and
needs of the stakeholders while reaching its objectives and giving the end results is
Both experts and people working in the construction industry agree that
health, the reputation of the construction firm, and the eventual success of the project
(A. S. Akintoye & MacLeod, 1997)
. Key Performance Indicators (KPIs) is
commonly used to measure how well a project is going, the effectiveness and the
stakeholders’ satisfaction. These indicators are important tools for looking at project
cost, construction time, defects, client satisfaction with both the product and service,
contrast, indicators like the predictability of design cost and time, predictability of
construction cost and time, and safety are often categorized as aspects of process-
overall success and effectiveness of a construction project across its entire life cycle.
Authors Definition
(A. Akintoye, Project performance is the refers to the overall success and
(A. S. Akintoye The ability of construction project to meet the expectations and
& MacLeod, needs of the stakeholders while reaching its objectives and
serve a particular purpose within its historical context. Taking inspiration from the
Joint Contracts Tribunal Form's ("JCT 1963 form") structure and design, it came into
(Rajoo, 2010)
being as an organized document suited for specific applications .
The PAM standard form of building contract is a widely used template in
Malaysia, making up about 90% of private sector building contracts. It falls under the
(Harisudin et al., 2022)
category of contracts created by professional institutions .
unique conditions. In essence, it's a crucial and widely accepted framework for
(Rajoo, 2010)
contractual agreements in the Malaysian construction industry . A
obligations of the parties involved and outlining, with reasonable clarity, the scope of
(Zakaria et al., 2022)
the project . The PAM contract is commonly employed to
oversee the contractual relationship between the employer and the contractor
(Chia, 2012)
.
SME CONTRACTOR
Retentions can cause cash flow issues for both contractors and
subcontractors, requiring large borrowing during times when interest rates are high.
(Raina & Tookey, n.d.)
As a result, owners or clients face higher building costs .
Insufficient cash can result in project failure and the bankruptcy of a business
(Al-Joburi, Al-Aomar, et al., 2012)
. Financial difficulties are more likely to impact
common lack of precise control, which amplifies the risk factor owing to the
(Marzouq AL-NASSAFI, 2022)
significant expenses involved in execution . The
uniqueness of each project, coupled with intense competition and market volatility
related to construction activities, increases the susceptibility of construction firms to
(Aluko, 2016)
financial distress .
Besides, it has been proven that the construction industry has suffered from a
late release of retention money by client can affect the contractors’ cash flow which
However, the is also critical factor that cause the contractor to encounter cash
flow problem. The delay in the payment of retention money emerges as a significant
retention money in an unnecessary manner can also cause bankruptcy in the SME
vulnerable to client-induced payment delays due to two key issues. For instance,
their weak bargaining power during negotiations frequently leads them to accept
(Bilotta, 2013)
unreasonable payment delays . Then, the limited liquidity of SMEs
renders them more vulnerable to the negative implications of late payments than
(Bilotta, 2013)
larger rivals .
The delayed release of retention funds, which are vital working capital for
(Namaiwa, 2022)
contractors in the construction industry, directly harms their cash flow
. Consequently, disruptions in this crucial process can seriously jeopardize a
contractor's financial stability, impeding their ability to handle financial demands and
Another research by Odeyinka (2005) has also identified that the practice of
retention money has negatively impacted the SME contractor's cash flow. The
negative impact of retention money on contractor’s cash flow has been further
reinforced by the Latham Report which strongly highlighted the negative impact of
(Latham, 1994a)
retention on contractors' cash flow .
