Professional Documents
Culture Documents
2019
WAPCOS LIMITED
(International Consultant in water Resources
Power and Infrastructure, Development)
76-C, Sector – 18, Institutional Area, Gurugram,
Haryana, India, Tele-fax : + 91-124-2399427
E-mail: wrd@wapcos.co.in
2019
Upper Sileru Pumped Storage HEP
SALIENT FEATURES
Chapter 1 GENERAL
Chapter 2 JUSTIFICATION OF THE PROJECT
Chapter 3 BASIN DEVELOPMENT
Chapter 4 INTER-STATE / INTER-NATIONAL ASPECTS
Chapter 5 SURVEY & INVESTIGATION
Chapter 6 HYDROLOGY
Chapter 7 RESERVOIR
Chapter 8 POWER POTENTIAL & INSTALLED CAPACITY
Chapter 9 DESIGN OF CIVIL STRUCTURES
Chapter 10 ELECTRO MECHANICAL WORKS
Chapter 11 CONSTRUCTION PROGRAMME & PLANT PLANNING
Chapter 12 ENVIRONMENTAL & ECOLOGICAL STUDIES
Chapter 13 COST ESTIMATE
Chapter 14 ECONOMIC EVALUATION
Chapter 15 RECOMMENDATIONS
SALIENT FEATURES
7 GUNTAWADA RESERVOIR
(UPPER RESERVOIR)
7.1 Full Reservoir level (FRL) 414.50 m
7.2 Minimum Draw Down Level 406.75 m
(MDDL)
8 DONKARAYI RESERVOIR
(LOWER RESERVOIR)
8.1 Full Reservoir level (FRL) 316.0 m
8.2 Minimum Draw Down Level 291.0 m
(MDDL)
9 POWER INTAKE STRUCTURE
9.1 Type Open Rectangular
9.2 FRL 414.50 m
9.3 MDDL 406.75 m
9.4 Top of intake platform 417.0 m
9.5 Elevation at Intake center Line 381.0 m
9.6 Elevation of bell mouth bottom 375.0 m
9.7 Sill level of Intake 371.0 m
9.8 Length of Intake Pool 1840 m
9.9 Rated Design Discharge for power 1652 m3/s
generation
9.10 Intake Trash-rack
9.10.1 No of bays 40 Nos.
9.10.2 Dimensions W 3.7 X H 34.0 m
9.11 Intake Service Gate-6 Nos. W 6.0 x H 12.0 m (Vertical Lift fixed
wheel type)
9.12 Intake Emergency Gate-6 Nos. W 6.0 x H 12.0 m (Vertical Lift fixed
wheel type)
10 HEAD RACE TUNNEL (HRT)
10.1 Type Finished Modified Horse Shoe
10.2 Diameter 12 m
10.3 Nos. 3
CHAPTER-I
INTRODUCTION
CHAPTER-I
INTRODUCTION
TABLE OF CONTENTS
1.0 General 1-1
1.1 Type of the Project 1-3
1.2 Location of Project Area 1-4
1.3 Access 1-6
1.4 General Climatic Condition in the Project Area 1-8
1.5 General Description of Topography, Physiography and Geology of 1-8
the Project Area
1.5.1 Topography and Physiography 1-8
1.5.2 Geology of Project Area 1-9
1.6 Historical Background of the Project 1-10
1.7 Need for the Project, Possible Options and Justification for Selected 1-14
Option
1.8 Alternatives Configurations 1-15
1.9 Natural Resources of the State/Region 1-20
1.10 Socio-Economic Aspects 1-22
1.11 Land required for the Project Construction 1-22
1.12 Population affected by the project 1-23
1.13 Environmental Aspects 1-23
1.14 Inter State / International Aspects 1-24
1.15 Defence Angle 1-24
1.16 Cost and Benefits of the Scheme 1-24
1.17 Construction Programme 1-25
CHAPTER-I
INTRODUCTION
1.0 GENERAL
The state of Andhra Pradesh (AP) is located in the southern part of India and forms a
major constituent of the southern grid. The Government of Andhra Pradesh was one
of the pioneer states to initiate the power sector reforms in 1998. Major electricity
generation happens through the thermal and the hydro power plants. The erstwhile
Andhra Pradesh State Electricity Board (APSEB) was unbundled into three entities to
focus on the core operation of Power Generation (APGENCO), Power Transmission
(APTRANSCO) and Distribution (APDISCOMS). Significant amount of investments
were made for building up generation capacity, strengthening transmission and
distribution network, industrial feeder segregation, loss reduction and improving quality
of power supply.
overall installed power generation capacity of the state, followed by renewable energy
with a contribution of 6,598.43 MW.
The state has 10 hydro power projects under operation & 2 under construction.
Additionally, the state has 1 operational wind power project. World’s largest single-
location solar park is located in Kurnool district. The project entailed an investment of Rs
7,000 crore (US$ 1.08 billion) and is now fully operational.
In budget 2017-18, the state government announced plans to invest Rs 4,311 crore (US$
669.13 million) for the development of the energy sector in the state.
The government had approved setting up of 6 light-water nuclear reactors in the state in
2016. The nuclear reactors will be set up in Kovvada and will have a capacity of 1,208
MW each. As of January 2018, discussions with Westinghouse Electric Company are in
progress to arrive at a viable proposal.
During 2015-16, the aggregate technical & commercial losses declined to 10.29% as
compared to 11.81% in 2014-15.
Additionally, during the same period, the state government supplemented an additional
capacity of 2,290 MW of power in the state. The state government is targeting
development of an additional capacity of 4,800 MW within the coming 3 years.
As defined by the United States Army Corps of Engineers, pumped storage hydropower
is “a special type of hydropower development, in which pumped water rather than natural
stream flow provides the source of energy” (USACE, 1985). In general terms, pumped
storage hydropower is a technology that stores low-cost off-peak energy or excess or
unusable energy (perhaps generated from renewable energy sources) for later use. While
pumped storage hydropower projects are a net consumer of electricity, they provide
many useful power system operational benefits, including system storage capacity and
power grid ancillary services, which allow other types of electrical plants in the system to
operate more efficiently. From the 1960s to the 1980s, pumped storage hydropower
projects became popular in the United States and Japan as a way to meet fluctuating
power demands in conjunction with nuclear power plants, which are unable to adjust to
changing demands in a timely manner. As renewable energy sources are integrated onto
the power grid, pumped storage hydropower projects are again gaining international
recognition as an effective power storage technology. With the ever growing appeal of
renewable energy sources, wind and solar plants are being developed worldwide. Due to
the unpredictable and sometimes intermittent nature of wind and solar power, pumped
storage hydropower projects are a reliable fall back to compensate for the variability of
wind and solar power, and to store excess or unusable energy from renewable sources,
and therefore allow for the better integration of these types of renewable energy into the
power grid. The majority of modern pumped storage hydropower projects use reversible
pump/turbine units that act as both a pump and a turbine. Most projects in the United
States were built over 30 years ago, before adjustable speed units were available;
consequently, they have single speed units. Advancements in technology have resulted in
the development of adjustable speed units. Consequently, the majority of new pumped
storage hydropower projects utilize adjustable speed units.
The present Upper Sileru Pumped Storage Project is proposed to be constructed on river
Sileru- a tributary of the major river in its own right of the Godavari River System. The
Godavari River has its origin in the Western Ghats of central India near Nashik in
Maharashtra, 80 km from the Arabian Sea. It flows for 1,465 km, first eastwards across
the Deccan Plateau then turns southeast, entering the West Godavari district and East
Godavari district of Andhra Pradesh, until it splits into two distributaries that widen into
a large river delta and flow into the Bay of Bengal.
The Upper Sileru Pumped Storage Hydroelectric Project (“USPSHEP” and/or “Project”)
is located on Sileru River near Sileru village about 200 km from Visakhapatnam /
Rajahmundry. The project envisages re-utilisation of water of the Guntawada reservoir
which is presently being used for power generation at existing Hydro Electric Power
Station and surplus spilled from the reservoir. This water shall be stored in Donkarayi
reservoir located in the downstream side for reutilisation during pumping mode. The
Geographical coordinates of Guntawada reservoir are at longitude 82 0 02' 18'' East and
latitude is 180 03' 34'' North.
The existing Guntawada reservoir near Sileru village is the upper reservoir for the
proposed project. The dam is under operation with a live storage capacity of 3.108 TMC.
The existing Donkarayi reservoir near Donkarayi village will be the lower reservoir to
enable Upper Sileru PSP to operate as a peak station. The dam is under operation with a
live storage capacity of 13.30 TMC.
The project comprises about 2.764 km long head race tunnels (3 nos.) to a surface power
house and have an installed capacity of 1350 MW. Other components of the project
include approach channel, intake, Surge Shaft (2 nos.), underground Penstock and a Tail
Race Tunnel to discharge the flow back into Sileru River downstream of existing Upper
Sileru Hydro Electric Project Power House. The project also involves construction of a
24 m high weir near Villarti village for storage of water of about 1.50 TMC at about 7.5
km upstream of existing Donkarayi reservoir.
The proposed pumped storage project is located in Gudem Kotha Veedhi tehsil of district
Visakhapatnam in the state of Andhra Pradesh. The project is situated close to Sileru
village which is around 190 km from Visakhapatnam. The intake site is located at village
Sileru, which is about 1.50 km from existing Guntawada Dam on Sileru River. The
power house is located on the left bank of the Sileru River, which is about 2.50 km from
Sileru village. The coordinates of the proposed intake at the diversion site are latitude
18°3’3.62” N and longitude 82°2’17.53” E while that of the power house are latitude
18°1’57.60” N and longitude 82°1’15.23” E. Index map of USPSP is placed as Map 1.1
below.
1.3 ACCESS
There is no direct connectivity by Rail or Air to the project site, whereas, the project site
can be reached by Road from various cities / towns / villages. The nearest well settled
towns are Rajahmundry and Visakhapatnam; both are around 200 km far from the project
site. Upper Sileru APSRTC Bus Station, Sileru APSRTC Bus Station, Donkarai
APSRTC Bus Station are the nearby by Bus Stations to Sileru. APSRTC runs Number of
busses from major cities to here.
To reach Sileru, two major approaches are available i.e. Visakhapatnam – Anakapalle –
Makavarapalem - Narsipatnam – Lammasingi – Chintapalle – Gudem Kotha Veedhi –
Sileru route (Refer Map 1.2) which is around 189 km from Visakhapatnam and another
route Rajahmundry – Korukonda – Rampachodavaram – Maredumilli – Guduru –
Mothugudem – Donkarayi – Villarti - Sileru which is around 200 km long. (Refer Map
1.3)
Intake, Power House and TRC of the project can be accessed from Sileru – Donkarayi
road by taking the available bridal paths from Sileru, Pilligedda & Busikonda villages.
Approach roads shall have to be constructed to reach Power House, Surge Shafts and
other structures of the project during project development stage.
It is hot and humid in summer (March to May). Gudem Kotha Veedhi summer highest
day temperature is in between 30°c to 41°c. Average temperatures of March is 27°C,
April is 30°C and May is 32°C. The air gets warmer towards the interior and cools down
in the hilly areas on account of elevation and vegetation. June to September is monsoon
season when the mandal receives heavy rainfall. Winters, continuing from December to
February, are quite pleasant with temperatures ranging from 18°C to 28°C.
Total area of Gudem Kotha Veedhi is 736 km² including 731.77 km² rural area and 3.77
km² urban area. Gudem Kotha Veedhi has a population of 63,174 peoples. There are
14,944 houses in the sub-district. There are about 167 villages in Gudem Kotha Veedhi
block.
The USPSP area is located in the flat terrain in some portions and thick forest in some
portions. The intake and Tail Race Channel areas are under flat terrain in general and
mostly covered with vegetation / agricultural lands. The rest of the project area is mainly
covered by overburden and dense forests with charnockitic rocks, streaky gneiss, granitic
gneiss and granulite group of rocks belonging to Eastern Ghats.
road level near weir site viz. El ±418 m and at El ±390m in the energy dissipation
structure just downstream of the existing Guntawada weir. Detailed geological and
geotechnical investigations has been carried out to confirm the suitability of project
alignment for PFR preparation.
Government of Andhra Pradesh has resolved to harness the hydropower potential of the
State as its central strategy for taking the State on a path of accelerated economic
development. With this objective, a feasibility report (FR) was prepared in the year 2017
through the consultant M/s Aarvee Associates, Hyderabad, APGENCO desired to bring
out a PFR after carrying out topographical survey & investigations, relevant studies etc.
WAPCOS Limited (WAPCOS), thereafter, was assigned to prepare the PFR and DPR
with allied activities in terms of reference / scope of works vide APGENCO LOI no.
CE/C/Hydel,GS,C&I/SE/C/Hyd-1, C&I/F.SLR PSP/D.No. 121/18 dated 29th March
2018 with utilization of Guntawada reservoir as the Upper Reservoir.
As per earlier FR studies, the pumped storage plant with an underground powerhouse,
will be located in the adjoining area of the existing Guntawada reservoir. The power
plant shall be equipped with six vertical axis reversible type hydroelectric units
composed each of a generator/motor and a turbine/pump each having
generating/pumping capacity of 150MW/171MW. Gas insulated switchgear (GIS) will
be provided in separate underground cavern suitably located nearby area of the Machine
Hall. Step up transformers will also be placed in the same Cavern, which will be
connected by bus duct galleries to machine hall.
2 no’s 400 kV double circuit transmission system shall be used by the plant, for
evacuation of generated Power and for Supply of power during pumping mode which
will be connected to Vemagiri and Visakhapatnam 400KV substations.
6 no’s, 216.42m long and 6.0m dia penstock tunnel & pressure shaft, each for one
unit
An underground Power house having an installation of 6 nos. reversible Francis
turbine each of 150 MW capacities operating under a rated head of 97.14 m in
generating mode and 107.88 m in pumping mode.
25 m wide typical Tail Tunnel Surge Chamber accommodating Draft tube gates
2 no’s, 5000m long and 12.0m dia tail race tunnel connecting to tail race channel to
carry the power house releases back to the D/s reservoir.
An ungated weir in Donkarayi reservoir at Ch. 11.75 km (upstream of Donkarayi
reservoir) for temporary storage of 1 TMC of re-utilizable water for USPSP.
Transformer Hall equipped with 18 no’s 1 phase 70MVA step up/step down
transformer and GIS.
In March 2018, APGENCO engaged WAPCOS as a consultant for studying the project
further and for getting the PFR/DPR prepared for the project. As part of this exercise,
extensive survey and investigation works have been carried out to study the project in
detail and identify the best project development alternative. The project being envisaged
with installed capacity of 1350 MW.
Proposed site for Intake Structure and underground powerhouse is within pondage
area of Guntawada reservoir. Inspection / Investigation of area around the proposed
intake location did not indicate presence of bed rock in the exposed area. Exposed
bed rock was observed about 1000 m away from intake location in the area
downstream of spillway of main Guntawada dam at El + 388 m. An appropriate
construction planning needs to be developed along with design of a suitable coffer
dam to facilitate construction of intake and penstock tunnels within Guntawada
reservoir.
Proposed location of a weir for storage of 1.5 TMC of water within Donkarayi
reservoir has been reviewed. Adequate construction planning of the weir within
Donkarayi reservoir within available construction period is needed and appears a
very difficult task if not unfeasible.
Entire project area is covered with top soil with very few rock exposures. However,
competent rock is exposed at the proposed portal for Main Access Tunnel (to
powerhouse cavern).
1.7 NEED FOR THE PROJECT, POSSIBLE OPTIONS AND JUSTIFICATION FOR
SELECTED OPTION
As per CEA, Hydro share as on 31.03.2017 is
It would be seen from above, hydro share of Andhra Pradesh state is lesser than All India
share. It shows the power system demands for more power generation projects such as
hydro power, pumped storage scheme etc. in order to meet the peak demand.
Pumped hydroelectric storage facilities store energy in the form of water in an upper
reservoir, pumped from another reservoir at a lower elevation. During periods of high
electricity demand, power is generated by releasing the stored water through turbines in
the same manner as a conventional hydropower station. During periods of low demand
(usually nights or weekends when electricity is also lower cost), the upper reservoir is
recharged by using lower-cost electricity from the grid to pump the water back to the
upper reservoir. Reversible pump-turbine/motor-generator assemblies can act as both
pumps and turbines. Pumped storage stations are unlike traditional hydroelectric stations
in that they are a net consumer of electricity, due to hydraulic and electrical losses
incurred in the cycle of pumping from lower to upper reservoirs. However, these plants
are typically highly efficient and can prove very beneficial in terms of balancing load
within the overall power system. Pumped-storage facilities can be very economical due
to peak and off-peak price differentials and their potential to provide critical ancillary
grid services.
It is in this context, the development of hydropower in Andhra Pradesh state will not only
benefit the state but also meet the power requirements of the neighboring states and
Southern region of the country. The development of Upper Sileru Pumped Storage
Project is a step in the direction of achieving the demands of the state.
The proposed Upper Sileru PSP is needed for improving the share of hydropower in
overall power supply and to bridge the gap between the power demand and supply at the
regional level. It is also the more environment friendly and sustainable option when
compared with a thermal alternative, the potential for which is non-existent in the state.
Upon review of project layout as proposed in FR, it is foreseen that investigation for PFR
preparation are likely to take about 18 to 24 months’ time due to requirement for
constructing a drift to proposed powerhouse location for assessing its geological
condition. Also, as discussed earlier, a longer construction period of 6 years will be
required with this layout as the project envisages a 1400 m long main access tunnel for
approach to underground powerhouse. With the objective of optimising the investigation
time requirement as well as shorter construction period, three alternative layouts have
been studied based on available data and interpretation of topographical data from
Google maps and Survey of India Toposheets. Description of the three alternatives is
given below:
Length (m)
Component
ALT-1 ALT-2A ALT-3
Approach Channel 138 193 148
In Alternative 1, alignment and length of water conductor system has been kept identical
to the alignment adopted. However, in place of underground powerhouse, transformer
cavern and surge pool, a surface powerhouse with open to sky upstream and downstream
surge pools is proposed. The powerhouse is proposed about 3325m downstream of intake
location. In place of underground transformer cavern, a surface switchyard is proposed.
Suitable adits for excavation of HRT, TRT, upstream and downstream surge pools and
powerhouse will be required. Powerhouse excavation is expected to extend up to depth of
80m below natural ground level and will need adequate rock support planning. Total
length of water conductor system in this alternative is 5858 m and is least but suitable
rock cover is not available to support HRTs, TRTs and other structures.
In Alternative-3, approach channel is proposed in between the spillway of main dam and
head regulator of existing power house. Approach channel length of 148 m is proposed
followed by 3959 m long HRT and 2360 m long TRT. The total length of water
conductor system in this alternative is about 7068 m. This alternative involves about
1621 m longer Water Conductor System in comparison to Alt-1 including 25 m longer
approach channel, 1500 m longer HRT and 96 m longer TRT. Availability of adequate
rock cover for a part of HRT length exists based on the detailed topographic survey
carried out in this area. In this alternative, the TRT will pass below the tailrace channel of
existing powerhouse and adequate rock cover is available at the crossing based on
topographical survey and geological investigation.
Out of above alternatives, Alternative 3 has longest water conductor system and also the
TRT will pass below the tailrace channel of existing project. Therefore, this alternative is
not considered suitable for development of Upper Sileru PSP. Water Conductor system
of Alternative 2 is longer than Alternative 1 by about 692 m. Alternatives 2 have the
advantage of availability of adequate rock cover along entire length of water conductor
system as well as availability of favourable geological condition for HRT excavation.
Alternative - 2 has the shortest water conductor system compared to Alternate-3 and with
suitable rock cover is available along the proposed water conductor system. Accordingly,
Alternative 2 is proposed to be adopted for further development and for planning of
geological investigation. Project layout as per Alternative 2 has been optimized with
respect to hydraulic, geological and structural stability.
A brief description of the project components along the proposed layout in Alternative 2
is given in subsequent paragraphs:
Approach Channel
About 138 m long approach channel shall be designed to feed required quantum of water
to three nos of intake tunnels. Bed level of approach channel shall be kept at El + 405 m
based on required water cushion for intake tunnels. Suitable ramp from river bed level to
bottom of intake tunnels shall be provided. Suitable cofferdam shall be designed to
facilitate construction of approach channel and intake structure.
Intake Structure
Intake structure shall be designed to draw required quantity of water through three
headrace tunnels of 12 m diameter each in place of six penstock tunnels as proposed in
FR. Provision for trashrack and gates shall be made in intake structure. The location of
intake structure was optimised based on results of geological investigation.
Headrace Tunnels
Based on present pumped storage plant capacity of 1350 MW, three HRTs each of 12 m
finished diameter and about 2764 m length are proposed from downstream of Intake till
upstream Surge shaft. The three HRTs are separated by a distance of 63 m. The proposed
alignment of HRT has sufficient rock cover based on the topographical survey &
geotechnical investigations carried out.
Upstream Surge Shaft
An open to sky upstream Surge shaft is proposed about 2764 m downstream of intake
location. Bottom of surge shaft is proposed at El 362.0 m and the top of surge shaft is
proposed at El 425.0 m. Depending on availability of natural ground elevation, about 10-
15 m of upstream surge shaft may have to be kept above ground level. Nine no’s pressure
shaft of 6 m diameter each take off from surge shaft to feed nine Francis turbine
machines located in powerhouse. Tentative size of upstream surge pool is adopted as 150
m x 40 m. The option of providing individual surge pool for each HRT needs to be
explored as this will provide greater flexibility in project construction and maintenance.
Powerhouse and Switchyard/ transformer yard
A surface powerhouse with deepest excavation level at El 262.0 m, service bay at El
295.0 m and centre line of pump/turbine at El 281.0 m is proposed about 392 m
downstream of upstream surge shaft. Powerhouse will have nine pumps cum turbine of
150 MW each. Width of powerhouse is proposed as 25 m and total length of about 205
m. From powerhouse, bus duct shafts are proposed to evacuate / supply power from / to
surface switchyard. Transformers are also proposed to be kept at ground level.
Downstream Surge shaft
The downstream surge shaft is proposed to be located about 78 m downstream of
powerhouse. Nine no’s of draft tube tunnels enter in to the downstream surge shaft and
three no’s tailrace tunnels of 12 m diameter take off from the downstream surge shaft.
Bottom elevation of surge pool is proposed at El 284 m and top of surge shaft is
proposed at El 340 m i.e. near the existing ground level. Dimension of surge shaft shall
be similar to upstream surge pool and shall be verified based on detailed transient
studies.
Tailrace Tunnels
3 nos. of tailrace tunnels each of 12 m diameter are proposed from downstream surge
shaft up to outlet structure located near Donkarayi reservoir. The length of tailrace tunnel
in the revised layout is reduced from 4937 m to about 2486 m.
Outlet Structure near Sileru River/ Donkarayi reservoir
This structure as proposed in FR has been retained for this report. The details of outlet
structure has been reviewed and found feasible based on available detailed site specific
parameters relating to topography and geology/ geotechnical characteristics.
Weir in Donkarayi Reservoir
About 749 m long weir having maximum height of about 31 m is proposed within
Donkarayi reservoir at a distance of about 7.2 km upstream of Donkarayi diversion
structure. Crest of this weir is proposed at EL 310.50 m and FRL is proposed at EL 316
m to pass the design flood with a rubber dam on top of the weir. MDDL at the weir is
considered at EL 310.5 m while the average river bed level at this location is at EL 288
m. At this weir, gross storage of about 1.5 TMC is proposed for re-utilisation of water for
Upper Sileru PSP. Construction of such a structure within an existing reservoir poses a
great challenge. Further, in case of occurrence of design flood during the construction
period of this weir, the flood level is likely to exceed the proposed maximum water level
of 316 m. The capacity of water storage could also reduce over time due to siltation in
the pondage area of this weir.
Water Resources:
The state of Andhra Pradesh is blessed with about 40 major and medium rivers out of
which Godavari, Krishna and Pennar rivers contribute to the major chunk of the surface
waters. The state has about 40000 minor irrigation sources spread over the thirteen
districts.
Agriculture:
Agriculture is the main source of occupation of the state. Rice is the major crop and
staple food of the state and contributing about 80% to 85% of the total food-grain
production of the state. The state is surplus in rice production. Other important crops are
Jowar, Bajra, Maize, Ragi, Small Millets, Pulses, Castor, Tobacco, Cotton, Sugarcane,
Groundnut and Banana. The state accounts for about 55% of the country's entire
production of castor and 94% of Virginia tobacco. Important forests products are teak,
eucalyptus, cashew, casuarina, bamboo, soft wood, etc.
The District has mineral deposits of Bauxite Apatite (Rock Phosphate) Calcite,
Crystaline limestone confined to tribal tracts. Bauxite deposits at Sapparla, Jerrila and
Gudem of G.K.Veedhi Mandal are considered to be the largest in the country. Bauxite
deposits are also identified at Galikonda, Katuki, Chittemgodndi of Araku group
deposits, Katamrajukonda of Gurthedu sub-group of deposits. Phosphate Apatite is
available in Kasipatnam village of Ananthagiri mandal. Rich deposits of Crystaline
limestone and Calcite are mapped in Borra Caves and along the Valley up to Araku from
Borra and around Valasi village of Ananthagiri mandal. Ruby Mica is another mineral
available in the District essential for electrical and electronic industries. The mineral
occurs in the form of Phologopite and is confined to Borra tract.
Quartz is another mineral found mostly in Bheemunipatnam, Padmanabham, Devarapalli,
K.Kotapadu and Ananthagiri mandals. Vermiculate found near Kasipatnam of
Ananthagiri mandal. Clay deposits near Malivalasa of Araku mandal are identified.
Limeshell useful for manufacture of chemical grade lime is also available in the district.
Red and Yellow ochre deposits are also identified in Araku and Ananthagiri mandals.
Power:
The major power projects of the state are-the Nagarjunasagar and Neelam Sanjiva Reddy
Sagar (Srisailam Hydel Project), Upper Sileru, Lower Sileru, Tungabhadra Hydel
Projects and Nellore, Ramagundam, Kothagudem, Vijayawada and Muddanur thermal
projects. Main Hydel power generation projects are Srisailam Hydro Electric Project
(installed capacity of 770 MW) and Nagarjunasagar Complex (installed capacity of 960
MW), whereas Vijayawada Thermal Power Station and Kothagudem Thermal Power
Station are the main source of thermal power generation with installed capacity of 1260
MW and 1180 MW respectively. Simhadri Thermal Power Station with installed capacity
of 1000 MW aims at supplying the entire power generated to the state.
Sikh 8 (0.01%) 1 7
Buddhist 15 (0.02%) 8 7
Jain 17 (0.03%) 12 5
The major project components are underground structures. There is no settlement in the
project area that is where the intake and other permanent project works will be located.
As such no population is affected by the project. As per information available till date, all
the land in the project area belongs to the local farmers, state government and forest
department.
Sileru River on which the project components are located is a tributary of Sabari River. It
originates in Andhra Pradesh and also flows through Odisha before merging with Sabari.
Sileru (known as Machkund in its upper reaches) river joins Sabari river tri-junction
boundary point of Andhra Pradesh, Chhattisgarh and Odisha.
The USPSP project components are located well in the state of Andhra Pradesh and there
is no impact on other states due to construction of this pumped storage project. As such,
there is no interstate boundary passing through its project components. Therefore, no
interstate aspects are involved in this project. It is worth mentioning here that, there is an
existing Donkarayi reservoir on which the weir is proposed for storage of about 1.5 TMC
for the pumped storage project with the same FRL of +316 m as of Donkarayi Dam
which is already exists. Thus, the present project for hydropower development does not
involve any flow regulation or diversion out of the river for consumptive use. Some more
details about the aforesaid agreement are given in chapter on Interstate / International
Aspects.
CHAPTER-II
JUSTIFICATION OF THE PROJECT
CHAPTER-II
TABLE OF CONTENTS
2.1 Justification of Project 2-1
2.5 Peak Power and Energy Requirement in Future (up to likely 2-9
date of project completion)
2.6.1 Demand and Supply Scenario at the end of 11th Plan 2-16
2.6.2 Demand and Supply Scenario at the end of 12th Plan 2-16
CHAPTER-II
Western
2 Region 70328.62 1540 10806 0 82675.1 1840 7547.5 21024.2 113086.79
Southern
3 Region 42542.02 3240 6473.7 761.58 53017.3 3320 11774.8 35971.1 104083.16
Eastern
4 Region 27201.64 0 100 0 27301.6 0 4942.12 1083.64 33327.4
North
5 Eastern 520.02 0 1775.8 36 2331.83 0 1427 287.45 4046.28
Region
Islands
6 0 0 0 40.05 40.05 0 0 12.56 52.61
ALL
7 INDIA 190292.5 6360 24937 837.63 222427 6780 45399.2 72012.8 346619.37
The limited coal resources and difficult oil position all over the world and
Table 2.2 depicts the present status of hydropower development at the country and
state/region level. While in most developed countries, major portion of this non-
polluting & environment friendly source of power generation is already exploited, in
India status of development of hydro potential remains rather poor in comparison. As
will be shown from this data, the southern Region have very low potential of which
about 32 percent is yet to be utilized and Andhra Pradesh State in particular has
exhausted all of its hydro-electric potential as of date.
(Source: CEA)
The need for implementing new hydroelectric schemes in the region for providing
peak power besides energy at competitive rates therefore needs no further emphasis.
While many forms of energy storage systems have been installed globally, Pumped
Storage Plants (PSP) are playing an increasingly important role in providing peaking
power and maintaining system stability in the power system of many countries.
Pumped storage technology is the long term technically proven, cost effective,
highly efficient and operationally flexible way of energy storage on a large scale to
store intermittent and variant energy generated by solar and wind.
pumping process makes the plant a net consumer of energy overall, the system
increases revenue by selling more electricity during periods of peak demand, when
electricity prices are highest.
Total 4785.6
3 Sharavathy-Karnataka 2000
Total 2920
Given the day by day increasing demand for power all over India, and the thrust on
the development of Pumped Storage hydropower to meet the peak power
requirements, the proposed Upper Sileru pumped Storage hydroelectric project in
Andhra Pradesh will not only benefit the state but will go a long way to meet the
overall power and mix requirements at the country level, especially the Southern Region
of the country.
Though the state is presently more or less sufficient in its electrical power/energy
generation to meet its own requirement, there is an urgent need to make up for the
peaking demand which is going to grow in the near future by harnessing its huge
untapped hydro power potential by developing new pumped hydro-electric projects, in
larger interest of the country and the regional power requirements in general and with
the specific purpose of the overall economic well-being of the people of the state. The
development of Upper Sileru Pumped Storage Hydroelectric Project has been taken
up in the direction of achieving the above goals.
The most feasible option for power evacuation is to establish 4 nos 400KV circuits
Chapter.2: Justification of Project 2-6 PFR
Upper Sileru Pumped Storage Project
which are to be transmitted through 2 nos 400KV D/C transmission lines with ACSR
quad Moose conductors. Out of the two transmission lines, One line will be evacuated
to 400KV substation near Visakhapatnam and another line to 400KV substation at
Vemagiri. Cumulative distance of the two evacuation lines is of about 320Kms
(Approx). The option of proposing multi circuit towers capable of carrying all the 4
circuits may be examined subject to availability of capacity at the receiving end
substation. The cost for construction of transmission lines of approx. 650 Crore for
construction of 2 nos 400KV D/C transmission lines is not added to the project cost.
Energy Peak
Peak
Requirement Availability Surplus(+)/Deficts(-) Peak Met Surplus(+) / Deficts(-)
Year Demand
(MU) (MU) (MU) (%) (MW) (MW) (MW) (%)
2009-10 8,30,594 7,46,644 -83,950 -10.1 1,19,166 1,04,009 -15,157 -12.7
The status of the demand-supply position for the Southern Region for the year 2017-18
is given in Table-2.5. It indicates that there was a deficit of -0.2% and -0.4%
respectively in meeting the energy and peak power requirements. The corresponding
figures for the Andhra Pradesh are much lower on account of its relatively small
requirements and imports of power from outside. The year by year situation to date for
the state is reflected in details presented in the following Table 2.6. These show a
similar and rising gap in energy and peak power supply in percentage terms.
Table-2.5: Energy Supply and Peak Power Position in Southern Region for 2017-
18
Surplus / Deficit (-) Surplus / Deficit (-)
Peak Peak
State / System / Requirement Availability
Demand Met
Region (MU) (MU)
(MU) (%) (MW) (MW) (MU) (%)
Andhra Pradesh 58,384 58,290 -94 -0.2 8,993 8,983 -10 -0.1
Karnataka 67,869 67,702 -167 -0.2 10,857 10,802 -55 -0.5
Kerala 25,004 24,916 -88 -0.4 3,892 3,870 -22 -0.6
Tamil Nadu 1,06,006 1,05,839 -167 -0.2 15,001 14,975 -26 -0.2
Telangana 60,318 60,237 -81 -0.1 10,298 10,284 -14 -0.1
Puducherry 2,669 2,662 -7 -0.3 390 387 -3 -0.8
Lakshadweep 48 48 0 0 9 9 0 0
Southern
3,20,248 3,19,642 -606 -0.2 47,385 47,210 -175 -0.4
Region
Table-2.6: Actual Power and Energy Supply Position to date for Andhra Pradesh
Peak Peak Energy Energy
Energy Energy Peak
Deficit / Deficit / Peak Met Deficit / Deficit /
Period Requirement Availability Demand
Surplus Surplus (MW) Surplus Surplus
(MU) (MU) (MW)
(MW) (%) (MU) (%)
2008-09 71511 66673 -4838 -6.8 11083 9997 -1086 -9.8
2009-10 78996 73765 -5231 -6.6 12168 10880 -1288 -10.6
2010-11 78970 76450 -2520 -3.2 12630 11829 -801 -6.3
2011-12 91730 85149 -6581 -7.2 14054 11972 -2082 -14.8
2012-13 99692 82171 -17521 -17.6 14582 11630 -2952 -20.2
2013-14 95662 89036 -6626 -6.9 14072 13162 -910 -6.5
2014-15* 59198 56313 -2885 -4.9 7144 6784 -360 -5.0
2015-16 50437 50366 -71 -0.1 7400 7391 -9 -0.1
2016-17 54301 54257 -44 -0.1 7969 7965 -4 -0.1
2017-18 58384 58290 -94 -0.2 8993 8983 -10 -0.1
Projection of Demand at the end of 12th, 13th Plan and 14th Plan
The demand projections for the end of 12th ,13th and 14th plan based on Electrical Power
Survey (EPS-18 & 19) published by CEA are given in Table-2.7 below for the country
as a whole. The expected demand by 2012-17 (i.e. by the end of 12th plan), 2017-21
(13th plan) and by 2021-27 (i.e. by the end of 14th plan) are 11,60,429 MW, 15,66,023
MW and 20,47,434 MW respectively.
Table 2.7: All India wise Demand Projections Under EPS-18th & 19th
Peak Demand (MW) Energy Requirement (MU)
Plan Period 18th EPS As per 19th 18th EPS As per 19th
Forecasts EPS Forecasts EPS
2016-17 1,99,540 1,61,834 13,54,874 11,60,429
2021-22 2,83,470 2,25,751 19,04,861 15,66,023
2026-27 4,00,705 2,98,774 27,10,058 20,47,434
Source: CEA
Table 2.8: Region wise Demand Projections upto 2026 under EPS - 19th
Source: CEA
As can be seen from above tables that, as per 18th EPS, the projected demand by 2026-
27 would be 27, 10, 058 MW while 19th EPS forecast this to be 20, 47, 434 MW. It may
be worthwhile to mention that the total demand as projected in 18th EPS is on a higher
side than that estimated by 19th EPS on account of reduced demand in the base year
(2015-16) itself as compared to 18th EPS projections.
Further, projections of 19th EPS takes into consideration the reduction in electricity
demand due to aggressive demand side management (DSM), improvement of energy
efficiency and energy conservation measures leading to savings of 95 BU in the year
2016-17, 206 BU in the year 2021-22 and 273 BU in the year 2026-27.
As evident from Table, CAGR of electrical energy requirement from 2016-17 to 2021-
22 works out to 6.18 % and the CAGR of electrical energy requirement from 2021-22
to 2026-27 works out to 5.51 %. The CAGR of electrical energy requirement in the
country from the year 2010-11 to 2015-16 has been 5.28 %.
Table 2.9: Estimation with the Addition of 99,210 MW and enhanced performance in 12th Plan
Capacity at the end of 12th Availability at the end of 12th Plan-
Capacity at the Plan 2016-17
Region end of 11th
Plan (MW) Addition Energy {Col.(4) x Peak {Col. (4) x
Total (MW)
(MW) 0.55 x 8.760} 0.7}
1 2 3 4 5 6
NR 53926 19911 73837 355746 51686
WR 64394 43979 108373 522142 75861
SR 52740 22370 75110 361880 52577
ER 26286 11446 37732 181792 26412
Considering the demand projections for the year 2021-22 as per the 19th EPS (where
CAGR works out to be 6.18%), committed capacity addition from Gas 406 MW, Hydro
6,823 MW, Nuclear 3,300 MW, RES 1,17,756 MW and likely retirement of 22,716
MW (5,927 MW-old and inefficient units + 16,789 MW completing 25 years by 2022
and without FGD space) of coal based capacity during 2017-22, the study result reveals
that coal based capacity addition of 6,445 MW is required during the period 2017-22.
However, a total capacity of 47,855 MW coal based power projects are currently under
different stages of construction and are likely to yield benefits during the period 2017-
22. Thereby, the total capacity addition during 2017-22 is likely to be 1,76,140 MW.
The likely installed capacity from different fuel types at the end of 2021-22 in base case
works out to be 4,79,419 MW including 47,855 MW of Coal based capacity addition
currently under construction and likely to yield benefits during 2017-22 and is given in
Table 2.10.
* This IC does not include Imports from Neighbouring countries during 2017- 22
The likely installed capacity from different fuel type by the end of year 2026-27 is given
in Table 2.11.
The data indicating supply status is given in the following tables for year 2018-19.
Table 2.12: Likely Power Supply Position at All India Level at the End of 2018-19
(As Per LGBR-2018-19)
Period Peak Peak Peak Peak Energy Energy Energy Energy
Demand Met Deficit / Deficit / Requirement Availability Deficit / Deficit /
(MW) (MW) Surplus Surplus (MU) (MU) Surplus Surplus
(MW) (%) (MU) (%)
Table 2.13: Likely Power Supply Position in Andhra Pradesh at the End of 2018-19
Demand and Supply Scenario at the end of 12th Plan with the addition of 99,210 MW
and enhanced performance in 12th plan has been worked out and presented in Table
2.14 below:
Table 2.14: Demand and Supply Scenario at the end of 12th Plan
Region Capacity at the Peak Energy Energy Deficit Peak Demand Deficit /
end of 12th Requirement* Requirement* Availability** / Availability** Surplus
Plan (MW) (MW) (MU) (MU) Surplus (MW) (%)
(%)
73837 55596 356521 -3.65 -5.37
NR 343513 52612
108373 50141 352304 -2.04 -3.65
WR 345127 48313
75110 44782 307047 -0.63 -5.69
SR 305107 42232
37732 20883 128300 -1.12 -10.03
ER 126868 18788
4050 2810 15876 -7.28 -11.92
NER 14720 2475
76 - 381
ISLANDS - -
Table 2.15: Demand and Supply Scenario at the end of 13th Plan
Capacity at the end of Demand (as per 19th Availability at the end
13th Plan EPS) of 13th Plan
Region
Peak Deficit /
Energy Peak Energy Deficit /
Demand Surplus
(MU) (MW) (MU) Surplus (%)
(MW) (%)
All India 2309836 335593 15,66,023 32.2 2,25,751 32.7
From the Table 2.14, it can be seen that Southern Region in particular is expected to
face both energy and peak power shortage of 0.63% and 5.69% respectively at the end
of 12th Plan.
It will be observed also that the deficit in peak power will cease to exists at the end of
13th Plan to the extent of approx. 33% on all India basis because of reliance on Non-
renewable sources of energy which contributes a staggering 1,75,000 MW (36.5%) of
the total installed capacity which necessitates the development of pumped storage
schemes when the reliance on non-conventional sources of energy increases., given that
the National Electricity Policy has set the goal of adding new generation capacity to not
only eliminate energy and peaking shortages but to also have a spinning reserve of 5%
in the system.
In view of the above future scenario, with shortages projected in both energy and peak
power generation at the end of 12th Plan for Southern Region and overall peak power
requirement at the end of 13th Plan because of increase of reliance on non-conventional
sources of energy, development of Upper Sileru Pumped Storage Hydro Electric Project
during the 12th Plan is therefore fully consistent with CEA forecasts of demand and
supply situation and is considered essential, apart from achieving ideal thermal-hydro
mix ratio and socio-economic development of the State.
CHAPTER-III
BASIN DEVELOPMENT
CHAPTER-III
BASIN DEVELOPMENT
TABLE OF CONTENTS
CHAPTER-III
BASIN DEVELOPMENT
The proposed project is located over Sileru River, which is one of the main tributaries
of river Kolab/Sabri of Godavari River basin. So, the Sileru River can be known as
the sub-tributary of Godavari River and its catchment is as such the part of the
Godavary river basin.
The river Sileru known as Machkund River also in the upper reaches, rises in the
Mudugal hills of Visakhapatnam District and nearby Ondra Gadda it becomes the
boundary between Andhra Pradesh and Odisha. For over 48 km the river runs nearly
north along a meandering course through the Padwa Valley. About 48 km south of
Jeypore, it winds westward along the edge of the Plateau and then suddenly turns at a
short angle to the south-west down a steep descent popularly known as Duduma Falls.
It is situated at the eastern limit of the Dandakaranya physiographic region and has a
course of about 190 miles (305 km).
The Machkund River flows northward into Jalaput Reservoir on the border with
Odisha state. Leaving the reservoir—as the Sileru—it makes a sharp bend to the
southwest and flows for a stretch through southwestern Odisha before forming the
border first between Odisha and Andhra Pradesh and then between Odisha and far
eastern Telangana state. During its generally southwestward course there, the river is
parallel to the mountain ranges to the southeast, its channel at an elevation of some
2,000 to 3,000 feet (600 to 900 metres) above sea level. The Sileru empties into the
Sabari River, opposite Konta, in far southern Chhattisgarh state, just a short distance
north-northeast of the Sabari’s junction with the Godavari River in Telangana.
Hydroelectric dams on the Machkund River at Jalaput Reservoir and on the upper and
lower courses of the Sileru are a significant source of power for the region. It has
huge potential of hydro electricity generation which has been substantially harnessed
by constructing of following projects.
Table 3.1: Hydroelectric Projects in Sileru River Basin
Installed
Sl. No. Name of the Project FRL(m) TWL (m)
Capacity (MW)
1 Machkund 838.2 510.85 120
A map depicting the river course of Sileru and the location of above listed projects
marked therein is shown in Fig 3.1 below.
The river Sileru flows almost through the gorge and the catchment of the river is hilly.
So there is absolutely no scope of developing irrigation within the catchment of this
river. If any state authority desires to use Sileru’s water for irrigation, the water needs
to be transferred to neighboring catchment/basin.
The State authority of Odisha is transferring the water released from the Balimela
power station for irrigation use in the Potteru tributary basin of Sabari in Odisha
territory. At present the water released from the other power stations is not useful to
irrigation needs except during lean flow period in main Godavari River for the
requirements of Godavari delta. Uttarandhra region can create huge irrigation
potential with the perennial water supply from the available water storages in Seleru
river basin. The mid lands of East Godavari district can get augmented water supply
by diverting Sileru river water from Donkarayi reservoir (310 m MSL) towards east
of Eastern Ghats by constructing 35 km long tunnel with enhanced power potential.
Similarly, mid lands of Vishakhapatnam District, Vizianagaram district and
Srikakulam district can get augmented water supply by diverting Sileru river water
from Guntawada weir (head works of Upper Sileru power station) at 410 m MSL
towards east by constructing 30 km long tunnel with enhanced power potential. The
diverted water of Sileru River to the east can also be used to supply water to the
Polavaram left bank canal and Visakhapatnam city's continuous drinking water needs
when water level is not adequate in Polavaram reservoir during non-monsoon months.
The water released from the Lower Sileru power station can be diverted to Yeleru
reservoir by gravity with a 70 km long tunnel to create additional irrigation in East
Godavari district. Part of the water released by Lower Sileru power station can also be
used for the planned Lower Sileru irrigation scheme located in Sileru and Sabari
basins.
There is an agreement between the two riparian states to divert the surplus water
available in Upper Kolab reservoir on Kolab/Sabari River to Machkund/Sileru River
for augmentation of its water availability. Diverted water will help in enhancing the
energy production by existing hydel power projects on Sileru River.
