BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
IBR required for the steam coil for tags 401-AC-007, 401-AC-008, 401-AC-013 &
401-AC-014. Supplier shall be responsible for design, drawings, fabrication,
2 inspection and testing of Steam coils in accordance with latest IBR code.
Obtaining IBR approval is in supplier's scope. Calculations as per IBR code shall
be performed by supplier.
Vibration analysis and natural frequency calculation for air fin cooler support
8 X
structure including Noise Data sheet
Nozzle loads shall be considered 3 times the allowable loads given in of Table-4 of
9 X
API 661.
BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
B SCOPE OF SUPPLY
Tube bundle assembly including, finned tubes, bundle supports, header box, plug
1 X
sheet, plugs, gaskets, cover plates, etc.
Minimum thickness as per API 661, however minimum tube sheet thickness shall 5.1.6 of IBCE-6373-C00-
3 X
be 22 mm (excluding corrosion allowance) STA-DEC-000-0001
Refer Paragraph
7.1.9.8.d) of IBCE-6373-
C00-STA-SPC-000-0004
Refer 5.14.4 of IBCE-
6373-C00-STA-DEC-000-
4 Nozzle assembly with Flanges X 0001 for flange rating.
Minimum flange rating to
be as per respective
Piping material
specifications IBCE-6373-
C00-PIP-SPC-000-0001.
MP connections (40 NB nozzles with BF) for PG/TI, one on one of the inlets & one 5.18.2 of IBCE-6373-C00-
6 X
on one of the outlets of each header. STA-DEC-000-0001
7 Blind Flange, Gaskets & Fasteners for Vent, Drain & MP connection Nozzle X
9 Plenum chamber X
10 Fan ring X
11 Fan guard X
12 Pulley Guard X
15 Motor Guard X
Headers with Cover for Air Cooler tags. 401-AC-004, 401-AC-007, 401-AC-008 &
16 X
401-AC-014. Plugs with gaskets shall be provided for rest of the tags.
17 Fan & its driving parts. (Fan blades in FRP are preferred) X
19 Bearings X
20 Fan assembly mounting frame (support from structure, Not from plenum) X
BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
25 Tube bundles shall be dry out with hot air after hydro test. X
Shop run-in test & trail assembly shall be done at shop for below parameters for at
least one bay for each type/tag number of Air fin cooler.
- Vibration test
- Air flow rate check
26 X
- noise level test
- Fan tip clearance and blade angle Check
- Temperature rise of bearing and amperage of motor Check
27 Final Painting - All header boxes shall be finally painted at vendor’s shop X
Air coolers structural shall be hot dip galvanized for the following:
a) Plenum chambers, bundle frames.
b) Motor suspension structure, Fan guards, handrails (with paint) & Gratings for
stairs & platforms.
28 X
c) All bolts / nuts for structures.
d) Wire Mesh for fin tube protection.
Lifting lugs:
a) Four lifting lugs for bundle lifting with bundle side frame (Single point lifting with
32 X
spreader beam)
b) Lifting lugs for lifting header covers as applicable.
33 Earthing Lugs X
36 Protective Covering ( for finned tubes) on bundle top -By heavy-duty wire mesh X
Stainless Steel tube connections shall be provided outside the fan guards to permit
lubrication of fan shaft bearings in running condition. Connections shall be
37 X
accessible from grade or platforms. Same provision shall also be made for motor
bearings
38 Fan cage (guard) with hinge type access manway below fan. X
Required lubricant type, grade and initial volume and Lubricants required for twelve
41 X
(12) months operation.
BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
Special tools & tackles (One set) shall be recommended by Vendor for installation
/
maintenance of Air Fin Coolers. Minimum tools & tackled required are 1 set of :
-Inclinometer for fan Cost shall be listed
43 X
-Torque wrench for Plugs separately in the offer.
-Belt Tensioner
-Torque wrench for installation of fan
-Pincer for Fin repair
44 Site Supervision & trial run at site X Based on per DIEM rates
Supervision for fan operating test in field (noise & vibration testing, Air flow &
45 X Based on per DIEM rates
Power consumption)
C ELECTRICAL
7 Cleats for Electrical cable tray support for power and control cables X
LCS (local control station), Emergency stop Push button (at grade), safety switch
8 X
as applicable
9 Cable Glands and lugs for all power and control cables. X
10 Power and Control Cables between MCC & VFD and VFD & Cooler X
Plant Lighting (General illumination). For light fixtures required supports will be
11 X
taken from cooler structure.
12 Earthing Strips within Package Battery limit X
BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
Access Platform Shall be provided, wherever possible on all the four sides with 6.3.6 of BCE-6373-C00-
5 X
grating and handrails, (width – 900 mm) with staircase on both sides. STA-DEC-000-0001
Pipe support
Extension of columns by min.300 mm with top base plate (min.12 thk) for
6 X arrangement for Fire
supporting pipe support arrangement for Fire Fighting Lines.
Fighting Lines by
7 Consideration of nozzle loads in the structural analysis X
Design & Supply of supporting arrangement to support the inlet/outlet piping from
8 X
air cooler structure
Fireproofing material by
11 Fireproofing cleats X
purchaser
BY BY SUPPLIER's CONFIRMATION
Rev. No. SR. NO DESCRIPTION REMARKS
SUPPLIER PURCHASER (YES / NO / N.A.)
F SPARES
Erection and commissioning spares along with main equipment (to be included in
2 quoted price). Also vendor to provide list of Erection and commissioning spares X
recommended by vendor along with offer.
Spares parts list with itemized unit price for two years of normal operation as Cost shall be listed
3 X
recommended by Vendor (apart from mandatory spares) along with the offer. separately in the offer.
Sea worthy export packing & delivery as per project specifications & standards, as
1 applicable. Tube bundles shall be protected by plywood panel over the top raw of X
finned tubes. Tube bundles shall be double-stacked at a maximum.
Rust prevention :
2 Dry N2 charging with pressure gauge to monitor N2 pressure and ½” non-return X
valve.
H EXCLUSIONS ( i.e. PURCHASER's SCOPE )
2 Site Installation X
5 Electrical Lighting X
I OPTIONAL QUOTES
Cost shall be listed
1 Transportation of Air Coolers to Site
separately in the offer.
2 Unit cost for caged ladder