Al-Joburi et al. (2012) argue that a company can endure a transitional phase
bankrupt will result from insufficient cash flow. Numerous researchers have explored
flow problems are one of the main causes that lead to bankruptcy of the contractor’s
firm. In short, upon studying these papers, it has shown that the withholding and late
release of retention money will cause the SME contractors to face cash flow
emphasize that they promptly issue retention payments upon the project's
that the “Delayed of Retention Payment” as “almost always’, which indicates that the
money practice did further exacerbates the financial strain by adding to the already
(Amoa-Abban, 2017)
challenging burden on cash flow .
research are from small and medium sized construction companies in Nigeria has
ranked the delays in payment to the contractors as the highest ranking of the causes
of cash flow problems. Besides, given that contractors work with a slim profit
Okereke (2020) also argued that the delayed payments such as late delayed
payment of retention money will cause cash flow problem, especially for small and
medium contractor’s firm. This can be explained that large contractor firms have
they might have developed methods to address any shortage in cash flow by using
(Okereke, 2020)
alternative funding sources . Conversely, small and medium
contractor firms will have to deal with the shortage of skilled staff in managing their
cash flow and they could not foresee the delayed payments, leading to extra financial
pressure. To cope, these contractors end up using borrowed money to cover the cash
poor cash flow can result in capital lock-up for contractors. In situations where
contractors face financial constraints, they may need to borrow money or utilize
company reserves to meet their obligations. This capital lock-up not only hinders the
cash from its interest-earning capabilities but can also lead to an increase in debt for
the contractor. The need to borrow money or tap into reserves indicates a strained
financial situation, emphasizing the detrimental impact of poor cash flow on the
also ranked as the top leading effects of delayed payments to contractors’ cash flow
As per mentioned in the above section that the retention money practice can
cause cash flow problem on contractors. The cash flow problem will eventually
difficulties in procuring materials and equipment as one of the effects cash flow
delayed payments in Trinidad has led to a casual cultural attitude, fostering higher
tolerance levels for late or non-payments and a disregard for agreed-upon contract
terms which will consequently lead to cash flow problem on contractors. Therefore,
problems is the main problem that caused difficulties for them in procuring materials
and equipment. The contractors claimed that lack of monetary resource will obstruct
them from having the complete set of necessary equipment. Besides, they also
claimed that because of not having enough funds, contractors find it hard to get
important materials like rocks, sand, tar, along with water and fuel oil for their jobs.
They borrow money until they get a point where they can't get more credit. The main
reason for this cash flow problem, according to the contractors, is the excessive delay
(Laryea, 2010)
in getting payment from the government .
Working capital are the financial resources that businesses require to continue
(Afrifa, 2016)
their day-to-day (short-term) operations . Working capital is often
(Makori & Jagongo, 2013)
called the life force of any business . A company's
(Afrifa, 2016) said that investing more money in working capital helps
companies work better. It makes sure operations run smoothly, prevent interruptions
of production, builds strong connections with customers over time and provide
financial flexibility. Although it has been proven that higher working capital can
enhance the overall performance of the firm, unfortunately, a company that facing
financial difficulty such as cash flow problem may not perform such action
(Wasiuzzaman, 2015)
.
Another research carried out in India had depicted that larger firms tend to
have higher working capital than small and medium firms (SME)
(Chauhan & Banerjee, 2018)
. This is due to large firms have extensive diversity, have greater
access to finance markets and can use this advantage to secure more trade credits.
Conversely, small and medium firms are subjected to more financial constraints
(Chauhan & Banerjee, 2018)
. Therefore, small and medium firms tend to face
Lastly, the data findings of a previous research done by Bao et al. (2012) has
shown that financially constrained firms are usually smaller firms with low cash
flow. Expectedly, this small firms will tend to face working capital constraints as
(Bao et al., 2012)
well . To cope with immediate financial needs, these firms often
resort to higher short-term debt. This situation hampers their ability to invest in long-
(Bao et al., 2012)
term assets, leading to reduced growth opportunities . In essence,
financial constraints create a cycle where smaller firms find it difficult to obtain good
working capital.
The previous research has identified that the retention money practice has
(Odeyinka, 2005)
impacted the SME contractors’ cash flow negatively .