The Pumped Storage Hydel Project is proposed to be located at Upper Sileru Hydel
Project site to produce electricity only to meet the peak hour demand without
interfering with normal working of existing power projects. The project will not use
water from the required quantum of water for existing hydel project. The water used
for generation of power during peak hour demand will be pumped back from tail pool
to upper reservoir using energy available in existing hydel project during low demand
hour. So, same water will always go on recycling. This concept has been accepted
universally economical to meet the peak hour demand. The topography of the
catchment is most suitable for production of hydel energy and this proposed project
will enhance the power generation during critical hour of need with no consumptive
use of water.
The existing six number power generation units have almost covered all the power
potential sites in the catchment for regular generation of hydel energy. There may be
few drops available for planning new hydel project. But to meet peak hour demand,
the projects like the proposed project has been recognized universally as most
suitable. There is also possibility to install huge capacity Pumped-storage
hydroelectricity station for the needs of peaking power using high water level drop at
other project site. As there is a cascade of hydel projects in this basin, the reservoir of
upper hydel project will serve as upper pond and the reservoir of lower hydel project
as tail pond for installing Pumped-storage hydroelectricity units. Such arrangement
may prove to be economical and hence advisable.
The proposed project will not require any regular inflows of Sileru River. It will use
always recycled water ie the water once used for hydel generation during peak
demand hour, will be pumped back to upper reservoir during low demand hour for re-
use. As the project does not interfere with the river’s daily flows, there will not be any
adverse effect on the proposed project even in case of any development in U/s and D/s
in future
CHAPTER-IV
CHAPTER-IV
TABLE OF CONTENTS
CHAPTER-IV
4.1 INTRODUCTION
After reorganization of states on linguistic basis and considering the River waters use
/ harnessing in states jurisdiction constitutionally, an interstate aspect is likely to
involve for the use, control and distribution of interstate river water. Govt. of India
enacted the Interstate River Water Disputes (IRWD) Act, in 1956 to resolve the water
disputes, in case it arises. The Indian Constitution provides a role for the Central
government in adjudicating conflicts surrounding inter-state rivers that arise among
the state/regional governments.
IRWD Act is applicable only to interstate rivers / river valleys. If an action of one
state affects the interests of one or more other states, then only water dispute is
deemed to have arisen under IRWD Act. It can be divided into two independent parts
for clarity purpose in understanding the techno-legal application of IRWD Act.
A downstream state’s action can affect the upstream state interest only in one case.
i.e. when a downstream state is building a dam / barrage near its state boundary and
submerging the territory of an upstream state on permanent / temporary basis. Other
than this action, no other action of a downstream state could affect the upstream states
interest which they have been using for economical, ecological and spiritual/ religious
aspects. The meaning of the word ‘interest’ in this context is concern / importance /
significance /relevance / consequence of losing the prevailing water use or purpose.
Whereas all the actions of an upstream state to use or control or distribute the water of
an interstate river can affect the downstream states in one way or the other. These
actions may be as follows:
1. Consuming river water for any beneficial use such as irrigation, drinking water,
industrial, recreation, recharging of ground water, ground water use, enhanced
evaporation losses, enhancing rain water use efficiency, obstructing non flood
flows of the river, transferring water to outside the river basin, etc. (i.e. any man
made /aided action of converting water into water vapour & losing to atmosphere
by evaporation /evapotranspiration processes and also transferring river water
outside the river basin. This is generally done by constructing water storage
reservoirs and subsequently using water for above purposes.
2. Quality of water can also be diminished / altered/ controlled in the action of using
water. It would take place by accumulating the dissolved salts in the remaining
water after its use. The dissolved salts content of water increases due to its
consumption and also addition of more salts by some other activities. Also
causing water more silt laden / turbid is a manmade water quality alteration which
can be caused by mining and deforestation activities. Bringing water from other
river basins for upstream states use also effects water quality in downstream
states.
Generally river water is transferred to water deficit areas for use after creating the
infrastructure for its storage (water reservoirs) and distribution network (canals,
pipelines, ground water charging, etc.). All these acts fall under river water
distribution and control category under IRWD Act. All the above actions of an
upstream state are legal causes of water dispute to the downstream states since their
existing interests are affected as given below:
When an upstream state contemplates water use, it would block the lean season river
flows initially by constructing low cost barrages and tries to store the peak flood
waters ultimately by constructing massive water storage reservoirs. In this process the
river flow regime is altered drastically converting it ephemeral / dry in most of the
time except during floods It also alters the ecology of the river located in downstream
states affecting its riverine vegetation and aquatic flora & fauna. Already the delta
area of rivers are eroding / shrinking when adequate river water is not reaching sea.
This process of river water harnessing affects the downstream states interests as they
are deprived of constantly available river water which they had been using for their
interests. Alternatively, downstream state needs to store more flood water in
reservoirs to cater to the existing water use.
The activities of an upstream state without affecting downstream state’s interests are
peak flood control measures by impounding the flood waters only (not base flows) in
100% or more capacity storage reservoirs for use without affecting water quality
appreciably and run off hydro power generation taken up in its territory.
This Act further has undergone amendments subsequently and its most recent
amendment took place in the year 2002.
The National Water Policy 2002 provides that the water sharing / distribution amongst
the States should be guided by a national perspective with due regard to water
resources availability and needs within the river basin.
The shares of the basin states in a river basin are normally decided either by
agreement among the basin states or by decisions of a tribunal and are given effect to
by themselves. In certain cases regulatory bodies with participation of representatives
of the concerned basin states are also established to facilitate the implementation of
terms of agreement /decision of Tribunal.
The river Sileru on which the project is proposed, is an interstate river rising in the
state of Andhra Pradesh (AP) known as Machkund River in its upper reaches. Andhra
Pradesh and Odisha states have jointly constructed a hydel project on this stream
known as Machkund hydro-electric Project (120 MW) long back i.e. in 1955. Below
this project it enters Odisha state territory and forms interstate boundary at places.
Again at interstate boundary where the river flows down from Odisha state to AP state
territory, both the states have jointly constructed Balimela dam in 1988 to develop
hydel projects of their own. Further downstream of Balimela dam in AP state
territory, it has developed Upper Sileru and Donkarayi Hydroelectric Project of 240
MW and 25 MW capacity respectively. Lower Sileru hydel projects is another hydel
project of 460 MW capacity in its lowermost reaches before it out falls into Sabri
river at the tri-junction point of Andhra Pradesh, Odisha and Chattisgarh states.
An index map of Sabri river basin including its tributaries such as Sileru, Potteru etc
is enclosed as Fig 4.1 for reference.
Sabari River
Godavari River
Sileru River
In accordance with the National Water Policy 2002, Andhra Pradesh (AP) as lower
riparian state and Odisha as upper riparian state entered into agreements to construct
Balimela dam as a joint project and share the Sileru river waters available equally at
Balimela dam site. The two states also agreed to construct their own hydel projects to
generate electricity for their own use. Apart from it, the two states have agreed to
divert the surplus water available in Upper Kolab Reservoir existing in upper reaches
of Kolab/Sabari river jointly to Machkund/Sileru river in order to enhance the hydro
power potential of Sileru river.
and the second on the left side named Gompakonda Main Canal. These two canals
were constructed under the Potteru Irrigation Project for irrigation in Malkangiri
district, the most backward district of the state and thereby lifting the living standard
of the inhabitants. Two more power generation units 75 MW each were added under
stage-2 to increase the installed capacity up to 510 MW.
The share of Andhra Pradesh from the available water in the Belimela is released
downstream into the river for generating hydro-electricity located at Upper Sileru,
Donkarai and lower Sileru Hydro power stations ultimately utilizing the water for
irrigation in the Godavari delta during dry season.
Even after agreement on sharing of Sileru water by the two states, there is some
disputes between the two states on implementation modality of the agreement. Odisha
is not permitting AP to install hydropower units (30 MW capacity) at the toe of
Balimela dam on the grounds of another jurisdiction. Though AP is permitted in the
agreements, Odisha says the site of power house is located in Odisha's territory and
AP cannot install the hydro power units in its land. Thus 30 MW power generation
capacity at a very low generation cost could not be developed for the last 40 years due
to the dispute. Kolab river surplus water available in Upper Kolab reservoir which
was to be diverted jointly by Odisha and AP to Sileru/Machkund river basin for
enhancing hydro power potential substantially has also not materialized till now.
CHAPTER-V
SURVEY AND INVESTIGATION
CHAPTER-V
TABLE OF CONTENTS
5.0 General 5-1
5.1 Topographical Survey 5-1
5.1.1 Project Location 5-2
5.1.2 Topographical Survey & Preparation of Maps 5-2
5.1.3 Boundary / Limits of Survey Area 5-3
5.1.4 Methodology adopted in Topographical Survey 5-3
5.1.5 Network of Benchmarks 5-6
5.2 Archaeological Surveys in Reservoir Area 5-9
5.3 Mineral Surveys in the Catchment Area 5-9
5.4 Right-of Way Survey 5-9
5.5 Communication Survey 5-10
5.6 Geology & Geotechnical Investigations 5-10
5.7 Seismicity 5-11
5.8 Foundation Investigations 5-13
5.8.1 Exploration by Drilling 5-13
5.8.2 Location of Drill holes 5-14
5.9 Construction Material Investigations 5-17
5.10 Hydrological and Meteorological Investigations 5-17
CHAPTER-V
5.0 GENERAL
For appropriate designing & constructing various components of a Pumped Storage
Project, it is necessary to obtain detailed information on geology and engineering
properties of strata at the selected site of works apart from carrying out detailed survey
of the area, hydrological studies & environmental studies etc. For preparation of Detailed
Project Report for Upper Sileru Pumped Storage Project, Survey, Investigation & studies
were awarded to M/s WAPCOS which included the following:
Detail topographical surveys covering the project area have been carried out by M/s
WAPCOS under the pre-construction investigations to firm up the project layout and
carrying out designs of various civil structures of the project for construction. Various
levels of topographical data were made available, based on which possible alternatives
were worked out. Depending upon the suitability of the confirmed alternative, further
detailed topographical investigation was asked for finalization of various components
of the project.
During the time of survey, WAPCOS survey team with Engineers & Geologist
accompanied the survey team all along the field activities.
The survey team was provided with all the necessary survey instruments, other tools &
plants, transport facility etc. for smooth operation of topographical survey.
Fig. 5.1 Area Surveyed for the proposed Pumped Storage Project
DGPS Survey
DGPS Survey incorporated survey of marking of 10 Static Points and 70 TBM Points.
The Control points planning was done on Google Earth by identifying the permanent
structure like Bridge location, major culverts or any topographic features which is
visible on the Google imagery and that can be later identified on Drone Imagery.
Differential GPS instrument (compatible with L1/L2 & Glonass) has been utilized for
this process to achieve “Sub-meter accuracy” of the ground control points.
LiDAR Survey
LiDAR Survey was carried out on a 12 km road stretch called Donkarayi-Sileru Road
laterally bisecting the AOI.
Drone Survey
Flight Planning was done on Google Earth followed by actual Drone Survey on the
Ground.
The rubber dam is proposed at 7.2 km upstream within the existing Donkarayi reservoir
with a FRL of EL +316.0 m, thus, this dam will act as a storage structure in the existing
reservoir. Therefore, no reservoir is forming due to construction of this dam. Since,
there is no archaeological structures are exists in the existing Donkarayi reservoir, no
separate surveys are considered under this project.
As the proposed rubber dam weir is to be constructed in the existing Donkarai reservoir,
thus, there is no known minerals found in the area, no mineral survey has been carried
out.
The proposed road leading to the project area has been surveyed by LiDAR. Andhra
Pradesh Power Generation Corporation Limited (APGENCO) should be given right of
way for these roads in order to have access at various project components.
Project site offices are proposed to be located within the project area itself. The project
is connected with two railway head, one is Visakhapatnam railway station and another
is Rajahmundry railway station. Both railway stations are on meter gauge (M.G) and
are well connected by roads with Sileru which is a nearby village of the project.
The road distance from Visakhapatnam railway station (MG) to Sileru is 189 km and
from Rajahmundry railway station is 200 km which are two lane black top roads. The
nearest domestic airport is in Visakhapatnam / Rajahmundry.
At present the Power house site is not directly approachable by Road. The existing
above mentioned roads are used to approach the major project components such as
Power House & Surge Shafts. The Power House site is located about 2.5 km from
village Sileru. The weir site is approachable from Mangampadu village and is about 23
km from Sileru. Since all the project components has been aligned on the left bank of
the river, it is proposed to strengthening the existing bridges on the canals / streams of
River Sileru through which all material and machineries for the Power house complex
will be supplemented.
Apart from widening of the existing road network and construction of bridges, for
which enough provision has been kept in the cost part, there are no. of RCC and
Masonry culverts falling the route, which also needs strengthening.
1. Geotechnical Investigation
6. Seismotectonic evaluation
During the course of the field investigations, several traverses were undertaken on the
alignment along the river for conducting geological and geotechnical investigations.
Drilling activity was started with four drill holes at Intake location at the location given
in the PFR. Due to significant level difference found in ground levels in the course of
topographic survey works being carried out simultaneously, the project alignment had
been modified. The selection of final alignment was done after considering various
alternatives which have been discussed in Chapter-1. Location of project components
Location of other project components were also critically analyzed keeping in view the
site conditions. Further, due to insufficient storage available at the proposed weir
location as per FR, weir axis was shifted to downstream.
5.7 SEISMICITY
The Bureau of Indian Standards (BIS), formerly Indian Standard Institution had initially
divided India into five seismic zones (Zone I to Zone V). However, the Bureau have
subsequently revised the five seismic zones into four seismic zones by merging zones
I & II (Fig. 1). The Seismic Zoning map of India places the area of the Upper Sileru
Pumped Storage Project in seismic zone II which has less intensity earthquakes.
As per the BIS, the maximum earthquake intensity in future earthquakes in different
seismic zones can be of the order indicated below:
Zone Maximum earthquake intensity
II VI
III VII
IV VIII
V IX & above
Earthquakes in the recent past have occurred along and off the Andhra Pradesh coast
and in regions in the Godavari river valley. In the north, faults associated with the
Godavari Graben show movement during the Holocene epoch. Another NW-SE
trending active fault called the Kaddam Fault runs in a section of the northern Andhra
Pradesh and continues in the same direction towards Bhusawal in north Maharashtra.
The other prominent active fault is the Gundlakamma Fault which trends in a NW-SE
direction from near Ongole on the coast running inland in the same direction for about
100 kilometres. Several smaller faults have been found in the delta region and along
the coast near Vishakhapatnam. However, it must be stated that proximity to faults does
not necessarily translate into a higher hazard as compared to areas located further away,
as damage from earthquakes depends on numerous factors such as subsurface geology
as well as adherence to the building codes.
Seismic Hazard
The seismic hazard map of India was updated in 2000 by the Bureau of Indian Standards
(BIS). According to the new map, the state of Andhra Pradesh lies in Zones II and III.
The south-eastern districts of Chitoor, Cudappah and Nellore have been placed in Zone
III. Sections of Anantapur district which formerly lay in Zones II and III of the 1984
BIS map now lies in Zone II. Districts that lie in the Godavari and Krishna river valleys,
including the Godavari-Krishna delta region lie in Zone III.
Acronyms Used:
Mw=Moment Magnitude, Mb=Body Wave Magnitude
* Source: http://asc-india.org/seismi/seis-andhra-pradesh.htm
The scope of work for Geotechnical Investigation for the said project envisages drilling
of boreholes in the various components of the project areas.
Details of bore holes to be drilled and the probable depth is indicated in below
Total 62 drill holes envisaged covering entire proposed alignment of the project and the
locations of these drill holes are indicated in
Table .
The coordinates mentioned in this table are taken at the drilling site using handheld
GPS and also given in the respective log sheet of the drill hole.
Location Depth
No. Easting Northing Latitude Longitude
ID (in M)
Location Depth
No. Easting Northing Latitude Longitude
ID (in M)
12 D12 608746.619 1994253.874 18° 2' 2.557" N 82° 1' 38.623" E 115
18 D18 608049.085 1994192.981 18° 2' 0.702" N 82° 1' 14.891" E 100
Location Depth
No. Easting Northing Latitude Longitude
ID (in M)
Location Depth
No. Easting Northing Latitude Longitude
ID (in M)
44 D44 608985.847 1994300.535 18° 2' 4.032" N 82° 1' 46.768" E 105
Location Depth
No. Easting Northing Latitude Longitude
ID (in M)
59 D59 608120.805 1994374.837 18° 2' 6.605" N 82° 1' 17.364" E 100
The hydrological studies for Upper Sileru Pumped Storage Project have been carried out
based on Hydrological data of the observation sites located in the project area and around
on river Sileru. There is no site specific data available at the project site or at any section
upstream of it. Hydro meteorological and sediment data collected so far and hydrological
studies are given in Chapter- Hydrology.
CHAPTER-VI
HYDROLOGY
CHAPTER-VI
HYDROLOGY
TABLE OF CONTENTS
6.1 Introduction 6-1
6.2 River System 6-1
6.3 Data Availability 6-4
6.4 Water Availability Study 6-4
6.5 Design Flood Studies 6-6
6.5.1 Design Flood Criteria 6-6
6.5.1.1 Design Flood Criteria – Dam 6-6
6.5.1.2 Design Flood Criteria – Barrage 6-6
6.5.2 Estimation of Design Flood Based on Unit Hydrograph 6-7
Method
6.5.2.1 Design Storm 6-7
6.5.2.2 Design Flood 6-10
6.6 Sedimentation Studies 6-11
6.6.1 General 6-11
6.6.2 Assessment of Sediment Inflow Rate 6-11
6.6.3 Criteria and Methodology 6-12
CHAPTER-VI
HYDROLOGY
6.1 INTRODUCTION
Since the existing Upper Sileru Hydel Project on Sileru river is incapable to meet the present
day’s demand of peak load, it has been decided to investigate possibility of providing an
additional storage of one TMC water, which can be used for generation of power during peak
demand hour only and same water can be pumped in the storage using excess energy available
from existing hydel project during off peak hour. Thus pumped storage plants have the
advantages of generating electricity at lower cost compared to other peak load plants (gas
and diesel power plants).
Sileru River is a tributary of Sabari River. It originates in Andhra Pradesh and also flows
through Odisha before merging with Sabari. Sileru (known as Machkund in its upper reaches)
river joins Sabari river at tri-junction boundary point of Andhra Pradesh, Chhattisgarh and
Odisha states. Sabari river crosses the border into Andhra Pradesh to merge with Godavari
river.
Sileru River is a part of Lower Godavari sub-basin which falls in Godavari basin.
The Sileru river rises at a general altitude of 1524 m above MSL and drains the western face
of the Eastern Ghats known as Machkund, in its uppermost reaches, it flows in a north-westerly
direction upto Chikanput, where it takes a sharp right angle bend and flows due south-west to
its confluence with the Sabari, an important tributary of the Godavari River. The river lies in a
hilly region and is covered with light jungle in the upper reaches (above Machkund) and dense
mature forest in the lower reaches. The area is sparsely populated and malarial.
For most of its course, the river is characterized by relatively lowe bed slopes, sharp drops being
encountered at the Duduma Falls (550 Ft.) and of the order of 300 ft. each in sharp bends of the
river below Guntawada and up stream of Polluru. Valley characteristics are generally
favourable for providing storage to regulate flow and the sharp drops lend themselves for
economic hydro-electric developments.
Sileru river has huge potential of hydro electricity generation which has been substantially
harnessed by constructing Machkund (120 MW), Balimela (510 MW), Upper Sileru (240 MW),
Donkarayi (25 MW) and Lower Sileru hydro (460 MW) power projects. Chitrakonda (60 MW)
hydro project located at the toe of Balimela earth dam is planned to utilise the head available
across the earth dam. The catchment areas of Sileru river intercepted by various project sites
are tabulated below.
An index map showing the river system and all the existing projects thereon is enclosed at Fig.
6.1. Catchment area of proposed Structure at Guntawada reservoir is appended at the end of the
chapter.
GODAVRI RIVER
Inflows into the reservoir of Upper Sileru Hydel Project are regularly observed and available
for the period from 1999 to 2017. The monthly inflow series thus available is shown in Annex
VI-1 which has been analyzed to find out availability of required quantity of water for the
additional storage as well as the energy available from existing generating unit for recycling
the water.
The river Sileru involves an interstate aspect having Odisha as upper riparian state and Andhra
Pradesh as lower riparian state. A hydel project with storage, known as Balimela Hydel Project
is located just U/s of interstate border i.e. in Odisha. The project uses a part of its upstream
inflows for hydel generation and there after diverting the same water to irrigation command
located in adjoining tributary of Sabari river ie Potteru’s catchment in Odisha territory. The
requirement of the irrigation command as per project report is shown in Annex VI-2.
At Balimela project site, both the Andhra Pradesh (AP) and Odisha states have entered into an
agreement for constructing Balimela dam as a joint project and share the Sileru river waters
available equally at Balimela dam site.
Available 18 year’s inflow records at Upper Sileru project site and the irrigation requirement
for Potteru command have been analyzed accordingly as shown in table at Annex VI-3. The
plot of annual flows at Balimela dam site is shown below.
85.00
80.00
75.00
70.00
65.00
Virgin Flow- Guntawada Reservoir
60.00
55.00
50.00
Using annual inflow values at Balimela project site, the flow duration diagram is drawn and
shown below. Annual flows with dependability of 50%, 75% and 90% at Balimela project site
and corresponding flows to be available at Upper Sileru project site are tabulated below.
Guntawada Reservoir
85.00
80.00
75.00
70.00
65.00
60.00
55.00
50.00
2006-2007
2007-2008
2014-2015
1999-2000
2003-2004
2004-2005
2013-2014
2015-2016
2008-2009
2017-2018
2005-2006
2001-2002
2010-2011
2016-2017
2000-2001
2011-2012
2012-2013
2009-2010
2002-2003
Probability of Exceedance
Annual flows to be available at Upper Sileru Project site have been segregated into monthly
flows as per the ratios based on observed inflow series recorded at Upper Sileru Project site.
The monthly flow series thus obtained is tabulated and appended at Annex VI-4. This monthly
flow series have been simulated at Upper Sileru Hydel Project site to find out the availability
of required quantum of water for proposed Pump Storage Hydel Project at Upper Sileru Hydel
Project Site.
The criteria for inflow design flood is given in IS: 11223-1985 "Guidelines for fixing spillway
capacity". The dams may be classified according to size by using the hydraulic head (from
normal or annual average flood level on the downstream to the maximum water level) and the
gross storage behind the dam as given below. The overall size classification for the dam would
be greater of the following two parameters:
The inflow design flood for safety of the dam would be as follows:
For derivation of unit hydrograph at the dam site proper short interval concurrent rainfall and
runoff data at the site is imperative. Since, no such data is available the procedure given in the
Flood Estimation Report published by CWC, for streams/rivers having small catchments in
India have been followed. The whole country is divided into Sub-Zones and as per the report,
the Sub Zone – 3(f) is applicable for proposed project i.e. proposed Structure on Sileru Near
Guntawada Reservoir, Andhra Pradesh for deriving the unit hydrograph for the project
catchments. The unit hydrographs developed accordingly for the project catchments are given
(Proposed Structure on Sileru at Guntawada reservoir are annexed as Annexure – VI- 5).
For design flood studies of proposed Structure on Sileru Near Guntawada Reservoir, Andhra
Pradesh, the design storm values are required i.e. rainfall having return period of 25 years, 50
years, 100 years, Standard Project Storm (SPS) and Probable Maximum Precipitation (PMP)
are required. These 25, 50 and 100 year return period design storm were estimated from the
iso-pluvial maps shown in the Flood Estimation Report for Lower Godavari Sub zone (3f)
whereas 2 Day SPS were taken from CWC’s PMP Atlas for Godavari River Basin (November
2014). The SPS is the highest storm depth recorded over the catchment or 500 year return period
depth, whichever is higher. Accordingly, 48 – hour storm may suffice for design flood peak,
which was considered in the study.
Considering the orography and location of the catchment, rainstorms that can affect this
catchment have been analysed using the DAD method. The storm centred over Koida (17.75
N, 81.33 E) which occurred on 16th - 17th June, 1996 was used as a contributory rainstorm to
the 2-day rainstorm DAD envelope of Godavari Basin (317) for catchment area equal to 5,000
Sq. Km. The 2-day rainstorm DAD envelope for Godavari Catchment is shown in Fig: 6.4.
The in-situ Standard Project Storm (SPS) were read from corresponding DAD envelope curves
of the basin for 2-day duration. These SPS (in-situ) values were multiplied with the MMF to
obtain in-situ PMP values. SPS (in-situ), contributing storm, MMF and PMP (in-situ) for 1-
day, 2-day, and 3-day durations for different areas for the catchment are given in Table 6.5.
Source: CWC’s PMP Atlas for Godavari River Basin (November 2014)
The 25, 50, 100 year return period depths along with Standard Project Storm and Probable
Maximum Precipitation depths for the proposed structures are enlisted below in Table 6.6.
Probable
100 year Standard
Proposed 25 year 24- 50 year 24 Maximum
24 Hour Project
S.No. Diversion Hour Rainfall Hour Rainfall Precipitation
Rainfall Storm
Structure (mm) (mm) (PMP)
(mm) (SPS) (mm)
(mm)
Sileru
1 (Guntawada 233.54 272.46 301.87 674.58 809.18
Reservoir)
Conversion Factor for converting maximum 1 - day rainfall (observed at 0830 hrs daily) to
maximum 24 hr depth unrestricted by observational hour, known as Clock Hour Correction -
CHC: 1.15
The 48 hour design storm in four bells (12 hourly) has been adopted with its time distribution
as given in CWC’s report for convolution on the unit hydrograph developed for each of the
project catchments and the flood values for 25, 50 and 100 year return period and Standard
Project Flood(SPF) as well Probable Maximum Flood (PMF) has been convoluted with time
distribution as given in CWC’s PMP Atlas for Godavari Basin (November 2014) obtained
accordingly with the addition of Base flow at the rate of 0.05 cumecs/sq.km for Proposed
structure on Sileru River respectively are given as(Annexure – VI-5).
6.6.1 GENERAL
In order to estimate the extent of reduction in the live capacity of the reservoir it is necessary
to determine the sediment trapped over a period and predict its distribution at various levels of
the pondage. It is well known that life of the reservoir is very much affected by sedimentation.
Therefore, it is very necessary that the capacity lost in the reservoir due to sedimentation during
its life is accounted properly. As the life of the hydro power project is considered to be 100
year, therefore, 50 years of reservoir sedimentation is considered for revised Elevation Area
Capacity curve for use in the simulation studies. The outlet sill level of the reservoir is kept
well above the 100 year New Zero Elevation (NZE). The procedure discussed in CBIP
publication No 19 “life of the reservoir” is used for obtaining the New Zero Elevation and the
revised Elevation-Area-Capacity curves expected after 50 yr. and 100 yr. sedimentation
respectively. The 100 year sediment load for the new zero elevation has been used for fixing
water supply outlets and MDDL of the reservoir. The 50 year revised area capacity curves for
reservoir would be used in the simulation/ working table studies.
Since no silt observations are available as yet for the project site proposed on Sileru, the rate of
sedimentation is inferred from the report published by CWC “Compendium on Silting of
Reservoirs in India, 2015”. An extract of the said report is given below for consideration of
sediment rate in the project area.
Accordingly, the annual sediment load at proposed structure at Guntawada reservoir on sileru
river has been estimated assuming 0.378 mm/yr from their intercepted catchments which rather
gives a conservative estimate in view of existing projects upstream of proposed projects which
are tabulated below.
Sileru
72.30 144.60 202.44 289.20
(Guntawada
Reservoir)
The sediment accumulation at the dam intake face (new zero elevation) have been provided for
a period of 100 years of sedimentation and the storage reservoir performance carried out based
on revised area capacity curve after 50 years of siltation. Sedimentation studies have
accordingly been made for different time horizons in the following steps.
Brune has developed curve which relate the capacity inflow ratio with reservoir trap efficiency
and he has also shown in his study that the capacity-inflow (C/I) ratio offers a much closer
correlation with reservoir trap efficiency and hence this method is widely used to find out the
trap efficiency. Keeping this in view, in the present study Brune’s Curve has been used for
finding out the trap efficiency, which is considered for estimating average annual silt load,
which determines the nature of silting problem.
To determine the severity of sedimentation problem at the dam site, as per the capacity inflow
ratio (C/I), the trap efficiency is worked out from Brune’s Curve. Using sediment rate of 0.378
mm/yr, the average annual sediment volume, the percentage ratio of average sediment volume
and gross capacity of the reservoir is determined. The sediment analysis results for proposed
dams are enclosed through Annexure- VI-6. Since the trapped annual sediment volume is not
greater than 0.5% of capacity reservoir, the sedimentation problem is not considered as
serious.
Total Silt load depends on the rate of sediment inflow and reservoirs trap efficiency. The trap
efficiency of a reservoir is defined as ratio of the deposited sediment to the total sediment
inflow. The trap efficiency depends on the sediment load characteristics and the detention
time of the inflow and the age of the reservoir. The important sediment characteristics are the
grade, size distribution and the behavior of finer fractions under the influence of varying
concentration, dissolved load, temperature etc.
As per Borland and Millar of U.S.B.R. the distribution pattern of sediment has been classified
into four standard types namely (A) Gorge (B) Hill (C) Foot plain – Foot hill and (D) Lake.
The shape of the reservoir is defined by depth to capacity relationship and classification is as
under:
1-1.5 Gorge IV
1.5 – 2.5 Hill III
Where M is the reciprocal of the slope of the line obtained by plotting reservoir depth as
ordinate and reservoir capacity as abscissa on log-log paper. The depth v/s capacity curve on
log-log scale were plotted (refer Fig-1 of Annexure- VI-6) and reciprocal of slope is found
out in order to categorize the reservoir type. Given the nature of topography, it is expected
that lower portion of reservoir will get lost partly due to higher rate of siltation during initial
years after reservoir construction as well as encroachment by the rolling bed load of pebbles,
boulders etc. As stated above, from this consideration the reciprocal of slope, the reservoir
type have been found to be in category Type-IV (Gorge Type) reservoir for proposed
structures on Sileru river. Consequently reservoir types has been taken in the subsequent
analysis for sedimentation.
The distribution of sediments was carried out by Empirical Area reduction method. It may be
worthwhile to mention that, empirical area reduction method is based on empirical sediment
distribution-area. Design curve for each of the four types of reservoir are used to distribute
the sediment throughout its depth. The equation for the design curve is of the following type:
C, m and n = are non-dimensional constants which have been fixed depending on the types of
reservoir. These curves are used to work out the probable sediment deposition in the reservoir
at different depths.
The detailed revised area-capacity curve after 25, 50, 70 and 100 years of sedimentation are
also appended in Annexure- VI-6.
Total Ayacut
38,921 22,113
(Ha)
Crop Water Demand
3950 3950
(mm)
Total Water Demand
1537.4 873.5
(MCM) 2410.843 MCM
85.15871 TMC
Annexure-VI-3
ANNUAL VIRGIN
YEAR FLOW RANK DEPENDABILITY
(TMC)
Stream Sileru
CA 5220.6 Sq.Km.
Catchment Area 5220.6 sq.km
Longest Flow Length 179.2 km
Flood Value
Particulars
(Cumecs)
13588
25 year return period flood
16232
50 year return period flood
18233
100 year return period flood
Standard Project Flood
43694
(SPF)
Probable Maximum Flood
52889
(PMF)
ANNEXURE-VI-5
Σ 179.238 107556.77
( 107556.77 /
179.24^2) =
3.348 m/km
0.003 m/m
1 in 299
ANNEXURE-VI-5
Therefore, following relationships have been used for estimating the 1 - h unitgraph parametere of the said catchment. 4.589 0.894 2.353 -1.005 1.351 -0.992 0.936 -1.047 0.579 -1.004 0.050 0.200
3f 0.348 0.454 1.842 -0.804
2 UG Runoff Vol. = Area under UG = Area*1cm 52206000.0 m3 1b 0.339 0.826 1.251 -0.61 6.662 0.613 2.215 -1.034 1.190 -1.057 0.834 -1.077 0.502 -1.065 0.207 -0.290 0.170
tp = 11.871 hr, but adopted tp= 3i 0.553 0.405 2.043 0.872 5.083 0.733 2.197 1.067 1.325 1.088 0.799 1.138 0.536 1.109 0.050 0.500
Linear Coeff 0.348 12 3h 0.325 0.447 0.996 -0.497 7.392 0.524 2.389 -1.065 1.415 -1.067 0.755 -1.229 0.558 -1.088 0.050 0.100
Power Coeff 0.454
Physio 2379.117 tp qp W50 W75 WR50 WR75 Tm Tb Qp
qp = 0.250 Cumec/sq.km 11.9 0.250 9.48 5.35 4.00 2.33 12 43 1304.21
Linear Coeff 1.842
Power Coeff -0.804
Physio 12.000
Qp= 1304.2 Cumec 0.36
Unit Duration (tr)= 1.00 hr
Time from rise to peak (Tm)= 12.37 hr
TB = 43.00 hr
Linear Coeff 4.589
Power Coeff 0.894
W50= 9.48 hr
W75= 5.35 hr
WR-50= 4.00 hr
TB= 24.06184
Linear Coeff 0.936
Power Coeff -1.047
WR-75= 2.33 hr
Guntawada reservoir
on Sileru River 18°
Time Ordinate
0 0.000 5220.6
1 25.000 GUNTAWADA RESERVOIR ON SILERU RIVER 18 ° 3'16.52"N 82° 2'6.69"E SUH
2 60.000 1400.000
3 100.000
4 150.000
1304.000
5 210.000
1250.0001250.000
6 300.000
7 400.000 1200.000
8 550.000
1120.000 1120.000
9 652.000
10 978.000 108.6666667
11 1120.000 1000.000
978.000 978.000
12 1250.000
13 1304.000
14 1250.000 108.6666667
15 1120.000 820.000
800.000
16 978.000
ORDINATE
17 820.000 108.6666667
18 652.000
652.000 652.000
19 525.000 5
20 392.000 600.000
5
21 294.000 5 550.000
525.000
22 237.000 5
23 192.000 5
24 162.000 400.000
5 400.000 392.000
25 132.000 5
26 105.000 5 300.000 294.000
27 96.000 5 326.000 108.6667
237.000
28 76.000 210.000 326.000 163
200.000 192.000
29 66.000 162.000
150.000
30 56.000 132.000
100.000 105.000
96.000
31 46.000 76.000
66.000
60.000 56.000
46.000
32 41.000 25.000
41.000
36.000
31.000
26.000
21.000
16.000
11.000
9.0006.0004.0002.0000.000
33 36.000 0.000 0.000
34 31.000 0 5 10 15 20 25 30 35 40 45 50
35 26.000 TIME (HOURS)
36 21.000
37 16.000
38 11.000
39 9.000
40 6.000
41 4.000
42 2.000
43 0.000
1.0000
ANNEXURE-VI-5
Rainfall to be analysed
23.35 cm
Time U.G. Ordinate Critical Arrangement of rainfall increments in bells Critical 1Hr excessive Rainfall arrangement Critical 1Hr excessive Rainfall after reversing
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 550.0 0.04 0.13 0.16 0.47 0.000 0.000 0.000 0.267 0.000 0.000 0.000 0.267
2 652.0 0.05 0.18 0.21 0.63 0.000 0.000 0.014 0.431 0.000 0.000 0.000 0.267
3 978.0 0.06 0.20 0.24 0.70 0.000 0.000 0.038 0.501 0.000 0.000 0.014 0.431
4 1120.0 0.06 0.22 0.26 0.77 0.000 0.016 0.062 0.571 0.000 0.003 0.046 0.524
5 1250.0 0.13 0.45 0.54 1.59 0.000 0.246 0.340 1.388 0.000 0.023 0.070 0.594
6 1304.0 0.36 1.26 1.53 4.48 0.158 1.058 1.325 4.284 0.000 0.364 0.483 1.808
7 1250.0 0.16 0.56 0.68 2.01 0.000 0.364 0.483 1.808 0.158 1.058 1.325 4.284
8 1120.0 0.06 0.22 0.27 0.79 0.000 0.023 0.070 0.594 0.000 0.246 0.340 1.388
9 978.0 0.06 0.20 0.25 0.72 0.000 0.003 0.046 0.524 0.000 0.016 0.062 0.571
10 820.0 0.05 0.18 0.21 0.63 0.000 0.000 0.014 0.431 0.000 0.000 0.038 0.501
11 652.0 0.04 0.13 0.16 0.47 0.000 0.000 0.000 0.267 0.000 0.000 0.014 0.431
12 525.0 0.04 0.13 0.16 0.47 0.000 0.000 0.000 0.267 0.000 0.000 0.000 0.267
1.10 3.85 4.67 13.73 0.16 1.71 2.39 11.33 0.16 1.71 2.39 11.33
ANNEXURE-VI-5
Total Flow
UH DSRO Base Flow
(hr) 0 0 0 0 0 0 0.15841 0 0 0 0 0 0 0 0 0.00316 0.02282 0.36359 1.05825 0.24563 0.01626 0 0 0 0 0 0.01448 0.04625 0.07008 0.48314 1.32516 0.34016 0.06214 0.03831 0.01448 0 0.26708 0.26708 0.431 0.524 0.594 1.808 4.284 1.388 0.571 0.501 0.431 0.267 Cumecs
ordinate
(Cumecs)
0 0.0 0.00 0.00 261.030 261.030
1 25.0 0.00 0.00 0.00 261.030 261.030
2 60.0 0.00 0.00 0.00 0.00 261.030 261.030
3 100.0 0.00 0.00 0.00 0.00 0.00 261.030 261.030
4 150.0 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
5 210.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
6 300.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
7 400.0 0.00 0.00 0.00 0.00 0.00 0.00 3.96 0.00 3.96 261.030 264.990
8 550.0 0.00 0.00 0.00 0.00 0.00 0.00 9.50 0.00 0.00 9.50 261.030 270.535
9 652.0 0.00 0.00 0.00 0.00 0.00 0.00 15.84 0.00 0.00 0.00 15.84 261.030 276.871
10 978.0 0.00 0.00 0.00 0.00 0.00 0.00 23.76 0.00 0.00 0.00 0.00 23.76 261.030 284.792
11 1120.0 0.00 0.00 0.00 0.00 0.00 0.00 33.27 0.00 0.00 0.00 0.00 0.00 33.27 261.030 294.296
12 1250.0 0.00 0.00 0.00 0.00 0.00 0.00 47.52 0.00 0.00 0.00 0.00 0.00 0.00 47.52 261.030 308.553
13 1304.0 0.00 0.00 0.00 0.00 0.00 0.00 63.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 63.36 261.030 324.395
14 1250.0 0.00 0.00 0.00 0.00 0.00 0.00 87.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87.13 261.030 348.156
15 1120.0 0.00 0.00 0.00 0.00 0.00 0.00 103.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 103.28 261.030 364.314
16 978.0 0.00 0.00 0.00 0.00 0.00 0.00 154.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 154.93 261.030 415.957
17 820.0 0.00 0.00 0.00 0.00 0.00 0.00 177.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.57 0.00 177.99 261.030 439.021
18 652.0 0.00 0.00 0.00 0.00 0.00 0.00 198.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37 9.09 0.00 208.47 261.030 469.503
19 525.0 0.00 0.00 0.00 0.00 0.00 0.00 206.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.28 21.82 26.46 0.00 257.12 261.030 518.152
20 392.0 0.00 0.00 0.00 0.00 0.00 0.00 198.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.42 36.36 63.50 6.14 0.00 307.43 261.030 568.462
21 294.0 0.00 0.00 0.00 0.00 0.00 0.00 177.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.79 54.54 105.83 14.74 0.41 0.00 357.72 261.030 618.751
22 237.0 0.00 0.00 0.00 0.00 0.00 0.00 154.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.84 76.35 158.74 24.56 0.98 0.00 0.00 422.40 261.030 683.433
23 192.0 0.00 0.00 0.00 0.00 0.00 0.00 129.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.13 109.08 222.23 36.84 1.63 0.00 0.00 0.00 508.81 261.030 769.836
24 162.0 0.00 0.00 0.00 0.00 0.00 0.00 103.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.55 145.44 317.48 51.58 2.44 0.00 0.00 0.00 0.00 632.77 261.030 893.798
25 132.0 0.00 0.00 0.00 0.00 0.00 0.00 83.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.88 199.98 423.30 73.69 3.42 0.00 0.00 0.00 0.00 0.00 798.42 261.030 1059.454
26 105.0 0.00 0.00 0.00 0.00 0.00 0.00 62.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.31 237.06 582.04 98.25 4.88 0.00 0.00 0.00 0.00 0.00 0.00 1006.64 261.030 1267.674
27 96.0 0.00 0.00 0.00 0.00 0.00 0.00 46.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.55 355.59 689.98 135.10 6.50 0.00 0.00 0.00 0.00 0.00 0.36 0.00 1259.67 261.030 1520.696
28 76.0 0.00 0.00 0.00 0.00 0.00 0.00 37.54 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.52 407.22 1034.97 160.15 8.94 0.00 0.00 0.00 0.00 0.00 0.87 1.16 0.00 1679.38 261.030 1940.410
29 66.0 0.00 0.00 0.00 0.00 0.00 0.00 30.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 29.75 454.49 1185.24 240.23 10.60 0.00 0.00 0.00 0.00 0.00 1.45 2.77 1.75 0.00 1956.71 261.030 2217.736
30 56.0 0.00 0.00 0.00 0.00 0.00 0.00 25.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.52 474.12 1322.82 275.11 15.90 0.00 0.00 0.00 0.00 0.00 2.17 4.62 4.20 12.08 0.00 2165.22 261.030 2426.245
31 46.0 0.00 0.00 0.00 0.00 0.00 0.00 20.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.55 454.49 1379.96 307.04 18.21 0.00 0.00 0.00 0.00 0.00 3.04 6.94 7.01 28.99 33.13 0.00 2285.27 261.030 2546.303
32 41.0 0.00 0.00 0.00 0.00 0.00 0.00 16.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 22.31 407.22 1322.82 320.30 20.33 0.00 0.00 0.00 0.00 0.00 4.34 9.71 10.51 48.31 79.51 8.50 0.00 2270.51 261.030 2531.543
33 36.0 0.00 0.00 0.00 0.00 0.00 0.00 15.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.71 355.59 1185.24 307.04 21.21 0.00 0.00 0.00 0.00 0.00 5.79 13.87 14.72 72.47 132.52 20.41 1.55 0.00 2164.33 261.030 2425.361
34 31.0 0.00 0.00 0.00 0.00 0.00 0.00 12.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.88 298.15 1034.97 275.11 20.33 0.00 0.00 0.00 0.00 0.00 7.96 18.50 21.02 101.46 198.77 34.02 3.73 0.96 0.00 2041.89 261.030 2302.918
35 26.0 0.00 0.00 0.00 0.00 0.00 0.00 10.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.98 237.06 867.77 240.23 18.21 0.00 0.00 0.00 0.00 0.00 9.44 25.44 28.03 144.94 278.28 51.02 6.21 2.30 0.36 0.00 1931.73 261.030 2192.765
36 21.0 0.00 0.00 0.00 0.00 0.00 0.00 8.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.94 190.89 689.98 201.42 15.90 0.00 0.00 0.00 0.00 0.00 14.16 30.15 38.54 193.26 397.55 71.43 9.32 3.83 0.87 0.00 0.00 1875.12 261.030 2136.146
37 16.0 0.00 0.00 0.00 0.00 0.00 0.00 7.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.71 142.53 555.58 160.15 13.34 0.00 0.00 0.00 0.00 0.00 16.21 45.23 45.69 265.73 530.06 102.05 13.05 5.75 1.45 0.00 6.68 0.00 1917.49 261.030 2178.516
38 11.0 0.00 0.00 0.00 0.00 0.00 0.00 6.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.41 106.90 414.84 128.96 10.60 0.00 0.00 0.00 0.00 0.00 18.09 51.80 68.54 315.01 728.84 136.06 18.64 8.04 2.17 0.00 16.02 6.68 0.00 2043.09 261.030 2304.120
39 9.0 0.00 0.00 0.00 0.00 0.00 0.00 5.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.38 86.17 311.13 96.29 8.54 0.00 0.00 0.00 0.00 0.00 18.88 57.81 78.49 472.51 864.00 187.09 24.85 11.49 3.04 0.00 26.71 16.02 10.76 0.00 2283.87 261.030 2544.898
40 6.0 0.00 0.00 0.00 0.00 0.00 0.00 4.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.70 69.81 250.81 72.22 6.37 0.00 0.00 0.00 0.00 0.00 18.09 60.31 87.60 541.12 1296.00 221.78 34.17 15.32 4.34 0.00 40.06 26.71 25.83 13.10 0.00 2792.26 261.030 3053.293
41 4.0 0.00 0.00 0.00 0.00 0.00 0.00 4.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.01 58.90 203.18 58.21 4.78 0.00 0.00 0.00 0.00 0.00 16.21 57.81 91.38 603.93 1484.17 332.68 40.51 21.07 5.79 0.00 56.09 40.06 43.06 31.44 14.85 0.00 3171.26 261.030 3432.293
42 2.0 0.00 0.00 0.00 0.00 0.00 0.00 3.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.40 47.99 171.44 47.16 3.85 0.00 0.00 0.00 0.00 0.00 14.16 51.80 87.60 630.02 1656.44 380.98 60.77 24.98 7.96 0.00 80.12 56.09 64.58 52.40 35.64 45.21 0.00 3524.91 261.030 3785.945
43 0.0 0.00 0.00 0.00 0.00 0.00 0.00 2.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.19 38.18 139.69 39.79 3.12 0.00 0.00 0.00 0.00 0.00 11.87 45.23 78.49 603.93 1728.00 425.20 69.59 37.46 9.44 0.00 106.83 80.12 90.42 78.60 59.40 108.51 107.10 0.00 3865.70 261.030 4126.727
44 0.00 0.00 0.00 0.00 0.00 1.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.73 34.90 111.12 32.42 2.63 0.00 0.00 0.00 0.00 0.00 9.44 37.92 68.54 541.12 1656.44 443.57 77.67 42.90 14.16 0.00 146.89 106.83 129.17 110.03 89.11 180.84 257.04 34.70 0.00 4130.93 261.030 4391.961
45 0.00 0.00 0.00 0.00 1.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.51 27.63 101.59 25.79 2.15 0.00 0.00 0.00 0.00 0.00 7.60 30.15 57.47 472.51 1484.17 425.20 81.03 47.88 16.21 0.00 174.14 146.89 172.22 157.19 124.75 271.27 428.40 83.28 14.27 0.00 4354.72 261.030 4615.754
46 0.00 0.00 0.00 0.95 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.28 24.00 80.43 23.58 1.71 0.00 0.00 0.00 0.00 0.00 5.67 24.28 45.69 396.18 1296.00 380.98 77.67 49.95 18.09 0.00 261.20 174.14 236.81 209.59 178.21 379.77 642.59 138.81 34.24 12.52 0.00 4694.33 261.030 4955.363
47 0.00 0.00 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.05 20.36 69.84 18.67 1.56 0.00 0.00 0.00 0.00 0.00 4.26 18.13 36.79 315.01 1086.63 332.68 69.59 47.88 18.88 0.00 299.13 261.20 280.72 288.18 237.61 542.53 899.63 208.21 57.07 30.04 10.76 0.00 5157.05 261.030 5418.083
48 0.00 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.94 16.73 59.26 16.21 1.24 0.00 0.00 0.00 0.00 0.00 3.43 13.60 27.47 253.65 864.00 278.93 60.77 42.90 18.09 0.00 333.85 299.13 421.08 341.63 326.72 723.38 1285.19 291.49 85.60 50.06 25.83 6.68 5848.18 261.030 6109.205
49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.82 14.91 48.68 13.76 1.07 0.00 0.00 0.00 0.00 0.00 2.78 10.96 20.60 189.39 695.71 221.78 50.95 37.46 16.21 0.00 348.27 333.85 482.22 512.44 387.31 994.64 1713.58 416.42 119.84 75.09 43.06 16.02 6767.85 261.030 7028.879
50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.71 13.09 43.39 11.30 0.91 0.00 0.00 0.00 0.00 0.00 2.34 8.88 16.61 142.04 519.46 178.58 40.51 31.41 14.16 0.00 333.85 348.27 538.20 586.85 580.97 1179.10 2356.18 555.23 171.20 105.13 64.58 26.71 7869.66 261.030 8130.689
51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.59 11.27 38.10 10.07 0.75 0.00 0.00 0.00 0.00 0.00 1.91 7.49 13.46 114.50 389.60 133.34 32.62 24.98 11.87 0.00 299.13 333.85 561.45 654.97 665.32 1768.65 2793.14 763.44 228.27 150.19 90.42 40.06 9139.42 261.030 9400.453
52 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.48 9.45 32.81 8.84 0.67 0.00 0.00 0.00 0.00 0.00 1.52 6.10 11.35 92.76 314.06 100.01 24.36 20.11 9.44 0.00 261.20 299.13 538.20 683.26 742.54 2025.45 4189.71 905.02 313.87 200.25 129.17 56.09 10975.85 261.030 11236.882
53 0.00 0.00 0.00 0.00 0.00 0.00 0.37 7.64 27.51 7.61 0.59 0.00 0.00 0.00 0.00 0.00 1.39 4.86 9.25 78.27 254.43 80.62 18.27 15.02 7.60 0.00 219.00 261.20 482.22 654.97 774.62 2260.55 4798.03 1357.53 372.08 275.34 172.22 80.12 12221.31 261.030 12482.341
54 0.00 0.00 0.00 0.00 0.00 0.25 5.82 22.22 6.39 0.50 0.00 0.00 0.00 0.00 0.00 1.10 4.44 7.36 63.77 214.68 65.31 14.73 11.26 5.67 0.00 174.14 219.00 421.08 586.85 742.54 2358.20 5354.95 1554.64 558.13 326.40 236.81 106.83 13063.07 261.030 13324.105
55 0.00 0.00 0.00 0.00 0.21 4.00 16.93 5.16 0.42 0.00 0.00 0.00 0.00 0.00 0.96 3.51 6.73 50.73 174.92 55.11 11.93 9.08 4.26 0.00 140.22 174.14 353.06 512.44 665.32 2260.55 5586.28 1735.09 639.16 489.60 280.72 146.89 13327.41 261.030 13588.437
56 0.00 0.00 0.00 0.14 3.27 11.64 3.93 0.34 0.00 0.00 0.00 0.00 0.00 0.81 3.05 5.33 46.38 139.14 44.90 10.07 7.35 3.43 0.00 104.69 140.22 280.72 429.66 580.97 2025.45 5354.95 1810.04 713.35 560.69 421.08 174.14 12875.75 261.030 13136.78
57 0.00 0.00 0.09 2.18 9.52 2.70 0.26 0.00 0.00 0.00 0.00 0.00 0.67 2.59 4.63 36.72 127.21 35.72 8.20 6.21 2.78 0.00 78.52 104.69 226.04 341.63 487.11 1768.65 4798.03 1735.09 744.17 625.77 482.22 261.20 11892.61 261.030 12153.642
58 0.00 0.05 1.45 6.35 2.21 0.18 0.00 0.00 0.00 0.00 0.00 0.59 2.13 3.92 31.89 100.71 32.66 6.52 5.06 2.34 0.00 63.30 78.52 168.78 275.09 387.31 1482.92 4189.71 1554.64 713.35 652.81 538.20 299.13 10599.81 261.030 10860.836
59 0.00 0.73 4.23 1.47 0.15 0.00 0.00 0.00 0.00 0.00 0.52 1.90 3.22 27.06 87.46 25.85 5.97 4.02 1.91 0.00 51.28 63.30 126.58 205.40 311.87 1179.10 3512.85 1357.53 639.16 625.77 561.45 333.85 9132.62 261.030 9393.651
60 0.00 2.12 0.98 0.10 0.00 0.00 0.00 0.00 0.00 0.45 1.66 2.87 22.22 74.21 22.45 4.72 3.68 1.52 0.00 43.27 51.28 102.04 154.05 232.86 949.43 2793.14 1138.22 558.13 560.69 538.20 348.27 7606.56 261.030 7867.586
61 0.00 0.49 0.07 0.00 0.00 0.00 0.00 0.00 0.38 1.43 2.52 19.81 60.96 19.05 4.10 2.91 1.39 0.00 35.25 43.27 82.67 124.18 174.65 708.91 2249.08 905.02 467.96 489.60 482.22 333.85 6209.76 261.030 6470.793
62 0.00 0.03 0.00 0.00 0.00 0.00 0.00 0.30 1.20 2.17 17.39 54.33 15.65 3.48 2.53 1.10 0.00 28.04 35.25 69.75 100.60 140.79 531.68 1679.31 728.74 372.08 410.51 421.08 299.13 4915.16 261.030 5176.190
63 0.00 0.00 0.00 0.00 0.00 0.00 0.23 0.97 1.82 14.98 47.71 13.95 2.86 2.15 0.96 0.00 25.64 28.04 56.83 84.88 114.05 428.60 1259.48 544.12 299.61 326.40 353.06 261.20 3867.54 261.030 4128.574
64 0.00 0.00 0.00 0.00 0.00 0.16 0.74 1.47 12.56 41.08 12.25 2.55 1.76 0.81 0.00 20.30 25.64 45.21 69.16 96.23 347.22 1015.30 408.09 223.71 262.82 280.72 219.00 3086.79 261.030 3347.822
65 0.00 0.00 0.00 0.00 0.13 0.51 1.12 10.15 34.45 10.54 2.24 1.57 0.67 0.00 17.63 20.30 41.33 55.02 78.41 292.97 822.52 328.97 167.78 196.24 226.04 174.14 2482.73 261.030 2743.756
66 0.00 0.00 0.00 0.09 0.42 0.77 7.73 27.83 8.84 1.93 1.38 0.59 0.00 14.96 17.63 32.72 50.30 62.37 238.71 694.00 266.51 135.25 147.18 168.78 140.22 2018.21 261.030 2279.238
67 0.00 0.00 0.06 0.28 0.63 5.31 21.20 7.14 1.62 1.19 0.52 0.00 12.29 14.96 28.42 39.82 57.03 189.89 565.48 224.87 109.57 118.65 126.58 104.69 1630.19 261.030 1891.220
68 0.00 0.03 0.18 0.42 4.35 14.58 5.44 1.30 1.00 0.45 0.00 10.95 12.29 24.11 34.58 45.15 173.61 449.82 183.23 92.45 96.12 102.04 78.52 1330.61 261.030 1591.640
69 0.00 0.09 0.28 2.90 11.93 3.74 0.99 0.80 0.38 0.00 9.61 10.95 19.81 29.34 39.21 137.44 411.26 145.75 75.33 81.10 82.67 63.30 1126.88 261.030 1387.907
70 0.00 0.14 1.93 7.95 3.06 0.68 0.61 0.30 0.00 8.28 9.61 17.65 24.10 33.27 119.36 325.58 133.25 59.92 66.08 69.75 51.28 932.83 261.030 1193.856
71 0.00 0.97 5.30 2.04 0.56 0.42 0.23 0.00 6.94 8.28 15.50 21.48 27.33 101.27 282.74 105.49 54.79 52.56 56.83 43.27 786.01 261.030 1047.040
72 0.00 2.65 1.36 0.37 0.34 0.16 0.00 5.61 6.94 13.35 18.86 24.36 83.19 239.90 91.61 43.37 48.06 45.21 35.25 660.60 261.030 921.632
73 0.00 0.68 0.25 0.23 0.13 0.00 4.27 5.61 11.19 16.24 21.39 74.15 197.06 77.73 37.66 38.05 41.33 28.04 554.02 261.030 815.052
74 0.00 0.12 0.15 0.09 0.00 2.94 4.27 9.04 13.62 18.42 65.10 175.64 63.85 31.96 33.04 32.72 25.64 476.61 261.030 737.644
75 0.00 0.08 0.06 0.00 2.40 2.94 6.89 11.00 15.44 56.06 154.22 56.91 26.25 28.03 28.42 20.30 409.01 261.030 670.039
76 0.00 0.03 0.00 1.60 2.40 4.74 8.38 12.47 47.02 132.80 49.97 23.40 23.03 24.11 17.63 347.59 261.030 608.617
77 0.00 0.00 1.07 1.60 3.88 5.76 9.50 37.98 111.38 43.03 20.54 20.53 19.81 14.96 290.04 261.030 551.066
78 0.00 0.53 1.07 2.58 4.72 6.53 28.94 89.96 36.09 17.69 18.02 17.65 12.29 236.08 261.030 497.106
79 0.00 0.53 1.72 3.14 5.35 19.89 68.54 29.15 14.84 15.52 15.50 10.95 185.14 261.030 446.169
80 0.00 0.86 2.10 3.56 16.28 47.12 22.21 11.98 13.02 13.35 9.61 140.09 261.030 401.122
81 0.00 1.05 2.38 10.85 38.56 15.27 9.13 10.51 11.19 8.28 107.22 261.030 368.247
82 0.00 1.19 7.23 25.70 12.49 6.28 8.01 9.04 6.94 76.89 261.030 337.921
83 0.00 3.62 17.14 8.33 5.14 5.51 6.89 5.61 52.22 261.030 313.252
84 0.00 8.57 5.55 3.42 4.51 4.74 4.27 31.06 261.030 292.089
85 0.00 2.78 2.28 3.00 3.88 2.94 14.88 261.030 275.905
86 0.00 1.14 2.00 2.58 2.40 8.13 261.030 269.161
87 0.00 1.00 1.72 1.60 4.33 261.030 265.356
88 0.00 0.86 1.07 1.93 261.030 262.959
89 0.00 0.53 0.53 261.030 261.564
13588
ANNEXURE-VI-5
Rainfall to be analysed
27.25 cm
Time U.G. Ordinate Critical Arrangement of rainfall increments in bells Critical 1Hr excessive Rainfall arrangement Critical 1Hr excessive Rainfall after reversing
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 550.0 0.04 0.15 0.19 0.54 0.000 0.000 0.000 0.345 0.000 0.000 0.000 0.345
2 652.0 0.06 0.21 0.25 0.74 0.000 0.006 0.050 0.536 0.000 0.000 0.000 0.345
3 978.0 0.07 0.23 0.28 0.82 0.000 0.029 0.078 0.617 0.000 0.006 0.050 0.536
4 1120.0 0.07 0.25 0.31 0.90 0.000 0.052 0.106 0.699 0.000 0.037 0.087 0.645
5 1250.0 0.15 0.52 0.63 1.85 0.000 0.320 0.430 1.653 0.000 0.060 0.115 0.726
6 1304.0 0.42 1.47 1.78 5.23 0.218 1.268 1.579 5.031 0.000 0.458 0.597 2.143
7 1250.0 0.19 0.66 0.80 2.34 0.000 0.458 0.597 2.143 0.218 1.268 1.579 5.031
8 1120.0 0.07 0.26 0.32 0.93 0.000 0.060 0.115 0.726 0.000 0.320 0.430 1.653
9 978.0 0.07 0.24 0.29 0.84 0.000 0.037 0.087 0.645 0.000 0.052 0.106 0.699
10 820.0 0.06 0.21 0.25 0.74 0.000 0.006 0.050 0.536 0.000 0.029 0.078 0.617
11 652.0 0.04 0.15 0.19 0.54 0.000 0.000 0.000 0.345 0.000 0.006 0.050 0.536
12 525.0 0.04 0.15 0.19 0.54 0.000 0.000 0.000 0.345 0.000 0.000 0.000 0.345
1.28 4.50 5.45 16.02 0.22 2.24 3.09 13.62 0.22 2.24 3.09 13.62
ANNEXURE-VI-5
Total Flow
UH DSRO Base Flow
(hr) 0 0 0 0 0 0 0.21815 0 0 0 0 0 0 0 0.00643 0.03702 0.05995 0.45753 1.26797 0.31991 0.05231 0.02937 0.00643 0 0 0 0.05022 0.08729 0.11509 0.597 1.57935 0.43019 0.10583 0.07802 0.05022 0 0.34493 0.34493 0.536 0.645 0.726 2.143 5.031 1.653 0.699 0.617 0.536 0.345 Cumecs
ordinate
(Cumecs)
0 0.0 0.00 0.00 261.030 261.030
1 25.0 0.00 0.00 0.00 261.030 261.030
2 60.0 0.00 0.00 0.00 0.00 261.030 261.030
3 100.0 0.00 0.00 0.00 0.00 0.00 261.030 261.030
4 150.0 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
5 210.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
6 300.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
7 400.0 0.00 0.00 0.00 0.00 0.00 0.00 5.45 0.00 5.45 261.030 266.484
8 550.0 0.00 0.00 0.00 0.00 0.00 0.00 13.09 0.00 0.00 13.09 261.030 274.119
9 652.0 0.00 0.00 0.00 0.00 0.00 0.00 21.81 0.00 0.00 0.00 21.81 261.030 282.845
10 978.0 0.00 0.00 0.00 0.00 0.00 0.00 32.72 0.00 0.00 0.00 0.00 32.72 261.030 293.752
11 1120.0 0.00 0.00 0.00 0.00 0.00 0.00 45.81 0.00 0.00 0.00 0.00 0.00 45.81 261.030 306.841
12 1250.0 0.00 0.00 0.00 0.00 0.00 0.00 65.44 0.00 0.00 0.00 0.00 0.00 0.00 65.44 261.030 326.474
13 1304.0 0.00 0.00 0.00 0.00 0.00 0.00 87.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00 87.26 261.030 348.289
14 1250.0 0.00 0.00 0.00 0.00 0.00 0.00 119.98 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 119.98 261.030 381.012
15 1120.0 0.00 0.00 0.00 0.00 0.00 0.00 142.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.16 0.00 142.39 261.030 403.423
16 978.0 0.00 0.00 0.00 0.00 0.00 0.00 213.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.39 0.16 0.00 213.90 261.030 474.926
17 820.0 0.00 0.00 0.00 0.00 0.00 0.00 244.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.64 0.39 1.50 0.00 246.85 261.030 507.884
18 652.0 0.00 0.00 0.00 0.00 0.00 0.00 272.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.96 0.64 3.60 11.44 0.00 289.33 261.030 550.359
19 525.0 0.00 0.00 0.00 0.00 0.00 0.00 284.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.35 0.96 6.00 27.45 31.70 0.00 351.93 261.030 612.957
20 392.0 0.00 0.00 0.00 0.00 0.00 0.00 272.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.93 1.35 8.99 45.75 76.08 8.00 0.00 414.79 261.030 675.817
21 294.0 0.00 0.00 0.00 0.00 0.00 0.00 244.33 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.57 1.93 12.59 68.63 126.80 19.19 1.31 0.00 477.35 261.030 738.377
22 237.0 0.00 0.00 0.00 0.00 0.00 0.00 213.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.54 2.57 17.99 96.08 190.20 31.99 3.14 0.73 0.00 559.58 261.030 820.615
23 192.0 0.00 0.00 0.00 0.00 0.00 0.00 178.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.19 3.54 23.98 137.26 266.27 47.99 5.23 1.76 0.16 0.00 669.27 261.030 930.296
24 162.0 0.00 0.00 0.00 0.00 0.00 0.00 142.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.29 4.19 32.97 183.01 380.39 67.18 7.85 2.94 0.39 0.00 0.00 827.44 261.030 1088.472
25 132.0 0.00 0.00 0.00 0.00 0.00 0.00 114.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.20 6.29 39.09 251.64 507.19 95.97 10.98 4.41 0.64 0.00 0.00 0.00 1037.94 261.030 1298.974
26 105.0 0.00 0.00 0.00 0.00 0.00 0.00 85.51 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.04 7.20 58.63 298.31 697.38 127.96 15.69 6.17 0.96 0.00 0.00 0.00 0.00 1305.87 261.030 1566.900
27 96.0 0.00 0.00 0.00 0.00 0.00 0.00 64.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.39 8.04 67.15 447.46 826.71 175.95 20.92 8.81 1.35 0.00 0.00 0.00 1.26 0.00 1630.18 261.030 1891.206
28 76.0 0.00 0.00 0.00 0.00 0.00 0.00 51.70 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.04 8.39 74.94 512.43 1240.07 208.58 28.77 11.75 1.93 0.00 0.00 0.00 3.01 2.18 0.00 2151.79 261.030 2412.824
29 66.0 0.00 0.00 0.00 0.00 0.00 0.00 41.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7.20 8.04 78.18 571.91 1420.12 312.87 34.10 16.15 2.57 0.00 0.00 0.00 5.02 5.24 2.88 0.00 2506.18 261.030 2767.205
30 56.0 0.00 0.00 0.00 0.00 0.00 0.00 35.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.29 7.20 74.94 596.62 1584.96 358.29 51.16 19.15 3.54 0.00 0.00 0.00 7.53 8.73 6.91 14.93 0.00 2775.58 261.030 3036.611
31 46.0 0.00 0.00 0.00 0.00 0.00 0.00 28.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.27 6.29 67.15 571.91 1653.43 399.88 58.58 28.72 4.19 0.00 0.00 0.00 10.55 13.09 11.51 35.82 39.48 0.00 2934.68 261.030 3195.713
32 41.0 0.00 0.00 0.00 0.00 0.00 0.00 22.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.19 5.27 58.63 512.43 1584.96 417.16 65.38 32.89 6.29 0.00 0.00 0.00 15.07 18.33 17.26 59.70 94.76 10.75 0.00 2926.00 261.030 3187.031
33 36.0 0.00 0.00 0.00 0.00 0.00 0.00 20.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.38 4.19 49.16 447.46 1420.12 399.88 68.21 36.71 7.20 0.00 0.00 0.00 20.09 26.19 24.17 89.55 157.94 25.81 2.65 0.00 2803.65 261.030 3064.685
34 31.0 0.00 0.00 0.00 0.00 0.00 0.00 16.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.52 3.38 39.09 375.17 1240.07 358.29 65.38 38.30 8.04 0.00 0.00 0.00 27.62 34.92 34.53 125.37 236.90 43.02 6.35 1.95 0.00 2657.49 261.030 2918.517
35 26.0 0.00 0.00 0.00 0.00 0.00 0.00 14.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.89 2.52 31.48 298.31 1039.73 312.87 58.58 36.71 8.39 0.00 0.00 0.00 32.74 48.01 46.04 179.10 331.66 64.53 10.58 4.68 1.26 0.00 2523.48 261.030 2784.513
36 21.0 0.00 0.00 0.00 0.00 0.00 0.00 12.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.52 1.89 23.50 240.20 826.71 262.32 51.16 32.89 8.04 0.00 0.00 0.00 49.12 56.91 63.30 238.80 473.81 90.34 15.87 7.80 3.01 0.00 0.00 2459.43 261.030 2720.462
37 16.0 0.00 0.00 0.00 0.00 0.00 0.00 10.03 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.24 1.52 17.63 179.35 665.68 208.58 42.89 28.72 7.20 0.00 0.00 0.00 56.25 85.37 75.04 328.35 631.74 129.06 22.22 11.70 5.02 0.00 8.62 0.00 2516.23 261.030 2777.265
38 11.0 0.00 0.00 0.00 0.00 0.00 0.00 8.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.04 1.24 14.21 134.51 497.04 167.95 34.10 24.08 6.29 0.00 0.00 0.00 62.78 97.77 112.56 389.25 868.64 172.08 31.75 16.39 7.53 0.00 20.70 8.62 0.00 2677.47 261.030 2938.501
39 9.0 0.00 0.00 0.00 0.00 0.00 0.00 7.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.85 1.04 11.51 108.43 372.78 125.40 27.46 19.15 5.27 0.00 0.00 0.00 65.49 109.11 128.91 583.87 1029.74 236.60 42.33 23.41 10.55 0.00 34.49 20.70 13.39 0.00 2978.34 261.030 3239.373
40 6.0 0.00 0.00 0.00 0.00 0.00 0.00 6.76 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.68 0.85 9.71 87.85 300.51 94.05 20.50 15.42 4.19 0.00 0.00 0.00 62.78 113.83 143.87 668.64 1544.61 280.48 58.20 31.21 15.07 0.00 51.74 34.49 32.14 16.12 0.00 3593.70 261.030 3854.726
41 4.0 0.00 0.00 0.00 0.00 0.00 0.00 5.67 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.62 0.68 7.91 74.12 243.45 75.82 15.38 11.51 3.38 0.00 0.00 0.00 56.25 109.11 150.08 746.25 1768.88 420.72 69.00 42.91 20.09 0.00 72.43 51.74 53.57 38.68 18.16 0.00 4056.41 261.030 4317.440
42 2.0 0.00 0.00 0.00 0.00 0.00 0.00 4.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.49 0.62 6.30 60.39 205.41 61.42 12.40 8.63 2.52 0.00 0.00 0.00 49.12 97.77 143.87 778.49 1974.19 481.81 103.50 50.87 27.62 0.00 103.48 72.43 80.35 64.46 43.58 53.58 0.00 4487.89 261.030 4748.915
43 0.0 0.00 0.00 0.00 0.00 0.00 0.00 3.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.42 0.49 5.76 48.04 167.37 51.82 10.04 6.96 1.89 0.00 0.00 0.00 41.18 85.37 128.91 746.25 2059.48 537.73 118.53 76.31 32.74 0.00 137.97 103.48 112.49 96.70 72.64 128.59 125.78 0.00 4900.44 261.030 5161.465
44 0.00 0.00 0.00 0.00 0.00 2.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.36 0.42 4.56 43.92 133.14 42.23 8.47 5.64 1.52 0.00 0.00 0.00 32.74 71.58 112.56 668.64 1974.19 560.97 132.28 87.39 49.12 0.00 189.71 137.97 160.70 135.37 108.96 214.32 301.88 41.32 0.00 5222.36 261.030 5483.390
45 0.00 0.00 0.00 0.00 1.96 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.36 3.96 34.77 121.72 33.59 6.90 4.76 1.24 0.00 0.00 0.00 26.37 56.91 94.38 583.87 1768.88 537.73 138.00 97.53 56.25 0.00 224.89 189.71 214.26 193.39 152.54 321.48 503.13 99.17 17.48 0.00 5485.52 261.030 5746.549
46 0.00 0.00 0.00 1.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.26 0.30 3.36 30.20 96.37 30.71 5.49 3.88 1.04 0.00 0.00 0.00 19.69 45.83 75.04 489.54 1544.61 481.81 132.28 101.74 62.78 0.00 337.34 224.89 294.61 257.85 217.91 450.07 754.70 165.28 41.95 15.43 0.00 5886.26 261.030 6147.291
47 0.00 0.00 0.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.23 0.26 2.76 25.62 83.69 24.31 5.02 3.08 0.85 0.00 0.00 0.00 14.77 34.22 60.42 389.25 1295.07 420.72 118.53 97.53 65.49 0.00 386.32 337.34 349.24 354.55 290.55 642.96 1056.57 247.91 69.91 37.04 13.39 0.00 6428.49 261.030 6689.516
48 0.00 0.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 0.23 2.46 21.05 71.01 21.11 3.98 2.82 0.68 0.00 0.00 0.00 11.90 25.66 45.12 313.43 1029.74 352.75 103.50 87.39 62.78 0.00 431.16 386.32 523.87 420.30 399.51 857.27 1509.39 347.08 104.87 61.74 32.14 8.62 7238.50 261.030 7499.526
49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.17 0.20 2.16 18.76 58.33 17.91 3.45 2.23 0.62 0.00 0.00 0.00 9.64 20.69 33.84 234.02 829.16 280.48 86.78 76.31 56.25 0.00 449.79 431.16 599.93 630.46 473.60 1178.75 2012.52 495.83 146.82 92.61 53.57 20.70 8316.71 261.030 8577.739
50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.14 0.17 1.86 16.47 51.99 14.72 2.93 1.94 0.49 0.00 0.00 0.00 8.14 16.76 27.28 175.52 619.11 225.85 69.00 63.98 49.12 0.00 431.16 449.79 669.56 721.99 710.40 1397.36 2767.22 661.10 209.74 129.65 80.35 34.49 9608.24 261.030 9869.268
51 0.00 0.00 0.00 0.00 0.00 0.00 0.10 0.14 1.56 14.18 45.65 13.12 2.41 1.64 0.42 0.00 0.00 0.00 6.63 14.14 22.10 141.49 464.33 168.63 55.56 50.87 41.18 0.00 386.32 431.16 698.49 805.80 813.54 2096.04 3280.41 909.01 279.65 185.22 112.49 51.74 11094.01 261.030 11355.042
52 0.00 0.00 0.00 0.00 0.00 0.07 0.10 1.26 11.90 39.31 11.52 2.14 1.35 0.36 0.00 0.00 0.00 5.27 11.52 18.65 114.62 374.31 126.48 41.48 40.96 32.74 0.00 337.34 386.32 669.56 840.61 907.97 2400.37 4920.61 1077.59 384.52 246.96 160.70 72.43 13239.03 261.030 13500.060
53 0.00 0.00 0.00 0.00 0.06 0.07 0.96 9.61 32.97 9.92 1.88 1.20 0.30 0.00 0.00 0.00 4.82 9.17 15.19 96.71 303.24 101.95 31.11 30.59 26.37 0.00 282.84 337.34 599.93 805.80 947.19 2678.98 5635.06 1616.39 455.83 339.56 214.26 103.48 14692.78 261.030 14953.812
54 0.00 0.00 0.00 0.04 0.06 0.66 7.32 26.63 8.32 1.62 1.06 0.26 0.00 0.00 0.00 3.82 8.38 12.08 78.80 255.86 82.60 25.08 22.94 19.69 0.00 224.89 282.84 523.87 721.99 907.97 2794.72 6289.13 1851.08 683.75 402.54 294.61 137.97 15670.56 261.030 15931.595
55 0.00 0.00 0.03 0.04 0.54 5.03 20.29 6.72 1.36 0.91 0.23 0.00 0.00 0.00 3.31 6.63 11.05 62.69 208.47 69.69 20.32 18.49 14.77 0.00 181.09 224.89 439.23 630.46 813.54 2678.98 6560.82 2065.94 783.03 603.81 349.24 189.71 15971.31 261.030 16232.338
56 0.00 0.01 0.03 0.36 4.12 13.95 5.12 1.10 0.76 0.20 0.00 0.00 0.00 2.81 5.76 8.75 57.31 165.83 56.78 17.14 14.98 11.90 0.00 135.21 181.09 349.24 528.60 710.40 2400.37 6289.13 2155.19 873.91 691.48 523.87 224.89 15430.30 261.030 15691.33
57 0.00 0.01 0.24 2.75 11.41 3.52 0.84 0.62 0.17 0.00 0.00 0.00 2.31 4.89 7.60 45.37 151.62 45.17 13.97 12.64 9.64 0.00 101.41 135.21 281.22 420.30 595.63 2096.04 5635.06 2065.94 911.67 771.74 599.93 337.34 14264.23 261.030 14525.262
58 0.00 0.12 1.83 7.61 2.88 0.58 0.47 0.14 0.00 0.00 0.00 2.06 4.02 6.45 39.40 120.03 41.30 11.11 10.30 8.14 0.00 81.75 101.41 209.98 338.43 473.60 1757.41 4920.61 1851.08 873.91 805.08 669.56 386.32 12725.56 261.030 12986.590
59 0.00 0.92 5.07 1.92 0.47 0.32 0.10 0.00 0.00 0.00 1.81 3.58 5.29 33.43 104.24 32.69 10.16 8.19 6.63 0.00 66.23 81.75 157.48 252.70 381.35 1397.36 4125.67 1616.39 783.03 771.74 698.49 431.16 10978.16 261.030 11239.190
60 0.00 2.54 1.28 0.31 0.26 0.07 0.00 0.00 0.00 1.56 3.14 4.72 27.46 88.44 28.39 8.04 7.49 5.27 0.00 55.88 66.23 126.95 189.52 284.74 1125.17 3280.41 1355.26 683.75 691.48 669.56 449.79 9157.72 261.030 9418.749
61 0.00 0.64 0.21 0.18 0.06 0.00 0.00 0.00 1.31 2.71 4.14 24.48 72.65 24.09 6.98 5.93 4.82 0.00 45.53 55.88 102.85 152.78 213.55 840.13 2641.43 1077.59 573.29 603.81 599.93 431.16 7486.12 261.030 7747.150
62 0.00 0.10 0.12 0.04 0.00 0.00 0.00 1.05 2.27 3.57 21.49 64.75 19.79 5.93 5.15 3.82 0.00 36.22 45.53 86.78 123.77 172.15 630.10 1972.27 867.70 455.83 506.26 523.87 386.32 5934.87 261.030 6195.896
63 0.00 0.06 0.03 0.00 0.00 0.00 0.80 1.83 2.99 18.51 56.86 17.64 4.87 4.37 3.31 0.00 33.11 36.22 70.71 104.43 139.46 507.94 1479.20 647.88 367.04 402.54 439.23 337.34 4676.37 261.030 4937.401
64 0.00 0.01 0.00 0.00 0.00 0.55 1.40 2.42 15.52 48.96 15.49 4.34 3.59 2.81 0.00 26.21 33.11 56.24 85.09 117.67 411.49 1192.42 485.91 274.06 324.13 349.24 282.84 3733.52 261.030 3994.548
65 0.00 0.00 0.00 0.00 0.45 0.96 1.84 12.54 41.06 13.34 3.81 3.20 2.31 0.00 22.77 26.21 51.42 67.69 95.88 347.20 966.01 391.70 205.54 242.02 281.22 224.89 3002.06 261.030 3263.089
66 0.00 0.00 0.00 0.30 0.79 1.27 9.55 33.17 11.18 3.28 2.81 2.06 0.00 19.32 22.77 40.71 61.89 76.27 282.90 815.07 317.33 165.69 181.51 209.98 181.09 2438.92 261.030 2699.949
67 0.00 0.00 0.20 0.52 1.04 6.57 25.27 9.03 2.75 2.42 1.81 0.00 15.87 19.32 35.35 48.99 69.73 225.03 664.13 267.75 134.23 146.32 157.48 135.21 1969.03 261.030 2230.059
68 0.00 0.10 0.35 0.69 5.37 17.37 6.88 2.22 2.03 1.56 0.00 14.14 15.87 30.00 42.55 55.20 205.75 528.29 218.16 113.26 118.54 126.95 101.41 1606.68 261.030 1867.715
69 0.00 0.17 0.46 3.58 14.21 4.73 1.69 1.64 1.31 0.00 12.42 14.14 24.64 36.10 47.94 162.88 483.00 173.54 92.29 100.02 102.85 81.75 1359.36 261.030 1620.392
70 0.00 0.23 2.39 9.48 3.87 1.16 1.25 1.05 0.00 10.69 12.42 21.96 29.65 40.68 141.45 382.38 158.66 73.41 81.50 86.78 66.23 1125.23 261.030 1386.265
71 0.00 1.19 6.32 2.58 0.95 0.86 0.80 0.00 8.97 10.69 19.28 26.43 33.41 120.02 332.07 125.61 67.12 64.83 70.71 55.88 947.71 261.030 1208.745
72 0.00 3.16 1.72 0.63 0.70 0.55 0.00 7.24 8.97 16.61 23.21 29.78 98.59 281.75 109.08 53.13 59.27 56.24 45.53 796.17 261.030 1057.203
73 0.00 0.86 0.42 0.47 0.45 0.00 5.52 7.24 13.93 19.98 26.15 87.87 231.44 92.55 46.14 46.92 51.42 36.22 667.60 261.030 928.625
74 0.00 0.21 0.31 0.30 0.00 3.79 5.52 11.25 16.76 22.52 77.15 206.28 76.03 39.15 40.75 40.71 33.11 573.85 261.030 834.881
75 0.00 0.16 0.20 0.00 3.10 3.79 8.57 13.54 18.89 66.44 181.13 67.76 32.16 34.57 35.35 26.21 491.88 261.030 752.909
76 0.00 0.10 0.00 2.07 3.10 5.89 10.31 15.25 55.72 155.97 59.50 28.66 28.40 30.00 22.77 417.75 261.030 678.783
77 0.00 0.00 1.38 2.07 4.82 7.09 11.62 45.01 130.81 51.24 25.17 25.31 24.64 19.32 348.48 261.030 609.507
78 0.00 0.69 1.38 3.21 5.80 7.99 34.29 105.66 42.97 21.67 22.23 21.96 15.87 283.72 261.030 544.753
79 0.00 0.69 2.14 3.87 6.54 23.58 80.50 34.71 18.18 19.14 19.28 14.14 222.76 261.030 483.793
80 0.00 1.07 2.58 4.36 19.29 55.34 26.44 14.68 16.05 16.61 12.42 168.84 261.030 429.872