Latham (1994)
has further reinforced this issue by strongly emphasizing the negative impact
The influence of cash flow permeates every facet of the construction project
business failure. Scholars have investigated the role of cash flow concerning
scheduling, project delays, business setbacks, and predictive forecasting
(Al-Joburi, AlAomar, et al., 2012)
.
variation on project performance has examined that cash flow problem will have
(Marzouq AL-NASSAFI, 2022)
negative impacts on project performance . Another
research in Ghana also stated that weak cash flow will impact the construction firm’s
(Adjei et al., 2018)
profitability which eventually affects project delivery . In essence,
it has been proven that the retention money will impact the contractors’ cash flow
(Odeyinka, 2005; Latham, 1994;
which further affects the project performance
Al-Joburi et al., 2012;
Marzouq AL-NASSAFI, 2022; Adjei et al., 2018).
In simple terms, a delay in a project is like running late—it's when things take
more time than initially planned, surpassing the agreed-upon date in the contract or
(Abdul-Rahman et al., 2009)
the one decided upon by everyone involved . According
(Abdul-Rahman et al., 2009)
to financial problem has contributed significantly to the
Sweis et al. (2008)
delay in construction project. has supported the statement by
stating that many of the delay in construction projects in Jordan was due to the
According to
Construction Industry Working Group on Payment (WG10). (2007)
, if there are issues with payments, it will create a domino effect, causing
serious cash flow problems down the chain of contracts. Cash flow problem will
cause shortage of financial resources which will then lead to project delay
(Kaming et al., 1997)
Al Mohsin et al. (2014)
. further support the statement of retention
money will cause delay in construction project by saying that the retention money
payment will affect the contractors for not able to achieve minimum cash needed for
cash outflow which further cause some activities to be delayed at the site.
turn, slows down the work on the construction site because many sub-contractors and
suppliers face difficulties with money. As a result, materials don't get delivered to the
(Abdul-Rahman et al., 2009)
site on time and the project progress will be delayed . In
(Abdul-Rahman et al., 2009)
the context of Malaysia construction industry, also
mentioned that financial problem faced by contractors has led to the delay in
Tarawneh et al. (2023)
construction project. also mentioned that the contractors
reflected that poor cash flow affect every phase of construction projects. For
example, buying equipment and raw materials as well as the timely disbursement of
money practice, cash flow problems, and subsequent project delays in the
construction industry.
fulfilling the criteria set by the designer, constructor, regulatory bodies, and the
(Mallawaarachchi & Senaratne, 2015)
owner .
retention money. This has also caused negative cash flow on contractors for a long
(Shash & Qarra, 2018) Shash & Qarra (2018)
period of time . In the same research,
also identified that insufficient of cash of contractors will eventually impact the
Abas et al. (2015)
project quality negatively. had also mentioned that cash flow
problem can impact the construction project quality negatively as agreed by some of
the respondents.
Research by Sambasivan & Soon (2007) has also gathered the perspective of
client saying that poor cash flow of contractors can lead to low quality of works.
When contractors face cash flow problems, they might use lower-quality materials to
save costs (Chadee et al., 2023) . This choice, driven by contractors’ cash flow
problem, can harm the overall quality of the construction project. Using sub-standard
materials may lead to structural problems, less durability, and more maintenance
issues in the future. So, resolving financial issues is not just about money but also
that poor material is one of the factors which contributed significantly to low quality
of construction projects, and it is agreed by some of the respondents with the mean
connection between poor cash flow in the construction industry and compromised
project quality. The research consistently emphasizes that insufficient cash flow
negatively impacts the procurement of quality materials and hinders the ability to
projects have suffered from cost overruns of within 5 to 10% of the total contract
value. Cost overrun is defined as the difference between total cost incurred by a
construction project once it was completed, and contract cost as per agreed by the
(Raykar, 2016)
client and the contractor . Cost overrun will happen when the incurred
(Raykar, 2016) Raykar (2016)
expenses exceed the initial amount budgeted . Moreover,
also state that cost overruns in construction projects can impact the
was ranked number 2 among the factors that will impact cost in construction
projects. This implies that the contractor might find it difficult to finance the current
project if they encounter negative cash flow on most or all of their previous projects.
As a result, there could be project extensions, which would eventually result in cost
(El-Kholy, 2015) Raykar (2016)
overruns . had highlighted that cash flow of
contractor form one of the major factors contributing to cost overrun and he
emphasized that having sufficient cash flow is very crucial for a contractor to operate
his business.
Apart from that, (El-Kholy, 2015) also emphasized that the client’s financial
situation was the most significant factor contributing to cost overruns in construction
Hasmori, Said, et al. (2012)
projects. This statement has been supported by by stating
that client’s financial problem will cause the delay in payment such as retention
money payment which can further lead to cash flow problems in contractors. Another
researcher also argues that the client’s financial limitations has contributed to the cost
(Raykar, 2016)
overrun of construction projects . He also emphasized that the
sufficient cash flow and allocation of adequate money and time during design stage
(Raykar, 2016)
.
examined the significant impact of cash flow on cost overruns. El-Kholy (2015)
further supports this notion, ranking cash flow of contractors as a major factor
(2015) and supported by Hasmori, Said, et al. (2012) and Raykar (2016), is identified
problem may lead to delays in payments, such as late in retention money payment,
productivity accounts for a significant portion of the production input for building
pleasant atmosphere among stakeholders of project management team and impact the
difficulties in procuring materials and equipment are due to cash flow problems arise
who encountered cash flow problems will not have adequate cash to pay the
Laryea (2010)
suppliers for the construction materials required. ,
Abdul Kadir et al. (2005)
Muhammad et al. (2015)
and has supported the statement by identifying cash
flow problems were the main challenge that hindered the contractors’ capacity to
materials by the suppliers which further impact the labour productivity negatively
(Abdul Kadir et al., 2005)
.
As per mentioned by Omopariola et al. (2020), the source of cash outflow for
contractors entails the payment of wages to the labour. The contractors who
encountered cash flow problem will lead to timely payment of wages to the labour.
Ellis et al. (2014) Shinde & Hedaoo (2008)
The previous research by and have
identified that timely payment in wages to the labour will lead to decreased in labour
Mj & Suman (2021)
productivity. The statement is further reinforced by by saying
that late in payments will cause the labour productivity to be impacted negatively.
one of the factors which will lead to decreased in labour productivity. Most of the
employers tend to reduce the wages paid to the labour if they were facing cash flow
(Turnea et al., 2020)
problem . For instance, a survey carried out by ILO Score
Programme in Roman has shown that some of the companies with its cash flow
to labour productivity by showing that countries with higher wages result in higher
(Nikulin, 2015) Ellis et al. (2014)
labour productivity and vice versa . However, have
suggested that prompt payment of wages can motivate the labour and hence increase
the labour productivity. This has shown that rate of wages is intricately linked to
labour productivity.
the reduction in wage rates during periods of cash flow challenges, as evidenced by
various studies, highlights the intricate link between financial stability and labour
(Irfan et al., 2020; Turnea et al., 2020; Nikulin, 2015; Ellis et al., 2014)
productivity .
Ultimately, the evidence strongly justifies the assertion that poor cash flow can
certain undertaking faces multiple challenges and reaches the point of no return in
occupation. Four criteria have been established by the ministry of housing and local
No. Criteria
the abandonment of the project. Financial strain arises, impeding the project's ability
to meet obligations. In the context of cash flow analysis, the presence of negative
cash flows signals financial instability and questions the project's viability. If these
challenges persist without getting an effective solution, they may continue to escalate
and make the project financially unsustainable as well leading into decision of
(Omopariola et al., 2020)
abandonment . The briefs state that negative cash flows not
only spoil a project’s financial health, but they also lead to abandonment.