81 0.00 1.29 2.91 12.86 45.28 18.18 11.19 12.97 13.93 10.69 129.29 261.030 390.317
82 0.00 1.45 8.57 30.19 14.87 7.69 9.88 11.25 8.97 92.87 261.030 353.904
83 0.00 4.29 20.13 9.92 6.29 6.79 8.57 7.24 63.23 261.030 324.255
84 0.00 10.06 6.61 4.19 5.56 5.89 5.52 37.84 261.030 298.866
85 0.00 3.31 2.80 3.70 4.82 3.79 18.42 261.030 279.451
86 0.00 1.40 2.47 3.21 3.10 10.19 261.030 271.216
87 0.00 1.23 2.14 2.07 5.45 261.030 266.477
88 0.00 1.07 1.38 2.45 261.030 263.481
89 0.00 0.69 0.69 261.030 261.720
16232
ANNEXURE-VI-5
Rainfall to be analysed
30.19 cm
Time U.G. Ordinate Critical Arrangement of rainfall increments in bells Critical 1Hr excessive Rainfall arrangement Critical 1Hr excessive Rainfall after reversing
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 550.0 0.05 0.17 0.21 0.60 0.000 0.000 0.005 0.404 0.000 0.000 0.005 0.404
2 652.0 0.07 0.23 0.28 0.82 0.000 0.029 0.077 0.615 0.000 0.000 0.005 0.404
3 978.0 0.07 0.25 0.31 0.91 0.000 0.054 0.108 0.706 0.000 0.029 0.077 0.615
4 1120.0 0.08 0.28 0.34 1.00 0.000 0.080 0.139 0.796 0.000 0.063 0.118 0.736
5 1250.0 0.16 0.58 0.70 2.05 0.000 0.376 0.498 1.853 0.000 0.088 0.149 0.826
6 1304.0 0.46 1.63 1.97 5.80 0.263 1.426 1.771 5.596 0.008 0.528 0.683 2.396
7 1250.0 0.21 0.73 0.88 2.60 0.008 0.528 0.683 2.396 0.263 1.426 1.771 5.596
8 1120.0 0.08 0.29 0.35 1.03 0.000 0.088 0.149 0.826 0.000 0.376 0.498 1.853
9 978.0 0.07 0.26 0.32 0.94 0.000 0.063 0.118 0.736 0.000 0.080 0.139 0.796
10 820.0 0.07 0.23 0.28 0.82 0.000 0.029 0.077 0.615 0.000 0.054 0.108 0.706
11 652.0 0.05 0.17 0.21 0.60 0.000 0.000 0.005 0.404 0.000 0.029 0.077 0.615
12 525.0 0.05 0.17 0.21 0.60 0.000 0.000 0.005 0.404 0.000 0.000 0.005 0.404
1.42 4.98 6.04 17.75 0.27 2.67 3.64 15.35 0.27 2.67 3.64 15.35
ANNEXURE-VI-5
Total Flow
UH DSRO Base Flow
(hr) 0 0 0 0 0 0.007511 0.26328 0 0 0 0 0 0 0 0.02871 0.0626 0.08801 0.52849 1.42641 0.37602 0.07954 0.05413 0.02871 0 0.00535 0.00535 0.07723 0.1183 0.1491 0.68302 1.7714 0.4982 0.13883 0.10803 0.07723 0.00535 0.40374 0.40374 0.615 0.736 0.826 2.396 5.596 1.853 0.796 0.706 0.615 0.404 Cumecs
ordinate
(Cumecs)
0 0.0 0.00 0.00 261.030 261.030
1 25.0 0.00 0.00 0.00 261.030 261.030
2 60.0 0.00 0.00 0.00 0.00 261.030 261.030
3 100.0 0.00 0.00 0.00 0.00 0.00 261.030 261.030
4 150.0 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
5 210.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
6 300.0 0.00 0.00 0.00 0.00 0.00 0.19 0.00 0.19 261.030 261.218
7 400.0 0.00 0.00 0.00 0.00 0.00 0.45 6.58 0.00 7.03 261.030 268.063
8 550.0 0.00 0.00 0.00 0.00 0.00 0.75 15.80 0.00 0.00 16.55 261.030 277.578
9 652.0 0.00 0.00 0.00 0.00 0.00 1.13 26.33 0.00 0.00 0.00 27.45 261.030 288.485
10 978.0 0.00 0.00 0.00 0.00 0.00 1.58 39.49 0.00 0.00 0.00 0.00 41.07 261.030 302.099
11 1120.0 0.00 0.00 0.00 0.00 0.00 2.25 55.29 0.00 0.00 0.00 0.00 0.00 57.54 261.030 318.572
12 1250.0 0.00 0.00 0.00 0.00 0.00 3.00 78.98 0.00 0.00 0.00 0.00 0.00 0.00 81.99 261.030 343.018
13 1304.0 0.00 0.00 0.00 0.00 0.00 4.13 105.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 109.44 261.030 370.473
14 1250.0 0.00 0.00 0.00 0.00 0.00 4.90 144.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 149.70 261.030 410.730
15 1120.0 0.00 0.00 0.00 0.00 0.00 7.35 171.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.72 0.00 179.72 261.030 440.751
16 978.0 0.00 0.00 0.00 0.00 0.00 8.41 257.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.72 0.72 0.00 268.34 261.030 529.370
17 820.0 0.00 0.00 0.00 0.00 0.00 9.39 294.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.87 1.72 2.20 0.00 311.06 261.030 572.085
18 652.0 0.00 0.00 0.00 0.00 0.00 9.79 329.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.31 2.87 5.28 13.21 0.00 364.56 261.030 625.594
19 525.0 0.00 0.00 0.00 0.00 0.00 9.39 343.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.03 4.31 8.80 31.71 35.66 0.00 439.21 261.030 700.242
20 392.0 0.00 0.00 0.00 0.00 0.00 8.41 329.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.61 6.03 13.20 52.85 85.58 9.40 0.00 513.19 261.030 774.220
21 294.0 0.00 0.00 0.00 0.00 0.00 7.35 294.87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.49 8.61 18.48 79.27 142.64 22.56 1.99 0.00 587.26 261.030 848.294
22 237.0 0.00 0.00 0.00 0.00 0.00 6.16 257.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.79 11.49 26.40 110.98 213.96 37.60 4.77 1.35 0.00 686.00 261.030 947.028
23 192.0 0.00 0.00 0.00 0.00 0.00 4.90 215.89 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.72 15.79 35.20 158.55 299.55 56.40 7.95 3.25 0.72 0.00 816.92 261.030 1077.949
24 162.0 0.00 0.00 0.00 0.00 0.00 3.94 171.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.08 18.72 48.41 211.40 427.92 78.96 11.93 5.41 1.72 0.00 0.00 1008.16 261.030 1269.189
25 132.0 0.00 0.00 0.00 0.00 0.00 2.94 138.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.16 28.08 57.38 290.67 570.56 112.81 16.70 8.12 2.87 0.00 0.13 0.00 1260.66 261.030 1521.686
26 105.0 0.00 0.00 0.00 0.00 0.00 2.21 103.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.89 32.16 86.07 344.58 784.52 150.41 23.86 11.37 4.31 0.00 0.32 0.13 0.00 1579.04 261.030 1840.067
27 96.0 0.00 0.00 0.00 0.00 0.00 1.78 77.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.44 35.89 98.57 516.87 930.02 206.81 31.82 16.24 6.03 0.00 0.54 0.32 1.93 0.00 1961.65 261.030 2222.684
28 76.0 0.00 0.00 0.00 0.00 0.00 1.44 62.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.89 37.44 110.01 591.91 1395.03 245.16 43.75 21.65 8.61 0.00 0.80 0.54 4.63 2.96 0.00 2562.23 261.030 2823.258
29 66.0 0.00 0.00 0.00 0.00 0.00 1.22 50.55 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.16 35.89 114.76 660.62 1597.57 367.75 51.86 29.77 11.49 0.00 1.12 0.80 7.72 7.10 3.73 0.00 2974.11 261.030 3235.140
30 56.0 0.00 0.00 0.00 0.00 0.00 0.99 42.65 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.08 32.16 110.01 689.16 1783.01 421.14 77.79 35.29 15.79 0.00 1.61 1.12 11.58 11.83 8.95 17.08 0.00 3288.24 261.030 3549.268
31 46.0 0.00 0.00 0.00 0.00 0.00 0.79 34.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.54 28.08 98.57 660.62 1860.03 470.02 89.08 52.94 18.72 0.00 2.14 1.61 16.22 17.74 14.91 40.98 44.29 0.00 3475.04 261.030 3736.071
32 41.0 0.00 0.00 0.00 0.00 0.00 0.72 27.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.72 23.54 86.07 591.91 1783.01 490.33 99.42 60.62 28.08 0.00 2.94 2.14 23.17 24.84 22.37 68.30 106.28 12.46 0.00 3472.59 261.030 3733.615
33 36.0 0.00 0.00 0.00 0.00 0.00 0.57 25.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 15.07 18.72 72.17 516.87 1597.57 470.02 103.72 67.66 32.16 0.00 3.49 2.94 30.89 35.49 31.31 102.45 177.14 29.89 3.47 0.00 3336.89 261.030 3597.925
34 31.0 0.00 0.00 0.00 0.00 0.00 0.50 20.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.26 15.07 57.38 433.37 1395.03 421.14 99.42 70.58 35.89 0.00 5.24 3.49 42.48 47.32 44.73 143.43 265.71 49.82 8.33 2.70 0.00 3172.89 261.030 3433.924
35 26.0 0.00 0.00 0.00 0.00 0.00 0.42 17.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.44 11.26 46.20 344.58 1169.65 367.75 89.08 67.66 37.44 0.00 6.00 5.24 50.35 65.06 59.64 204.91 371.99 74.73 13.88 6.48 1.93 0.00 3020.08 261.030 3281.110
36 21.0 0.00 0.00 0.00 0.00 0.00 0.35 14.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.81 8.44 34.50 277.46 930.02 308.34 77.79 60.62 35.89 0.00 6.69 6.00 75.53 77.13 82.01 273.21 531.42 104.62 20.83 10.80 4.63 0.13 0.00 2947.95 261.030 3208.984
37 16.0 0.00 0.00 0.00 0.00 0.00 0.31 12.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.51 6.81 25.87 207.17 748.86 245.16 65.22 52.94 32.16 0.00 6.98 6.69 86.50 115.70 97.21 375.66 708.56 149.46 29.16 16.20 7.72 0.32 10.09 0.00 3012.39 261.030 3273.419
38 11.0 0.00 0.00 0.00 0.00 0.00 0.27 10.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.65 5.51 20.86 155.38 559.15 197.41 51.86 44.38 28.08 0.00 6.69 6.98 96.54 132.50 145.82 445.33 974.27 199.28 41.65 22.69 11.58 0.54 24.22 10.09 0.00 3196.54 261.030 3457.566
39 9.0 0.00 0.00 0.00 0.00 0.00 0.23 9.48 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.79 4.65 16.90 125.25 419.36 147.40 41.76 35.29 23.54 0.00 6.00 6.69 100.71 147.87 166.99 668.00 1154.95 274.01 55.53 32.41 16.22 0.80 40.37 24.22 15.38 0.00 3537.83 261.030 3798.856
40 6.0 0.00 0.00 0.00 0.00 0.00 0.20 8.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.01 3.79 14.26 101.47 338.06 110.55 31.18 28.42 18.72 0.00 5.24 6.00 96.54 154.26 186.38 764.99 1732.43 324.83 76.36 43.21 23.17 1.12 60.56 40.37 36.90 18.39 0.00 4228.57 261.030 4489.598
41 4.0 0.00 0.00 0.00 0.00 0.00 0.16 6.85 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.76 3.01 11.62 85.62 273.87 89.12 23.38 21.22 15.07 0.00 4.39 5.24 86.50 147.87 194.43 853.78 1983.97 487.24 90.52 59.42 30.89 1.61 84.79 60.56 61.51 44.15 20.66 0.00 4750.18 261.030 5011.214
42 2.0 0.00 0.00 0.00 0.00 0.00 0.12 5.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.18 2.76 9.24 69.76 231.08 72.20 18.85 15.91 11.26 0.00 3.49 4.39 75.53 132.50 186.38 890.66 2214.25 557.99 135.78 70.44 42.48 2.14 121.12 84.79 92.26 73.58 49.58 59.90 0.00 5236.13 261.030 5497.164
43 0.0 0.00 0.00 0.00 0.00 0.00 0.08 4.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.90 2.18 8.45 55.49 188.29 60.92 15.27 12.83 8.44 0.00 2.81 3.49 63.33 115.70 166.99 853.78 2309.91 622.76 155.49 105.65 50.35 2.94 161.50 121.12 129.16 110.37 82.64 143.77 139.90 0.00 5699.71 261.030 5960.744
44 0.00 0.00 0.00 0.00 0.07 2.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.61 1.90 6.69 50.74 149.77 49.63 12.89 10.39 6.81 0.00 2.10 2.81 50.35 97.01 145.82 764.99 2214.25 649.66 173.54 121.00 75.53 3.49 222.06 161.50 184.52 154.52 123.95 239.61 335.76 46.32 0.00 6062.15 261.030 6323.181
45 0.00 0.00 0.00 0.05 2.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.32 1.61 5.81 40.17 136.93 39.48 10.50 8.77 5.51 0.00 1.57 2.10 40.54 77.13 122.26 668.00 1983.97 622.76 181.04 135.04 86.50 5.24 263.24 222.06 246.02 220.74 173.54 359.41 559.59 111.16 19.90 0.00 6354.33 261.030 6615.359
46 0.00 0.00 0.03 1.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.18 1.32 4.93 34.88 108.41 36.10 8.35 7.14 4.65 0.00 1.27 1.57 30.27 62.11 97.21 560.08 1732.43 557.99 173.54 140.87 96.54 6.00 394.86 263.24 338.28 294.32 247.91 503.18 839.39 185.27 47.77 17.64 0.00 6800.31 261.030 7061.340
47 0.00 0.02 1.05 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.03 1.18 4.05 29.60 94.14 28.58 7.64 5.68 3.79 0.00 1.03 1.27 22.71 46.37 78.28 445.33 1452.55 487.24 155.49 135.04 100.71 6.69 452.19 394.86 401.01 404.69 330.54 718.83 1175.14 277.91 79.62 42.34 15.38 0.00 7401.97 261.030 7663.000
48 0.00 0.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.89 1.03 3.61 24.31 79.88 24.82 6.04 5.20 3.01 0.00 0.87 1.03 18.30 34.78 58.45 358.59 1154.95 408.53 135.78 121.00 96.54 6.98 504.68 452.19 601.52 479.74 454.50 958.44 1678.78 389.07 119.43 70.56 36.90 10.09 8301.00 261.030 8562.035
49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.75 0.89 3.17 21.67 65.61 21.06 5.25 4.11 2.76 0.00 0.71 0.87 14.83 28.04 43.84 267.75 929.99 324.83 113.84 105.65 86.50 6.69 526.48 504.68 688.86 719.61 538.79 1317.85 2238.37 555.82 167.20 105.84 61.51 24.22 9498.00 261.030 9759.032
50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.60 0.75 2.73 19.03 58.48 17.30 4.45 3.57 2.18 0.00 0.56 0.71 12.51 22.71 35.34 200.81 694.39 261.56 90.52 88.59 75.53 6.00 504.68 526.48 768.81 824.10 808.18 1562.25 3077.76 741.09 238.85 148.18 92.26 40.37 10931.31 261.030 11192.344
51 0.00 0.00 0.00 0.00 0.00 0.00 0.46 0.60 2.29 16.38 51.35 15.42 3.66 3.03 1.90 0.00 0.51 0.56 10.19 19.16 28.63 161.88 520.79 195.30 72.89 70.44 63.33 5.24 452.19 504.68 802.03 919.75 925.52 2343.38 3648.54 1019.00 318.47 211.68 129.16 60.56 12578.96 261.030 12839.987
52 0.00 0.00 0.00 0.00 0.00 0.32 0.46 1.85 13.74 44.22 13.54 3.26 2.49 1.61 0.00 0.41 0.51 8.11 15.62 24.15 131.14 419.82 146.47 54.42 56.72 50.35 4.39 394.86 452.19 768.81 959.48 1032.95 2683.62 5472.81 1207.97 437.90 282.25 184.52 84.79 14955.74 261.030 15216.770
53 0.00 0.00 0.00 0.00 0.26 0.32 1.41 11.10 37.09 11.66 2.86 2.22 1.32 0.00 0.35 0.41 7.41 12.42 19.68 110.65 340.11 118.07 40.82 42.35 40.54 3.49 331.07 394.86 688.86 919.75 1077.57 2995.11 6267.43 1811.96 519.11 388.09 246.02 121.12 16565.49 261.030 16826.517
54 0.00 0.00 0.00 0.17 0.26 0.97 8.46 29.95 9.78 2.47 1.95 1.18 0.00 0.30 0.35 5.87 11.36 15.66 90.16 286.97 95.66 32.90 31.76 30.27 2.81 263.24 331.07 601.52 824.10 1032.95 3124.50 6994.90 2075.05 778.66 460.06 338.28 161.50 17645.06 261.030 17906.088
55 0.00 0.00 0.11 0.17 0.79 5.81 22.82 7.90 2.07 1.68 1.03 0.00 0.25 0.30 5.10 8.99 14.31 71.72 233.82 80.71 26.66 25.60 22.71 2.10 211.96 263.24 504.34 719.61 925.52 2995.11 7297.08 2315.90 891.71 690.09 401.01 222.06 17972.30 261.030 18233.335
56 0.00 0.06 0.11 0.53 4.76 15.69 6.02 1.67 1.41 0.89 0.00 0.22 0.25 4.32 7.81 11.33 65.57 186.00 65.76 22.49 20.74 18.30 1.57 158.27 211.96 401.01 603.36 808.18 2683.62 6994.90 2415.95 995.22 790.29 601.52 263.24 17363.02 261.030 17624.05
57 0.00 0.06 0.35 3.17 12.84 4.14 1.27 1.14 0.75 0.00 0.19 0.22 3.55 6.62 9.84 51.91 170.05 52.31 18.33 17.50 14.83 1.27 118.70 158.27 322.90 479.74 677.62 2343.38 6267.43 2315.90 1038.21 882.02 688.86 394.86 16058.22 261.030 16319.247
58 0.00 0.18 2.11 8.56 3.38 0.87 0.87 0.60 0.00 0.17 0.19 3.17 5.44 8.35 45.08 134.63 47.83 14.58 14.26 12.51 1.03 95.69 118.70 241.10 386.29 538.79 1964.79 5472.81 2075.05 995.22 920.12 768.81 452.19 14333.36 261.030 14594.394
59 0.00 1.06 5.71 2.26 0.72 0.60 0.46 0.00 0.14 0.17 2.78 4.85 6.86 38.25 116.91 37.86 13.33 11.34 10.19 0.87 77.52 95.69 180.83 288.43 433.84 1562.25 4588.65 1811.96 891.71 882.02 802.03 504.68 12373.95 261.030 12634.976
60 0.00 2.85 1.50 0.48 0.49 0.32 0.00 0.11 0.14 2.39 4.26 6.11 31.42 99.20 32.88 10.55 10.37 8.11 0.71 65.41 77.52 145.77 216.33 323.93 1257.95 3648.54 1519.23 778.66 790.29 768.81 526.48 10330.80 261.030 10591.828
61 0.00 0.75 0.32 0.32 0.26 0.00 0.09 0.11 2.01 3.67 5.37 28.00 81.48 27.90 9.16 8.21 7.41 0.56 53.29 65.41 118.09 174.38 242.95 939.27 2937.86 1207.97 652.86 690.09 688.86 504.68 8451.34 261.030 8712.372
62 0.00 0.16 0.22 0.17 0.00 0.06 0.09 1.62 3.08 4.62 24.59 72.63 22.92 7.77 7.13 5.87 0.51 42.39 53.29 99.64 141.27 195.85 704.45 2193.60 972.68 519.11 578.60 601.52 452.19 6706.03 261.030 6967.058
63 0.00 0.11 0.11 0.00 0.05 0.06 1.24 2.48 3.88 21.17 63.77 20.43 6.39 6.05 5.10 0.41 38.76 42.39 81.19 119.20 158.66 567.87 1645.20 726.27 417.99 460.06 504.34 394.86 5288.03 261.030 5549.060
64 0.00 0.06 0.00 0.03 0.05 0.85 1.89 3.13 17.76 54.91 17.94 5.69 4.97 4.32 0.35 30.68 38.76 64.58 97.13 133.87 460.05 1326.23 544.70 312.10 370.45 401.01 331.07 4222.59 261.030 4483.619
65 0.00 0.00 0.02 0.03 0.70 1.30 2.39 14.34 46.06 15.44 5.00 4.43 3.55 0.30 26.65 30.68 59.04 77.26 109.08 388.17 1074.42 439.10 234.08 276.60 322.90 263.24 3394.77 261.030 3655.799
66 0.00 0.01 0.02 0.46 1.06 1.64 10.93 37.20 12.95 4.30 3.89 3.17 0.25 22.61 26.65 46.74 70.64 86.77 316.28 906.54 355.72 188.69 207.45 241.10 211.96 2757.05 261.030 3018.075
67 0.00 0.01 0.31 0.71 1.34 7.51 28.34 10.46 3.61 3.35 2.78 0.22 18.57 22.61 40.59 55.92 79.33 251.59 738.66 300.14 152.87 167.23 180.83 158.27 2225.25 261.030 2486.283
68 0.00 0.15 0.47 0.89 6.15 19.49 7.97 2.92 2.81 2.39 0.19 16.55 18.57 34.44 48.56 62.80 230.02 587.57 244.56 128.98 135.48 145.77 118.70 1815.45 261.030 2076.482
69 0.00 0.24 0.60 4.10 15.94 5.48 2.22 2.27 2.01 0.17 14.53 16.55 28.29 41.20 54.54 182.10 537.21 194.54 105.09 114.31 118.09 95.69 1535.17 261.030 1796.201
70 0.00 0.30 2.73 10.63 4.48 1.53 1.73 1.62 0.14 12.52 14.53 25.22 33.85 46.28 158.14 425.29 177.86 83.60 93.14 99.64 77.52 1270.74 261.030 1531.769
71 0.00 1.37 7.09 2.99 1.25 1.19 1.24 0.11 10.50 12.52 22.14 30.17 38.01 134.18 369.33 140.81 76.43 74.09 81.19 65.41 1070.00 261.030 1331.026
72 0.00 3.54 1.99 0.83 0.97 0.85 0.09 8.48 10.50 19.07 26.49 33.88 110.22 313.37 122.28 60.51 67.74 64.58 53.29 898.68 261.030 1159.712
73 0.00 1.00 0.56 0.65 0.70 0.06 6.46 8.48 15.99 22.81 29.75 98.24 257.41 103.75 52.55 53.63 59.04 42.39 753.46 261.030 1014.489
74 0.00 0.28 0.43 0.46 0.05 4.44 6.46 12.92 19.13 25.62 86.26 229.43 85.23 44.59 46.57 46.74 38.76 647.36 261.030 908.393
75 0.00 0.22 0.31 0.03 3.63 4.44 9.84 15.45 21.49 74.28 201.45 75.96 36.62 39.51 40.59 30.68 554.52 261.030 815.549
76 0.00 0.15 0.02 2.42 3.63 6.77 11.77 17.35 62.30 173.47 66.70 32.64 32.46 34.44 26.65 470.78 261.030 731.815
77 0.00 0.01 1.61 2.42 5.54 8.09 13.22 50.32 145.49 57.43 28.66 28.93 28.29 22.61 392.64 261.030 653.670
78 0.00 0.81 1.61 3.69 6.62 9.09 38.34 117.51 48.17 24.68 25.40 25.22 18.57 319.72 261.030 580.750
79 0.00 0.81 2.46 4.41 7.44 26.36 89.53 38.91 20.70 21.87 22.14 16.55 251.19 261.030 512.218
80 0.00 1.23 2.94 4.96 21.56 61.56 29.64 16.72 18.35 19.07 14.53 190.56 261.030 451.592
81 0.00 1.47 3.31 14.38 50.36 20.38 12.74 14.82 15.99 12.52 145.96 261.030 406.991
82 0.00 1.65 9.58 33.58 16.67 8.76 11.29 12.92 10.50 104.95 261.030 365.978
83 0.00 4.79 22.38 11.12 7.17 7.76 9.84 8.48 71.54 261.030 332.569
84 0.00 11.19 7.41 4.78 6.35 6.77 6.46 42.96 261.030 303.986
85 0.00 3.71 3.18 4.23 5.54 4.44 21.10 261.030 282.130
86 0.00 1.59 2.82 3.69 3.63 11.74 261.030 272.769
87 0.00 1.41 2.46 2.42 6.29 261.030 267.324
88 0.00 1.23 1.61 2.85 261.030 263.875
89 0.00 0.81 0.81 261.030 261.837
18233
ANNEXURE-VI-5
1 19.2
2 Day DAD CURVE SPS
Area SPS 3 34.6
(Sq. Km) Values 6 44.3
5000 518 9 52.8
7500 475 12 58.8
5220.6 514.21 15 64.8
Clock Hour Correction 1.15 18 69.8
Design Storm 674.58 mm 21 74.3
24 78.8
Ist 12 hour Bell 396.6558 27 83.3
IInd 12 hour Bell 134.9169 30 87.8
IIIrd 12 hour Bell 111.3065 33 92.3
IVth 12 hour Bell 31.70548 36 95.3
39 96.8
42 98.3
45 99.5
48 100
Time
Duration(Hrs) Distributi
on (%)
1 19.2 32.65
2 26.0 44.22
3 34.6 58.84
4 38.0 64.63
5 41.3 70.24
6 44.3 75.34
7 47.0 79.93
8 49.7 84.52
9 52.8 89.80
10 54.8 93.20
11 56.8 96.60
12 58.8 100.00
ANNEXURE-VI-5
Rainfall to be analysed
67.46 cm
U.G.
Time Critical Arrangement of rainfall increments in bells Critical 1Hr excessive Rainfall arrangement Critical 1Hr excessive Rainfall after reversing
Ordinate
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 550.0 0.11 0.38 0.46 1.35 0.000 0.179 0.259 1.149 0.000 0.179 0.259 1.149
2 652.0 0.15 0.51 0.62 1.82 0.000 0.311 0.420 1.621 0.000 0.179 0.259 1.149
3 978.0 0.16 0.57 0.69 2.02 0.000 0.368 0.488 1.824 0.000 0.311 0.420 1.621
4 1120.0 0.18 0.62 0.76 2.23 0.000 0.425 0.557 2.026 0.000 0.387 0.511 1.891
5 1250.0 0.37 1.29 1.56 4.59 0.167 1.087 1.360 4.387 0.000 0.444 0.580 2.094
6 1304.0 1.04 3.63 4.41 12.95 0.835 3.434 4.205 12.752 0.264 1.428 1.773 5.601
7 1250.0 0.46 1.63 1.97 5.80 0.264 1.428 1.773 5.601 0.835 3.434 4.205 12.752
8 1120.0 0.18 0.64 0.78 2.29 0.000 0.444 0.580 2.094 0.167 1.087 1.360 4.387
9 978.0 0.17 0.59 0.71 2.09 0.000 0.387 0.511 1.891 0.000 0.425 0.557 2.026
10 820.0 0.15 0.51 0.62 1.82 0.000 0.311 0.420 1.621 0.000 0.368 0.488 1.824
11 652.0 0.11 0.38 0.46 1.35 0.000 0.179 0.259 1.149 0.000 0.311 0.420 1.621
12 525.0 0.11 0.38 0.46 1.35 0.000 0.179 0.259 1.149 0.000 0.179 0.259 1.149
3.17 11.13 13.49 39.67 1.27 8.73 11.09 37.27 1.27 8.73 11.09 37.27
ANNEXURE-VI-5
Computation of SPF
Total Flow
UH DSRO Base Flow
(hr) 0 0 0 0 0 0.26372 0.83528 0.166662 0 0 0 0 0.1786 0.17859 0.3111 0.38682 0.44361 1.42795 3.4345 1.08722 0.42468 0.36789 0.3111 0.17859 0.2589 0.2589 0.41952 0.5113 0.58013 1.77327 4.20545 1.36026 0.55719 0.48835 0.41952 0.2589 1.14917 1.14917 1.621 1.891 2.094 5.601 12.752 4.387 2.026 1.824 1.621 1.149 Cumecs
ordinate
(Cumecs)
0 0.0 0.00 0.00 261.030 261.030
1 25.0 0.00 0.00 0.00 261.030 261.030
2 60.0 0.00 0.00 0.00 0.00 261.030 261.030
3 100.0 0.00 0.00 0.00 0.00 0.00 261.030 261.030
4 150.0 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
5 210.0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 261.030 261.030
6 300.0 0.00 0.00 0.00 0.00 0.00 6.59 0.00 6.59 261.030 267.623
7 400.0 0.00 0.00 0.00 0.00 0.00 15.82 20.88 0.00 36.71 261.030 297.735
8 550.0 0.00 0.00 0.00 0.00 0.00 26.37 50.12 4.17 0.00 80.66 261.030 341.685
9 652.0 0.00 0.00 0.00 0.00 0.00 39.56 83.53 10.00 0.00 0.00 133.09 261.030 394.116
10 978.0 0.00 0.00 0.00 0.00 0.00 55.38 125.29 16.67 0.00 0.00 0.00 197.34 261.030 458.369
11 1120.0 0.00 0.00 0.00 0.00 0.00 79.12 175.41 25.00 0.00 0.00 0.00 0.00 279.52 261.030 540.554
12 1250.0 0.00 0.00 0.00 0.00 0.00 105.49 250.58 35.00 0.00 0.00 0.00 0.00 0.00 391.07 261.030 652.101
13 1304.0 0.00 0.00 0.00 0.00 0.00 145.05 334.11 50.00 0.00 0.00 0.00 0.00 4.46 0.00 533.62 261.030 794.652
14 1250.0 0.00 0.00 0.00 0.00 0.00 171.95 459.40 66.66 0.00 0.00 0.00 0.00 10.72 4.46 0.00 713.19 261.030 974.225
15 1120.0 0.00 0.00 0.00 0.00 0.00 257.92 544.60 91.66 0.00 0.00 0.00 0.00 17.86 10.72 7.78 0.00 930.54 261.030 1191.568
16 978.0 0.00 0.00 0.00 0.00 0.00 295.37 816.90 108.66 0.00 0.00 0.00 0.00 26.79 17.86 18.67 7.78 0.00 1292.03 261.030 1553.056
17 820.0 0.00 0.00 0.00 0.00 0.00 329.65 935.51 163.00 0.00 0.00 0.00 0.00 37.50 26.79 31.11 18.67 11.09 0.00 1553.32 261.030 1814.350
18 652.0 0.00 0.00 0.00 0.00 0.00 343.89 1044.10 186.66 0.00 0.00 0.00 0.00 53.58 37.50 46.67 31.11 26.62 35.70 0.00 1805.83 261.030 2066.856
19 525.0 0.00 0.00 0.00 0.00 0.00 329.65 1089.21 208.33 0.00 0.00 0.00 0.00 71.44 53.58 65.33 46.67 44.36 85.68 85.86 0.00 2080.10 261.030 2341.126
20 392.0 0.00 0.00 0.00 0.00 0.00 295.37 1044.10 217.33 0.00 0.00 0.00 0.00 98.23 71.44 93.33 65.33 66.54 142.80 206.07 27.18 0.00 2327.71 261.030 2588.737
21 294.0 0.00 0.00 0.00 0.00 0.00 257.92 935.51 208.33 0.00 0.00 0.00 0.00 116.44 98.23 124.44 93.33 93.16 214.19 343.45 65.23 10.62 0.00 2560.85 261.030 2821.881
22 237.0 0.00 0.00 0.00 0.00 0.00 216.25 816.90 186.66 0.00 0.00 0.00 0.00 174.66 116.44 171.11 124.44 133.08 299.87 515.17 108.72 25.48 9.20 0.00 2898.00 261.030 3159.027
23 192.0 0.00 0.00 0.00 0.00 0.00 171.95 684.93 163.00 0.00 0.00 0.00 0.00 200.02 174.66 202.84 171.11 177.44 428.39 721.24 163.08 42.47 22.07 7.78 0.00 3330.98 261.030 3592.009
24 162.0 0.00 0.00 0.00 0.00 0.00 138.45 544.60 136.66 0.00 0.00 0.00 0.00 223.24 200.02 304.26 202.84 243.98 571.18 1030.35 228.32 63.70 36.79 18.67 4.46 0.00 3947.53 261.030 4208.562
25 132.0 0.00 0.00 0.00 0.00 0.00 103.38 438.52 108.66 0.00 0.00 0.00 0.00 232.89 223.24 348.43 304.26 289.23 785.37 1373.80 326.17 89.18 55.18 31.11 10.72 6.47 0.00 4726.62 261.030 4987.647
26 105.0 0.00 0.00 0.00 0.00 0.00 77.53 327.43 87.50 0.00 0.00 0.00 0.00 223.24 232.89 388.88 348.43 433.85 931.02 1888.97 434.89 127.40 77.26 46.67 17.86 15.53 6.47 0.00 5665.83 261.030 5926.855
27 96.0 0.00 0.00 0.00 0.00 0.00 62.50 245.57 65.33 0.00 0.00 0.00 0.00 200.02 223.24 405.68 388.88 496.84 1396.54 2239.29 597.97 169.87 110.37 65.33 26.79 25.89 15.53 10.49 0.00 6746.14 261.030 7007.166
28 76.0 0.00 0.00 0.00 0.00 0.00 50.63 197.96 49.00 0.00 0.00 0.00 0.00 174.66 200.02 388.88 405.68 554.51 1599.31 3358.94 708.87 233.57 147.16 93.33 37.50 38.84 25.89 25.17 12.78 0.00 8302.70 261.030 8563.730
29 66.0 0.00 0.00 0.00 0.00 0.00 42.72 160.37 39.50 0.00 0.00 0.00 0.00 146.45 174.66 348.43 388.88 578.47 1784.94 3846.64 1063.30 276.89 202.34 124.44 53.58 54.37 38.84 41.95 30.68 14.50 0.00 9411.94 261.030 9672.974
30 56.0 0.00 0.00 0.00 0.00 0.00 34.81 135.32 32.00 0.00 0.00 0.00 0.00 116.44 146.45 304.26 348.43 554.51 1862.05 4293.12 1217.68 415.34 239.86 171.11 71.44 77.67 54.37 62.93 51.13 34.81 44.33 0.00 10268.05 261.030 10529.081
31 46.0 0.00 0.00 0.00 0.00 0.00 27.69 110.26 27.00 0.00 0.00 0.00 0.00 93.76 116.44 255.10 304.26 496.84 1784.94 4478.58 1359.02 475.64 359.80 202.84 98.23 103.56 77.67 88.10 76.69 58.01 106.40 105.14 0.00 10805.97 261.030 11067.001
32 41.0 0.00 0.00 0.00 0.00 0.00 25.32 87.70 22.00 0.00 0.00 0.00 0.00 70.01 93.76 202.84 255.10 433.85 1599.31 4293.12 1417.73 530.85 412.04 304.26 116.44 142.40 103.56 125.85 107.37 87.02 177.33 252.33 34.01 0.00 10894.19 261.030 11155.221
33 36.0 0.00 0.00 0.00 0.00 0.00 20.04 80.19 17.50 0.00 0.00 0.00 0.00 52.51 70.01 163.33 202.84 363.76 1396.54 3846.64 1359.02 553.78 459.86 348.43 174.66 168.80 142.40 167.81 153.39 121.83 265.99 420.55 81.62 13.93 0.00 10645.41 261.030 10906.442
34 31.0 0.00 0.00 0.00 0.00 0.00 17.41 63.48 16.00 0.00 0.00 0.00 0.00 42.33 52.51 121.95 163.33 289.23 1170.92 3358.94 1217.68 530.85 479.73 388.88 200.02 253.21 168.80 230.73 204.52 174.04 372.39 630.82 136.03 33.43 12.21 0.00 10329.43 261.030 10590.457
35 26.0 0.00 0.00 0.00 0.00 0.00 14.77 55.13 12.67 0.00 0.00 0.00 0.00 34.29 42.33 91.46 121.95 232.89 931.02 2816.29 1063.30 475.64 459.86 405.68 223.24 289.97 253.21 273.52 281.21 232.05 531.98 883.14 204.04 55.72 29.30 10.49 0.00 10025.16 261.030 10286.192
36 21.0 0.00 0.00 0.00 0.00 0.00 12.13 46.78 11.00 0.00 0.00 0.00 0.00 28.93 34.29 73.73 91.46 173.89 749.67 2239.29 891.52 415.34 412.04 388.88 232.89 323.63 289.97 410.29 333.37 319.07 709.31 1261.64 285.66 83.58 48.84 25.17 6.47 0.00 9898.82 261.030 10159.847
37 16.0 0.00 0.00 0.00 0.00 0.00 10.81 38.42 9.33 0.00 0.00 0.00 0.00 23.57 28.93 59.73 73.73 130.42 559.76 1803.11 708.87 348.24 359.80 348.43 223.24 337.61 323.63 469.86 500.05 378.25 975.30 1682.18 408.08 117.01 73.25 41.95 15.53 28.73 0.00 10077.83 261.030 10338.855
38 11.0 0.00 0.00 0.00 0.00 0.00 9.49 34.25 7.67 0.00 0.00 0.00 0.00 18.75 23.57 50.40 59.73 105.14 419.82 1346.32 570.79 276.89 301.67 304.26 200.02 323.63 337.61 524.40 572.65 567.37 1156.18 2313.00 544.11 167.16 102.55 62.93 25.89 68.95 28.73 0.00 10523.91 261.030 10784.937
39 9.0 0.00 0.00 0.00 0.00 0.00 8.18 30.07 6.83 0.00 0.00 0.00 0.00 17.14 18.75 41.07 50.40 85.17 338.42 1009.74 426.19 222.96 239.86 255.10 174.66 289.97 323.63 547.05 639.12 649.75 1734.26 2741.95 748.15 222.87 146.51 88.10 38.84 114.92 68.95 40.53 0.00 11319.15 261.030 11580.179
40 6.0 0.00 0.00 0.00 0.00 0.00 6.86 25.89 6.00 0.00 0.00 0.00 0.00 13.57 17.14 32.67 41.07 71.86 274.17 813.98 319.64 166.47 193.14 202.84 146.45 253.21 289.97 524.40 666.73 725.16 1986.07 4112.93 886.89 306.45 195.34 125.85 54.37 172.38 114.92 97.28 47.28 0.00 12890.98 261.030 13152.010
41 4.0 0.00 0.00 0.00 0.00 0.00 5.54 21.72 5.17 0.00 0.00 0.00 0.00 11.79 13.57 29.87 32.67 58.56 231.33 659.42 257.67 124.86 144.21 163.33 116.44 212.30 253.21 469.86 639.12 756.49 2216.59 4710.11 1330.34 363.29 268.59 167.81 77.67 241.33 172.38 162.14 113.47 52.34 0.00 14083.15 261.030 14344.182
42 2.0 0.00 0.00 0.00 0.00 0.00 4.22 17.54 4.33 0.00 0.00 0.00 0.00 10.00 11.79 23.64 29.87 46.58 188.49 556.39 208.75 100.65 108.16 121.95 93.76 168.80 212.30 410.29 572.65 725.16 2312.35 5256.81 1523.50 544.93 318.41 230.73 103.56 344.75 241.33 243.21 189.12 125.62 140.04 0.00 15189.67 261.030 15450.697
43 0.0 0.00 0.00 0.00 0.00 0.00 2.90 13.36 3.50 0.00 0.00 0.00 0.00 8.22 10.00 20.53 23.64 42.59 149.93 453.35 176.13 81.54 87.19 91.46 70.01 135.92 168.80 344.00 500.05 649.75 2216.59 5483.91 1700.33 624.05 477.61 273.52 142.40 459.67 344.75 340.49 283.68 209.36 336.09 318.80 0.00 16244.13 261.030 16505.164
44 0.00 0.00 0.00 0.00 2.37 9.19 2.67 0.00 0.00 0.00 0.00 7.32 8.22 17.42 20.53 33.71 137.08 360.62 143.51 68.80 70.63 73.73 52.51 101.49 135.92 273.52 419.26 567.37 1986.07 5256.81 1773.78 696.48 546.95 410.29 168.80 632.04 459.67 486.41 397.15 314.04 560.14 765.12 109.68 0.00 17069.35 261.030 17330.378
45 0.00 0.00 0.00 1.58 7.52 1.83 0.00 0.00 0.00 0.00 6.43 7.32 14.31 17.42 29.28 108.52 329.71 114.16 56.06 59.60 59.73 42.33 76.12 101.49 220.25 333.37 475.71 1734.26 4710.11 1700.33 726.57 610.44 469.86 253.21 749.26 632.04 648.55 567.36 439.65 840.21 1275.20 263.23 50.65 0.00 17733.67 261.030 17994.703
46 0.00 0.00 1.05 5.01 1.50 0.00 0.00 0.00 0.00 5.54 6.43 12.76 14.31 24.84 94.24 261.02 104.37 44.59 48.56 50.40 34.29 61.36 76.12 164.45 268.43 378.25 1454.09 4112.93 1523.50 696.48 636.81 524.40 289.97 1123.89 749.26 891.76 756.49 628.08 1176.30 1912.80 438.72 121.57 45.59 0.00 18740.14 261.030 19001.175
47 0.00 0.53 3.34 1.00 0.00 0.00 0.00 0.00 4.64 5.54 11.20 12.76 20.41 79.97 226.68 82.63 40.77 38.63 41.07 28.93 49.71 61.36 123.34 200.43 304.57 1156.18 3448.47 1330.34 624.05 610.44 547.05 323.63 1287.07 1123.89 1057.14 1040.17 837.44 1680.43 2677.93 658.08 202.61 109.43 40.53 0.00 20092.33 261.030 20353.359
48 0.00 1.67 0.67 0.00 0.00 0.00 0.00 3.75 4.64 9.64 11.20 18.19 65.69 192.33 71.76 32.28 35.32 32.67 23.57 41.94 49.71 99.43 150.32 227.41 930.97 2741.95 1115.42 544.93 546.95 524.40 337.61 1436.46 1287.07 1585.71 1233.07 1151.47 2240.57 3825.61 921.31 303.92 182.38 97.28 28.73 22107.98 261.030 22369.011
49 0.00 0.33 0.00 0.00 0.00 0.00 2.86 3.75 8.09 9.64 15.97 58.55 157.99 60.88 28.03 27.96 29.87 18.75 34.17 41.94 80.55 121.18 170.56 695.12 2207.86 886.89 456.89 477.61 469.86 323.63 1498.52 1436.46 1815.94 1849.61 1365.02 3080.79 5100.81 1316.15 425.49 273.56 162.14 68.95 24782.37 261.030 25043.397
50 0.00 0.00 0.00 0.00 0.00 1.96 2.86 6.53 8.09 13.75 51.41 140.81 50.01 23.78 24.28 23.64 17.14 27.18 34.17 67.96 98.17 137.49 521.34 1648.54 714.14 363.29 400.45 410.29 289.97 1436.46 1498.52 2026.72 2118.16 2047.53 3652.13 7013.61 1754.87 607.84 382.99 243.21 114.92 27974.23 261.030 28235.256
51 0.00 0.00 0.00 0.00 1.61 1.96 4.98 6.53 11.53 44.27 123.64 44.58 19.54 20.60 20.53 13.57 24.85 27.18 55.38 82.83 111.39 420.27 1236.40 533.22 292.52 318.41 344.00 253.21 1287.07 1436.46 2114.28 2364.02 2344.82 5478.20 8314.32 2412.95 810.45 547.13 340.49 172.38 31635.55 261.030 31896.585
52 0.00 0.00 0.00 1.07 1.61 3.42 4.98 9.32 37.13 106.47 39.14 17.41 16.92 17.42 11.79 19.68 24.85 44.05 67.49 93.98 340.47 996.69 399.92 218.42 256.38 273.52 212.30 1123.89 1287.07 2026.72 2466.14 2616.98 6273.60 12471.48 2860.44 1114.37 729.50 486.41 241.33 36912.37 261.030 37173.399
53 0.00 0.00 0.71 1.07 2.80 3.42 7.10 29.99 89.30 33.70 15.29 15.08 14.31 10.00 17.09 19.68 40.27 53.69 76.58 287.27 807.45 322.38 163.81 191.43 220.25 168.80 942.32 1123.89 1815.94 2364.02 2730.04 7001.79 14282.27 4290.66 1321.04 1003.06 648.55 344.75 40459.80 261.030 40720.825
54 0.00 0.36 0.71 1.87 2.80 4.88 22.85 72.12 28.27 13.17 13.24 12.76 8.22 14.50 17.09 31.88 49.08 60.91 234.07 681.28 261.17 132.05 143.58 164.45 135.92 749.26 942.32 1585.71 2118.16 2616.98 7304.26 15940.03 4913.64 1981.55 1189.09 891.76 459.67 42799.66 261.030 43060.691
55 0.00 0.36 1.24 1.87 3.99 15.71 54.95 22.83 11.04 11.40 11.20 7.32 11.91 14.50 27.69 38.86 55.69 186.19 555.12 220.36 106.98 115.74 123.34 101.49 603.31 749.26 1329.53 1849.61 2344.82 7001.79 16628.64 5483.97 2269.27 1783.63 1057.14 632.04 43432.79 261.030 43693.822
56 0.00 0.62 1.24 2.66 12.85 37.78 17.40 8.92 9.57 9.64 6.43 10.61 11.91 23.49 33.75 44.09 170.23 441.57 179.55 90.26 93.76 99.43 76.12 450.47 603.31 1057.14 1550.79 2047.53 6273.60 15940.03 5720.88 2532.66 2042.60 1585.71 749.26 41935.89 261.030 42196.92
57 0.00 0.62 1.77 8.57 30.91 11.96 6.79 7.73 8.09 5.54 9.32 10.61 19.30 28.63 38.29 134.77 403.72 142.83 73.55 79.11 80.55 61.36 337.86 450.47 851.22 1233.07 1716.74 5478.20 14282.27 5483.97 2642.07 2279.69 1815.94 1123.89 38859.42 261.030 39120.452
58 0.00 0.89 5.71 20.61 9.78 4.67 5.89 6.53 4.64 8.03 9.32 17.20 23.52 32.49 117.04 319.61 130.59 58.50 64.46 67.96 49.71 272.35 337.86 635.58 992.89 1365.02 4593.17 12471.48 4913.64 2532.66 2378.18 2026.72 1287.07 34763.77 261.030 35024.797
59 0.00 2.86 13.74 6.52 3.82 4.05 4.98 3.75 6.73 8.03 15.10 20.96 26.69 99.30 277.56 103.38 53.49 51.28 55.38 41.94 220.64 272.35 476.69 741.36 1099.13 3652.13 10456.66 4290.66 2269.27 2279.69 2114.28 1436.46 30108.87 261.030 30369.897
60 0.00 6.87 4.35 2.55 3.31 3.42 2.86 5.44 6.73 13.01 18.41 23.79 81.57 235.51 89.78 42.35 46.88 44.05 34.17 186.17 220.64 384.27 556.02 820.69 2940.75 8314.32 3597.48 1981.55 2042.60 2026.72 1498.52 25234.76 261.030 25495.788
61 0.00 2.17 1.70 2.21 2.80 1.96 4.14 5.44 10.91 15.85 20.88 72.70 193.45 76.17 36.77 37.11 40.27 27.18 151.69 186.17 311.30 448.22 615.51 2195.76 6694.81 2860.44 1661.43 1783.63 1815.94 1436.46 20713.11 261.030 20974.142
62 0.00 0.85 1.47 1.87 1.61 2.85 4.14 8.81 13.29 17.98 63.84 172.42 62.57 31.20 32.23 31.88 24.85 120.66 151.69 262.66 363.11 496.18 1646.82 4998.79 2303.27 1321.04 1495.48 1585.71 1287.07 16504.36 261.030 16765.392
63 0.00 0.74 1.24 1.07 2.33 2.85 6.71 10.74 15.08 54.97 151.40 55.77 25.63 27.35 27.69 19.68 110.32 120.66 214.02 306.38 401.97 1327.54 3749.10 1719.77 1063.72 1189.09 1329.53 1123.89 13059.23 261.030 13320.255
64 0.00 0.62 0.71 1.55 2.33 4.61 8.18 12.18 46.11 130.37 48.97 22.84 22.46 23.49 17.09 87.34 110.32 170.24 249.64 339.16 1075.47 3022.23 1289.83 794.24 957.47 1057.14 942.32 10436.94 261.030 10697.970
65 0.00 0.36 1.04 1.55 3.78 5.62 9.28 37.24 109.34 42.17 20.06 20.02 19.30 14.50 75.85 87.34 155.65 198.58 276.35 907.43 2448.39 1039.76 595.68 714.91 851.22 749.26 8384.68 261.030 8645.707
66 0.00 0.52 1.04 2.52 4.60 6.38 28.37 88.31 35.37 17.27 17.58 17.20 11.91 64.35 75.85 123.22 181.56 219.83 739.39 2065.83 842.34 480.19 536.18 635.58 603.31 6798.70 261.030 7059.732
67 0.00 0.52 1.68 3.07 5.22 19.51 67.29 28.57 14.49 15.14 15.10 10.61 52.86 64.35 107.01 143.73 200.98 588.15 1683.27 710.72 389.02 432.23 476.69 450.47 5480.68 261.030 5741.706
68 0.00 0.84 2.05 3.48 15.96 46.26 21.76 11.70 12.70 13.01 9.32 47.12 52.86 90.80 124.82 159.11 537.74 1338.96 579.11 328.23 350.16 384.27 337.86 4468.10 261.030 4729.133
69 0.00 1.02 2.32 10.64 37.85 14.96 8.91 10.26 10.91 8.03 41.37 47.12 74.58 105.91 138.18 425.71 1224.19 460.65 267.45 295.45 311.30 272.35 3769.16 261.030 4030.194
70 0.00 1.16 7.09 25.23 12.24 6.13 7.81 8.81 6.73 35.62 41.37 66.48 87.00 117.24 369.69 969.15 421.17 212.74 240.74 262.66 220.64 3119.72 261.030 3380.750
71 0.00 3.55 16.82 8.16 5.01 5.37 6.71 5.44 29.88 35.62 58.37 77.54 96.31 313.68 841.63 333.43 194.51 191.49 214.02 186.17 2623.71 261.030 2884.742
72 0.00 8.41 5.44 3.34 4.40 4.61 4.14 24.13 29.88 50.26 68.08 85.84 257.67 714.11 289.55 153.99 175.08 170.24 151.69 2200.88 261.030 2461.906
73 0.00 2.72 2.23 2.93 3.78 2.85 18.39 24.13 42.16 58.63 75.37 229.66 586.59 245.68 133.72 138.61 155.65 120.66 1843.75 261.030 2104.783
74 0.00 1.11 1.95 2.52 2.33 12.64 18.39 34.05 49.17 64.90 201.65 522.83 201.81 113.46 120.37 123.22 110.32 1580.73 261.030 1841.765
75 0.00 0.98 1.68 1.55 10.34 12.64 25.94 39.72 54.43 173.64 459.07 179.87 93.20 102.13 107.01 87.34 1349.55 261.030 1610.584
76 0.00 0.84 1.04 6.90 10.34 17.84 30.26 43.97 145.64 395.31 157.94 83.07 83.89 90.80 75.85 1143.67 261.030 1404.697
77 0.00 0.52 4.60 6.90 14.59 20.80 33.50 117.63 331.55 136.00 72.94 74.77 74.58 64.35 952.74 261.030 1213.769
78 0.00 2.30 4.60 9.73 17.02 23.03 89.62 267.79 114.07 62.81 65.66 66.48 52.86 775.96 261.030 1036.989
79 0.00 2.30 6.49 11.35 18.84 61.62 204.03 92.13 52.68 56.54 58.37 47.12 611.45 261.030 872.484
80 0.00 3.24 7.56 12.56 50.41 140.27 70.19 42.55 47.42 50.26 41.37 465.85 261.030 726.878
81 0.00 3.78 8.37 33.61 114.77 48.26 32.42 38.30 42.16 35.62 357.29 261.030 618.320
82 0.00 4.19 22.41 76.51 39.48 22.29 29.18 34.05 29.88 257.98 261.030 519.014
83 0.00 11.20 51.01 26.32 18.24 20.06 25.94 24.13 176.91 261.030 437.935
84 0.00 25.50 17.55 12.16 16.41 17.84 18.39 107.85 261.030 368.875
85 0.00 8.77 8.10 10.94 14.59 12.64 55.05 261.030 316.085
86 0.00 4.05 7.30 9.73 10.34 31.42 261.030 292.448
87 0.00 3.65 6.49 6.90 17.03 261.030 278.058
88 0.00 3.24 4.60 7.84 261.030 268.869
89 0.00 2.30 2.30 261.030 263.328
43694
ANNEXURE-VI-5
Time
Duration(Hrs) Distributi
on (%)
1 19.2 32.65
2 26.0 44.22
3 34.6 58.84
4 38.0 64.63
5 41.3 70.24
6 44.3 75.34
7 47.0 79.93
8 49.7 84.52
9 52.8 89.80
10 54.8 93.20
11 56.8 96.60
12 58.8 100.00
ANNEXURE-VI-5
Rainfall to be analysed
80.92 cm
U.G.