A few other researchers also claimed that the contractor’s cash flow problem
(Abdul-Rahman et al., 2009;
can eventually lead to construction project abandonment
Abdul-Rahman et al., 2006).
Besides, financial difficulties, specifically cash flow
client as aforementioned and this will lead to their inability to make timely payments
to subcontractors. Subcontractors, less financially resilient, were dependent on
unpaid debts for their ability to continue working. Eventually, the unpaid debts and a
failure to handle cash flow issues raised the chance of project abandonment
(Na Ayudhya & Kunishima, 2017;
Chen Tan et al., 2010)
.
Previous study by Ariffin et al. (2018) discussed the possibility that a lack of
finances would have an influence on the project's cash flow and create a delay in site
may potentially lead to project abandonment. Poor cash flow of contractors has
restricted them from paying for the wages, materials, machinery, and equipment
involved in the project. Consequently, the contractor may decide to pause the work
financial challenges still persist after the payment of due amounts to employers, the
contractor may opt for liquidation which results in the project being abandoned since
correlation between poor cash flow and termination of construction projects. The
V. Doraisamy et al. (2015)
definitions and criteria as given by and
Abdul-Rahman et al. (2015)
has explained the complicated nature of project abandonment. The report
Dahlan (2006)National Housing Department (2017) Salam et al. (2023)
by and about
cash flows are key drivers for project abandonment due to financial strain and
questioning sustainability of the projects. Other researchers including
Abdul-Rahman et al. (2009)
Na Ayudhya & Kunishima (2017) Chen Tan et al. (2010)
, ,
Ariffin et al. (2018)
KWAME BOATENG AMOAKO -BSc (2011)
and collectively confirm that
project abandonment can take place as a result of poor cash flow of contractors.
2.4 POTENTIAL STRATEGIES TO MINIMIZE THE IMPACTS OF
PERFORMANCE
Commons report explicitly raised concerns about the uncertain benefits of retentions,
(Raina, 2015a)
advocating for their elimination . Sir Michael Latham has criticized
Upon analysis from the previous literature, the common potential strategies to
minimize the impact of retention money practice is listed in the table below.
Strategy Source
Bausman (2004)
Raina (2015)
Escrow Account Amusan (2016)
Hartoonian (n.d.)
Cheng et al. (2009)
Retention Bonds (A. E. Oke (2013)
(A. Oke & Ogunmola (2014)
Central Unit on Procurement (1994)
Latham (1994)
Raina (2015)
Ganiyu et al. (2015)
OPPAGA (2000)
Hartoonian (n.d.)
Line-Item Releases Stockenberg & Limbaugh (2002)
Bausman (2004)
Escrow accounts allow the client to deposit the funds retained from
contractors into a third-party account. While the money is held in this account, it
remains reserved from the contractor. Importantly, this arrangement also ensures that
the client, who would typically withhold this sum, cannot employ the funds for its
own purposes, thus preserving the rightfully earned earnings of the contractor
(Bausman, 2004; Raina, 2015)
. Hence, escrow accounts, while not a direct
replacement for retention money, offer a different method of holding funds. This
variation bestows increased legitimacy upon the client’s decision to withhold money
from the contractor, as the funds are designated solely for insurance purposes and
cannot be utilized for any other reason. As a result, the use of escrow accounts has
the potential to foster greater trust among contractors regarding the client’s motives
for retaining funds, potentially reducing relational challenges such as cash flow
(Hartoonian, n.d.;
problem stemming from retention money controversies
Raina, 2015)
.
escrow account has been rated as one of the retention money intervention systems to
money can be found in the construction industry of France, New Mexico, and Hong
Kong. In essence, the escrow account has been identified as the potential strategy to
A retention bond provides a guarantee that, even after the contractor has
received complete payment upon concluding the contract, they are obligated to
(A. E. Oke, 2013)
promptly rectify any identified structural or other defects .
level of protection for defective work, similar to the retention money practice.
According to Central Unit on Procurement (1994), the data findings from the
research has shown that retention bonds provide contractors with enhanced and
predictable cash flow by ensuring full payment at each stage compared to retention
money practice. Moreover, Sir Michael Latham has also reported that the retention
money practice was not liked by many contractors and subcontractors, and they
retention bonds can lead to enhanced cash flow for contractors, providing an
potentially resulting in reduced costs. To further strengthen the fact that retention
bond is a potential strategy to minimize the impact of retention money practice, the
retention bonds has been widely implemented in Europe and International contracts
(Raina, 2015)
and some major UK clients .
clients receive monetary protection while contractors maintain control over their cash
(Ganiyu et al., 2015)
flow . Choosing a retention bond over cash retention not only
ensures financial security for clients but also brings cost savings for contractors. The
money practices.
payment and is kept until the eventual completion of the project, which can span
months or even years. This practice imposes a substantial financial burden on cash
flow of certain contractors, particularly those engaged in early project stages like
(OPPAGA, 2000)
excavation or foundation work .
scope of work, rather than waiting for the entire project to be completed
(Hartoonian, n.d.;
Bausman, 2004)
. This ensures that trades achieving substantial completion can
receive their entitled retained money, even if the contract initially stipulates
(Hartoonian, n.d.)
completion of the entire project .
In order to strengthen the fact that line-item releases is a potential strategy to
Stockenberg & Limbaugh (2002)
minimize the impact of retention money, have
stated that seven states presently have statutes allowing the line-item releases on
public projects. Moreover, in 2001, New Mexico passed a law requiring the release
SME contractor, cash flow, project performance, PAM construction contracts. The
inception of "Retention Money" dates back to the 1840s, suggesting the practice of
reserving a segment of payments until the project reaches completion to guarantee its
employees and an annual income below RM5 million, graded by CIDB from G1 to
satisfaction, quality, safety, cost, and time. The narrative concludes by emphasizing
Chapter 2 also explores the impact of the "Retention Money" practice on the
payments until project completion, can lead to cash flow challenges for contractors
and subcontractors, resulting in the need for substantial borrowing during periods of
high interest rates and increased building costs for owners or clients. The chapter
nature of projects, and fierce competition. The delayed release of retention funds
directly impacts cash flow, hindering financial stability and potentially leading to
borrow money, straining their financial situation. The resulting capital lock-up not
only limits cash from earning interest but also contributes to an increase in debt for
contractors. Difficulties in procuring materials and equipment arise from cash flow
particularly for SME contractors who may face challenges securing trade credits and
resort to higher short-term debt to meet immediate financial needs, limiting their
contractors' cash flow, a pivotal element that permeates all aspects of construction
affirm that cash flow challenges arising from retention negatively influence project
performance. The subsequent sections delve into specific consequences of poor cash
flow, beginning with the widespread issue of project delays. Drawing on global
Malaysian construction industry, are shown to be intricately tied to cash flow issues,
emphasizing the importance of sufficient cash flow for project financing and cost
as cash flow problems hinder material procurement and timely wage payments,
The last part of this chapter delves into strategies to alleviate the adverse
and the House of Commons. Alternative strategies include retention bonds, ensuring
preserving funds in a third-party account for proper use, and line-item releases,
allowing gradual fund release tied to project milestones. These strategies aim to
Last but not least, the next chapter will then describe and elaborate more on
the methodology of the research and the method of data collection for this research.
REFERENCES
Abas, M., Khattak, S. B., Hussain, I., Maqsood, S., Abas, M., Khattak, S. B., Hussain, I.,
Maqsood, S., & Ahmad, I. (2015). Evaluation of Factors affecting the Quality of
Abdul Kadir, M. R., Lee, W. P., Jaafar, M. S., Sapuan, S. M., & Ali, A. A. A. (2005).