Time Critical Arrangement of rainfall increments in bells Critical 1Hr excessive Rainfall arrangement Critical 1Hr excessive Rainfall after reversing
Ordinate
1st 2nd 3rd 4th 1st 2nd 3rd 4th 1st 2nd 3rd 4th
1 550.0 0.13 0.45 0.55 1.62 0.000 0.254 0.350 1.418 0.000 0.254 0.350 1.418
2 652.0 0.17 0.61 0.74 2.18 0.000 0.413 0.543 1.985 0.000 0.254 0.350 1.418
3 978.0 0.19 0.68 0.83 2.43 0.000 0.481 0.626 2.228 0.000 0.413 0.543 1.985
4 1120.0 0.21 0.75 0.91 2.67 0.013 0.549 0.708 2.470 0.001 0.504 0.653 2.308
5 1250.0 0.44 1.54 1.87 5.50 0.240 1.344 1.672 5.302 0.020 0.572 0.736 2.551
6 1304.0 1.24 4.36 5.28 15.54 1.042 4.160 5.084 15.336 0.356 1.753 2.167 6.759
7 1250.0 0.56 1.95 2.37 6.96 0.356 1.753 2.167 6.759 1.042 4.160 5.084 15.336
8 1120.0 0.22 0.77 0.94 2.75 0.020 0.572 0.736 2.551 0.240 1.344 1.672 5.302
9 978.0 0.20 0.70 0.85 2.51 0.001 0.504 0.653 2.308 0.013 0.549 0.708 2.470
10 820.0 0.17 0.61 0.74 2.18 0.000 0.413 0.543 1.985 0.000 0.481 0.626 2.228
11 652.0 0.13 0.45 0.55 1.62 0.000 0.254 0.350 1.418 0.000 0.413 0.543 1.985
12 525.0 0.13 0.45 0.55 1.62 0.000 0.254 0.350 1.418 0.000 0.254 0.350 1.418
3.80 13.35 16.18 47.58 1.67 10.95 13.78 45.18 1.67 10.95 13.78 45.18
ANNEXURE-VI-5
Computation of PMF
Total Flow
UH DSRO Base Flow
(hr) 0 0 0 0.0005 0.01991 0.356244 1.04185 0.239821 0.01344 0 0 0 0.2541 0.25413 0.41308 0.50391 0.57203 1.75277 4.15968 1.34405 0.54932 0.4812 0.41308 0.25413 0.35046 0.35046 0.54313 0.65322 0.73579 2.167 5.08446 1.67158 0.70827 0.6257 0.54313 0.35046 1.41837 1.41837 1.985 2.308 2.551 6.759 15.336 5.302 2.470 2.228 1.985 1.418 Cumecs
ordinate
(Cumecs)
0 0.0 0.00 0.00 261.030 261.030
1 25.0 0.00 0.00 0.00 261.030 261.030
2 60.0 0.00 0.00 0.00 0.00 261.030 261.030
3 100.0 0.00 0.00 0.00 0.00 0.00 261.030 261.030
4 150.0 0.00 0.00 0.00 0.01 0.00 0.01 261.030 261.043
5 210.0 0.00 0.00 0.00 0.03 0.50 0.00 0.53 261.030 261.558
6 300.0 0.00 0.00 0.00 0.05 1.19 8.91 0.00 10.15 261.030 271.181
7 400.0 0.00 0.00 0.00 0.08 1.99 21.37 26.05 0.00 49.49 261.030 310.518
8 550.0 0.00 0.00 0.00 0.11 2.99 35.62 62.51 6.00 0.00 107.22 261.030 368.254
9 652.0 0.00 0.00 0.00 0.15 4.18 53.44 104.18 14.39 0.34 0.00 176.68 261.030 437.710
10 978.0 0.00 0.00 0.00 0.20 5.97 74.81 156.28 23.98 0.81 0.00 0.00 262.05 261.030 523.083
11 1120.0 0.00 0.00 0.00 0.28 7.96 106.87 218.79 35.97 1.34 0.00 0.00 0.00 371.22 261.030 632.252
12 1250.0 0.00 0.00 0.00 0.33 10.95 142.50 312.55 50.36 2.02 0.00 0.00 0.00 0.00 518.71 261.030 779.742
13 1304.0 0.00 0.00 0.00 0.50 12.98 195.93 416.74 71.95 2.82 0.00 0.00 0.00 6.35 0.00 707.27 261.030 968.303
14 1250.0 0.00 0.00 0.00 0.57 19.47 232.27 573.02 95.93 4.03 0.00 0.00 0.00 15.25 6.35 0.00 946.89 261.030 1207.920
15 1120.0 0.00 0.00 0.00 0.63 22.30 348.41 679.28 131.90 5.38 0.00 0.00 0.00 25.41 15.25 10.33 0.00 1238.89 261.030 1499.922
16 978.0 0.00 0.00 0.00 0.66 24.89 398.99 1018.93 156.36 7.39 0.00 0.00 0.00 38.12 25.41 24.78 10.33 0.00 1705.87 261.030 1966.902
17 820.0 0.00 0.00 0.00 0.63 25.96 445.31 1166.87 234.55 8.76 0.00 0.00 0.00 53.37 38.12 41.31 24.78 14.30 0.00 2053.96 261.030 2314.993
18 652.0 0.00 0.00 0.00 0.57 24.89 464.54 1302.31 268.60 13.15 0.00 0.00 0.00 76.24 53.37 61.96 41.31 34.32 43.82 0.00 2385.07 261.030 2646.103
19 525.0 0.00 0.00 0.00 0.50 22.30 445.31 1358.57 299.78 15.06 0.00 0.00 0.00 101.65 76.24 86.75 61.96 57.20 105.17 103.99 0.00 2734.47 261.030 2995.495
20 392.0 0.00 0.00 0.00 0.42 19.47 398.99 1302.31 312.73 16.80 0.00 0.00 0.00 139.77 101.65 123.92 86.75 85.80 175.28 249.58 33.60 0.00 3047.08 261.030 3308.112
21 294.0 0.00 0.00 0.00 0.33 16.33 348.41 1166.87 299.78 17.53 0.00 0.00 0.00 165.69 139.77 165.23 123.92 120.13 262.92 415.97 80.64 13.73 0.00 3337.25 261.030 3598.278
22 237.0 0.00 0.00 0.00 0.27 12.98 292.12 1018.93 268.60 16.80 0.00 0.00 0.00 248.54 165.69 227.19 165.23 171.61 368.08 623.95 134.41 32.96 12.03 0.00 3759.40 261.030 4020.427
23 192.0 0.00 0.00 0.00 0.20 10.45 232.27 854.32 234.55 15.06 0.00 0.00 0.00 284.63 248.54 269.33 227.19 228.81 525.83 873.53 201.61 54.93 28.87 10.33 0.00 4300.45 261.030 4561.476
24 162.0 0.00 0.00 0.00 0.15 7.80 187.03 679.28 196.65 13.15 0.00 0.00 0.00 317.67 284.63 403.99 269.33 314.61 701.11 1247.90 282.25 82.40 48.12 24.78 6.35 0.00 5067.22 261.030 5328.247
25 132.0 0.00 0.00 0.00 0.12 5.85 139.65 546.97 156.36 11.02 0.00 0.00 0.00 331.39 317.67 462.65 403.99 372.96 964.02 1663.87 403.22 115.36 72.18 41.31 15.25 8.76 0.00 6032.60 261.030 6293.634
26 105.0 0.00 0.00 0.00 0.10 4.72 104.74 408.40 125.91 8.76 0.00 0.00 0.00 317.67 331.39 516.35 462.65 559.44 1142.81 2287.82 537.62 164.80 101.05 61.96 25.41 21.03 8.76 0.00 7191.39 261.030 7452.419
27 96.0 0.00 0.00 0.00 0.08 3.82 84.43 306.30 94.01 7.06 0.00 0.00 0.00 284.63 317.67 538.66 516.35 640.67 1714.21 2712.11 739.23 219.73 144.36 86.75 38.12 35.05 21.03 13.58 0.00 8517.83 261.030 8778.864
28 76.0 0.00 0.00 0.00 0.07 3.23 68.40 246.92 70.51 5.27 0.00 0.00 0.00 248.54 284.63 516.35 538.66 715.03 1963.11 4068.17 876.32 302.13 192.48 123.92 53.37 52.57 35.05 32.59 16.33 0.00 10413.62 261.030 10674.652
29 66.0 0.00 0.00 0.00 0.05 2.63 57.71 200.03 56.84 3.95 0.00 0.00 0.00 208.39 248.54 462.65 516.35 745.92 2190.97 4658.84 1314.48 358.16 264.66 165.23 76.24 73.60 52.57 54.31 39.19 18.39 0.00 11769.72 261.030 12030.746
30 56.0 0.00 0.00 0.00 0.05 2.09 47.02 168.78 46.05 3.19 0.00 0.00 0.00 165.69 208.39 403.99 462.65 715.03 2285.62 5199.60 1505.34 537.23 313.74 227.19 101.65 105.14 73.60 81.47 65.32 44.15 54.17 0.00 12817.16 261.030 13078.190
31 46.0 0.00 0.00 0.00 0.04 1.91 37.41 137.52 38.85 2.58 0.00 0.00 0.00 133.42 165.69 338.73 403.99 640.67 2190.97 5424.22 1680.07 615.24 470.61 269.33 139.77 140.19 105.14 114.06 97.98 73.58 130.02 127.11 0.00 13479.09 261.030 13740.124
32 41.0 0.00 0.00 0.00 0.03 1.51 34.20 109.39 31.66 2.18 0.00 0.00 0.00 99.62 133.42 269.33 338.73 559.44 1963.11 5199.60 1752.64 686.65 538.94 403.99 165.69 192.76 140.19 162.94 137.18 110.37 216.70 305.07 41.79 0.00 13597.12 261.030 13858.149
33 36.0 0.00 0.00 0.00 0.03 1.31 27.07 100.02 25.18 1.77 0.00 0.00 0.00 74.72 99.62 216.87 269.33 469.06 1714.21 4658.84 1680.07 716.31 601.50 462.65 248.54 228.50 192.76 217.25 195.97 154.52 325.05 508.45 100.29 17.71 0.00 13307.59 261.030 13568.622
34 31.0 0.00 0.00 0.00 0.02 1.11 23.51 79.18 23.02 1.41 0.00 0.00 0.00 60.23 74.72 161.93 216.87 372.96 1437.27 4068.17 1505.34 686.65 627.48 516.35 284.63 342.75 228.50 298.72 261.29 220.74 455.07 762.67 167.16 42.50 15.64 0.00 12935.89 261.030 13196.923
35 26.0 0.00 0.00 0.00 0.02 0.92 19.95 68.76 18.23 1.29 0.00 0.00 0.00 48.79 60.23 121.45 161.93 300.31 1142.81 3410.94 1314.48 615.24 601.50 538.66 317.67 392.52 342.75 354.12 359.27 294.32 650.10 1067.74 250.74 70.83 37.54 13.58 0.00 12576.66 261.030 12837.692
36 21.0 0.00 0.00 0.00 0.02 0.82 16.39 58.34 15.83 1.02 0.00 0.00 0.00 41.17 48.79 97.90 121.45 224.23 920.21 2712.11 1102.12 537.23 538.94 516.35 331.39 438.08 392.52 531.18 425.90 404.68 866.80 1525.34 351.03 106.24 62.57 32.59 8.76 0.00 12430.00 261.030 12691.035
37 16.0 0.00 0.00 0.00 0.02 0.72 14.61 47.92 13.43 0.89 0.00 0.00 0.00 33.55 41.17 79.31 97.90 168.18 687.09 2183.83 876.32 450.44 470.61 462.65 317.67 457.01 438.08 608.30 638.85 479.73 1191.85 2033.78 501.47 148.74 93.85 54.31 21.03 35.46 0.00 12648.76 261.030 12909.793
38 11.0 0.00 0.00 0.00 0.01 0.62 12.82 42.72 11.03 0.75 0.00 0.00 0.00 26.68 33.55 66.92 79.31 135.57 515.32 1630.59 705.63 358.16 394.58 403.99 284.63 438.08 457.01 678.91 731.61 719.60 1412.88 2796.45 668.63 212.48 131.40 81.47 35.05 85.10 35.46 0.00 13187.01 261.030 13448.036
39 9.0 0.00 0.00 0.00 0.01 0.52 11.04 37.51 9.83 0.62 0.00 0.00 0.00 24.40 26.68 54.53 66.92 109.83 415.41 1222.95 526.87 288.39 313.74 338.73 248.54 392.52 438.08 708.24 816.52 824.08 2119.32 3315.07 919.37 283.31 187.71 114.06 52.57 141.84 85.10 49.62 0.00 14143.92 261.030 14404.946
40 6.0 0.00 0.00 0.00 0.01 0.42 9.26 32.30 8.63 0.55 0.00 0.00 0.00 19.31 24.40 43.37 54.53 92.67 336.53 985.84 395.15 215.33 252.63 269.33 208.39 342.75 392.52 678.91 851.80 919.74 2427.04 4972.60 1089.87 389.55 250.28 162.94 73.60 212.75 141.84 119.09 57.71 0.00 16031.64 261.030 16292.665
41 4.0 0.00 0.00 0.00 0.01 0.32 7.48 27.09 7.43 0.48 0.00 0.00 0.00 16.77 19.31 39.66 43.37 75.51 283.95 798.66 318.54 161.50 188.63 216.87 165.69 287.38 342.75 608.30 816.52 959.47 2708.75 5694.59 1634.80 461.79 344.13 217.25 105.14 297.86 212.75 198.48 138.51 63.78 0.00 17463.54 261.030 17724.574
42 2.0 0.00 0.00 0.00 0.00 0.22 5.70 21.88 6.24 0.42 0.00 0.00 0.00 14.23 16.77 31.39 39.66 60.06 231.37 673.87 258.06 130.19 141.47 161.93 133.42 228.50 287.38 531.18 731.61 919.74 2825.76 6355.57 1872.17 692.68 407.95 298.72 140.19 425.51 297.86 297.72 230.85 153.07 168.97 0.00 18792.31 261.030 19053.338
43 0.0 0.00 0.00 0.00 0.00 0.18 3.92 16.67 5.04 0.35 0.00 0.00 0.00 11.69 14.23 27.26 31.39 54.91 184.04 549.08 217.74 105.47 114.04 121.45 99.62 183.99 228.50 445.36 638.85 824.08 2708.75 6630.13 2089.47 793.26 611.93 354.12 192.76 567.35 425.51 416.81 346.27 255.12 405.54 383.41 0.00 20058.30 261.030 20319.328
44 0.00 0.00 0.00 0.12 3.21 11.46 3.84 0.28 0.00 0.00 0.00 10.42 11.69 23.13 27.26 43.47 168.27 436.77 177.41 88.99 92.39 97.90 74.72 137.38 183.99 354.12 535.64 719.60 2427.04 6355.57 2179.74 885.33 700.78 531.18 228.50 780.10 567.35 595.44 484.78 382.68 675.90 920.18 132.56 0.00 21049.19 261.030 21310.224
45 0.00 0.00 0.08 2.14 9.38 2.64 0.22 0.00 0.00 0.00 9.15 10.42 19.00 23.13 37.75 133.21 399.33 141.13 72.51 77.95 79.31 60.23 103.04 137.38 285.14 425.90 603.35 2119.32 5694.59 2089.47 923.58 782.12 608.30 342.75 924.77 780.10 793.92 692.54 535.76 1013.85 1533.63 318.15 61.76 0.00 21847.00 261.030 22108.030
46 0.00 0.04 1.42 6.25 2.16 0.15 0.00 0.00 0.00 7.88 9.15 16.94 19.00 32.03 115.68 316.14 129.03 57.68 63.52 66.92 48.79 83.06 103.04 212.91 342.94 479.73 1776.94 4972.60 1872.17 885.33 815.91 678.91 392.52 1387.16 924.77 1091.64 923.39 765.37 1419.38 2300.45 530.24 148.22 55.69 0.00 23055.14 261.030 23316.169
47 0.00 0.71 4.17 1.44 0.12 0.00 0.00 0.00 6.61 7.88 14.87 16.94 26.31 98.16 274.54 102.15 52.73 50.53 54.53 41.17 67.29 83.06 159.68 256.06 386.29 1412.88 4169.26 1634.80 793.26 782.12 708.24 438.08 1588.57 1387.16 1294.09 1269.66 1020.49 2027.69 3220.62 795.37 247.03 133.65 49.62 0.00 24677.81 261.030 24938.842
48 0.00 2.08 0.96 0.08 0.00 0.00 0.00 5.34 6.61 12.81 14.87 23.45 80.63 232.94 88.71 41.75 46.20 43.37 33.55 56.78 67.29 128.72 192.05 288.43 1137.67 3315.07 1370.69 692.68 700.78 678.91 457.01 1772.96 1588.57 1941.13 1505.12 1403.17 2703.59 4600.89 1113.51 370.55 222.75 119.09 35.46 27096.20 261.030 27357.231
49 0.00 0.48 0.05 0.00 0.00 0.00 4.07 5.34 10.74 12.81 20.59 71.86 191.35 75.27 36.26 36.57 39.66 26.68 46.26 56.78 104.28 154.81 216.32 849.46 2669.34 1089.87 580.78 611.93 608.30 438.08 1849.55 1772.96 2222.97 2257.68 1663.40 3717.43 6134.52 1590.73 518.76 334.13 198.48 85.10 30303.65 261.030 30564.683
50 0.00 0.03 0.00 0.00 0.00 2.80 4.07 8.67 10.74 17.73 63.10 170.55 61.83 30.76 31.76 31.39 24.40 36.80 46.26 87.99 125.42 174.38 637.10 1993.11 877.58 461.79 513.07 531.18 392.52 1772.96 1849.55 2480.99 2585.48 2495.09 4406.85 8434.97 2120.98 741.09 467.79 297.72 141.84 34130.31 261.030 34391.344
51 0.00 0.00 0.00 0.00 2.29 2.80 6.61 8.67 14.87 54.34 149.75 55.11 25.27 26.95 27.26 19.31 33.64 36.80 71.69 105.82 141.27 513.58 1494.83 655.26 371.84 407.95 445.36 342.75 1588.57 1772.96 2588.17 2885.58 2857.37 6610.27 9999.27 2916.34 988.12 668.26 416.81 212.75 38518.52 261.030 38779.549
52 0.00 0.00 0.00 1.52 2.29 4.54 6.61 12.01 45.57 128.95 48.39 22.52 22.14 23.13 16.77 26.64 33.64 57.03 86.23 119.20 416.06 1205.02 491.44 277.64 328.49 354.12 287.38 1387.16 1588.57 2480.99 3010.24 3189.03 7570.05 14998.91 3457.19 1358.67 891.02 595.44 297.86 44842.46 261.030 45103.486
53 0.00 0.00 1.02 1.52 3.72 4.54 9.15 36.81 108.15 41.67 19.78 19.73 19.00 14.23 23.13 26.64 52.14 68.59 97.12 351.05 976.22 396.16 208.23 245.27 285.14 228.50 1163.06 1387.16 2222.97 2885.58 3326.79 8448.71 17176.67 5185.79 1610.64 1225.15 793.92 425.51 49089.47 261.030 49350.500
54 0.00 0.51 1.02 2.48 3.72 6.29 28.04 87.35 34.95 17.03 17.32 16.94 11.69 19.63 23.13 41.28 62.71 77.26 286.04 823.68 320.94 167.86 183.95 212.91 183.99 924.77 1163.06 1941.13 2585.48 3189.03 8813.70 19170.39 5938.74 2415.96 1452.36 1091.64 567.35 51884.31 261.030 52145.341
55 0.00 0.51 1.65 2.48 5.15 19.28 66.55 28.23 14.28 14.92 14.87 10.42 16.12 19.63 35.85 49.64 70.64 227.53 671.15 270.80 135.99 148.29 159.68 137.38 744.64 924.77 1627.53 2257.68 2857.37 8448.71 19998.55 6628.05 2766.74 2178.54 1294.09 780.10 52627.81 261.030 52888.837
56 0.00 0.83 1.65 3.43 15.77 45.76 21.50 11.54 12.51 12.81 9.15 14.37 16.12 30.42 43.11 55.92 208.03 533.87 220.65 114.74 120.13 128.72 103.04 556.00 744.64 1294.09 1892.94 2495.09 7570.05 19170.39 6914.39 3087.88 2494.85 1941.13 924.77 50810.28 261.030 51071.31
57 0.00 0.83 2.29 10.52 37.44 14.78 8.79 10.11 10.74 7.88 12.62 14.37 24.98 36.58 48.56 164.69 488.11 175.52 93.49 101.36 104.28 83.06 417.00 556.00 1042.02 1505.12 2092.00 6610.27 17176.67 6628.05 3221.28 2784.44 2222.97 1387.16 47093.96 261.030 47354.989
58 0.00 1.14 7.01 24.96 12.10 6.04 7.70 8.67 6.61 10.86 12.62 22.27 30.05 41.20 143.02 386.42 160.47 74.37 82.59 87.99 67.29 336.15 417.00 778.04 1211.94 1663.40 5542.36 14998.91 5938.74 3087.88 2904.72 2480.99 1588.57 42142.08 261.030 42403.111
59 0.00 3.51 16.64 8.06 4.94 5.29 6.61 5.34 9.11 10.86 19.55 26.78 33.85 121.35 335.57 127.04 67.99 65.70 71.69 56.78 272.33 336.15 583.53 904.92 1339.39 4406.85 12575.77 5185.79 2766.74 2784.44 2588.17 1772.96 36513.71 261.030 36774.737
60 0.00 8.32 5.38 3.30 4.33 4.54 4.07 7.36 9.11 16.84 23.52 30.17 99.68 284.73 110.32 53.83 60.07 57.03 46.26 229.78 272.33 470.40 678.69 1000.08 3548.46 9999.27 4348.00 2415.96 2494.85 2480.99 1849.55 30617.20 261.030 30878.228
61 0.00 2.69 2.20 2.89 3.72 2.80 5.61 7.36 14.12 20.25 26.49 88.85 233.89 93.61 46.75 47.55 52.14 36.80 187.22 229.78 381.08 547.11 750.06 2649.52 8051.56 3457.19 2025.65 2178.54 2222.97 1772.96 25141.32 261.030 25402.354
62 0.00 1.10 1.92 2.48 2.29 3.86 5.61 11.41 16.98 22.81 78.01 208.46 76.89 39.66 41.30 41.28 33.64 148.93 187.22 321.54 443.23 604.64 1987.14 6011.83 2783.78 1610.64 1826.59 1941.13 1588.57 20042.93 261.030 20303.961
63 0.00 0.96 1.65 1.52 3.15 3.86 8.69 13.72 19.13 67.18 183.04 68.53 32.58 35.04 35.85 26.64 136.16 148.93 261.99 373.97 489.83 1601.88 4508.87 2078.56 1296.91 1452.36 1627.53 1387.16 15865.70 261.030 16126.732
64 0.00 0.83 1.02 2.10 3.15 5.97 10.45 15.45 56.34 157.62 60.18 29.04 28.78 30.42 23.13 107.80 136.16 208.40 304.72 413.30 1297.72 3634.71 1558.92 968.36 1169.46 1294.09 1163.06 12681.17 261.030 12942.201
65 0.00 0.51 1.40 2.10 4.89 7.19 11.77 45.51 132.20 51.82 25.50 25.65 24.98 19.63 93.61 107.80 190.54 242.39 336.76 1094.95 2944.57 1256.68 726.27 873.20 1042.02 924.77 10186.70 261.030 10447.733
66 0.00 0.70 1.40 3.26 5.88 8.09 34.67 106.77 43.46 21.96 22.53 22.27 16.12 79.43 93.61 150.84 221.61 267.88 892.18 2484.48 1018.07 585.46 654.90 778.04 744.64 8258.26 261.030 8519.295
67 0.00 0.70 2.17 3.92 6.62 23.84 81.35 35.10 18.41 19.40 19.55 14.37 65.24 79.43 131.00 175.44 244.92 709.69 2024.39 859.00 474.30 527.93 583.53 556.00 6656.31 261.030 6917.336
68 0.00 1.09 2.61 4.41 19.50 55.93 26.75 14.87 16.27 16.84 12.62 58.15 65.24 111.15 152.36 193.89 648.86 1610.31 699.92 400.19 427.69 470.40 417.00 5426.05 261.030 5687.084
69 0.00 1.31 2.94 13.00 45.76 18.39 11.33 13.14 14.12 10.86 51.06 58.15 91.30 129.27 168.38 513.68 1472.29 556.76 326.08 360.86 381.08 336.15 4575.93 261.030 4836.956
70 0.00 1.47 8.67 30.51 15.04 7.79 10.01 11.41 9.11 43.97 51.06 81.38 106.19 142.87 446.09 1165.56 509.03 259.38 294.04 321.54 272.33 3787.44 261.030 4048.472
71 0.00 4.33 20.34 10.03 6.37 6.88 8.69 7.36 36.88 43.97 71.45 94.65 117.36 378.50 1012.20 402.99 237.15 233.89 261.99 229.78 3184.80 261.030 3445.835
72 0.00 10.17 6.69 4.25 5.63 5.97 5.61 29.79 36.88 61.53 83.10 104.60 310.91 858.83 349.96 187.74 213.84 208.40 187.22 2671.14 261.030 2932.167
73 0.00 3.34 2.83 3.75 4.89 3.86 22.69 29.79 51.60 71.56 91.84 277.12 705.47 296.94 163.04 169.29 190.54 148.93 2237.49 261.030 2498.521
74 0.00 1.42 2.50 3.26 3.15 15.60 22.69 41.68 60.02 79.09 243.32 628.79 243.91 138.34 147.02 150.84 136.16 1917.80 261.030 2178.833
75 0.00 1.25 2.17 2.10 12.77 15.60 31.76 48.48 66.33 209.53 552.11 217.40 113.63 124.74 131.00 107.80 1636.66 261.030 1897.694
76 0.00 1.09 1.40 8.51 12.77 21.83 36.94 53.58 175.73 475.43 190.89 101.28 102.47 111.15 93.61 1386.66 261.030 1647.694
77 0.00 0.70 5.67 8.51 17.86 25.39 40.82 141.94 398.74 164.38 88.93 91.33 91.30 79.43 1155.01 261.030 1416.038
78 0.00 2.84 5.67 11.91 20.78 28.06 108.14 322.06 137.86 76.58 80.19 81.38 65.24 940.72 261.030 1201.751
79 0.00 2.84 7.94 13.85 22.96 74.35 245.38 111.35 64.23 69.05 71.45 58.15 741.56 261.030 1002.586
80 0.00 3.97 9.23 15.31 60.83 168.70 84.84 51.88 57.92 61.53 51.06 565.26 261.030 826.292
81 0.00 4.62 10.20 40.55 138.03 58.33 39.52 46.78 51.60 43.97 433.61 261.030 694.637
82 0.00 5.10 27.04 92.02 47.72 27.17 35.64 41.68 36.88 313.25 261.030 574.280
83 0.00 13.52 61.35 31.81 22.23 24.50 31.76 29.79 214.96 261.030 475.986
84 0.00 30.67 21.21 14.82 20.05 21.83 22.69 131.28 261.030 392.309
85 0.00 10.60 9.88 13.37 17.86 15.60 67.32 261.030 328.347
86 0.00 4.94 8.91 11.91 12.77 38.52 261.030 299.555
87 0.00 4.46 7.94 8.51 20.90 261.030 281.934
88 0.00 3.97 5.67 9.64 261.030 270.673
89 0.00 2.84 2.84 261.030 263.867
52889
ANNEXURE-VI-6
Table -1
Sedimentation study for Guntawada Reservoir
Gross Capacity of Reservoir (C) upto FRL 739.92 MCM
1.9
Fig.1: Reservoir Type Classification
1.8
1.7
1.6
1.5
1.4
y = 0.7386x - 1.0005
1.3 R² = 0.9609
1.2
1.1
1.0
0.9
Log (Depth)
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0 0.5 1 1.5 2 2.5 3 3.5 4
Log (Capacity)
Table-2.1
Sediment Deposition ( Empeirical Area Reduction Method)
( for 100 years)
Stream Bed Elevation 396.2 m K= 1166.41
Maximum noraml water surface elevation 426.7 m
Total Sediment 289.20 MCM
Acc. Acc.
S. Original Realtive Sediment Sediment Revised
Elevation Original Area Depth Ap Type-II Sediment sediment Revised Area
No. Capacity depth Area Volume Capacity
Volume Volume
(m) (ha) (Mm3) (m) (ha) (ham) (ham) (MCM) (ha) (Mm3)
1 457.20 21789.59 4972.44 60.96 1.0000 0.0000 0.000 6.320 28920.000 289.20 21789.59 4683.24
2 455.68 20940.07 4658.12 59.44 0.9750 0.0107 12.441 32.512 28913.680 289.14 20927.63 4368.99
3 454.15 20090.55 4345.79 57.91 0.9500 0.0272 31.700 65.215 28881.168 288.81 20058.85 4056.98
4 452.63 19241.04 4046.19 56.39 0.9250 0.0471 54.943 103.193 28815.953 288.16 19186.09 3758.04
5 451.10 18391.52 3759.35 54.86 0.9000 0.0697 81.341 145.591 28712.760 287.13 18310.18 3472.22
6 449.58 17542.00 3485.52 53.34 0.8750 0.0947 110.465 191.921 28567.169 285.67 17431.54 3199.85
7 448.06 16692.49 3225.01 51.82 0.8500 0.1218 142.061 241.876 28375.247 283.75 16550.42 2941.25
8 446.53 15842.97 2976.95 50.29 0.8250 0.1509 175.965 295.254 28133.372 281.33 15667.00 2695.62
9 445.01 14993.45 2741.92 48.77 0.8000 0.1818 212.068 351.925 27838.118 278.38 14781.38 2463.54
10 443.48 14143.94 2519.92 47.24 0.7750 0.2146 250.304 411.810 27486.192 274.86 13893.63 2245.05
11 441.96 13294.42 2285.45 45.72 0.7500 0.2492 290.631 474.867 27074.382 270.74 13003.79 2014.71
12 440.44 12697.68 2115.55 44.20 0.7250 0.2855 333.035 541.086 26599.515 266.00 12364.65 1849.56
13 438.91 12100.69 1923.85 42.67 0.7000 0.3237 377.517 610.486 26058.429 260.58 11723.18 1663.26
14 437.39 11503.96 1743.75 41.15 0.6750 0.3636 424.098 683.111 25447.942 254.48 11079.86 1489.27
15 435.86 10906.97 1573.28 39.62 0.6500 0.4054 472.815 759.030 24764.831 247.65 10434.15 1325.64
16 434.34 10310.23 1411.88 38.10 0.6250 0.4490 523.721 838.337 24005.801 240.06 9786.51 1171.82
17 432.82 9713.24 1264.91 36.58 0.6000 0.4946 576.887 921.154 23167.464 231.67 9136.35 1033.24
18 431.29 9116.51 1115.68 35.05 0.5750 0.5422 632.401 1007.629 22246.310 222.46 8484.10 893.22
19 429.77 8519.51 981.46 33.53 0.5500 0.5919 690.371 1097.946 21238.680 212.39 7829.14 769.08
20 428.24 7922.78 856.02 32.00 0.5250 0.6438 750.927 1192.323 20140.734 201.41 7171.85 654.61
21 426.72 7325.79 739.92 30.48 0.5000 0.6981 814.227 1291.021 18948.412 189.48 6511.56 550.44
22 425.20 6736.05 632.60 28.96 0.4750 0.7548 880.458 1394.354 17657.391 176.57 5855.59 456.02
23 423.67 6146.31 506.02 27.43 0.4500 0.8143 949.842 1502.695 16263.037 162.63 5196.46 343.39
24 422.15 5556.56 445.14 25.91 0.4250 0.8768 1022.648 1616.496 14760.342 147.603 4533.92 297.54
25 420.62 4966.82 365.00 24.38 0.4000 0.9424 1099.198 1736.299 13143.846 131.438 3867.63 233.57
26 419.10 4377.08 293.65 22.86 0.3750 1.0116 1179.885 1862.768 11407.547 114.075 3197.20 179.57
27 417.58 3787.34 231.63 21.34 0.3500 1.0847 1265.188 1996.722 9544.779 95.448 2522.15 136.18
28 416.05 3197.60 178.40 19.81 0.3250 1.1623 1355.703 2139.183 7548.057 75.481 1841.90 102.92
29 414.53 2607.86 134.22 18.29 0.3000 1.2450 1452.176 2291.447 5408.874 54.089 1155.68 80.13
30 413.00 2018.12 98.83 16.76 0.2750 1.3336 1555.565 1601.734 3117.427 31.174 462.56 67.65
32 412.00 1628.21 81.44 15.76 0.2585 1.3959 1628.211 790.471 1515.693 15.157 0.000 66.281
31 411.48 1427.60 72.49 15.24 0.2500 1.4293 1427.602 725.222 725.222 7.252 0.00 65.24
33 409.96 0.00 50.97 13.72 0.2250 1.5333 0.000 0.000 0.000 0.000 0.00 50.97
34 408.43 0.00 35.40 12.19 0.2000 1.6478 0.000 0.000 0.000 0.000 0.00 35.40
35 406.91 0.00 28.03 10.67 0.1750 1.7754 0.000 0.000 0.000 0.000 0.00 28.03
36 402.34 0.00 15.57 6.10 0.1000 2.2946 0.000 0.000 0.000 0.000 0.00 15.57
37 396.24 0.00 0.00 0.00 0.0000 #DIV/0! 0.000 0.000 0.000 0.000 0.00 0.00
ANNEXURE-VI-6
Area (ha)
30000.0 25000.0 20000.0 15000.0 10000.0 5000.0 0.0
500 500
RevisedArea
Revised Capacity
450 450
400 400
Original Capacity
Elevation (m)
Elevation (m)
Original Area
350 350
300 300
250 250
200 200
Capacity (MCM)
ANNEXURE-VI-6
Table-2.1
Sediment Deposition ( Empeirical Area Reduction Method)
( for 70 years)
Stream Bed Elevation 396.2 m K= 802.27
Maximum noraml water surface elevation 426.7 m
Total Sediment 202.44 MCM
Acc. Acc.
S. Original Realtive Sediment Sediment Revised
Elevation Original Area Depth Ap Type-II Sediment sediment Revised Area
No. Capacity depth Area Volume Capacity
Volume Volume
(m) (ha) (Mm3) (m) (ha) (ham) (ham) (MCM) (ha) (Mm3)
1 457.20 21789.59 4972.44 60.96 1.0000 0.0000 0.000 4.347 20244.000 202.44 21789.59 4770.00
2 455.68 20940.07 4658.12 59.44 0.9750 0.0107 8.557 22.362 20239.653 202.40 20931.51 4455.73
3 454.15 20090.55 4345.79 57.91 0.9500 0.0272 21.804 44.856 20217.291 202.17 20068.75 4143.61
4 452.63 19241.04 4046.19 56.39 0.9250 0.0471 37.791 70.978 20172.435 201.72 19203.24 3844.47
5 451.10 18391.52 3759.35 54.86 0.9000 0.0697 55.947 100.140 20101.457 201.01 18335.57 3558.33
6 449.58 17542.00 3485.52 53.34 0.8750 0.0947 75.980 132.007 20001.317 200.01 17466.02 3285.51
7 448.06 16692.49 3225.01 51.82 0.8500 0.1218 97.712 166.366 19869.310 198.69 16594.77 3026.31
8 446.53 15842.97 2976.95 50.29 0.8250 0.1509 121.031 203.080 19702.944 197.03 15721.94 2779.92
9 445.01 14993.45 2741.92 48.77 0.8000 0.1818 145.864 242.060 19499.864 195.00 14847.59 2546.92
10 443.48 14143.94 2519.92 47.24 0.7750 0.2146 172.163 283.250 19257.804 192.58 13971.77 2327.34
11 441.96 13294.42 2285.45 45.72 0.7500 0.2492 199.901 326.621 18974.554 189.75 13094.52 2095.71
12 440.44 12697.68 2115.55 44.20 0.7250 0.2855 229.067 372.168 18647.933 186.48 12468.62 1929.07
13 438.91 12100.69 1923.85 42.67 0.7000 0.3237 259.662 419.902 18275.765 182.76 11841.03 1741.09
14 437.39 11503.96 1743.75 41.15 0.6750 0.3636 291.701 469.855 17855.863 178.56 11212.26 1565.19
15 435.86 10906.97 1573.28 39.62 0.6500 0.4054 325.210 522.073 17386.008 173.86 10581.76 1399.42
16 434.34 10310.23 1411.88 38.10 0.6250 0.4490 360.224 576.622 16863.935 168.64 9950.01 1243.24
17 432.82 9713.24 1264.91 36.58 0.6000 0.4946 396.792 633.584 16287.313 162.87 9316.45 1102.04
18 431.29 9116.51 1115.68 35.05 0.5750 0.5422 434.976 693.064 15653.728 156.54 8681.53 959.15
19 429.77 8519.51 981.46 33.53 0.5500 0.5919 474.848 755.185 14960.665 149.61 8044.66 831.86
20 428.24 7922.78 856.02 32.00 0.5250 0.6438 516.500 820.099 14205.480 142.05 7406.28 713.96
21 426.72 7325.79 739.92 30.48 0.5000 0.6981 560.039 887.985 13385.381 133.85 6765.75 606.07
22 425.20 6736.05 632.60 28.96 0.4750 0.7548 605.593 959.059 12497.396 124.97 6130.45 507.62
23 423.67 6146.31 506.02 27.43 0.4500 0.8143 653.316 1033.578 11538.337 115.38 5492.99 390.64
24 422.15 5556.56 445.14 25.91 0.4250 0.8768 703.394 1111.852 10504.759 105.048 4853.17 340.09
25 420.62 4966.82 365.00 24.38 0.4000 0.9424 756.046 1194.254 9392.907 93.929 4210.78 271.08
26 419.10 4377.08 293.65 22.86 0.3750 1.0116 811.544 1281.242 8198.653 81.987 3565.54 211.66
27 417.58 3787.34 231.63 21.34 0.3500 1.0847 870.217 1373.378 6917.411 69.174 2917.13 162.46
28 416.05 3197.60 178.40 19.81 0.3250 1.1623 932.474 1471.365 5544.033 55.440 2265.13 122.96
29 414.53 2607.86 134.22 18.29 0.3000 1.2450 998.830 1576.094 4072.669 40.727 1609.03 93.50
30 413.00 2018.12 98.83 16.76 0.2750 1.3336 1069.942 1688.720 2496.574 24.966 948.18 73.86
31 411.48 1427.60 72.49 15.24 0.2500 1.4293 1146.668 327.657 807.854 8.079 280.93 64.41
32 411.20 1161.67 68.48 14.96 0.2453 1.4480 1161.667 480.198 480.198 4.802 0.000 63.680
33 409.96 0.00 50.97 13.72 0.2250 1.5333 0.000 0.000 0.000 0.000 0.00 50.97
34 408.43 0.00 35.40 12.19 0.2000 1.6478 0.000 0.000 0.000 0.000 0.00 35.40
35 406.91 0.00 28.03 10.67 0.1750 1.7754 0.000 0.000 0.000 0.000 0.00 28.03
36 402.34 0.00 15.57 6.10 0.1000 2.2946 0.000 0.000 0.000 0.000 0.00 15.57
37 396.24 0.00 0.00 0.00 0.0000 #DIV/0! 0.000 0.000 0.000 0.000 0.00 0.00
ANNEXURE-VI-6
Area (ha)
30000.0 25000.0 20000.0 15000.0 10000.0 5000.0 0.0
500 500
RevisedArea
Revised Capacity
450 450
400 400
Original Capacity
Elevation (m)
Elevation (m)
Original Area
350 350
300 300
250 250
200 200
Capacity (MCM)
ANNEXURE-VI-6
Table-2.1
Sediment Deposition ( Empeirical Area Reduction Method)
( for 50 years)
Stream Bed Elevation 396.2 m K= 565.19
Maximum noraml water surface elevation 426.7 m
Total Sediment 144.60 MCM
Acc. Acc.
S. Original Realtive Sediment Sediment Revised
Elevation Original Area Depth Ap Type-II Sediment sediment Revised Area
No. Capacity depth Area Volume Capacity
Volume Volume
(m) (ha) (Mm3) (m) (ha) (ham) (ham) (MCM) (ha) (Mm3)
1 457.20 21789.59 4972.44 60.96 1.0000 0.0000 0.000 3.062 14460.000 144.60 21789.59 4827.84
2 455.68 20940.07 4658.12 59.44 0.9750 0.0107 6.028 15.754 14456.938 144.57 20934.04 4513.55
3 454.15 20090.55 4345.79 57.91 0.9500 0.0272 15.360 31.600 14441.184 144.41 20075.19 4201.38
4 452.63 19241.04 4046.19 56.39 0.9250 0.0471 26.623 50.002 14409.583 144.10 19214.41 3902.10
5 451.10 18391.52 3759.35 54.86 0.9000 0.0697 39.414 70.547 14359.581 143.60 18352.11 3615.75
6 449.58 17542.00 3485.52 53.34 0.8750 0.0947 53.526 92.996 14289.034 142.89 17488.48 3342.63
7 448.06 16692.49 3225.01 51.82 0.8500 0.1218 68.836 117.202 14196.038 141.96 16623.65 3083.05
8 446.53 15842.97 2976.95 50.29 0.8250 0.1509 85.264 143.066 14078.837 140.79 15757.70 2836.16
9 445.01 14993.45 2741.92 48.77 0.8000 0.1818 102.758 170.527 13935.770 139.36 14890.69 2602.56
10 443.48 14143.94 2519.92 47.24 0.7750 0.2146 121.286 199.544 13765.244 137.65 14022.65 2382.26
11 441.96 13294.42 2285.45 45.72 0.7500 0.2492 140.826 230.098 13565.700 135.66 13153.59 2149.80
12 440.44 12697.68 2115.55 44.20 0.7250 0.2855 161.373 262.185 13335.601 133.36 12536.31 1982.20
13 438.91 12100.69 1923.85 42.67 0.7000 0.3237 182.927 295.813 13073.416 130.73 11917.77 1793.11
14 437.39 11503.96 1743.75 41.15 0.6750 0.3636 205.498 331.004 12777.603 127.78 11298.46 1615.98
15 435.86 10906.97 1573.28 39.62 0.6500 0.4054 229.104 367.791 12446.599 124.47 10677.86 1448.82
16 434.34 10310.23 1411.88 38.10 0.6250 0.4490 253.771 406.219 12078.808 120.79 10056.46 1291.09
17 432.82 9713.24 1264.91 36.58 0.6000 0.4946 279.533 446.348 11672.589 116.73 9433.71 1148.19
18 431.29 9116.51 1115.68 35.05 0.5750 0.5422 306.432 488.250 11226.241 112.26 8810.07 1003.42
19 429.77 8519.51 981.46 33.53 0.5500 0.5919 334.522 532.013 10737.991 107.38 8184.99 874.08
20 428.24 7922.78 856.02 32.00 0.5250 0.6438 363.864 577.744 10205.977 102.06 7558.91 753.96
21 426.72 7325.79 739.92 30.48 0.5000 0.6981 394.537 625.569 9628.233 96.28 6931.25 643.64
22 425.20 6736.05 632.60 28.96 0.4750 0.7548 426.629 675.639 9002.665 90.03 6309.42 542.57
23 423.67 6146.31 506.02 27.43 0.4500 0.8143 460.249 728.136 8327.026 83.27 5686.06 422.75
24 422.15 5556.56 445.14 25.91 0.4250 0.8768 495.527 783.278 7598.890 75.989 5061.04 369.15
25 420.62 4966.82 365.00 24.38 0.4000 0.9424 532.620 841.329 6815.611 68.156 4434.20 296.85
26 419.10 4377.08 293.65 22.86 0.3750 1.0116 571.717 902.611 5974.282 59.743 3805.37 233.90
27 417.58 3787.34 231.63 21.34 0.3500 1.0847 613.051 967.519 5071.671 50.717 3174.29 180.92
28 416.05 3197.60 178.40 19.81 0.3250 1.1623 656.910 1036.548 4104.153 41.042 2540.69 137.35
29 414.53 2607.86 134.22 18.29 0.3000 1.2450 703.657 1110.329 3067.604 30.676 1904.20 103.55
30 413.00 2018.12 98.83 16.76 0.2750 1.3336 753.754 1189.671 1957.276 19.573 1264.37 79.25
31 411.48 1427.60 72.49 15.24 0.2500 1.4293 807.806 521.448 767.604 7.676 619.80 64.82
32 410.84 831.72 63.51 14.60 0.2396 1.4716 831.720 246.156 246.156 2.462 0.000 61.047
33 409.96 0.00 50.97 13.72 0.2250 1.5333 0.000 0.000 0.000 0.000 0.00 50.97
34 408.43 0.00 35.40 12.19 0.2000 1.6478 0.000 0.000 0.000 0.000 0.00 35.40
35 406.91 0.00 28.03 10.67 0.1750 1.7754 0.000 0.000 0.000 0.000 0.00 28.03
36 402.34 0.00 15.57 6.10 0.1000 2.2946 0.000 0.000 0.000 0.000 0.00 15.57
37 396.24 0.00 0.00 0.00 0.0000 #DIV/0! 0.000 0.000 0.000 0.000 0.00 0.00
ANNEXURE-VI-6
Area (ha)
30000.0 25000.0 20000.0 15000.0 10000.0 5000.0 0.0
500 500
RevisedArea
Revised Capacity
450 450
400 400
Original Capacity
Elevation (m)
Elevation (m)
Original Area
350 350
300 300
250 250
200 200
Capacity (MCM)
ANNEXURE-VI-6
Table-2.1
Sediment Deposition ( Empeirical Area Reduction Method)
( for 25 years)
Stream Bed Elevation 396.2 m K= 277.76
Maximum noraml water surface elevation 426.7 m
Total Sediment 72.30 MCM
Acc. Acc.
S. Original Realtive Sediment Sediment Revised
Elevation Original Area Depth Ap Type-II Sediment sediment Revised Area
No. Capacity depth Area Volume Capacity
Volume Volume
(m) (ha) (Mm3) (m) (ha) (ham) (ham) (MCM) (ha) (Mm3)
1 457.20 21789.59 4972.44 60.96 1.0000 0.0000 0.000 1.505 7230.000 72.30 21789.59 4900.14
2 455.68 20940.07 4658.12 59.44 0.9750 0.0107 2.963 7.742 7228.495 72.28 20937.11 4585.84
3 454.15 20090.55 4345.79 57.91 0.9500 0.0272 7.549 15.530 7220.753 72.21 20083.00 4273.58
4 452.63 19241.04 4046.19 56.39 0.9250 0.0471 13.084 24.573 7205.223 72.05 19227.95 3974.14
5 451.10 18391.52 3759.35 54.86 0.9000 0.0697 19.370 34.670 7180.650 71.81 18372.15 3687.54
6 449.58 17542.00 3485.52 53.34 0.8750 0.0947 26.305 45.702 7145.980 71.46 17515.70 3414.06
7 448.06 16692.49 3225.01 51.82 0.8500 0.1218 33.829 57.598 7100.278 71.00 16658.66 3154.00
8 446.53 15842.97 2976.95 50.29 0.8250 0.1509 41.902 70.309 7042.680 70.43 15801.07 2906.52
9 445.01 14993.45 2741.92 48.77 0.8000 0.1818 50.500 83.804 6972.372 69.72 14942.95 2672.20
10 443.48 14143.94 2519.92 47.24 0.7750 0.2146 59.605 98.064 6888.568 68.89 14084.33 2451.03
11 441.96 13294.42 2285.45 45.72 0.7500 0.2492 69.208 113.080 6790.504 67.91 13225.21 2217.55
12 440.44 12697.68 2115.55 44.20 0.7250 0.2855 79.305 128.849 6677.424 66.77 12618.38 2048.78
13 438.91 12100.69 1923.85 42.67 0.7000 0.3237 89.898 145.375 6548.575 65.49 12010.79 1858.36
14 437.39 11503.96 1743.75 41.15 0.6750 0.3636 100.990 162.669 6403.200 64.03 11402.97 1679.72
15 435.86 10906.97 1573.28 39.62 0.6500 0.4054 112.591 180.748 6240.531 62.41 10794.37 1510.88
16 434.34 10310.23 1411.88 38.10 0.6250 0.4490 124.714 199.633 6059.783 60.60 10185.52 1351.28
17 432.82 9713.24 1264.91 36.58 0.6000 0.4946 137.374 219.354 5860.150 58.60 9575.87 1206.31
18 431.29 9116.51 1115.68 35.05 0.5750 0.5422 150.593 239.947 5640.796 56.41 8965.91 1059.28
19 429.77 8519.51 981.46 33.53 0.5500 0.5919 164.398 261.454 5400.849 54.01 8355.12 927.45
20 428.24 7922.78 856.02 32.00 0.5250 0.6438 178.818 283.927 5139.396 51.39 7743.96 804.62
21 426.72 7325.79 739.92 30.48 0.5000 0.6981 193.892 307.430 4855.468 48.55 7131.89 691.36
22 425.20 6736.05 632.60 28.96 0.4750 0.7548 209.663 332.037 4548.038 45.48 6526.38 587.12
23 423.67 6146.31 506.02 27.43 0.4500 0.8143 226.186 357.836 4216.001 42.16 5920.12 463.86
24 422.15 5556.56 445.14 25.91 0.4250 0.8768 243.523 384.936 3858.164 38.582 5313.04 406.56
25 420.62 4966.82 365.00 24.38 0.4000 0.9424 261.752 413.464 3473.229 34.732 4705.07 330.27
26 419.10 4377.08 293.65 22.86 0.3750 1.0116 280.966 443.580 3059.764 30.598 4096.12 263.05
27 417.58 3787.34 231.63 21.34 0.3500 1.0847 301.279 475.479 2616.184 26.162 3486.06 205.47
28 416.05 3197.60 178.40 19.81 0.3250 1.1623 322.833 509.403 2140.705 21.407 2874.77 156.99
29 414.53 2607.86 134.22 18.29 0.3000 1.2450 345.806 545.662 1631.302 16.313 2262.05 117.91
30 413.00 2018.12 98.83 16.76 0.2750 1.3336 370.426 584.654 1085.640 10.856 1647.69 87.97
31 411.48 1427.60 72.49 15.24 0.2500 1.4293 396.990 439.057 500.986 5.010 1030.61 67.48
32 410.40 417.18 57.26 14.16 0.2323 1.5020 417.176 61.929 61.929 0.619 0.000 56.640
33 409.96 0.00 50.97 13.72 0.2250 1.5333 0.000 0.000 0.000 0.000 0.00 50.97
34 408.43 0.00 35.40 12.19 0.2000 1.6478 0.000 0.000 0.000 0.000 0.00 35.40
35 406.91 0.00 28.03 10.67 0.1750 1.7754 0.000 0.000 0.000 0.000 0.00 28.03
36 402.34 0.00 15.57 6.10 0.1000 2.2946 0.000 0.000 0.000 0.000 0.00 15.57
37 396.24 0.00 0.00 0.00 0.0000 #DIV/0! 0.000 0.000 0.000 0.000 0.00 0.00
ANNEXURE-VI-6
Area (ha)
30000.0 25000.0 20000.0 15000.0 10000.0 5000.0 0.0
500 500
RevisedArea
Revised Capacity
450 450
400 400
Original Capacity
Elevation (m)
Elevation (m)
Original Area
350 350
300 300
250 250
200 200
Capacity (MCM)
CATCHMENT AREA-PROPOSED STRUCTURE AT GUNTAWADA RESERVOIR
Jalaput Dam
Balimela Dam
CHAPTER-VII
RESERVOIR
CHAPTER-VII
RESERVOIR
The Upper Sileru Pumped Storage Project is proposed and designed as a Pumped
Storage Project for power generation. A rubber dam was proposed at 7.2 km upstream
within the existing Donkarayi reservoir with a FRL of EL +316.0 m, thus, this dam will
act as a storage structure in the existing reservoir without creating a new reservoir.
Thus, no reservoir studies are carried out under this project.
CHAPTER-VIII
POWER POTENTIAL & INSTALLED CAPACITY
CHAPTER-VIII
TABLE OF CONTENTS
CHAPTER – VIII
8.1 INTRODUCTION
Sileru River is a tributary of Sabari River. It originates in Andhra Pradesh and also flows
through Odisha before merging with Sabari. Sabari River crosses the border into Andhra
Pradesh to merge with Godavari River. Sileru (known as Machkund in its upper reaches)
river joins Sabari River at tri-junction boundary point of Andhra Pradesh, Chhattisgarh and
Odisha. The river drains the Western face of Eastern Ghats and starts at an altitude of
+1645.90 m (5400 ft). It flows in a north-westernly direction upto Chikinput, where it takes
a short right angle bend and flows due South-West to its confluence with Sabari, an
Sileru river has a vast potential of hydro electricity generation which has been substantially
harnessed by constructing Machkund (120 MW), Balimela (510 MW), Upper Sileru (240
MW), Donkarayi (25 MW) and Lower Sileru hydro (460 MW) power projects. Chitrakonda
(60 MW) hydro project located at the toe of Balimela earth dam is planned to utilise the
head available across the earth dam.
The total catchment area of the Sileru River up to the proposed Upper Sileru Pumped
Storage Project Site is 5164.44 sq km (1994 sq miles). The intercepted catchment above
Machkund Diversion Dam is 2222.21 sq km (858 sq miles). The free catchment of
Guntwada reservoir is 2942.22 sq km (1136 sq miles). Based on the inflow data and the
flows used for power generation at the existing power house, review of hydrological data
was carried out for assessment of storage capacity of D/S reservoir. Operational pattern of
Pumped Storage Plant has been kept in such a way that 47.6 MCM (1.7 TMC) of water
will be utilised for the proposed pumped storage project without affecting the existing
commitments at Donkarayi Reservoir. The project is a pumped storage scheme and hence,
no consumptive utilisation of water is required for its operation. The design flood at the
Gutntawada diversion weir is 6937.63 cum/sec (2,45,000 cusec).
Actual discharge from the reservoir utilised for power genberation was collected from the
project authorities from 2001-02 to 2011-12. The average annual runoff was computed as
1987.16 Mcum. The details of flows utilised for power generation for 1999-2000 to 2017-
18 are appended in the Chapter-6-Annexer VI-1.
The Upper Sileru PSP is envisaged to utilise 47.6 MCM (1.7 TMC) of water to be pumped
to the upper reservoir in 9 hours. The project is a pumped storage scheme and hence, no
consumptive utilisation of water is required for its operation.
The existing Donkarayi reservoir is the existing reservoir, D/s of Guntwada reservoir. The
MDDL of Donkarayi reservoir is 955 ft (291.08m). The length of tail race tunnel would be
approximately 20 km if the upper sileru PSP is to be operated upto the MDDL of Donkarayi
reservoir. In order to economise the cost of construction and decrease the length of the
tunnels, a new overflow dam at 7.20 kms upstream of Donkarayi Reservoir is proposed
with an FRL of 316.00 m (1036.75 ft). Live storage of the proposed new diversion weir at
7.20 km is 1.7 TMC with an MDDL 309.00 m (1014 ft). The river shall be channelised for
a length of approx. 1Km from the exit of TRT to facilitate operation of Upper Sileru PSP
upto the proposed MDDL of 309.00 m (1014 ft) there by decreasing the length of tail race
tunnel by 15 Km. The water from Guntawada reservoir, after generation, passes through a
6 km water conductor system.
The area-capacity curve of existing Donkarayi reservoir is given below as Table 8.3.
In order to determine the area-capacity at the proposed Rubber dam, hydrographic survey
was carried out and the data is given in Table 8.4 below.
The volume of water required for turbine mode of operation is equated to the pumped
mode.
Annual energy generation by Upper Sileru PSP in Turbine mode is 3780.00 MU.
Annual energy consumption by Upper Sileru PSP in Pump mode is 4820.00 MU.
Cycle efficiency – 78.43%
Load factor in turbine mode – 27.39 %
Load factor in Pump mode – 30.82 %
During wet years PSP can be operated in turbine mode to maximize the energy production.
Rated Head is defined as that head where rated power is obtained with wicket gates fully
opened. Thus, it is the minimum head at which rated output can be obtained. A generator
is selected with a rated capacity to match the rated power output of the turbine at a specific
power factor (Usually 0.9 for large synchronous generators) Above rated head, the
generator capacity limits power output, so the unit's full rated capacity can be obtained at
all heads above rated head. Below rated head, the maximum achievable power output with
turbine gates fully open is less than rated capacity. Rated head is the minimum head at
which the turbine manufacturer guarantees rated output.
The Specific Speed of a turbine is the speed in revolutions per minute at which the turbine
would rotate, if reduced homo-logically, so that it would develop 1 Hp (1metric horse
power) under 1 meter of head at full gate. Low specific speeds are associated with high
heads and high specific speeds are associated with low heads. Moreover there is a wide
range of specific speeds, which may be suitable for a given head.
CHAPTER-IX
DESIGN OF CIVIL STRUCTURES
CHAPTER-IX
DESIGN OF CIVIL STRUCTURES
TABLE OF CONTENTS
CHAPTER-IX
DESIGN OF CIVIL STRUCTURES
9.1 GENERAL
The proposed 1350 MW (9 x 150 MW each unit) Upper Sileru pumped storage scheme
envisages utilization of water from the existing Guntawada reservoir as the upper
reservoir during generation mode and Donkarayi reservoir as the lower reservoir located
adjacent to the existing 240 MW (4 X 60 MW) Upper Sileru hydroelectric project
during the pumping mode.
The proposed Upper Sileru Pumped Storage Project (USPSP) envisages construction of
power intake to draw water for power generation mode from Guntawada reservoir. The
power intake feeds three headrace tunnels having a length of about 2746 m each
terminating at primary/ upper surge pool. The surge pool is provided to absorb hydraulic
transients during generation and pumping mode and is open to sky. Nine individual
pressure shafts having a length of about 385 m each take off from upper surge pool to
feed nine reversible pump turbines housed in a semi-underground powerhouse. From
the powerhouse, nine individual draft tube tunnels having a length of about 65 m each
carry water to the downstream or secondary surge pool. Three tailrace tunnels having a
length of about 2478 m each carry water from downstream surge pool to Lower
Donkarayi reservoir. A pump intake is provided in Donkarayi reservoir to draw water
during pumping mode. A weir is also proposed in Donkarayi reservoir to facilitate
creation of a balancing reservoir for USPSP with a storage capacity of 1.5 TMC. The
transfer of water from the existing Guntawada reservoir to the existing Donkarayi
reservoir during power generation mode and vice versa during pumping mode is
proposed corresponding to the storage capacity at downstream weir of around 1.5 TMC
or 42.5 MCM.
One number straight type power intake structure having symmetrical approach via an
approach channel has been envisaged on the existing upper Guntawada reservoir to
draw a design discharge of 1652 cumec for generation of power.
The power intake structure comprises of an independent intake located on the left side
of the existing intake for Upper Sileru Hydro Electric Project (USHEP). A common
intake structure is provided with three bell mouth inlet structure for three Head Race
Tunnels. The intake has been provided with a trash-rack structure at the upstream edge.
An approach channel for smooth diversion of flows from Guntawada reservoir to the
power intake has been proposed. The head race tunnel entry is provided with a smooth
bell mouth transition for entry of the required discharges. Each bell mouth for the power
Intake for each of the three HRTs has been designed for a discharge of 550.67 cumec
(total design discharge of 1652 cumec).
A Gate shaft has been proposed downstream of bell mouth entry at power intake for
housing the hydro mechanical Gates and their operating mechanism. Each bell mouth
entry is equipped with an independent gate shaft which is joined at the hoisting platform
level. Accordingly, there are two numbers of emergency and two numbers of service
gates for each opening with an intermediate pier. The two numbers of Gates for each
power intake shall be operated (lifting or lowering) in tandem for regulation of
discharges through each Head Race Tunnel.
FRL EL.414.50 m
MDDL EL.406.75 m
The basic considerations for finalization of the trash-rack structures are as under:
Based on the above requirements and the intake location based on site topography, an
inclined trash-rack has been proposed for the project and the design has been done as
per IS 11388: 2012 “Recommendations for Design of Trash racks for Intakes”.
Trashracks are proposed with an inclination of 800 with horizontal apron.
The inclined height of the trash-rack has been divided into 10 equal parts of size 3400
mm each while the horizontal width has been divided into fifty equal parts of 3700 mm
clear width. As such, a total of 500 nos. of metallic Trash Rack Panels of size 3.7m (W)
X 3.40 m (H) has been provided. The steel flats/bars of size 75 x 16 mm thick with
rounded edge @76mm c/c has been provided as trash bars. The clear spacing between
the trash bars shall however be verified by the supplier of the turbine machines based on
the minimum spacing's of the runner blades. Each panel of the Trash rack has been
divided into four numbers of horizontal sub panels using ISMC-400 so that the
unsupported length of the trash bars should not be more than the value permitted in IS
code & the vibration in the panel are within allowable limit.
Provision of lifting lugs in each panel has been made. All the units /panels of the trash
rack are interchangeable. The TR panels are proposed to be lifted by means of TRCM
having an auxiliary hoist equipped with an automatic lifting beam. The maintenance of
trash rack panels shall be carried out at EL.417.00 (Top of deck slab). An automatic
hydraulic trash cleaning machine for mechanical cleaning and removal of trash shall be
installed at EL. 417.00. A breast wall supported on the columns and intermediate beams
have been proposed above EL 405.00 m after justifying the net flow area requirements.
The trash panels will be supported on main piers, intermediate piers & rib beams of
reinforced concrete. For structural requirement, the width of end pier and intermediate
piers has been kept as 2.0m & 1.5m respectively.
The Pump Intake is located at the end of the tailrace tunnel located near the existing
lower Donkarayi reservoir. One number straight type pump Intake structure having
symmetrical approach has been envisaged on the Donkarayi reservoir to pump back the
design pump discharges of 1242 cumec back into the upper Guntawada reservoir.
The size and shape of the pump intake located at the end of the tail race tunnel opening
in the lower reservoir is almost similar to the power intake. The tail race tunnel inlet
entry is provided with a smooth bell mouth transition for entry of the required
discharges. Each bell mouth for the pump intake for each of the three TRTs is designed
for a discharge of 414 cumec (total 1242 cumec). The submergence depth and shape has
been worked out as explained above based on the various codal provisions and
requirements.
The following basic parameters have been considered for the hydraulic design of Pump
Intake structure:
Total No. of bell mouth Intakes Two nos. converging into one
Size of the Gate 6.0 m (W) X 12.0 m (H)
Diameter of TRT 12 m
Based on the above data and keeping the Froude number as less than 0.5, the
submergence of the C/L of the intake from MDDL works out to be as under:- As per IS
code; Submergence($) = 8.47 m, and As per Gordon's formula, Submergence(S) =
7.576 m. Accordingly the maximum of the above two values, i.e. 8.47 m has been
provided as minimum submergence. The centre line of the Bell mouth intake has
accordingly been fixed at EL 283.0 m & the sill level works out to EL.277 m. The
Centre line of the TRT at its starting has been fixed as EL. 283 m in order to keep the
soffit of the tail race tunnel at the same level as that of the Intake gates.
The trash rack supporting structure is of the similar type, shape and dimensions as that
proposed at the power intake. Accordingly, the deck slab of the trash rack supporting
structure is proposed at EL.319.00 m to match with natural ground level which is 3m
above the FRL (EL.316.00 m) at the lower reservoir. The flow in the intake will have its
entry only through the trash rack panels. A breast wall has been proposed above the
required net flow area. Access to the deck slab has been planned from the hoisting slab.
A Gate shaft has been proposed downstream of bell mouth entry at pump intake for
housing the hydro mechanical Gates and their operating mechanism. Each bell mouth
entry is equipped with an independent gate shaft which is joined at the hoisting platform
level. Accordingly, there are two numbers of emergency and two numbers of service
gates for each opening with an intermediate pier. The two numbers of Gates for each
pump intake shall be operated (lifting or lowering) in tandem for regulation of
discharges through each Tail Race Tunnel. The details of gates & their operating
mechanism are indicated in the relevant drawings.
FRL EL.316.00 m
MDDL EL.306.00 m
A trash-rack structure is proposed in front of the three bellmouth intake conduits for
TRT to prevent the entrance of any trash bigger than the smallest opening in the turbine
runner. No part of the trash-rack structure shall fall within 80% of the intake height
from the center point of the intake.
The basic considerations for finalization of the trash-rack structures are similar to those
for power intake. Based on these requirements and pump intake location based on site
topography, an inclined trash-rack has been proposed with an inclination of 800 with
horizontal apron. The inclined height of the trash-rack has been divided into 09 equal
parts of size 3700 mm each while the horizontal width has been divided into fifty equal
parts of 3700 mm clear width. As such, a total of 450 nos. of metallic Trash Rack Panels
of size 3.7m (W) X 3500 m (H) has been provided. The steel flats/bars of size 75 x 16
mm thick with rounded edge @76mm c/c has been provided as trash bars. The clear
spacing between the trash bars shall however be verified by the supplier of the turbine
machines based on the minimum spacing's of the runner blades. Each panel of the Trash
rack has been divided into four numbers of horizontal sub panels using ISMC-400 so
that the unsupported length of the trash bars should not be more than the value
permitted in IS code & the vibration in the panel are within allowable limit.
Provision of lifting lugs in each panel has been made. All the units /panels of the trash
rack are interchangeable. The TR panels are proposed to be lifted by means of TRCM
having aux. hoist equipped with an automatic lifting beam. The maintenance of trash
rack panels shall be carried out at EL.319.00 (Top of deck slab). An automatic trash
cleaning machine for mechanical cleaning and removal of trash shall be installed at EL.
319.00. A breast wall supported on the columns and intermediate beams have been
proposed above EL 304.00 m after justifying the net flow area requirements.
The trash panels will be supported on main piers, intermediate piers & rib beams of
reinforced concrete. For structural requirement, the width of end pier and intermediate
piers has been kept as 2.0m & 1.5m respectively.
The existing Guntawada reservoir with a live storage capacity of 88 mm3 created for the
USHEP is proposed to be utilized and act as the upper reservoir with downstream
Donkarayi reservoir as lower reservoir for re-utilization of waters at proposed USPSP
along with water released from present USHEP scheme. Three numbers 12 m finished
diameter horse shoe shaped and around 2746 m long Head race tunnel takes off from
the power intake at Guntawada reservoir. The proposed head race tunnel is aligned on
the Left side of the adjoining area of the existing Upper Sileru hydro electric project.
The HRT is proposed to be excavated from HRT Inlet portal, intermediate adit and adit
to upstream surge gallery near power house. HRT shall be excavated using heading and
benching approach. Rock support for HRT as per rock class encountered during actual
excavation shall be provided as per details shown in relevant drawings.
Each HRT is designed to carry a discharge of 550.67 cumec of water. Maximum flow
velocity in the concrete line HRT will be about 4.61 m/s. Minimum ground cover over
the HRT is about 46.0 m and maximum ground cover is about 140 m. The centre line of
HRT at inlet is proposed at EL. 381 m and centre line at its junction with primary surge
pool is at EL.360 m. HRT will be provided with a concrete lining of 500 mm thickness.
The construction of the underground head race tunnel is proposed to be taken up from
the power intake side after the construction of a coffer dam. However, for facilitating
the construction of primary surge pool as well as downstream reach of HRT, a
construction Adit 2 having dimensions of 8m (W) X 8m (H) D-shaped and having a
length of about 375 m is proposed at the primary or upstream surge shaft and will also
provide Access to Valve house located downstream of primary surge pool. HRT is
excavated with heading and benching method. As the HRT passes through relatively
low ground cover, possibility of occasional adverse geological condition with water
seepage is expected. Also, excavation from intake is prone to water ingress. For timely
project completion and to ensure ease of construction, an additional intermediate adit
(Adit-1) is proposed having a length of 675 m. This adit shall assist in the excavation of
HRT independently from the two sides of surge shaft end as well as the intake side.
Sound rock is expected at the portal location. The construction adits shall be supported
with rock bolts and shotcrete as per details shown in the relevant drawings. The
construction adits shall be plugged after construction.
Based on above considerations a PCC concrete lining (grade M25 A20) of 500mm
thickness is proposed to be adopted for HRT.
A surge shaft is provided to reduce the pressure surges created due to water hammer and
to limit its further transmission to HRT. It assists in improving the regulation and
provide water supply to turbines in case of sudden start-up of a machine. A surge tank is
usually necessary if the ratio of length of water conductor system from reservoir up to
centre-line of the generating unit to the net head for the project is more than 5.
In the present case, length of water conductor system (L) from intake to center-line of
the surge shaft is 2746 m and the rated net head (H) of the project is 92.58 m. Therefore,
the L/H ratio works out to about 29 and is much more than 5. Accordingly, for the
stability of the present hydraulic system, a surge shaft is required. Hence, it is proposed
to have an open to sky surge shaft from topographical consideration.
For the present case a simple vertical surge shaft connected directly to the HRT &
Pressure shafts has been proposed because of following advantages:
This vertical surge shaft is cost effective and suitable for the present case. The
surge shaft is open to sky with its top deck slab at EL.430 m.
An Underground Surge shaft cavity has not been proposed as it does not suit the
topography at its location.
The primary surge shaft has dimension of 42.5 m (w) x 275 m (L) with bottom at EL.
350 m and top at EL. 430 m. Concrete lining will be provided in full height of primary
surge pool.
Service gate will be provided in each of the three HRTs at their entry in to primary
surge pool to facilitate maintenance of surge pool and pressure shafts. The gate
dimensions will be similar to the service gate provided at power intake structure. The
gates operating mechanism shall be provided at the top of surge pool at El 430 m.
Nine numbers 6.0 m diameter steel lined pressure shafts have been provided taking off
from the primary surge shaft to convey the design discharges to the generating units.
The underground pressure shafts are steel lined up to the proposed semi underground
powerhouse. The total length of each pressure shaft works to around 385 meters. The
pressure shaft shall have a horizontal length of about 110 m downstream of primary
surge pool followed by an inclined shaft between El 360 m and El 281.50 m. A
horizontal pressure length of about 166.25 is proposed upstream of power house. The
excavated dimensions of horizontal reach of pressure shaft shall have dimensions of 8 m
D shape and in inclined reach, excavated dimension shall be 8 m diameter circular in
shape.
The total design discharge for generation of 1350 MW (9 units x 150 MW each) power
has been computed as 1652 cumec. Accordingly, design discharge for individual
pressure shaft having 6.0 m diameter is 183.55 cumec generating a velocity of 6.5 m/s
The alignment of the pressure shaft has been fixed in such a way that the individual
tunnels have adequate rock ledge between the two adjoining pressure shafts.
The Layout of the power house complex for the proposed Pumped Storage Scheme lies
in the lower hill slopes of the Upper Sileru Hydro Electric Project. A semi underground
powerhouse of size 25.5m (W) x 65.0m (H) x 313m (L) has been proposed on the left
bank of the Tail race channel of Upper Sileru hydroelectric power project. The
powerhouse complex is located downstream slope of surge shaft in the same hill range
at the location. The powerhouse shall house nine (9) nos. generating units of 150 MW
each for the generation of 1350 MW of power under rated head of around 92.58 m.
The transformer will be located immediately downstream of the power house at ground
level at EL 330 m. The transformer hall shall have a GIS system on floor at EL. 337.50
m above the transformers. Nine numbers of Bus Duct connect the Generating units to
the Transformers.
The discharge from the power house after generation as well as for pumping is
conveyed through nine numbers of unit draft tube tunnels each of size 7.8 m (w) X 10 m
(H). The draft tube gates shall be provided below the secondary surge pool with sill
level EL.270.0 m. Individual hoisting mechanism shall be provided for the draft tube
gate of each unit for quick closing under the unbalanced condition of water pressure.
The discharges from nine units are conveyed into the lower reservoir through three
tailrace tunnels.
Machine Hall
There are four main floors in the machine hall. The lowest floor is at El.274.00 m and
houses the main inlet valve (MIV) for the units. Cooling water pumps, dewatering &
drainage pumps, flood water pumps shall be located on the MIV floor. The nine
Generating units are spaced at 26.0 m c/c. The 48 m long Service / erection bay is
located at the end of the machine hall. The centerline of turbines machines is set at EL
281.50 m around 24.5 m below the minimum TWL of EL 306.0 m in order to avoid any
negative pressures in the system.
The Pump Turbine floor is provided at EL. 285.00 m and houses the various pump
turbine auxiliaries and oil pressure units for governors including MIV for each unit.
The generator floor is provided at EL 290.30 m and houses various Unit Auxiliary
boards (UAB's) neutral grounding cubicles, HP lubrication system, marshaling panels,
etc. Necessary hatches for erection and removal of MIV shall be provided at various
floors in the machine hall cavern.
The machine hall floor is at EL. 295.70 m. This is the main operating floor and houses
the unit control boards, control panels and excitation panels etc.
Service/Erection Bay
A service/ erection bay of size 48 m (L) x 25.5m (W) has been provided to facilitate the
erection & maintenance of the various electrical/ electro-mechanical & hydro-
mechanical components. The approach to the service bay is through the 750 m long
main access tunnel (MAT) joining it at EL 295.70m. The approach to the transformer
hall is located at natural ground level of EL. 330.0 m between the B-line of PH & A line
of the transformer hall.
EOT Crane
Two EOT cranes of 225T/40T/10T capacity each shall be installed in the powerhouse
cavern for handling the various plant and equipment in the service bay and machine
hall. Sufficient clearance has been provided between the machine hall floor and the
EOT crane which is supported on crane beams at EL 308.50m.
Structural Framework
The structural framework inside the machine hall and service bay is proposed as a
reinforced concrete frame. The layout and size of the beams & columns for supporting
the floors at various elevations and the EOT crane is indicated in the relevant floor plan
drawings. The EOT crane supporting RCC columns are proposed to be approx. size 1.8
m (W) x 2.0m (D).
Transformer Building
The transformer building of size 248.0m (L) x 19.375m (W) x 23.5 m (H) is located
downstream of the powerhouse at EL 330.0 m. The building will be founded on rock.
GIS floor has been kept at EL 337.50 m. An EOT crane of capacity 10T with crane
beam at EL. 345.50m has been provided in the transformer building for handling
various equipments. The structural framework of the building shall be of RCC.
Main Access Tunnel for approach to the power house is proposed to be through an
underground tunnel of size 8m (W) x 8m (H) D-shaped, with its inlet portal at around
EL.345.0 m located near the existing road. The MAT has been proposed to reach the
service bay at EL. 295.70 m of the powerhouse cavern. The D-shaped MAT has a length
of around 750 m in a slope of 1 in 15.
One Adit 2 (8 m x 8 m D-shaped) from the access road and near the powerhouse has
been proposed for erection of the ferrules, excavation of primary surge pool with invert
-EL. 350.0 m and for providing access to Valve House.
The valve house of size12.5m (W) X 25m (H) X 229 m (L) located at the top horizontal
reach of the pressure shaft near its inclined bend is envisaged to be used for erection of
ferrules.
Each generating unit is connected to a Draft Tube Tunnel from the draft tube liner
between the B-line of PH and the A line. The draft tube liner at the outlet is connected
to the Draft Tube tunnel (DTT) which is 7.8m (W) X 10m (H). A vertical slide gate type
with a hydraulic hoist has been proposed for each of the DTT in downstream surge pool
with its invert level EL.270.00. These gates shall be operated during the maintenance of
the generating units, from a platform at the top of downstream surge pool at EL. 341.50
m.
Individual hoisting mechanism shall be provided for the draft gates of each unit for
quick closing under the unbalanced head condition of water pressure. The details of the
gate and its hoisting arrangement have been indicated in the relevant drawings.
The Draft tube tunnel (length around 65m) is proposed to be RCC Lined (min. 500mm
thk) in the entire reach. Necessary transitions shall be provided at the relevant locations.
The details of the excavation and rock support measures are based on the Empirical
criteria used for estimation of the rock support system given by Barton & USACE. The
rock support system for different rock mass classification for the draft tube tunnel is
indicated in the relevant power house drawings for support measures.
Three numbers tail race tunnels each of 12.0m diameter have been envisaged to convey
550.67 cumec each of design discharge from the generating units back to the lower
reservoir. The length of tailrace tunnels is approximately 2478 m. The invert level of the
tailrace tunnel at the start is EL. 270.0 m and at the outfall is 277 m. The minimum Tail
Water Level is EL. 306.0m in the lower reservoir.
The end of the tail race tunnel joins with a pump intake structure located in the lower
reservoir. The pump intake structure is equipped with a service and an emergency gate.
A trash rack supporting structure for installation of trash rack units is also proposed at
the intake to be used in the event of pumping mode. The Gates with its operating
platform above the maximum TWL has been proposed at EL.316.0m and the gate trash
rack deck slab is proposed at EL. 319.0 m to match with natural ground level.
9.12.1 General
One number Straight type Power Intake structure having symmetrical approach via an
Approach channel has been envisaged on the existing Guntawada Upper Reservoir, to
divert a design discharge of 1652 cumec, for generation of power. The discharges shall
be lead through a water conductor system (HRT + surge shaft +Pressure Shafts) for
generation of power at a semi underground powerhouse, equipped with 9 nos. reversible
pump turbines before releasing the discharge into the existing Donkarayi Lower
Reservoir through tail race tunnels.
The water after power generation will flow through the tail race tunnel and would be
stored in Lower Reservoir. During lean power demand hours, the surplus power
available from the Grid will flow back to the Pumped Storage plant through the same
transmission line which was used to evacuate the power during peak demand hours. The
generators will then run as motors and the turbines will operate as pumps to lift the
water from lower to upper reservoir. The entire power and hydraulic system would run
in the reversed mode. During next peak hour cycle the turbines and generators will
operate in the normal mode to produce power.
Three head race tunnels (HRT) of diameter 12.0m is proposed for water conductor
system. Each HRT Intake is divided in two openings by provision of an intermediate
pier. A gate shaft is proposed to accommodate the service and emergency gates for HRT
Intake.
Service Gates
Two (2) vertical lift fixed wheel type service gates for two openings of size 6.00m x
12.00 m each are proposed to cut off water flow from the upper reservoir into each
HRT. Sill of Power Intake Gates is proposed at EL 375.00m. The gates shall be
designed for a water head corresponding to FRL 414.50m, as per the provisions
contained in IS: 4622. The service gate will have down-stream skin plate and sealing.
These gates shall be either fully open or closed condition and not be used for regulation
of discharge. The gate will normally be stored on dogging beams on top of gate shaft at
EL. 417.00m.
The gates shall be operated by rope drum hoist of adequate capacity mounted on hoist-
bridge and steel trestles fixed at top of gate shaft EL. 417.00m. Overall arrangement of
rope drum hoist shall be as per the provision contained in lS: 6938.
The gate shall be designed for closure by its own weight and dimensioned such that the
self-weight is sufficient to effect positive closure. If necessary, ballast can also be added
to gate for this purpose. The intake service gate shall be operated under balanced head
conditions created by closure of MIV in power house and/ or butterfly valves located in
valve house. Balanced condition during raising cycle shall be created by crack opening
the gate. Provision of air vent on downstream side of gate and removable guide in
trestles shall be made.
Two (2) vertical lift fixed wheel type emergency gates for the openings of size 6.00m x
12.00m, are proposed on the upstream (upper reservoir) side of each power intake, to
facilitate repair and maintenance of service gates. Sill of power intake gates is proposed
at EL. 375.00m. The gates shall be designed as per the provisions contained in IS: 4622
for water head corresponding to FRL 414.50m. The emergency gate will have upstream
skin plate and sealing.
The gate shall be operated by rope drum hoist of adequate capacity, mounted on hoist-
bridge and steel trestles fixed at top of gate shaft EL 417.00m. The Rope drum hoist
shall be designed as per the provision contained in IS: 6938 (latest edition). The gate
shall be designed for closure by its own weight and dimensioned such that the self-
weight is sufficient to effect positive closure. If necessary, ballast can also be added to
gate for this purpose. Provision of removable guide in trestles will be made. The gate
will normally be stored on dogging beams on top of gate shaft EL 417.00m. Ordinarily
emergency gate shall be lowered under balanced head condition when service gate is
closed. While lifting also, it will be lifted under balanced head created by filling valve
provided in gate leaf. However, emergency gate shall be capable of closing under
flowing water conditions when intake service gate is under distress.
One common Primary surge shaft is proposed at the end of three Head Race Tunnels.
Two gates at the end of each HRT are proposed with two equal downstream openings in
each Tunnel with gate size 6m (W) x 12 m (H) thus total 6 gates are provided in the
upstream of Primary Surge Shaft.
Nine Butter Fly Valves are proposed in each pressure shaft in its horizontal portion near
inclined bend to isolate particular pressure shaft from primary surge shaft for inspection
and maintenance purpose.
Draft tube gates are provided for the purpose of isolating the pump-turbines for
inspection and maintenance, as and when required. The closing and opening of gate will
be done only in the condition when pump-turbine is brought to standstill.
Nine (9) vertical lift fixed wheel type gate (one for each opening) for a clear vent
opening of 7.80 m x 10.00 m are proposed to prevent entry of back water from tail race
tunnel side, entering the unit side during maintenance of the generating units. Invert
level of gate is proposed at EL. 270.00m. The overall arrangement and design of gate
shall be as per the provisions of IS: 4622.
Each draft tube gate shall be operated by an individual electric rope drum hoist of
adequate capacity mounted on steel trestles and hoist bridge structure, which is fixed at
top of the gate shaft at EL. 341.50 m. The gate shall normally be kept in full open
position when turbine is in operation. The gate will be closed for the maintenance,
inspection and repair work to prevent the flow into the draft tubes. The gate will be
lifted under balanced head conditions, to be achieved by the opening of filling valves
installed on the gate leaf for filling water in the draft tube. Gate maintenance is
proposed at deck level EL. 341.50 m.
Three (3) Tail Race Tunnels (TRT) of diameter 12.0m are proposed for discharging
water into lower reservoir after generation of power during peak hours and to draw
water from lower reservoir while pumping of water back to upper reservoir during off-
peak hours. Each pump intake is divided in two openings by provision of an
intermediate pier. Two service gates and two emergency gates for opening of size
6.00m x 12.00m, are proposed in each TRT to stop the water flow from Lower
Reservoir.
Two (2) vertical lift fixed wheel type service gates are proposed to cut off water flow
from lower reservoir into each TRT. Sill of pump intake gates is proposed at EL.
277.00m. The gates shall be designed for a water head corresponding to FRL 316.0m.
The service gate will have skin plate and sealing on the power house side. The gates
shall be designed as per provisions contained in IS: 4622.
The gate shall be operated by rope drum hoist of adequate capacity, mounted over hoist
bridge and steel trestles fixed at deck level 319.00m. The Rope drum hoist shall be
designed as per the provision contained in IS: 6938 (latest edition). The gate shall be
designed for closure by its own weight and dimensioned such that the self-weight is
sufficient to effect positive closure. If necessary, ballast can also be added to gate for
this purpose. Each pump intake service gate shall be operated under balanced head
conditions with the help of rope drum hoist of adequate capacity. Balanced condition
during raising cycle shall be created by crack opening the gate. These gates shall be
either fully open or closed. The gate will not be used for regulation of discharge.
Provision of air vent and removable guide in trestles will be made. The gate will
normally be stored on dogging beams on deck at EL 319.00m
Two (2) vertical lift fixed wheel type emergency gates are proposed on the down-
stream (lower reservoir) side for closure of each TRT, to facilitate repair and
maintenance of service gate. Sill of pump intake emergency gates is proposed at EL.
277.00m. The gates shall be designed for a water head corresponding to FRL 316.00m,
as per the provisions contained in IS: 4622. The emergency gate will have skin plate and
sealing on the lower reservoir side.
The gate shall be operated by rope drum hoist of adequate capacity, mounted over hoist
bridge and steel trestles fixed at deck level 319.0m. The Rope drum hoist shall be
designed as per the provision contained in IS: 6938 (latest edition). The gate shall be
designed for closure by its own weight and dimensioned such that the self-weight is
sufficient to effect positive closure. If necessary, ballast can also be added to gate for
this purpose. Provision of removable guide in trestles will be made. The gate will
normally be stored on dogging beams on deck at EL 319.00m. Ordinarily it shall be
lowered under balanced head condition when service gate is closed. While lifting also, it
will be lifted under balanced head created by filling valve provided in gate leaf.
Emergency gate shall be operated with the help of rope drum hoists of adequate
capacity under conditions as stated above. However, emergency gate shall be capable of
closing under flowing water conditions when Pump (TRT) intake service gate is under
distress.
Trash Rack arrangement for HRT Intake and Pump (TRT) Intake:
Trashracks are proposed, at the entry of the both HRT and TRT. The trash rack shall be
designed as per IS: 11388. The trash racks shall be constructed from structural steel
conforming to IS: 2062 and bolted with the embedded parts. The embedded parts have
to be embedded and suitably anchored into 1st stage concrete. The openings of the trash
rack shall be decided as per the requirement of the machinery for both turbine and pump
operation. An automatic hydraulic trash rack cleaning machine (TRCM) shall be
provided at both HRT Intake and Pump Intake locations for cleaning of trash racks. The
TRCM shall run on the rails provided at the top of the pier and shall be able to serve
each trash rack bay. The TRCM shall also have suitable mechanism for taking the trash-
rack panels to the deck level for periodical inspection /maintenance.
9.12.1.5 Miscellaneous
One complete set of remote control system for the remote control operation of all
service gates along-with programmable computerized automatic reservoir monitoring
control system is provided in the main control room, in addition to individual operation
system provided at top of pier. The programmable reservoir monitoring and control
system shall include all necessary instrumentation required for monitoring and control
of reservoir including water level measuring systems, gate position indication
transducers, discharge measuring devices etc. The communication system shall be
through fibre optic cable. Diesel Generating Set Two numbers, three-phase synchronous
type diesel generating set of 500 KVA, 450 Volts, 50 Hz, one each for Left as well as
right side, are envisaged for the emergency operations of the HM equipments. The
diesel generating set shall be located in the control rooms to provide back-up supply to
gate operating equipments and for the computerized control system in case of power
failure.
9.12.1.6 Materials
All the materials shall be of tested quality, new, unused, and free from defects and of
the grade/classification envisaged in the designs. The contractor shall furnish the test
certificate for each lot of material, if so required by the owner. Plates with laminations
discovered during welding or during inspection shall be rejected. Materials not supplied
according to the approved design/drawings shall be rejected, removed and replaced.
Approval of owner shall not relieve the contractor from the responsibility of supply of
suitable materials. Recommended materials for some of the components are appended
below:-
Design of rope drum and chain hoists for hydraulic gates code
3 IS: 6938
of practice
Guidelines for d esign a nd use of differen t types of rubber seals
4 IS: 11855
for hydraulic gates
Recommendations for inspection, testing and maintenance of
5 IS: 7718
fixed wheel and slide gate
6 IS: 14177 Guidelines for painting system for hydraulic gates and hoists
7 IS: 10210 Criteria for design of hydraulic hoists for gates
8 IS: 800 General construction in steel -Code of practice
Design Erection and Testing (Structural Portion) of cranes and
9 IS:807
hoists.
10 IS: 1893 Criteria for Earthquake Resistant Design of structures.
11 IS: 456 Plain and Reinforced concrete -code of practice.
12 IS: 11388 Recommendations for Design of Trash Racks for Intakes
Particulars Power Intake Power Intake Power Intake Primary Draft Tube Pump Intake Pump Intake Pump Intake
Trash Rack Emergency Service Gate Surge Shaft Gates Trash Rack Emergency Service Gate
Gate Gates Gate
Type of Gate Inclined & Fixed Wheel Fixed Wheel Fixed Wheel Fixed Wheel Inclined & Fixed Wheel Fixed Wheel
removable equipped with removable equipped with
filler valves filler valves
Number of 50 Sets (10 2 Nos. for each 2 Nos. for each 2 Nos. at each 9 Nos. 50 Sets (9 2 Nos. for each 2 Nos. for each
Gates panels in each Intake (Total 6 Intake (Total 6 HRT Outlet panels in each Intake (Total 6 Intake (Total 6
set) Nos.) Nos.) (Total 6 Nos.) set) Nos.) Nos.)
Size of
Opening (w x 3.70 x 34.0 6.0 x 12.0 6.0 x 12.0 6.0 x 12.0 7.80 x 10.0 3.70 x 31.0 6.0 x 12.0 6.0 x 12.0
h) in (m)
Skin Plate --- Upstream Downstream Upstream Power House --- Upstream Downstream
Location side
Seal Location --- Upstream Downstream Upstream Power House --- Upstream Downstream
side
Design Head 6.0 (Trash 39.50 39.50 60.50 60.0 6.0 (Trash 39.0 39.0
(m) Bars) Bars)
7.0 (Supports) 7.0 (Supports)
Sill Level (m) 371.0 375.0 375.0 354.0 270 273.0 277.0 277.0
Operating --- Balanced Unbalanced Balanced Balanced --- Balanced Unbalanced
Condition
Type of Hoist TRCM Electric RDH Electric RDH Electric RDH Electric RDH TRCM Electric RDH Electric RDH
Hoist Capacity 5.0 100 135 150 145 5.0 100 135
(t)
9.13.1 General
The Sileru Weir has been proposed at 7.2 km upstream of existing Donkarayi Dam on
Sileru River, a tributary of Sabari River for fulfilling the requirement of storage for
hydro power generation. Therefore, a need of reservoir with pond level of +316.0 m has
been proposed. Weir is located at 81° 51’ 10.96” E longitude and 17° 57’ 42.84” N
latitude on main Sileru River, Gudem Kotha Veedi mandal, Visakhapatnam District.
The Weir and its appurtenant structures are designed on the basis of standard design
criteria established for other weir / barrages and allied structures, already constructed on
the other River and its tributaries. The design criteria, including formulae, coefficients
and constants used in all hydraulic designs in the present study are based on prevailing
BIS and other relevant codes. Weir or low head dam is basically a barrier structure built
across a river that alters the river flow characteristics and can be stored water for
various purposes of irrigation, hydroelectric power generation, domestic water supply,
industrial water supply, etc.
In the present project, purpose of proposed weir is to store sufficient water for pumping
back to upper reservoir through water conductor system for hydro power generation.