Abdul-Rahman, H., Takim, R., & Min, W. S. (2009). Financial-related causes contributing
https://doi.org/10.1057/rlp.2009.11
Abdul-Rahman, H., Wang, C., & Ariffin, N. H. (2015). Identification of Risks Pertaining
Adjei, E. A.-G., Fugar, F. D. K., Adinyira, E., Edwards, D. J., & Parn, E. A. (2018).
Afrifa, G. A. (2016). Net working capital, cash flow and performance of UK SMEs.
2015-0031
performance. https://www.researchgate.net/publication/284823994
Akintoye, A. S., & MacLeod, M. J. (1997). Risk analysis and management in
https://doi.org/10.1016/S0263-7863(96)00035-X
Al-Joburi, Al‐Aomar, & Bahri, M. E. (2012). Analyzing the impact of negative cash flow
Al-Joburi, K. I., Al-Aomar, R., & Bahri, M. E. (2012). Analyzing the Impact of Negative
5479.0000123
SACPCMP.
https://www.researchgate.net/publication/366418834
https://www.researchgate.net/publication/311808133
Argenti, J. (1976). Corporate Collapse: The causes and Symptoms, MacGraw Hill,
London.
Ariffin, N. F., Ali, M. I., Ramli, N. I., Md Jaafar, M. F., Wan Ahmad, S., Shukor Lim, N.
H. A., & Abd Khalid, N. H. (2018). The Study on Cause and Effect of Abandoned
Banwell, H. (1964). The Placing and Management of Contracts for Building and Civil
Bao, D., Chan, K. C., & Zhang, W. (2012). Asymmetric cash flow sensitivity of cash
https://doi.org/10.1016/j.jcorpfin.2012.05.003
Construction Industry.
Construction Industry.
Bilotta, C. (2013). Issue 2 Article 5 2013 Ending the Commercial Siesta: The
38).
Central Unit on Procurement. (1994). Bonds and Guarantees - A Guidance Paper of the
Chadee, A., Ali, H., Gallage, S., & Rathnayake, U. (2023). Modelling the Implications of
05
Chauhan, G. S., & Banerjee, P. (2018). Financial constraints and optimal working capital
Chen Tan, H., Choy Chia, F., Yap, E., Tan, H., & Chia, F. (2010). Causes of Abandoned
Cheng, T., Soo, G., Kumaraswamy, M., & Jin, W. (2009). Are There Ways to Ensure Fair
Chong, H. Y., & Zin, R. M. (2010). A case study into the language structure of
Cui, Q., Hastak, M., & Halpin, D. (2010). Systems analysis of project cash flow
https://doi.org/10.1080/01446191003702484
Doraisamy, S. V., Akasah, Z. A., & Khamis, A. (2016). Factors towards the restoration of
https://doi.org/10.5923/j.ijcem.20150404.01
Ellis, L., Hickson, B. G., & Ellis, L. A. (2014). Factors affecting Construction Labour
https://www.researchgate.net/publication/258245754
Harisudin, M., Adi, R. K., & Qonita, R. R. A. (2022). SYNERGY GRAND STRATEGY
Hartoonian, A. (n.d.). Confronting Retainage and its Disruptive Effects on the Business
Hasmori, M. F., Said, I., & Ismail, I. (2012). Issues of Late and Non-Payment Among
Contractors in Malaysia.
Hoque, M. I., Safayet, M. A., Rana, M. J., Bhuiyan, A. Y., & Quraishy, G. S. (2023).
https://doi.org/10.1108/IJBPA-03-2021-0032
Irfan, M., Zahoor, H., Abbas, M., & Ali, Y. (2020). Determinants of labor productivity for
Kaming, P., Olomolaiye, P., Holt, G., & Harris, F. (1997). Factors influencing construction
Kazaz, A., & Birgonul, Talat. M. (2005). Determination of Quality Level in Mass Housing
195.
Koopman, K., & Cumberlege, R. (2021). Cash flow management by contractors. IOP
https://doi.org/10.1088/1755-1315/654/1/012028
CONTRACTORS.