Thus, an ogee spillway weir is proposed with a 5.5 m high rubber dam at the crest of
weir. The raised crest is connected to the horizontal floors on the upstream and
downstream sides by means of slopping glacis. The structure is protected against scours
during high flood by means of cutoffs at the ends of the floor extending to rock below
the floor.
In case rocky foundation is available at the bed level of the river or at very shallow
depths below the bed, the ogee weir can be founded on the same. In such cases, the
requirement of a downstream impervious floor is considerably reduced with, the energy
dissipation being achieved by throwing the discharge directly on the sound rocky
formations in the bed.
Gauge-discharge curve plays a very important part in the hydraulic design of a diversion
/ storage structure. Normally, a statistically analyzed gauge-discharge curve is prepared
based on the observed values made available. If no such data is easily available, the
same may be worked out by Manning’s formula. This curve is the un-retrogressed G-D
curve to be used for waterway and freeboard calculations.
However, as a result of ponding up of river flow, relatively silt free water escaping over
the structure and progressive degradation or retrogression of levels takes place. This
lowering of bed levels in the early stages after commissioning of the structure, if not
duly taken care of, in the designs, it may result in failure of the structure, as the value of
exit gradient may be increased and the energy dissipation through hydraulic jump
impaired. Retrogression is low at high flood stages say 0.3m to 0.5m and high at low
stages of flow, say even 1.0m. Hence a retrogressed G-D curve is also drawn allowing
the retrogressions at higher and lower stages as above. The following points may be
borne in mind in this connection, while fixing the value of retrogressions:-
A retrogressed rating curve to be used in the designs for energy dissipation, protection
works, etc., may be obtained from the normal rating curve, by subtracting the
retrogression for various flood discharges, which can be taken to vary in a logarithmic
fashion between the design flood and low flood stages.
The design flood discharge may be estimated by any one or more of the following
methods:-
Unit hydrograph
Frequency analysis
Slope area method
Use of empirical formulae
Use of flood curves
The design flood for any given return period is usually estimated by the frequency
analysis method. Appropriate type of frequency distribution will be selected from
among the following:
A return period of 100 years is generally adopted in the design of important and costly
structures where possible consequences of failure are very serious. Accordingly, the
estimation of design flood will be carried out for various return periods of 100 years,
200 and 500 years subject to Client’s concurrence. However, the actual recorded peak
flood discharge will be reviewed for design if it exceeds the discharge calculated for the
concerned return period.
9.13.4 Waterway
The overall waterway between the abutments would normally be adjusted to the actual
width of the river at design flood level, in case of deep and confined rivers with stable
banks. For shallow and meandering alluvial rivers, generally the minimum stable width
‘P’ metres obtained from Lacey’s formula,
P = 4.75 Q1/2
Where Q is the design flood discharge in cumecs, is adopted for 1 in 100 yr flood. Ratio
of waterway available between the abutments to the Lacey’s stable width is known as
the ‘looseness factor’. Generally this varies between 1.10 and 1.50, though in a few
cases, this factor may be even less than 1.00, on account of site constraints.
While a low looseness factor, may result in higher afflux and greater intensity of
discharge, a high looseness factor may cause siltation of pond to occur with attendant
problems. Fixation of waterway of a barrage is therefore closely linked with various
parameters such as the discharge, cross section of the river at the location of the
structure, nature of bed materials, sediment content carried by the river, crest level
proposed to meet the pond requirements, permissible afflux etc.
9.13.5 Afflux
The rise in maximum flood level of the river upstream of the weir as a result of its
construction is defined as Afflux. Afflux, though confined in the beginning to a short
length of the river above the weir, extends gradually very far up till the final slope of the
river upstream of the structure is established. This rise in water level travels as a
backwater curve on the upstream. Afflux is required to be limited, due to the proximity
of the structure to populated or industrial towns or plantations situated on the banks or
cultivated fields and homesteads thereon. Further, the afflux created would determine
the top levels of the various components of the structure like, abutments, piers, wing
walls, afflux and marginal bunds etc. The afflux would also govern the energy
dissipation arrangements and its interrelated waterway provisions. Where the river is
well defined and the natural banks on either side are sufficiently high, to contain the
river during flood flows, the afflux created by the structure of low height may not pose a
problem. In case the diversion structure is high and the river has low banks, it is then
essential to fix a limit for such ‘afflux’ and accordingly design the crest and the length
of the structure.
Cut offs are barriers provided below the floor of the structure both at the upstream and
downstream ends. These can be in the form of a concrete lug, sheet pile or concrete
diaphragm wall. Their main purpose is to lengthen the seepage path below the structure
and also to prevent piping action below the floor. The cutoffs on the upstream and
downstream end shall be continuous lines without break. Cutoffs in the transverse
direction known as cross cut offs are provided and these are properly joined to the
upstream and downstream cut offs so as to provide a boxing effect adding stability to
the different units. The depth of the cut off is as per hydraulic considerations as per BIS
Code 6966: 1989 (Part-I).
In this case, good rock is available below the foundation of ogee weir, so exit gradient
consideration is not important.
Data:
Span of a bay 100 m
Number of bays 6 no.
Clear Water Way 100 x 6 600 m
Length of the Barrage 620 m
3
Design Flood Discharge 16500 m /sec
Full Reservoir Level 316 m
Afflux 1.5 m
Maximum Water Level 317.5 m
Crest Level Assumed 311 m
Head Over Crest 6.5 m
Average Bed Level 288 m
Tail Water Level at Design Discharge 316 m
No. of Piers Assuming Width of Each Pier as 4.00 m 5
Thickness of Piers 4m
i) Effect of Approach Depth
Height of Crest From Bed, ' P ' = 23 m
Face of Ogee Crest Vertical
Head Over Crest Hd = 6.5 m
P/Hd = 3.54
The crest is designed for full design discharge to avoid sub pressure along spillway surface. At discharge higher
than design head , some negative pressure may be expected, but they will be with in allowable limits.
At discharge less than the design discharge, the coefficient of discharge will be reduced proportionaly according to
(H/Hd) ratio.
dy/dx = 1.18
X = 1.99 m
Y= 1.27 m
Up Stream Profile
UPSTREAM PROFILE
For A1= 0.3825 B1= 0.219
X Y R.L.
0.000 0.219 316.00
0.050 0.217 316.00
0.100 0.211 315.99
0.150 0.201 315.98
0.200 0.187 315.97
0.250 0.166 315.95
0.300 0.136 315.92
0.350 0.088 315.87
0.375 0.043 315.82
0.380 0.025 315.81
DOWNSTREAM PROFILE
0.00 0.000 316.000
0.10 0.005 315.995
0.20 0.018 315.982
0.30 0.038 315.962
0.40 0.065 315.935
0.50 0.098 315.902
0.60 0.138 315.862
0.70 0.183 315.817
Spillway Design Annexure-2
Unit
Design discharge Q cumec 1651.54
Acceleration due to gravity g m/s2 9.81
Manning's 'n' value for concrete n - 0.0140
Manning's 'n' value for Steel n - 0.0100
Discharge in HRT/ TRT Q m3/s 550.51
3
Discharge in penstock m /s 183.50
2 2 4/3
4) Friction loss in HRT n xv xl/R
(Ref: IS 4880 Clause:4.1.1)
Diameter of HRT d m 12.00
Cross sectional Area of HRT A sq.m 119.42 119.4226
Wetted Perimeter of HRT P m 37.70
Length of concrete lined HRT l m 2763
Manning's 'n' value for concrete n - 0.014
Hydraulic radius R m 3.1678
Discharge in HRT Q cumec 550.51
Velocity in HRT v m/s 4.610
Friction loss in concrete lined HRT HL m 2.474
2 2 4/3
9) Friction loss in Pressure shaft n xv xl/R
(Ref: IS 4880 Clause:4.1.1)
Diameter of pressure shaft d m 6.00
Length of pressure shaft l m 391
Manning's 'n' value for steel n - 0.0100
Cross sectional area of pressure shaft A m2 28.27
Wetted Perimeter of pressure shaft P m 18.85
Hydraulic radius R m 1.5
Velocity in pressure shaft v m/s 6.49
Friction loss in Pressure shaft HL m 0.959
2 2 4/3
14) Friction loss in Draft tube tunnel n xv xl/R
(Ref: IS 4880 Clause:4.1.1)
Cross sectional Area of Draft tube A sq.m 96.00
Equivalent Diameter of Draft tube d m 11.06
Wetted Perimeter of Draft tube P m 34.73
Length of concrete lined Draft tube l m 77
Manning's 'n' value for concrete n - 0.014
Hydraulic radius R m 2.7640
Discharge in draft tube Q cumec 183.50
Velocity in draft tube v m/s 1.912
Friction loss in concrete lined Draft tube HL m 0.014
16) Exit loss from Draft tube tunnel to Surge shaft KxV2/(2xg)
(Ref: IS 2951 Clause:2.2.1)
Exit loss Coefficient K - 1.000
Velocity in HRT after transition v m/s 1.912
Head loss HL m 0.186
2 2 4/3
18) Friction loss in TRT n xv xl/R
(Ref: IS 4880 Clause:4.1.1)
Diameter of TRT d m 12.00
Cross sectional Area of TRT A sq.m 119.42
Wetted Perimeter of TRT P m 37.70
Length of concrete lined TRT l m 2485
Manning's 'n' value for concrete n - 0.014
Hydraulic radius R m 3.1678
Discharge in TRT Q cumec 550.51
Velocity in TRT v m/s 4.610
Friction loss in concrete lined TRT HL m 2.225
Say 10.000 m
Upper Sileru Pumped Storage Project
CHAPTER-X
CHAPTER-X
TABLE OF CONTENTS
CHAPTER-X
10.1 INTRODUCTION
The Upper Sileru Pumped storage hydroelectric project will have an installation of 1350
MW consisting of 9 units of 150 MW each reversible Pump- turbine units driven motor-
Generators to maximize benefits by making available of Peaking power based on the
regenerating the water between the two reservoirs based on the available water and
operating heads in the two reservoirs. The design head is 92.69 m and the design
discharge is 183.5 cumecs per unit. For the above parameters and the reasons indicated
in Chapter-VIII of CEA Guide lines, Power Potential & Installed Capacity; Vertical
Francis reversible Pump- Turbines are selected.
The power House proposed is of surface type. All the Auxiliary equipment such as
generator and turbine auxiliaries, MV and LV switchgear equipment, Transformers,
Gas Insulated switchgear, firefighting system equipment etc. were placed in the
Annexure floors as detailed below.
The approach into the Power House for men and material is from EL 295.70m through
Main Access Tunnel (MAT).
All the turbine auxiliaries such as compressors and tanks, Pressure receivers and
controllers of Governor and MIV shall be placed in this floor. Drainage and Dewatering
pumps along with emergency submersible pumps are also be placed in this floor. The
access to turbine pit is from turbine floor.
Necessary Boundary metering equipment and line protection CVT and CT’s along with
Line isolator with earth switch are placed and the line termination with Gantry structure
for 4 Nos. feeders to enable to interconnect with APTRANSCO lines for Power
evacuation.
Suitable Ventilation along with ducts as required will be provided to all the locations
with a ventilation system designed for complete power house and located at EL 330.00
m.
Necessary Fire hydrant protection system with all required items covering the entire
area inside and outside of the power house is considered.
2 nos. DG sets of 1000KVA shall be provided to meet the Emergencies.
EOT Crane for Unloading bay – 1 no. and for erection 2 nos. and for GIS equipment
floor- 1 no. are being provided.
Necessary hatches with protecting covers will be provided as required for MIV,
material handling for different floors.
Pump-Turbine Description
Francis type of reversible pump turbine motor generator units are proposed to be
installed in this power station.
Described are single stage pump- Turbines with guide vanes with vertical shaft and
spiral casing embedded in concrete. All removable parts as runner, main shaft, guide
bearing and head cover can be removed from above. The pump is designed with one
guide bearing located close and above the impeller. The units are suitable for
continuous operation as pump as well as Turbine. The pump- Turbines shall include all
associated auxiliary equipment, including Governor controller, OPU system for
Governor controller, Main inlet valve, lubrication system, cooling water system, water
and air piping with necessary instrumentation, auxiliary pump-motor sets, control and
safety devices etc. and common equipment like compressed air system complete with
all accessories, drainage and dewatering system pumps with necessary piping, valves
etc. mandatory spares, as well as special tools and plant as per standard specifications
and requirements, whether they are specifically mentioned in this or not.
The chosen hydraulic design is based on an existing / proven model and model test
conducted.
i. Type:
The Pump-turbines will be of vertical shaft Francis type, directly coupled to the
generator, with adjustable guide vanes by means of oil pressure supplied from the
governing system. The main parameters of the turbine are as under:
As Pump
a. Maximum head (net) 118.00 m
b. Rated head 112.00 m
c. Minimum head 94.20 m
Pump Mode
Head in Discharge Power in Efficiency in %
mtrs in cumecs MW
Rated 112.00 137 169 Average greater
Maximum 118.00 132 170 than 91%
Minimum 94.2 164 173
Turbine Mode
Head in Discharge Power in Efficiency in %
mtrs in cumecs MW
Rated 92.58 183.5 150 Average greater
Maximum 108.50 - - than 90%
Minimum 90.75 - -
iv. Runner:
a. Runner diameter: 5.60 m
b. Distributor axis Level: EL +281.5 m
The pump-turbines are to be designed to make available of the units and the units can
be changed from one mode of operation to other in minimum possible time. The
proposed response time shall be as given below.
Response
S. No. Mode of operation time in Remarks
seconds
1 Standstill to Turbine full 150 Loading of the unit from no load to full
load load will be in 20 seconds after
synchronisation
2 Turbine full load to 200 Deloading of the unit from Full load to
Standstill no load will be in 20 seconds
3 Standstill to pump full 330 The unit can be kept in Pump condenser
load mode in between at no load and load as
pump in less than 120 seconds
4 Pump full load to 180 The unit can be kept in Pump condenser
standstill mode in between at no load in less than
120 seconds and can be kept back as
pump as and when required
5 Turbine full load to 600
Pump full load
6 Pump full load to 240
Turbine full load
Stay ring
It shall be fabricated from welded steel plates and have set of streamlined stay vanes.
Two properly shaped strong guide rings shall guide the water to the guide apparatus.
The top ring shall be designed to carry the top cover and the pit liner and the lower ring
to carry the pivot ring. Strong streamlined stay vanes shall rigidly tie the two rings
together. Weld preparation shall be made at works for field welding to spiral casing at
site. Tapped grout holes shall be provided in the lower plate of stay ring to facilitate
placing of concrete under the ring. These holes shall be plugged after the concreting.
Two/one stay vanes shall have holes to drain the top cover leakage water by gravity.
The drain pipe shall be connected to embedded drain pipe.
Spiral casing
The spiral casing shall be fabricated from steel plates in minimum number of section
with a view to keep welding at site to the minimum feasible within the limitation of
transport and handling. It shall be designed to withstand maximum operating pressure
including water hammer. The spiral casing shall be pressure tested at site. Necessary
piezometer tapping for flow measurement shall be provided. Weld length of stay ring
spiral casing joints, Tee joints, circumferential joints and longitudinal joints shall be
ultrasonically tested.
It shall also be provided with strong and rigid pockets for guide vane servomotors.
These being also anchored in concrete and capable to transmit the servomotor thrust
load in to the concrete.
Suitable off take for connection of pressure / vacuum piping to top cover and gauges
shall be provided. Suitable piping connections shall also be provided around for
admission of air during water depression uniformly. A vertical water box with suitable
valves and flanges and water level gauge and 4 Nos. of level electrodes are to be
provided for automatic water depression of runner during starting of machine as pump
in quick and full auto start-up.
Adequate number of holes for free passage of air and grout, whilst the liner is being
concreted, shall be provided. The extent of the liner shall be up to a point as mentioned
in the water path drawings i.e. upto the water velocity is 5 m/sec. The liner shall be
assembled and match marked in the shop before shipment for convenience of proper
assembly and alignment at site. A drain box for dewatering the draft tube with two nos.
suitable long stem valves and common dewatering pipe shall be supplied.
Impeller
The impeller shall be of stainless steel integral cast/ cast welded construction. (13%
chromium and 4% nickel) or Material: A743 CA6NM acc. ASTM).
The impeller vanes shall be accurately ground using suitable templates so as to make
the contours homologous with the corresponding model test impeller. The impeller
shall be designed and constructed to safely withstand, without damage, the stresses
resulting from running at the maximum runaway speed under conditions of maximum
operating head. The impeller shall be statically balanced. Replaceable labyrinth rings,
at upper rim and lower rim shall be provided Removable split rings made of stainless
steel are mounted between the outer diameter of the impeller and the stay ring.
A polished corrosion resistance removable and renewable sleeve shall be fitted to the
shaft where it passes through shaft seal and gland. The impeller and shaft shall be
designed to withstand the maximum runaway speed attained at the maximum net head
in both the directions.
Guide bearing
Shall be of submerged, self-oil lubricating, pivoted pad type, with external / internal
Plug in type cooler arrangement. The bearing shall be situated above the shaft gland as
close to the impeller as possible. The guide bearing is located above the impeller and
bears the radial thrust of the Pump-Turbine.
The bearing shall permit sufficient vertical movement of the impeller and shaft to allow
for adjustment of the Generator-motor thrust bearing. Bearing pads shall be individually
adjustable, bolted to the support ring, lined with white metal and easily dismountable.
Pads shall be provided with thermometer pockets.
Oil sump of the whole bearing shall be arranged for continuous oil circulation while the
pump-Turbine is in operation. The guide bearing shall be designed such that the normal
working temperature of metal does not exceed 600c.
The bearing shall be capable of being operated safely for at least 15 (fifteen) minutes
at runaway speed with cooling water supply intact.
Top cover
As the Diameter is envisaged of higher size the Top cover is in suitable parts.
An air inlet piping fixing flanges at suitable locations around the top cover to enable
uniform air admission for water depression to well below the runner chamber shall be
provided.
Piping provision in the top cover shall be provided for runner top and bottom pressure
balancing by certain operating conditions which to be connected to Draft tube chamber
with suitable valves.
Hydraulic operated Air admission, Air makeup and air release valves and Piping system
shall be provided on the Top cover for Air admission to depress the water of the runner
chamber for smooth start as PUMP and to keep the machine in condenser mode prior
to loading as required.
Guide vanes shall be of cast stainless steel with integral stem. Guide vanes shall easily
turn in self-lubricated bushes in top guide vane housing and in pivot ring. Each guide
vane shall be provided with a thrust collar to carry the weight of the vane and to resist
any upward thrust.
Necessary arrangements shall be made for easy adjustment and maintaining the vertical
clearance of the guide vane.
All moving parts of the turning mechanism shall have self-lubricated bushes. Stops
shall be provided to prevent the movement of the guide vanes beyond the fully open
and closed position. The simultaneous movement of all the guide vanes is achieved
with the regulating ring mounted on inner top cover moved by guide vane servomotors.
Governor
The Governor will be of PLC based digital electro hydraulic type using microprocessor
technology with a sensitivity of 0.01%. The speed governing will be performed by
combination of the proportional, integral and derivative actions and by non-linear
characteristics. Necessary transient analysis will be conducted on the hydraulic system
to obtain the operating timings of the Governor for programming the same for safe
operation of the machine in all modes of operation.
The Governor shall be designed to control the wicket gates in both PUMP and Turbine
mode of operation.
The governor will control the flow of water to the turbine to match the load by adjusting
the positions of the guide vanes.
The governor shall be adaptable for use in an unattended station with automatic start-
up/shutdown, automatic synchronizing, automatic load frequency control of the
turbines in operation.
Safety devices capable of shutting down the turbine when the oil pressure falls or the
actuator drive fails, at the same time operating the alarm signals and providing signals
to SCADA.
The output of Generator Voltage transformer shall be used as one of the signal source
for speed sensing.
The capacity and the pressure rating of the oil pressure vessel shall be sufficient to meet
all the pressure oil requirements of the governor, guide vane servomotors and even
below its machine shut down oil level. It shall have an oil volume capable of performing
3 full operations that is close-open-close, with the governor oil pumps being out of
operation without reaching the very low trip oil level. The oil pressure vessel shall be
equipped with Pressure switches for automatic starting/ stop of oil pumping, a gauge
for indicating oil level in the tank and Pressure relief valve.
Each Pump-Turbine is provided with a Butterfly valve to act as a main inlet valve in
order to achieve quick closing to cut off the water supply for the Turbine in the event
of any machine tripping on a lock out fault. The oil pressure operated butter fly valve
or through flow type valve shall have maximum capacity to allow maximum flow of
pump-Turbine discharges. The valve will be designed to withstand the maximum of 2
times the design head or pump shut off head, whichever is higher. The Butter fly valve
will be of plain door type with rubber seals designed to open under unbalanced
conditions and close against full flow in emergency. The Butter fly valve shall be
normally opened and closed by hydraulic system and also have backup closing system
with dead weight for closing during emergency. The opening and closing time of the
valve shall not be more than 60-150 seconds, including the operating time of bypass
valve with normal operating pressure.
Hydraulic operated Bypass valve along with isolating valve is provided across the
Butterfly valve for smooth operation of the valve with pressure balance condition using
a differential pressure switch and auto operation scheme.
b) Valve Disc:
The valve disc shall be made of carbon steel casting or fabricated of rolled steel plates.
The disc shall be supported by forged steel trunnions through the disc. On the peripheral
surface of the disc a rubber ring shall be provided to seal off leakage together with a
stainless steel seat provided on the valve body inner surface.
c) Dismantling Joint:
The Joint shall be of Telescopic type and located on downstream of valve (between
Main inlet valve and Spiral case inlet) facilitating dismantling of valve during
maintenance. The joint between the valve and the delivery line shall be accomplished
with movable slip-type flanges and bolted.
The pumps shall be with pressure switch control and with a set of smoothly operating
unloader valve. Non-return valve and safety valve shall be provided to regulate the oil
level.
Required pressure switches, level switches, position switches, gauges, meters and
Transducers as per the requirement for total auto and remote operation shall be
provided.
h) High Pressure Compressed Air System for Governing and Valve OPU system:
Two sets of compressed air systems with inter connection isolated valves required for
the governor oil OPU system and Main inlet valve OPU system will be provided.
Compresssors and pressure air receivers are suitably sized. Necessary controls and
protection shall be envisaged for auto start stop of the compressors as per the pressure
switch settings.
j) Low Pressure Compressed Air System for Brakes, Isolating seal, Maintenance
Purpose:
Two sets of compressed air systems with inter connection isolated valves required for
the Brakes, Isolating seal and maintenance purpose will be provided. Necessary
controls and protection shall be envisaged for auto start stop of the compressors as per
the pressure switch settings.
For each unit the cooling water required for Bearings cooling, shaft seal, Stator, OPU
and transformers etc. shall be tapped from the Penstock with suitable valves and
Strainers and Dissipators shall be envisaged to supply water at required pressure along
with all instrumentation.
Cooling water required for the unit have to be tapped from intake through valves, and
strainers and shall be returned to the Draft tube after the coolers. Fine strainers required
for shaft seal cooling water shall be provided. The cooling system shall be so designed
that back flushing shall be possible by reversing the direction of flow of cooling water
to avoid clogging of cooler pipes.
Special considerations –
All embedded pipes shall be seamless pipes of thickness of next higher rating than
specified as per the IS standards for that requirement and application but not less
than 10 mm. All Valves used in water system in the power house area must be of
cast steel valves with raising stem only.
i. Type of Generator:
The Motor - generator will be of Synchronous vertical shaft salient pole type, 3 Phase,
50 Hz conforming to the latest edition of IS 4722 or IEC 34 or any other equivalent
international standards directly coupled to the turbine shaft.
Motor-Generator shall be star connected and the main and neutral leads shall be brought
out of the stator frame for connection to isolated Phase bus duct. The motor- generator
shall be grounded though a suitable rating distribution transformer grounding device,
to limit the ground fault current to less than 10 (Ten) Amps while delivering rated
output.
The motor- generator shall be rated for higher output corresponding to the pump
maximum discharge at the minimum net head but shall not be more than 110% of the
rated input at rated voltage, frequency and power factor. The hydro generator shall
deliver continuously the rated MVA at rated power factor when operating under rated
conditions with temperature rise / temperatures not exceeding Class - B values,
stipulated in the latest issue of the IEC 60034-1.
With a maximum cooling water temperature of 30° C. the motor- generator shall be
capable of delivering rated output to pump continuously at any voltage and frequency
in operating range and rated power factor without exceeding the following temperature
rise over a maximum ambient Temp of 45° C .
a) Stator winding : 85° C above ambient
b) Field winding : 95° C above ambient
c) Bearings by embedded : 70° – 80° C above ambient
The noise level of the generator will be limited to 90 db when measured at a distance
of 1m from any component of the generator.
a. Stator:
i. Construction:
The stator frame will be of welded steel structure. The core will be built up with low
loss high silicon, grain oriented steel laminations. The windings will be of class-F
insulation with temperature rise limited to class-B insulation. Provision will be made
on the main (Phase) side & neutral side of the Motor-generator for mounting of required
no of CTs for AVR, protection & metering.
b. Rotor:
Rotor shall be of salient pole type construction. The rim of the rotor will be constructed
out of laminated sheet steel having radial ventilating ducts located along the lengths &
bolted together to make a compact structure. The hub of the rotor will be securely
attached to the main shaft taking care of requirements both at normal operating speed
and at maximum runaway speed conditions. The rotor spider will be of fabricated
construction with arms radiating from the central hub. The pole insulation will be built
up of thin laminations secured by insulated bolts passing though supporting end plates.
Fans will be provided at the bottom and top of the rotor poles. The field windings will
be of class-F insulation with temperature rise limited to class-B insulation. A low
resistance damper winding of copper shall be provided on all the poles near the upper
surface of the pole shoes to dampen rotor oscillations when a sudden load change
occurs. The damper windings shall be strong enough to withstand all the electrical and
mechanical stresses occurring during operation.
e. Generator Housing:
RCC Generator barrel will be provided for housing the generator.
f. Shaft:
The generator shaft will be made of high quality manganese steel, properly heat treated
and will be accurately machined all over and polished at the bearing surfaces and at
accessible points for alignment checks. An integrally forged flange will be provided at
the bottom of the shaft for connecting to the turbine shaft flange. The shaft coupling
will comply with the requirements of IEEE-810 specifications. The shaft will be earthed
through a brush gear assembly to avoid eddy currents flowing through the shaft.
g. Brackets:
Top and bottom brackets will be provided to house thrust and guide bearings. The
brackets will be of fabricated steel construction. The thrust bearing bracket will be
designed to support the hydraulic thrust from the turbine in addition to the combined
weights of the rotating parts of the generator and turbine. The bracket arms will be
designed to rest on mild steel sole plates grouted into the concrete foundations.
shall be provided to measure the insulation of the generator bearing with the machine
in operation.
k. Heaters:
Space heaters will be provided for maintaining stator surrounding air temperature above
the ambient during prolonged shutdown period.
4 sets of suitable CT’s for protection, metering and AVR requirements will be provided
in the Bus duct connected in the phase and Neutral side of Motor- generator.
PT and SP cubicle shall consist of suitable Draw out type Voltage transformers for
protection, metering and AVR requirements along with Fuses and Circuit Breakers.
Surge capacitors and lightning arrestors are mounted in this cubicle to safe guard the
motor- generators.
Microprocessor based excitation system with thyristor control will be provided to suit
the Motor-generator characteristics for each unit. The AC power required for the
excitation will be tapped from the Motor-generator terminal, stepped down by means
of rectifier transformers and rectified by fully controlled thyristor bridges and then fed
to the Motor-generator field thereby controlling the generator voltage output. Any
change in the generator terminal voltage will be sensed by an error detector and cause
the voltage regulator to advance or retard the firing angle of the thyristors thereby
controlling the field excitation of the generator. Redundant DVR with auto and manual
channels in each and redundant thyristor bridges of 100% rating will be provided.
The excitation system for each unit will consist of the following:
a. Dry type Excitation transformer
b. A set of Thyristor converters of suitable numbers such that even in case of ONE
bridge failure, the remaining bridges shall cater to the maximum continuous and
ceiling current requirements.
c. Field flashing (both AC & DC) for excitation start up.
d. Field breaker and field discharge and suppression equipments.
e. Digital Automatic voltage regulator with auto and manual channels with all
standard limiter functions.
f. Aux Excitation system with Transformer, Connecting Breakers taking input
from station Aux supply source for initial excitation during SFC starting in
motor mode of operation.
Provision is also proposed for back to back starting of the units (at 400KV voltage). A
common starting bus with Phase reversing isolators etc are provided.
Starting of the Pump – turbine units as pump will be done in two methods
Due to the large sizing of the machines and the fault level is on high side on 13.8 KV
level it is preferred to have starting system at 400 KV side. The size and cost of 13.8
KV Phase reversal isolators and GCB is high due to the high fault level capacity. Hence
in order to economizing the power house size and cost, it is proposed to have the starting
scheme in 400KV due to compactness.
SFC Starting
Mainly to the extent possible the units will be started in back to back starting mode.
The last unit has to be started individually through SFC equipment. SFC equipment
works as a Variable frequency and variable voltage principle having converter and
inverter equipment and starts the unit as motor from the additional Station supply source
transformers (20/25 MVA). All the equipment will be provided to start any unit as pump
from any of the SFC provided as redundant. SFC supply will be extended to the unit
proposed for stating through Breaker and Isolator at 11/13.8 KV level by providing a
starting Bus at 13.8 KV side also.
Details of Equipment
Two (2) sets of Static Frequency Converter (SFC) systems are considered to have
redundancy of starting equipment as this starting equipment is common for all 9 Units
in the Power station. Starting equipment shall be suitable to start the units as pump-
motors smoothly with impeller in dewatered condition and without inrush current. The
Pump-motor shall be soft started and reach its rated speed within 5 minutes. It shall
include the necessary transformers, H.T switchgear and all the control equipment
required.
The isolator cubicles shall be provided with 2 Nos. Circuit breakers for incoming
feeders and 9 Nos. outgoing feeders one for each unit. The system shall be suitable to
start one pump at a time.
The power circuits of panels (13.8 KV system) starting system shall be designed so that
it can with stand system fault currents during starting of pumps.
The converter can be high-high type or 12/12- pulse type, two converters are connected
by a DC reactor which is necessary for the current source type SFC.
Breakers/Switches
The SFC system is equipped with input breakers and output breakers. A bypass switch/
breaker shall be installed as output transformer is configured.
Transformers
SFC system shall consist of Transformers at the input (11 KV) and output (13.8 KV) of
the frequency converter to match the network voltage and motor voltage to the
permitted converter voltages. They reduce the harmonics injected into the network,
limit the fault current inside the frequency converter and provide the required phase
shifting in case of 12-pulse configurations.
g. 11 KV INDOOR PANELS
The 11 KV Indoor panels shall consists of incoming sources with breakers from 20/25
MVA transformers and from 11KV outdoor substation and outgoing supplies with
Breakers to 2.5 MVA auxiliary supply transformers and with one bus coupler in the
configuration. All the protections are provided for isolation on fault and communicate
to SCADA system.
10.9 400 KV GIS SWITCHYARD
In order to reduce the huge land acquisition in the forest area 400 KV Gas insulated
switchgear is proposed instead of conventional 400 KV switchyard, GIS is of Indoor
type and placed in the Power house Area above the transformer floor.
Gas insulated EHV. Switchgear will be installed with suitable isolation arrangements.
The Motor- generator transformer circuit breakers, Isolating and earth switches, CTs,
Surge arrestors and PTs etc., will be located in this area.
This GIS shall receive 400 KV supply from 9 Nos. Motor-Generator Transformers and
shall feed to (4) four feeders. Two 400/11KV station transformers and two Bus reactors
with one in each bus section is considered. Bus sectionalisation with bus couplers are
provided.
Additionally one starting Bus with sectionalizer is provided along with isolators earth
switches etc. used for starting of the Units as Motors.
All the GIS and its equipment shall be designed and suitable for 63 KA fault current for
3 seconds.
400kV Gas Insulated Substation having two nos. of main bus and one no. Starting Bus
with Bus sectionalizers are envisaged.
The proposed single line diagram for 400 KV / 13.8 and 11 KV / 415 V Switchgear is
as indicated in drawing.
In addition to the above, POTHEAD YARD 400 KV outdoor equipment for power
evacuation are also being provided with the following details.
1. 400 KV Lighting Arrestors - 12Nos.
2. 400 KV CTs 2000-1000/1A for boundary metering - 12 Nos.
3. 400 KV CVT’s for boundary metering and protection - 12 Nos.
4. 400KV Isolator with earth switch motor operated - 4 Nos.
i. Motor- Generator:
Two nos. numerical integrated multi-functional Motor- Generator Protection Relays as
Main-I & Main-II of two different makes providing all the Protection Functions shall
be provided.
Capable of single & Three Phase Tripping and shall have carrier inter tripping facility.
7. Gateway control PC and Modem for data transfer to LDC/SRLDC through PLCC
(For gateway, it shall communicate with State load Dispatch Center (ALDC/SLDC)
on IEC 60870-5-101 protocol. And Provision for expandable to IEC 104 protocol.
2 Ports for ALDC/SLDC.
8. A common Large Video Screen Display system (with 8 Nos. 67 inch displays to be
mounted as a Two tier (2 X 4)) operable from OWS/EWS for display of mimics and
data as desirable.
9. A large video display screen with CCTV circuit for monitoring different locations
of power house areas. (Large Video screen: 67” SXGA+ Display Technology: DLP,
single chip 0.95” DMP 12”).
Provision for Remote control of the station i.e., units and feeders control from other
station / load dispatch center through standard communication networks and protocol.
High speed Dual Communication network allowing the data interchange between the
controllers and the central control room system.
I/O cards, output and other relays, Temperature and other parameter recorders,
indicating instruments redundant CPU, redundant power supply, redundant
communication etc.
The controllers of the control system shall have OPC compatibility and shall be able to
readily integratable to the OPC compliant devices.
Control for start/stop, emergency shutdown of the machine /equipment locally with a
provision of MIMIC and illuminated push buttons on the front panel with necessary
interlocks or through 19” Tough screen HMI provided on the front panel of the LCU
and from operator/work stations in control room in generating mode with provision to
choose Local / Remote control selection through Locable L/R Switch.
Each auxiliary shall have a local control board near the device with necessary controls,
indication, interlocks and protection i.e., overload relays, voltage and current meters,
control switch for start/stop, MCCB/HRC fuses for incoming supply, indications,
interlocks required for the process, single phase preventer etc., with feedbacks and
control input signal provisions from SCADA.
1. EOT Cranes:
a. The Unloading & erection bay at elevation EL 295.70 shall be provided with 2 Nos.
of EOT cranes of 225/40 T capacity as the maximum weight to be handled is the
assembled rotor expected to be of 400 Tonnes. These cranes are used for erection
of all the equipment.
Two cranes for lifting of the Heaviest Assembly in Tandom operation with lifting
beam will be provided. The type of cranes shall be of M5 duty class Indoor type
Main and Auxiliary Hoists, Long and Cross Travel motions shall be provided with
VVVF drives to enable even micro operations in all the main motions.
b. One EOT crane of 10 T capacity be installed in GIS hall.
3. Test Laboratory:
A testing laboratory is proposed for meter, relay and testing of transformer and bearing
oil, HV test kits and insulation testers.
b) Drainage system:
Two nos. Suitable capacity open type drainage sumps are provided on either end of the
Power house. All the seepage from walls and floors, Flushing pipe discharges, fire
extinguishing discharges will be routed to Drainage sumps through drains. To meet any
emergency these sumps are inter connected to Dewatering sumps through isolating
valves for early dewatering of the Power house area. Adequate quantity and capacity of
drainage pumps will be provided for each sump suitable to dewater the seepage water
collected in less period. Delivery of pumps shall be to the tail race.
The equipment for each of the dewatering and drainage system shall comprise motor
driven vertical turbine pumps/ submersible pumps, associated piping, valves, float
switches, suitable controls, accessories etc. The motors shall be suitable for 415 V, 3
Phase 50 Hz, AC supply and rated for continuous duty. They shall be suitable for
continuous starting and stopping duty. The motors shall be in complete form with their
star/ delta or Soft starters, over load protection and single phase preventing devices,
level switches, control gear for starting and stopping automatically through the contacts
of adjustable level sensing devices to be installed in the sumps.
The location of dewatering motors shall be generally above Turbine floor elevation. All
the control/starter panels of the Dewatering and drainage pumps shall be located above
the Generator- Motor floor to meet in all contingencies.
In addition to above dewatering and drainage pumps 4 Nos. submersible pumps along
with suitable starter panels shall be provided to meet the Emergency requirements i.e.
to use in case of requirement of flooding of power house.
8. Lifts:
2 (Two) Nos. ‘13’ passenger traction type lifts with lifting capacity 884 Kgs each
excluding the weight of car shall be with variable voltage (V3F) drive controller and
operating speed shall be 1 m/sec.
The Traveling distance is from the Turbine floor of Powerhouse to GIS floor are
envisaged.
It is proposed to provide four numbers, resin cast dry type, three phase transformer of
rating 2500 KVA, 11/0.415 KV, with off load tap changers. The HV side of the
Transformer will be connected to 11 KV metal clad switch gear through a required size
11 KV XLPE Cables. The LV side of the transformer will be connected to 415 volts LT
Switch (Reserve) boards through LV Busduct or with suitable size 3½ core, 1100 volts
grade cable.
The Incoming feeders from the supply source are connected to reserve boards and these
shall be provided with electrically operated draw out type air circuit breaker of 4 pole,
3 phase, 415 volts, specified capacity, 50 KA/sec. short circuit capacity and shall have
shunt trip facility with built in static type adjustable thermal over load and short circuit
protection with suitable high interrupting capacity etc. These Air circuit breakers can
be able to be operated from local /remote with necessary interlocks in full auto
operation through station auxiliary controller.
Reserve Boards (RB) will feed Station auxiliary Boards (SAB) and unit auxiliary
boards (UAB). Station auxiliary Boards (SAB) will feed all the common station
Auxiliary Loads. Each unit auxiliary board will feed unit auxiliaries of two units with
redundant source inputs.
Each Auxiliary Control Panel supply shall be fed from UAB/SAB and shall be fed to
pumps such as OPU pumps of oil Servomotors of Governing system, Main inlet valve,
cooling water pumps, etc. The panel shall contain soft starters or Star/ Delta starters
with minimum protection ‘3’ phase over current relays, Earth fault relays, temperature
relays, oil pressure relays etc.
Some Important loads are fed from AC emergency board to meet the emergency
requirements.
One DC distribution board along with Sub-Distribution boards required for unit wise
and area wise will be provided.
Lead Acid type PLANTE battery and Float and Float Cum Boost charger for each
battery set with static control circuits and Thyristor bridge rectifiers with complete
automatic voltage, current regulation shall be provided.
100% redundant UPS system with SCVS bypass with static switches which shall be
able to meet the loads of main control (SCADA) and HMIs and any instrumentation
and other loads. The UPS battery shall meet the UPS load for One hour back-up in case
of AC supply failure at rated load of UPS.
Power House emergency lighting load shall be considered on the UPS system. ACDB
with required no of feeders for SCADA, controllers, Emergency lighting with suitable
MCBs, fuses and indicating lamps shall be provided.
All the cables will be laid in Perforated GI cable trays with supporting structures in
horizontal laying and with Ladder type GI trays in Vertical placement. Copper tinned
lugs will be provided for all the terminations along with identification ferrules and Tags.
Necessary cable glands with fire protection sealing barriers shall be provided.
e. Illumination:
a. Normal 220 V AC system:
The lighting circuit will be normal 220 V AC lighting system fed from 415 V AC
distribution system.
Complete lighting system shall be provided for the following places in the Power
House. The illumination levels as requires in various locations of Power House are as
given below.
Place/Location Type of lighting Fixture Lighting
level
1 Main control room and Decorative LED fixtures 300 lux
conference rooms
2 Other areas inside the power Single or Twin LED lamps 100 lux
house
3 Machine hall (high bay) High bay fixtures LED lamps 260 lux
4 Transformer bay High bay fixtures LED lamps 100 lux
5 Draft tube gates Medium bay fixtures LED lamps 70 lux
6 400 KV GIS Flood light fixtures LED lamps 150 lux
7 Switch yard and other approach Street light fixtures LED lamps 70 lux
Roads
f. Earthing System:
Power House Earthing shall be provided with suitable size of Mild steel (MS) flat as
per the standards from the bottom most raft point of powerhouse. The earthing system
shall be suitable to meet the earthing of all the electrical equipment in the powerhouse.
Raisers connecting to the equipment above the mat shall be 75 x 16 mm and the raisers
exposed out for connection to the equipment shall be of Galvanised flats of sizes 50 X
8 mm or higher. Flexible copper cable connections shall be adopted for the local
equipment earthing from the main raisers according to the requirement.
All the electrical equipment shall be grounded at two points. Earthing shall be provided
by means of an earth mat laid right into the tail race to keep the earth resistance to
minimum of the order of 0.4 ohm. The earth mat shall be designed duly taking into
consideration of the local soil particulars.
The starting of DG set engine shall be by electrical self-starting unit with source of
energy from batteries. The engine shall be capable of running on load within 15 to 20
seconds of its starting.
The cooling of the engine shall be by water filled radiator. Noise level shall be less than
75 db.
i. PLCC Equipment
On 400 KV EHT line sections it shall be installed with SDH type optical line terminal
equipment (OLTE) with a capacity of STM4 upgradable to STM16 with 1+1 path
protection at optical level in each direction for signal transmission on 1310 nm & 1550
j. Transport limitations
(i) Maximum limiting dimensions (L x W x H) of packages for transport
6M x 5.5M x 5M
CHAPTER-XI
CONSTRUCTION PROGRAMME AND PLANT
PLANNING
CHAPTER-XI
TABLE OF CONTENTS
11.1 General 11-1
11.2 Construction planning of main components of the project 11-3
11.3 Bar-Chart Showing Quantity-wise Programme 11-10
11.4 Key Materials Planning 11-11
11.4.1 Requirements of Coarse and Fine Aggregates 11-11
11.5 Various alternatives for construction Programme 11-11
11.6 Construction Programme for Tunnel/Channel 11-11
11.6.1 Excavation Cycle Time for Tunnel/Channel 11-11
11.6.2 Cycle Time for Tunnel Lining 11-12
11.7 Scheduled Working Hours 11-12
CHAPTER-XI
11.1 GENERAL
The proposed project site is located at Upper Sileru on river Sileru, a tributary of Sabari.
The installed capacity of the proposed pumped storage project shall be 1350 MW (9 x
150 MW).
The project being close to glacial region the working season for over ground works is
considered as 8 months starting from October in a year to May depending upon the
onset and withdrawal of monsoons. However the underground works can be proceed
during the entire year subjected to supplies to site. The project is proposed to be
completed within a time span of 4 years excluding one year of pre-construction and
infrastructure activities. The testing and commissioning of units will be done by 4 years
of the construction activities.
Project headquarter is proposed to be located at site office near the project site itself.
The project is connected with two railway head, one is Visakhapatnam railway station
and another is Rajahmundry railway station. Both the railway heads are connected by
roads with Sileru which is a nearby village to the project site. The road distance from
Visakhapatnam railway station to Sileru is 187 km whereas from Rajahmundry to Sileru
is 200 km.
Provision of machinery like trucks, motor-grader, dozer, road rollers and other Q
special T & P required for carrying out the infrastructure works has been made in the
project estimate. Provision for inspection vehicles, personnel carriers, ambulances and
field workshop equipment have also been made in the project estimate for infrastructure
facilities.
The construction methodology and equipment planning for various works is based on
the site conditions prevailing in the project area. Construction activities are planned in
such a way that the project will be completed in the shortest possible time period. The
following assumptions have been made for construction methodology and equipment
planning of the project.
All the pre-construction activities like land acquisition, infrastructure works and
government approvals are completed before the start of construction works on
main components of the project.
All civil, hydro-mechanical and electro-mechanical works are executed in
following main packages of contract.
The major works for execution of the project include weir on lower Donkarayi
Reservoir, Power Intake & Pump Intake, Head Race Tunnel, Surge Shafts, Power House
Complex, Hydro-Mechanical Works and Electro-Mechanical Works. These will be
logically divided into following contract Packages, which are independent in nature
and having manageable interface problems:
CIVIL WORKS
Package –I: Civil Works which includes Diversion Works, Weir, Intakes.
Package –II: Power Plant Civil Works which includes Surge Shaft, Pressure
Shaft, Power House, Transformer cavern, Access and Auxiliary Tunnels in Power
House area, Head Race Tunnel, Tail Race Tunnel, Switch Yard, etc.
HYDRO-MECHANICAL WORKS
Package – III: Hydro mechanical works comprising of gates, hoists, steel liner in
Intake structures, Auxiliary Spillway, Surge shaft, Draft Tube Gate & TRT etc.