GHANA.
Latham, M. (1994a). Constructing the team : final report : joint review of procurement
Latham, M. (1994b). Constructing the Team- Final Report of the Government/ Industry
Industry.
Mac-Barango, D. (2017). Construction Project Abandonment: An Appraisal of Causes,
Effects and Remedies. In World Journal of Innovation and Modern Technology (Vol.
Makori, D. M., & Jagongo, A. (2013). Working Capital Management and Firm
Project Success.
Performance: An Empirical Study from Kuwait. Journal of Asian Finance, 9(3), 53–
0063. https://doi.org/10.13106/jafeb.2022.vol9.no3.0053
Mohamed, M. R., Rizal Mohamed, M., Fadhil Mohammad, M., Mahbub, R., Ramli, M.
A., Aizat, K., & Jamal, A. (2018). The Issues and Challenges of Small and Medium-
https://www.researchgate.net/publication/327417154
Muhammad, N. Z., Sani, A., Muhammad, A., Balubaid, S., Ernest Ituma, E., & Suleiman,
https://doi.org/10.11113/jt.v77.6314
Muhammed, U., Eze, E. C., Tsado, J. A., & Okokun, B. (2019). Assessment of bonds
https://doi.org/10.1016/j.procs.2017.11.032
Lumpur.
Nor Azhari Azman, M., Azman, M., Ahamad, M., Majid, T., & Hanafi, M. (2012). A
https://www.researchgate.net/publication/260202571
Oke, A., Aigbavboa, C., & Dlamini, E. (2017). Factors Affecting Quality of Construction
Projects in Swazilland.
Oke, A. E. (2013). Benefits and Level of Using Retention Bond for Construction Projects
Omopariola, E. D., Lowe, J. G., & Abimbola, W. (2017). The effects of cashflow on
Omopariola, E. D., Windapo, A., Edwards, D. J., & Thwala, W. D. (2020). Contractors’
04-2019-0099
Omran, A., Saleh, M. S. H., & Gebril, A. O. (2023). Factors Causing Time and Cost
Paul, S. Y., & Boden, R. (2011). Size matters: The late payment problem. Journal of
https://doi.org/10.1108/14626001111179776
Pavlović, R., Bukvić, R. M., & Pavlović, R. Ž. (n.d.). The Cash Flow Concept in Modern
construction industry.
construction industry.
Raina, P., & Tookey, J. (2012). World Construction Conference 2012-Global Challenges
Salam, S. A. nisaa, Ariffin, N. F., Ali, M. I., & Ramli, N. I. (2023). Assessment On
https://doi.org/10.30880/IJIE.2023.15.02.023
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian
https://doi.org/10.1016/j.ijproman.2006.11.007
Shah Ali, A. (2011). Building Defects: Possible Solution for Poor Construction
https://www.researchgate.net/publication/271201366
Shash, A. A., & Qarra, A. Al. (2018). Cash Flow Management of Construction Projects in
https://doi.org/10.1177/8756972818787976
Sweis, G., Sweis, R., Abu Hammad, A., & Shboul, A. (2008). Delays in construction
665–674. https://doi.org/10.1016/j.ijproman.2007.09.009
Tarawneh, S., Almahmoud, A. F., & Hajjeh, H. (2023). IMPACT OF CASH FLOW
https://doi.org/10.2478/emj-2023-0006
Turnea, E. S., Neștian, Ștefan A., Tiță, S. M., Vodă, A. I., & Guță, A. L. (2020).
demand and cash flow problems during the COVID-19 economic lockdown.
https://doi.org/10.1108/IJMF-01-2013-0016
Wong, J. M. W., Ng, S. T., & Kong, H. (2010). TS 1M-Project and Organisation
https://doi.org/10.46300/91014.2022.16.1
Zayed, T., & Liu, Y. (2014). Cash flow modeling for Construction projects. Engineering,
https://doi.org/10.1108/ECAM-08-2012-0082