ELECTRO-MECHANICAL
Package – IV: Generating Units (Turbine and Generator), MIVs, Cooling Water
System, Drainage/Dewatering System, Unit Control Protection and Automation,
Bus duct.
Package – V: Butterfly Valves
Package - VI: EOT Cranes
Package - VII: Gas Insulated Switchgear
Package - VIII: Gas Insulated Bus
Package - IX: Air Conditioning, Ventilation etc.
Package - X: Fire detection & fighting system
Package –XI: Transformers (Generator Transformer) & Shunt Reactors
Package - XII: 415 V Switchgear & 11 kV Switchgear
Package - XIII: Illumination
Package - XIV: DG sets (construction power)
Package - XV: Cable & Cable Trays
Package – XVI: Pot Head Yard Equipments, Protection metering & PLCC
Package - XVII: Transformer (Dry Type UAT SST)
Package - XVIII: DC System (Battery & Battery Charger), UPS
Package - XIX: Miscellaneous and finishing works
The Project has been planned to have the following main component structures and the
construction schedule has been prepared accordingly.
a) Diversion Works
River diversion works has been planned for construction of weir. The construction
of weir has to be taken up after flood period. The upstream & downstream coffer
dam will be constructed across the river in two stages. In the first stage, the upstream
and downstream coffer dams will be constructed across the river on the left bank of
river to divert the flow of river through right bank for creating dry working area in
the left bank to carry out the construction of half of the weir. Similarly, in the second
stage, the same construction procedure will be followed in the right bank of the river
for construction of second half of the weir.
b) Weir
It is a concrete gravity ogee weir of 620 m long and 31.5 m high above deepest
foundation level. The top elevation of the weir is 319.50 m. Four non over flow
blocks on right and left side of weir is a length of 126m are to be constructed.
The excavation for the dam at the abutments will be taken up after the completion of
the Diversion works and major part of completion of the upstream and downstream
Coffer Dam. All the excavation including river bed portion will be completed within
9 months since its beginning i.e. October 2020.
The work of foundation treatment will start as the excavation of foundation progressed
and all the consolidation work will be carried on simultaneously with the concreting of
the weir. The curtain grouting and drainage holes work will be done through the
foundation grouting provided in the weir after the weir blocks have reached about 8-10
m above the gallery and completed before reservoir filling.
The construction sequence for the weir and related works will be as under:-
The excavated material from the abutment will be used for the construction of the
cofferdams.
Most of the concreting would be completed in two working seasons with only
concreting in some abutment blocks and ogee weir portion will be taken up in the third
season.
Concreting upto river bed level would be taken up after blanket concreting and
consolidation grouting in river bed is completed. The construction of plunge pool will
be carried out during this period.
It is proposed to complete the ogee weir blocks upto the sluice spillway crest level
(EL.310.50 m) in the third working season. The placement of anti-abrasion
arrangements cladding Rails and supporting frames with rich concrete on the ogee weir
profile will be carried out during 2ndyear. Concreting in the ogee weir portion upto top
would be completed in the 2 years. The work will be completed as programmed in the
implementation schedule.
Intake is located on the left bank of the river Sileru on downstream of Guntawada
Reservoir weir. Invert level of the Intake will be at EL. 317.00 m. Intake will convey
water through Head race tunnel to Power House and Secondary intake for pumping
mode. Complete intake structure will be resting on the concrete platform supported on
strong foundation.
Construction of intake will be carried out along with the coffer dam. During the first
season, when river flow is diverted with coffer dam on upstream side creating the dry
area, concrete will be laid for the raft area of intake.
The excavation of intake structure and approach channel will be carried out in the
second season. This will include foundation grouting and shaving off the unwanted
projections on the finished level. Portion where the disintegrated rocks is found, it
needed to be concreted and compacted in order to provide the smooth level.
3 no. Head Race Tunnels are proposed with 12.0 m dia each. Each tunnel is of Circular
shaped and the average length is 3.094 km. HRT starts from the Power Intake transition
and ends at Primary Surge Shaft. There will be two nos. of access adits i.e. one adit just
at the upstream of surge shaft and other at the middle of HRT. Adits will be D-shaped
with adit portal development.
Construction of HRT will be taken up simultaneously from all faces and it is proposed
to complete the excavation of HRT in 32 months duration.
Excavation will be carried out in Full-Face by Drilling and Blasting Method. Drilling
will be done by mobilizing Single Boom Drill Jumbo whereas loading and mucking
will be done by excavator and Dumpers of required capacity. Support arrangement like
shotcrete and Rock bolting for the excavation profile of the tunnel will be carried out
as per the requirement and type of strata encountered. However, steel supports are also
proposed as rock support in incompetent geological formations. In case of Hot Water
Ingress during tunnel excavation, required arrangement will be carried out to provide
suitable and safe working environment at tunnel face. It is estimated an average
progress of 75 m per month per face for tunnel excavation.
Once excavation from all the faces of HRT will be completed, concrete lining will be
carried out by 12 m long Gantry from one end with the average monthly progress of
225 m. The work will be completed as programmed in the Implementation Schedule.
It is proposed to provide Primary Surge Shaft of size 42.5m (L)*275m (W)*80m (H)
and Secondary Surge Shaft of size 35m (L)*275m (W)*76.5m (H). Full length of the
Surge Shafts are located in the rocky strata. Berm of suitable width will be provided at
required vertical interval and this berm will be provided with the drain to remove excess
water. Shotcrete with wire mesh and rock anchors will be provided at slope as
protection works to the overburden materials all around the surge shaft opening.
Surge shaft are as mentioned above, thickness of concrete lining will be 2.5m upto EL
425m & EL 336.5m and above these levels lining thickness will be at 2.0 m interval
upto top of the surge shafts.
f) Valve House
A suitable Valve House chamber of size 12.5m length, 229.0m wide, 24 m height has
been proposed. A suitable crane has also been proposed for operation maintenance.
g) Pressure Shaft
It is proposed to provide Pressure Shaft of 6.0 m dia. circular shape to convey water
from Primary Surge Shaft to the Power House. From Surge Shaft, water will be
conveyed under pressure through the pressure shafts of 9 no. of 6m dia each feeding
each unit of surface Power House.
Excavation of 6.0 m dia. circular shaped pressure shaft will be carried from two ends
i.e. one from surge shaft end and another from Power House side. Inclined portion of
Pressure Shaft will be excavated from the surge shaft end with hoisting arrangement
with trolley attached. Men and material will be lowered through this arrangement,
whereas the horizontal part of Pressure shaft will be excavated from the Power house
side. Excavation will be done by Drilling and Blasting method by using Jack hammer
and excavator of suitable size and dimension will be mobilized.
After completion of excavation for the pressure shaft, steel liner will be laid with proper
alignment. Steel liner will be laid from bottom most part for the inclined portion by
hoisting arrangement placed at the surge shaft end. After aligning every ferrule,
concrete back filling will be carried out to maintain the fixed alignment. Similar process
will be carried out for the horizontal portion of the pressure shaft from the powerhouse
end.
Surface power house is proposed for this project which is central part of the project.
The location of PH is on the left bank of the Sileru River. The geological strata at this
location comprises of mostly granite substances as well as northerly dips due to broad
antiforms and synforms. This geological strata is considered suitable for Surface power
house. The roof and sides of the power house and the transformer cavities will be
provided with suitable supporting system like shotcrete, rock bolts etc. as necessary.
The surface power house complex of size 25.5m long, 280m wide and 65m height
which will house generating equipments. The generator floor and service bay will be at
EL 290.30m and 295.70 m respectively and the control block portion will be at higher
elevation with a workshop facility underneath. Besides the turbine & generators etc,
this power house will house 9 no. main inlet valves, one for each unit. The centre line
of turbines will be at EL 281.50 m. An EOT crane of suitable capacity will be provided
at EL 308.5 m which will run from the beginning of service bay to the end of machine
hall.
The excavation for the power house can be started from October 2020 and all the works
including sub-structure and super structure can be completed along with the installation
of electro-mechanical equipment of the units.
3 no. of 12.0m finish dia circular shape, 3025 long Tail Race Tunnel has been proposed
from secondary surge shaft to pump intake to discharge the water back to Sileru River
which again pumped to main Upper reservoir. TRT will be concrete lined. The
construction of Tail Race Tunnel will be done from outlet face of TRT and from
junction of the main access tunnel with TRT. The tunnel will be excavated by drill and
blast method using mechanized equipment. 2-boom drill jumbo will be used for drill
holes and robotic shotcrete machine will be used for temporary lining.
Concrete lining of TRT will commence immediately after the completion of excavation
work at respective faces. The lining of the tunnel is proposed to be done in two stages
i.e. overt concrete will be done firstly followed by invert concrete lining.
j) Hydro-mechanical works
The gates and hoists comprises of Primary and secondary Intake Structure, primary and
secondary Surge Shaft, Draft Tube Gate etc. The fabrication of the gates shall be done
partly in manufacturer’s workshop and partly at site. The civil contractors will co-
ordinate with the agencies supplying such equipment and provide them all necessary
support at site. Block outs and first stage anchor plates shall be provided in various
structures during first stage concreting. The second stage embedded parts comprising
of sill beams, tracks, seal seats & guides etc. shall be erected in these block outs before
undertaking second stage concreting.
The supply and installation of all hydro mechanical equipment required at different
locations shall be ensured to be completed in time so that the works related to
components can be completed in scheduled time.
Construction schedule of Upper Sileru Pumped Storage Project has been prepared
keeping in view optimum use of the equipment, completion of inter related activities in
the least feasible time and balanced flow of funds. It is planned to complete all the
construction activities so as to commission the project in a period of 60 months from
the date of start of the work. The ogee weir which is 31m high, Power Intake, 3 no.
HRT which are 3.034 km, 2 no of surge shafts, pressure shaft, valve house, power
house, tail race tunnel, Pump Intake and other major components of the project which
would takes sufficiently long time for execution.
11.4 KEY MATERIALS PLANNING
The quantity of concrete required for various structures of the project have been
worked out based on designs and drawings carried out for preparation of PFR
Report.
Plant/Equipment Planning
The concrete required for project components works has a volume of 3,30,000 cum.
Assuming an average aggregate weight of fine and coarse aggregate in concrete equal
to 2.10 T/m3, the total weight of aggregate to be processed will be about 6,93,000 MT.
The peak requirement of concrete has been estimated to be about 60 m3/hr which occurs
in 2nd working season. The requirement of coarse aggregate has been estimated to be
about 60 m3/hr as peak and about 45 m3/hr as average. The major requirement of
concrete and aggregate is for the weir construction. Keeping the project components in
consideration, it is proposed to provide 2 No. of Concrete Batching Plant of 30 m3/hr
capacity for each batching plan which is more or less equi-distance from the both intake
and surge shaft / surface power house site.
It is proposed to provide 2 nos Aggregate Crushing Plant of 100 MT capacity for each
batching plan, one at u/s of primary surge shaft and one at d/s secondary surge shaft of
the proposed location of the upper sileru project.
On completion of excavation of tunnel, concrete lining for the tunnels will be carried
out. Concrete lining will be carried out by Telescopic type Gantry Shutters 12 m length
for overt portion of the tunnel. Once overt concrete is complete, invert lining will be
carried through invert shuttering arrangement moving on rails on kerbs. Concrete lining
for the tunnels will be done in sequence as below:-
Kerb
Overt
Invert
As could be seen from the discharge data, there are very low discharges in river from
October to May i.e. for about 8 months, which would form the working season in the
area. All the surface works are proposed to be executed in two shifts except the weir,
which is proposed to be executed in three-shift operations. All the works are proposed
to be executed in three-shift operation throughout the year. The scheduled working
hours considering 25 working days per month accordingly works out as under:
On the basis of the above computation, in accordance with “Guidelines for Detailed
Calculations for the Requirement of Each Category and Size of the Production
Equipment, August 2000 published by the Central Water Commission” following
scheduled working hours have been considered in surface works.
Single shift work/day - 1200 hrs.
Two shift work/day - 2000 hrs.
Three shift work/day - 2500 hrs.
Works are generally not affected by the vagaries of weather and work has, thus, been
planned to continue throughout the year. However, since the production capability
would be affected during monsoon months especially for the supplies/services and
muck disposal, etc., suitable reduction in the progress has been taken into account for
the year as a whole. Two shifts working of equipments is normally considered most
economical in view of the high cost of three shift working on account of low availability
of equipment and higher stand-by equipment requirement.
Thus, planning for allover ground works has been carried out based on two shifts per
day working. Underground works in any case, are planned for three shifts working as
these involve cyclic operations, which do not follow normal shift operation. The work
in the weir especially below the crest level will have to be completed within the non-
monsoon period only and as such planned for the 3 shift working.
CHAPTER-XII
ENVIRONMENTAL AND ECOLOGICAL ASPECTS
CHAPTER-XII
ENVIRONMENTAL AND ECOLOGICAL ASPECTS
TABLE OF CONTENTS
CHAPTER-XII
ENVIRONMENTAL AND ECOLOGICAL ASPECTS
12.1 GENERAL
The study area considered for the Environmental Assessment study shall comprise of
the following:
Upper Sileru Pumped Storage Project. The baseline status has been assessed mainly
based on review of secondary data and site visits. The existing project related
documents too have been reviewed to assess the baseline environmental status.
12.3.1 Climate
The climate of project area varies considerably, depending on the geographical region.
Monsoons play a major role in determining the climate of the state. Summers last from
March to June. In the coastal plain, the summer temperatures are generally higher than
the rest of the state, with temperature ranging between 20° C and 41° C.
July to September is the season for tropical rains in Andhra Pradesh. The state receives
heavy rainfall from the Southwest Monsoon during these months. About one third of
the total rainfall in the Andhra Pradesh is brought by the Northeast Monsoon. October
and November see low pressure systems and tropical cyclones form in the Bay of
Bengal which, along with the Northeast Monsoon, brings rain to the southern and
coastal regions of the state. November, December, January and February are the winter
months in the Andhra Pradesh. Since the state has a long coastal belt the winters are not
very cold. The range of winter temperature is generally 12° C to 30° C.
Sileru River is a tributary of Sabari River. It originates in Andhra Pradesh and also
flows through Odisha before merging with Sabari. Sabari River crosses the border into
the Andhra Pradesh to merge with Godavari River. Sileru (known as Machkund in its
upper reaches) river joins Sabari River at tri-junction boundary point of Andhra
Pradesh, Chhattisgarh and Odisha. The river drains the Western face of Eastern Ghats
and starts at an altitude of +1645.90 M (5400 ft). It flows in a north-westerly direction
up toChikinput, where it takes a short right-angle bend and flows due South-West to its
confluence with Sabari, an important tributary of river Godavari.
Sileru river has vast potential of hydro electricity generation which has been
substantially harnessed by constructing Machkund (120 MW), Balimela (510 MW),
Upper Sileru (240 MW), Donkarayi (25 MW) and Lower Sileru hydro (460 MW) power
projects. Chitrakonda (60MW) hydro project located at the toe of Balimela earth dam
is planned to utilise the head available across the earth dam.
a) Construction Phase
The number of maximum personnel requirements for the employer and contractor has
been estimated to be of the order of 200 and 500 respectively. Thus, the peak
aggregation of labour and technical staff including their families will be 1500. The
immigration of labour population during construction phase will also induce secondary
migration in the area to cater to the various requirements of the project construction
staff. These will include persons to manage shops of various types, transportation,
workshops, etc.
Separate accommodation and related facilities for workers, service providers and
technical staff are to be provided as a part of the project. The congregation of labour
force is likely to create problem of sewage disposal, solid waste management and felling
of trees for meeting fuel requirements, etc.
During construction phase, various types of equipment will be brought to the site. These
include crushers, batching plant, drilling jumbos, earthmovers, etc. The sitting of this
construction equipment would require significant amount of space. In addition, land
will be required for storage of various construction materials as well. However, land for
this purpose will be temporarily acquired, i.e. for the duration of project construction
phase.
Soil erosion
The runoff from various construction sites will have a natural tendency to flow along
with the natural drainage. Thus, the disposal of drainage effluent with such high
turbidity levels is bound to affect the water quality, especially in the lean season. The
drains/nallahs close to various construction sites are seasonal in nature. Normally in
such streams, biological productivity is not high. Hence, the increase in turbidity levels
is not expected to be significant in nature.
b) Operation Phase
Acquisition of Land
The total land to be acquired for various project appurtenances is 410 ha. The details
are given in Table- 12.1.
2 Link Roads 10
Total 410
The tentative ownership status of land to be acquired for Upper Sileru Pumped Storage
Project is given in Table-12.2.
Table-12.2: Ownership status of land to be acquired
S. No. Category Area (ha)
1 Forest Land 380
2 Private Land -
3 Government Land 30
Total 410
As a part of CEIA study, detailed studies to assess the ownership status of the land to
be acquired for various project appurtenances shall be conducted. Suitable
compensatory measures as per the ownership status of the land to be acquired for the
project shall be formulated with the help of concerned state departments.
The construction phase, also leads to mushrooming of various allied activities to meet
the demands of the immigrant labour population in the project area. The domestic
water requirement has been estimated as70 lpcd. Thus, total water requirements work
out to 0.11 mld. It is assumed that about 80% of the water supplied will be generated
as sewage. Thus, total quantum of sewage generated is expected to be of the order of
0.08 mld. The BOD load contributed by domestic sources will be about 68kg/day. It is
recommended to commission units for treatment of sewage generated from labour
camps prior to disposal.
During construction phase, at least one crusher will be commissioned at site by the
contractor involved in construction activities. It is proposed only crushed material would
be brought at construction site. Water is required to wash the boulders and to lower the
temperature of the crushing edge. About 0.1m3 of water is required per ton of material
crushed. The effluent from the crusher would contain high suspended solids. It is
proposed to treat the effluent from crushers in settling tank prior to disposal, so as
ameliorate even the marginal impacts likely to accrue on this account.
b) Operation Phase
During project operation phase, due to absence of any large-scale construction activity,
the cause and source of water pollution will be much different. Since, only a small
number of O&M staff will reside in the area in a well-designed colony with sewage
treatment plant and other infrastructure facilities, problems of water pollution due to
disposal of sewage are not anticipated.
In the operation phase, about 100 families & 100 bachelors (total population of 400)
will be residing in the project colony. About 0.04 mld of sewage will be generated. The
total BOD loading will be order of 8kg/day. It shall been assured that sewage from the
project colony be treated in a sewage treatment plant so as to meet the disposal standards
for effluent. Thus, no impacts are anticipated as a result of disposal of effluents from the
project colony.
12.4.3 Impacts on Air Environment
In a water resources project, air pollution occurs mainly during project construction
phase. The major sources of air pollution during construction phase are:
A. Pollution due to fuel combustion in various equipment
B. Emission from various crushers
C. Dust emission from muck disposal
The operation of the crusher during the construction phase is likely to generate fugitive
emissions, which can move even upto 1km in predominant wind direction. During
construction phase, one crusher each is likely to be commissioned near proposed Power
Intake and proposed power house sites. During crushing operations, fugitive emissions
comprising mainly the suspended particulate will be generated. Since, there are no major
settlements close to proposed project site; hence, no major adverse impacts on this
account are anticipated. However, during layout design, care should be taken to ensure
that the labour camps, colonies, etc. are located on the leeward side and outside the
impact zone (say about 2km on the wind direction) of the crushers.
The loading and unloading of muck are one of the sources of dust generation. Since,
muck will be mainly in form of small rock pieces, stone, etc., with very little dust
particles, significant amount of dust is not expected to be generated on this account.
Thus, adverse impacts due to dust generation during muck disposal are not expected.
a) Construction Phase
In a water resource projects, the impacts on ambient noise levels are expected only
during the project construction phase, due to earth moving machinery, etc. Likewise,
noise due to quarrying, blasting, vehicular movement will have some adverse impacts
on the ambient noise levels in the area.
Under the worst-case scenario, considered for prediction of noise levels during
construction phase, it has been assumed that all this equipment generate noise from a
common point. The increase in noise levels due to operation of various construction
equipment is given in Table 12.4.
Table- 12.4 Increase in noise levels due to operation of various construction
equipment
Distance Ambient Increase in Increased Noise Increase in
(m) noise levels noise level due level due to ambient noise
dB(A) to construction level due to
construction activities dB(A) construction
activities activities dB(A)
dB(A)
100 36 45 45 34
200 3 39 39 29
500 3 31 31 25
1000 3 25 25 25
1500 3 21 21 24
2000 3 19 19 24
2500 3 17 17 24
3000 3 15 15 24
It would be worthwhile to mention here that in absence of the data on actual location of
various construction equipment, all the equipment has been assumed to operate at a
common point. This assumption leads to over estimation of the increase in noise levels.
Also, it is a known fact that there is a reduction in noise level as the sound wave passes
through a barrier. The transmission loss values for common construction materials are
given in Table- 12.5.
Table- 12.5: Transmission loss for common construction materials
Thickness of
Decrease in Noise level dB
Material Construction material
(A)
(inches)
4 38
Light concrete
6 39
Dense concrete 4 40
4 32
Concrete block
6 36
Brick 4 33
Granite 4 40
Thus, the walls of various houses will attenuate atleast 30dB (A) of noise. In addition,
there are attenuation clue to the following factors:
• Air absorption
• Rain
• Atmospheric in homogeneities
• Vegetal cover
Thus, no increase in noise levels is anticipated as a result of various activities, during
the project construction phase.
The effect of high noise levels on the operating personnel has to be considered as this
may be particularly harmful. It is known that continuous exposures to high noise levels
above 90dB (A) affects the hearing acuity of the workers/operators and hence, should
be avoided. To prevent these effects, it has been recommended by Occupational Safety
and Health Administration (OSHA) that the exposure period of affected persons be
limited as per the maximum exposure period specified inTable-12.6.
Table-12.6: Maximum Exposure Periods specified by OSHA
Maximum equivalent continuous Unprotected exposure period per day
Noise level dB(A) from 8hrs/day and 5 days/week
90 8
95 4
100 2
105 1
110 1/2
115 1/4
120 No exposure permitted at or above this
level
12.4.5 Impacts on Land Environment
a) Construction Phase
The major impacts anticipated on land environment during construction are as follows:
i) Operation and construction equipment
ii) Quarrying operations
iii) Muck disposal
iv) Acquisition of land
In addition, land will also be temporarily acquired, i.e. for the duration of project
construction for storage of quarried material before crushing, crushed material,
cement, rubble, etc.
Efforts must be made to site the Contractor's working space in such a way that the
adverse impacts on environment are minimal, i.e., to locate the construction
equipment, so that impacts on human and faunal population is minimal.
The quantum of construction material required for Upper Sileru Pumped Storage
Project is given in Table-12.7. Apart of the muck generated from the project shall be
used as construction material.
Table-12.7: Construction material requirement
S.No. Material Quantity (m3)
3 Impervious Material > 200000
4 Cement Concrete > 900000
5 Grouting > 100000
A permanent scaris likely to be left, once quarrying activities are over. With the
passage of time, rock from the exposed face of the quarry under the action of wind and
other erosion forces, get slowly weathered and after some time, they become a
potential source of landslide. Thus, it is necessary to implement appropriate slope
stabilization measures to prevent the possibility of soil erosion and landslides in the
quarry sites.
iii) Muck disposal
Muck generation and disposal could lead to various adverse impacts. The muck needs
to be disposed at designated sites. This could lead to following impacts:
Loss of land
Problems regarding stability of spoil dumps
Access to spoil dumps areas
Apart of the muck can be used for the following purposes:
Use of suitable rock from the excavation as aggregate in the mixing of concrete.
Use of muck for maintenance of roads.
Use as backfill material in quarry and borrow pits.
As a part the CEIA study a detailed muck management plan shall be formulated.
Siting of construction equipment, godowns, stores, labour camps, etc. may generally
disturb the fauna in the area. To minimize any adverse inputs due to poaching activities
from immigrant labour population, strict anti-poaching surveillance measures need to
be implemented, especially during project construction phase. The same shall be
covered in detail as a part of the Environmental Management Plan (EMP).
The project will also lead to certain negative impacts. The most important negative
impact would be during the construction phase. The labour force that would work in the
construction site would settle around the site. They would temporarily reside there. This
may lead to solid waste generation, sewage generation, etc. which can lead to harmful
impacts if proper mitigatory measures are not undertaken.
The employment opportunities in the area are limited. Thus, during project construction
phase, some of the locals may get employment. It has been observed during construction
phase of many of the projects; the major works are contracted out who bring their own
skilled labour. However, it is only in the unskilled category, that locals get employment.
ii) Economic Impact of the project
Apart from direct employment, the opportunities for indirect employment will also be
generated which would provide great impetus to the economy of the local area. Various
types of business-like shops, food-stall, tea stalls, etc. besides a variety of suppliers,
traders, transporters will concentrate here and benefit immensely as demand will
increase significantly for almost all types of goods and services. The business
community as a whole will be benefited. The locals will avail these opportunities arising
from the project and increase their income levels. With the increase in income levels,
there will be an improvement in the infrastructure facilities in the area.
iii) Impacts due to land acquisition
The key impact during construction phase will be that, pertaining to land acquisition.
About 410 ha of land is proposed to be acquired for the proposed Upper Sileru Pumped
Storage Project. No private land is to be acquired.
As a part of CEIA study, the exact quantum of private and forest land to be acquired
needs to be identified. Based on the ownership status, appropriate, compensatory
measures, Resettlement and Rehabilitation Plan will be formulated.
The excavation of earth from borrow pits etc. could accumulate water during rainy
season which could increase breeding ground for various vectors and mosquitoes.
However, in the present case, the borrow areas are within the river bed, which in any
case remain underwater. Thus, no additional habitat for mosquito breeding is created
due to excavation. However, fumigation and other measures are suggested in the EMP.
Labourer camps without adequate facilities for portable water supply and sewage
Lack of potable water supply could lead to increased incidence of water borne diseases
particularly in camp sites and in adjoining areas. There could incidence of spread of
water-borne diseases in labour camps/colonies. Communities located in direct impact
zone as well as indirect impact zone could also be severely affected from such
epidemics.
b) Operation phase
The construction of a reservoir replaces the river in ecosystem by a lacustrine ecosystem.
The vectors of various diseases breed in shallow areas not very far from the reservoir
margins. The magnitude of breeding sites for mosquitoes and other vectors in the
impounded water is in direct proportion to the length of the shoreline. Thus, there could
be increased incidence malaria and other vector-borne diseases during project
construction phase.
building stone.
Andhra Pradesh is listed top in the deposit and production of mica in India. Minerals
found the state include limestone, reserves of Oil and natural gas, manganese, asbestos,
Iron Ore Ball Clay, Fire Clay, Gold Diamonds, graphite, Dolomite, quartz, Tungsten,
Steatitic, Feldspar, Silica Sand. It has about one third of India's limestone reserves and
is known for large exclusive deposits of Barytes and Galaxy granite in the international
market.
As per the design and location of the project there is no impact on the mineral resources.
vats should be emptied at regular intervals and shall be disposed at identified landfill
sites. Suitable solid waste collection and disposal arrangement shall be provided. A
suitable landfill site should be identified and designed to contain municipal waste from
various Project Township, labour colonies, etc. The landfill site shall be finalized.
Muck disposal is done after creating terraces thus usable terraces are developed. The
overall idea is to enhance/maintain aesthetic view in the surrounding area of the project
in post-construction period and avoid contamination of any land or water resource due
to muck disposal.
The terraces of the muck disposal area will be ultimately covered with fertile soil and
suitable plants will be planted adopting suitable bio-technological measures.
Various activities proposed as a part of the management plan are given as below:
For stabilization of muck dumping areas following engineering and biological measures
have been proposed:
Engineering Measures
• Wire crate wall
• Boulder crate wall
• Retaining wall
• Catch water drain
Biological Measures
• Plantation of suitable tree species and soil binding species
• Plantation of ornamental plants
• Barbed wire fencing
There would be sufficient open space in power house complex and colony area. Forested
area in the power house complex would provide aesthetic view and add to natural scenic
beauty. The beautification in the colony area would be carried out by development of
flowering beds for plantation of ornamental plants, creepers, flower garden and a small
park, construction of benches for sitting, resting sheds, walk way and fountain.
As a part of the EIA study a detailed Bio diversity plan shall be formulated. The plan
shall cover measures for conservation of floral and faunal species including awareness
programme infrastructure development etc.
• Clearing of shoreline, mats and floating debris, etc. to reduce the proliferation
of mosquitoes.
• Development of medical facilities in the project area and near labour camps
• Implementation of mosquito control activities in the area.
Infrastructure
Dispensary:
Considering the number of rooms, staff quarters and open space etc., it is estimated that
10,000 sq.feet of plot will be required for dispensary, out of which about 8000 sq. feet
will be the built-up land which includes staff quarters, etc.
• Excessive soil on paved areas will be sprayed (wet) and/or swept and unpaved
areas will be sprayed and/or mulched. The use of petroleum products or similar
products for such activities will be strictly prohibited.
• Contractors will be required to cover stockpiled soils and trucks hauling soil,
sand, and other loose materials (or require trucks to maintain at least two feet of
freeboard).
• Contractor shall ensure that there is effective traffic management at site. The
number of trucks/vehicles to move at various construction sites to be fixed.
• Dust sweeping - The construction area and vicinity (access roads, and working
areas) shall be swept with water sweepers on a daily basis or as necessary to
ensure there is no visible dust.
• CAT plan would be prepared with year-wise Physical and financial details.
Identification of
water related
diseases,
Water related Three times a Labour Camps
2 adequacy of local
Diseases year and colonies
vector control
and curative
measures, etc.
Equivalent noise Once in three At major
3 Noise
level (Leg) months construction sites
Ambient air Once every At major
4 PM10, SO2, NO2
quality season construction sites
and curative
measures, etc.
• Upper and
Lower
Reservoir
• 1 and 5 km
Phytoplankton,
upstream of
Aquatic zooplankton,
6 Once in a year upper reservoir
Ecology benthic life, fish
dam site
composition
• 1,5 and 10 km
downstream of
Lower
Reservoir
Land use pattern Catchment area of
7 Land use using satellite Once in a year Upper and Lower
data Reservoirs
Catchment area of
pH, EC, texture,
8 Soils Once in a year Upper and Lower
Organic matter
Reservoirs
1 Compensatory Afforestation
Total 5867.50
12.11 CONCLUSIONS
Based on the preliminary assessment of environmental issues considered in the present
Chapter, it is proposed to conduct, a detailed Comprehensive EIA study with an
objective to assess various impacts likely to accrue as a result of construction and
operation of the proposed project on various aspects of Environment. Appropriate
management measures too shall be delineated as a part of Environmental Management
Plan (EMP), which will be covered as a part of the Comprehensive EIA study.
CHAPTER-XIII
COST ESTIMATE
CHAPTER-XIII
COST ESTIMATE
TABLE OF CONTENTS
13.1 General 13-1
13.2 Basis of the Cost Estimate 13-1
13.3 Broad Sub-head-wise Provision for Civil Works 13-2
13.4 Unit-I – Head Works, Power House Works 13-3
13.4.1 Direct Charges 13-3
13.4.1.1 I-Works 13-4
13.4.1.2 II - Establishment 13-6
13.4.1.3 III – Tools & Plants 13-6
13.4.1.4 IV-Receipts and Recoveries on Capital Account 13-7
13.4.2 Indirect Charges 13-7
13.5 Unit-III - Cost of Electro-mechanical works 13-7
13.6 Estimated cost of the project 13-7
CHAPTER-XIII
COST ESTIMATE
13.1 GENERAL
The present Upper Sileru Pumped Storage Project is proposed to be constructed on river
Sileru- a tributary of the major river in its own right of the Godavari River System. The
Upper Sileru Pumped Storage Project (USPSP) is located on Sileru River near Sileru
village about 200 km from Visakhapatnam / Rajahmundry. The project envisages re-
utilisation of water of the Guntawada reservoir which is presently being used for power
generation at existing Hydro Electric Power Station and surplus spilled from the
reservoir. This water shall be stored at proposed weir in Donkarayi reservoir located in
the downstream side for reutilisation during pumping mode.
The cost estimate has been prepared in detail to arrive at the total capital cost of “Upper
Sileru Pumped Storage project”. The estimate is based on the market rates for the year
2018-19 for material, labour, equipment etc.
The estimate has been prepared separately for civil, hydro-mechanical and electro-
mechanical works.
The total estimated cost of the project including direct and indirect charges is Rs.
8467.50 crores and including IDC with escalation is Rs.11054.10 Crores. The
detailed estimate of cost of civil works is based on planning and preliminary designs of
various components of works after review of site conditions, carrying out detailed field
investigations and analysis and studies etc.
General arrangement and layout details of various structures as well as their salient
features are shown in drawings Volume of this report.
Analysis of rates for major items of civil works has been carried out. Rate for minor
items of works and lump sum provisions for some works have been made on the basis
of experience on similar projects which have been completed recently or are under
construction.
The total costs of these schemes have been worked out on the basis of Andhra Pradesh
SOR 2018-19 and the same is given in the general abstracts of the cost. The quantities
have been worked out by calculating the quantities of different items of work involved
from the design drawings of different structures and then multiplying the respective
quantities with the applicable unit rates as per SOR 2018-19. The applicable unit rates,
in turn are based upon cost of material, labour input, cost of transportation etc. as
prevailing in the state of Andhra Pradesh.
The provisions under various sub-heads are based on “Guidelines for Preparation of
Detailed Project Reports of Irrigation and Multipurpose Projects” issued by the
Ministry of Water Resources and ‘Guidelines for Formulation of Detailed Project
Reports for Hydroelectric schemes, their acceptance and Examination for Concurrence”
issued by Central Electricity Authority.
The project cost is classified in two groups as per CWC guidelines. These groups are
following:
Rubber Dam
Intakes, Power House, Head Race Tunnels, Tail Race Tunnels, Penstocks etc.
Approach road
This unit includes the cost of electromechanical works. Total cost of the Unit-III items
is Rs 3446.50 crores.
ABSTRACT OF COST
Unit-I Unit-III Grand Total
Sl.No Description Amount Amount Amount
(Rs. in Lakhs) (Rs. In Lakhs) (Rs. In Lakhs)
A) DIRECT CHARGES
I Works 447785.91 312987.77 760773.68
II Establishment 17809.94 12519.51 30329.45
III Tools And Plants 5597.32 5597.32
IV Suspense 0.00 0.00
V Receipts And Recoveries -315.93 -315.93
VI Goods & Service Tax @ 6% 26714.90 18328.95 45043.85
Total Direct Charges 497592.14 343836.23 841428.37
I Works
II Establishment
III Tools and Plants
IV Suspense
V Receipt and Recoveries.
The details of above sub-heads under Direct Charges are given in the following
paragraphs.
13.4.1.1 I-Works
A-Preliminary
Under this sub-head provision has been made for topographical surveys, geological and
geophysical investigations including drilling, drifting, field and laboratory tests on
rocks, construction material investigations and testing, collection of hydrological and
meteorological data, hydraulic model studies and environmental and ecological studies.
Provision has also been made for consultant’s fees for preparation of the project report
and other reports. The total provision under this sub-head is Rs. 19.75 crores which is
less than 2% I-Works.
B-Land
This sub-head covers the provision for acquisition/purchase of land for permanent
works, approach roads, camp sites, workshops, stores, offices, residential and non-
residential areas for construction and maintenance staff etc. Provision for compensation
for houses and trees coming in the project area is also included in this sub-head. The
total provision under this sub-head is Rs.25.375 crores.
These cover the cost of civil engineering structures comprising of Rubber Dam, coffer
dam for construction of Rubber dam & Power Intake, intake, desilting chamber,
headrace tunnel, surge shafts, penstocks, power house complex, main access tunnel,
adits, tail race tunnel and pump intake etc.
A provision of Rs. 686.26 crores have been under the head of C- Civil Works while for
J-Power Plant civil Works a provision of Rs. 3574.79 crores has been considered.
K-Buildings
Provision has been made under this sub-head for permanent and temporary buildings
for various categories of staff, non-residential buildings for offices, work-shops, stores,
rest houses and field hostels and other service buildings such as hospital, school and
utility services etc. Provisions for land development, lawns and gardens fencing,
internal water supply, sanitation and electrical fittings have been made as per norms for
various types of buildings. The total provision under this sub-head is Rs. 35.48 crores.
M-Plantation
A provision of Rs. 1.20 crores has been kept under this sub-head.
O-Miscellaneous
Provision under this head has been made to cover the cost of the following
miscellaneous works:
A provision for Rs. 10.25 crores has been made for meeting cost of various items under
this head.
P-Maintenance
The provision has been made under this sub-head for maintenance of buildings, roads
and main civil works during the construction period of the project. The total provision
under this sub-head is 1% of I-Works less A-Preliminary, B-Land, Q-Special T&P, O-
Maintenance, M-Plantation and X-Environment and Ecology.
The provision under this head has been made to cover the residual value of the
equipment to be used for infrastructure works only re-capital cost of equipment less the
credit due to resale or transfer of equipments and life of machinery used in works. For
this purpose, the provision for the machinery likely to be used in infrastructure works
(like buildings, roads etc.) excluding inspection vehicles, has been taken as 25% of their
value and for inspection vehicles, 100% of the cost has been booked under this head.
R-Communications
Provision has been made under this sub-head for construction of approach roads/road
tunnel, widening of existing roads to make them suitable for the project. The total
provision under this sub-head is Rs. 10.69 crores.
Provision under this sub-head has been made for compensatory afforestation measures
for maintaining environment and ecological balance of the area, public health measures
etc. Provision has also been made for treatment of catchment area for prevention of soil
erosion etc. The total provision under this sub-head is Rs. 58.67 crores.
Y-Losses on Stock
Provision under this sub-head has been made as 0.25% of I-Works less A-Preliminary,
B-Land and Q- Special T&P which comes out to be Rs. 10.77 crores.
13.4.1.2 II-Establishment
Provision of @ 1% of I-works has been included under this heading and provision of
Rs. 55.97 crores has been considered.
These charges cover the cost towards fees for audit and accounts which has been taken
as 1% of I-works and 1% of S - E&M works as per norms. Provision has also been
made for capitalization of land abatement revenue. A provision of Rs. 45.08 crores in
total has been kept for the indirect charges.
Cost of generating plant and equipment is based on current budgetary prices of plant
for 9 x 150 MW generating units for Upper Sileru Pumped Storage Project.
A provision for initial spares has been made along with the cost of the equipment in
each case. Prices of major auxiliary equipment and services are based on current
budgetary prices while that of some minor items are based on prices for similar
equipment procured in the past for similar projects.
Provision for GST, insurance, and transport to site are based on prevalent rates. Erection
& commissioning charges have been provided based on practice for similar installations
in the country.
Provision of Rs. 3446.50 crores has been made for electromechanical works.
The total estimated cost of the project including direct and indirect charges is Rs.
8467.50 crores and including IDC with escalation is Rs.11054.10 Crores. The
detailed cost estimate of the project is appended at the end of this chapter.
ABSTRACT OF COST
Unit-I Unit-III
Grand Total (Rs.
Sl.No Description Amount Amount
in Lakhs)
(Rs. in Lakhs) (Rs. In Lakhs)
A) DIRECT CHARGES
II ESTABLISHMENT
Establishment charges at 4% of I works excluding B Land 17809.94
III TOOLS AND PLANTS
1 Tools & Plants @ 1% of cost of I-Works 4477.86
2 Consultancy 3rd party quality control and E procurement @ 0.25% 1119.46
IV SUSPENSE 0.00
V RECEIPTS AND RECOVERIES -315.93
VI Good and Service Tax @ 6% 26714.90
Total Direct Charges 497592.14
B) INDIRECT CHARGES
Capitalisation of abatement of land revenue at 5% of cost of cultivated
30.00
land
Audit and Accounts charges at 1% of I-works 4477.86
Total Indirect Charges 4507.86
Grand Total (Rs. in Lakhs ) : 502100.00
Grand Total (Rs. in Crore): 5021.00
UPPER SILERU PUMPED STORAGE PROJECT ( 9 X 150 MW)
c) Auxiliary mechanical equipment and services for power station - (Annex IV) 2064.30
e) Erection and commissioning charges @ 8 % of 2 (a), (b) & ( c ) excluding spares 19896.89
Total Generating Plant and Equipment
Sub-Total (Generating Plant and Equipment) 283530.64
a) Pohead yard equipment and auxiliary equipment and service for Pothead yard -
(Annex V) 824.00
4 400 kV Equipment
a) 400 KV GIS , XLPE CABLE, & Step down Transformer - (Annex VI) 20612.50
OVERHEADS
6 Establishment @ 4% 12519.51
9 GST
CHAPTER-XIV
ECONOMIC EVALUTION
CHAPTER – XIV
ECONOMIC EVALUATION
TABLE OF CONTENTS
14.1 Introduction 14-1
14.2 Policy Guidelines of the Government of India 14-1
14.3 Annual Charges 14-2
14.4 Energy Charges 14-2
14.5 Generation 14-2
14.6 Financial Analysis 14-2
14.6.1 General 14-2
14.6.2 Repayment Period 14-3
14.6.3 Annual Escalation 14-3
14.6.4 Front-End and Management Fees 14-3
14.6.5 Project Cost and Phasing of Expenditure 14-3
14.6.6 Units available for sale 14-4
14.6.7 Energy Cost 14-4
CHAPTER – XIV
ECONOMIC EVALUATION
14.1 INTRODUCTION
The Government of India has made a number of policy changes in the power sector for
providing an enabling framework for increased participation of various sectors in the
electricity generation, transmission and distribution. Restructuring and regulation of the
procedure for fixation of power tariff is part of this initiative and Central Electricity
Regulatory Commission (CERC) was constituted in July, 1988 under the Electricity
Regulatory Commissions Act, 1988 with the omission of Section 43A (2) of the
Electricity (Supply) Act, 1948, which enabled the Central Government to determine the
terms and conditions of tariff, the jurisdiction to regulate tariff came to be vested in the
Commission. Section 61 of the Electricity Act, 2003 the Commission specifies the
terms and conditions for the determinations of tariff while Section 62 of the Act
envisages that based on the terms and conditions specified by the Commission, the
Commission shall determine the actual tariff. The Energy cost for hydro power
generating stations shall comprise the recovery for annual capacity charges and energy
charges. Annual capacity charges will consist of interest on loan capital and
depreciation. Energy charges will consist of operation and maintenance expenses,
return on equity and interest on working capital.
Economic evaluation of Upper Sileru Pumped Storage Project has been made in
accordance with the CERC regulations No. L-1/144/2013/CERC dated February 21,
2014, which is also referred to as CERC (Terms and conditions of Tariff) Regulations
2014. This regulation has validity for a period of five years from April1 2014 to March
31, 2019.
b) Rate of depreciation per annum is taken as 5.28% of the total completed cost of the
project. The Salvage value of the asset shall be considered as 10% and the depreciation
shall be allowed up to 90% of the total cost of the project.
14.5 GENERATION
In a year, the planned peak power generation will be 2800 hours considering the rate of
8 hours per day for 350 days operation the estimated maximum annual energy
generation will be 3780 MU. The Pumping will have to be carried out for 2700 hours
(i.e. 300 days and 9 hours each day) per year. The energy required for pumping works
out to 4131 MU. The ratio of generation to pumping energy works out to 78.43 %. Load
factor in turbine mode will be 27.39% and in pumping mode will be 30.82%.
14.6.1 General
The project is proposed to be financed through term loans from financial institution and
balance through equity participation or as in practice of corporation. The basic
methodology for carrying out the financial analysis is to find out energy cost taking into
account the total project cost with an assured return of 16.5% as dividend on equity.
Debt: Equity ratio of 2.33: 1 i.e., loan and equity components of 70% and 30%
respectively of the total completed cost of the project has been considered. The rate of
interest during construction and repayment of loan has been taken as 9.95%.
All the Financial Institutions (both Indian and Foreign) charge what is known as Front-
end or Management fees on loan capital. These are made to cover the financial
commitment/servicing charges. Since this is an established practice, the same has been
taken into account in calculation of the capital cost. However, these charges have not
been considered.
Total 8467.50
Total Including IDC and Front end Fee without Escalation 9214.60
Total Including IDC and Front end Fee with Escalation 11054.10
As per CERC guidelines, 1.0% of the units generated are accounted for auxiliary
consumption, 0.5% of the units generated have been taken as the loss in the
transformation up to bus bars. Royalty charges (Free power to home state) of 0 % are
also considered is also considered in the analysis wherever applicable. Thus the net
units available considering the royalty charges will be 3720 Million Units.
The tariff has been worked out on the basis of the latest CERC guidelines. Details of
financial analysis including calculations of tariff during 35 years of operation are
presented at Table 14.1 through 14.4 for different cases as mentioned below.
Tariff rates for various cases
S. Sale rate of power, Levelized Escalation Annexure
No. Rs. Per Unit, during tariff
1st year of operation Rs. Per
Unit
Narmative Parameters
CHAPTER-XV
RECOMMENDATIONS
CHAPTER-XV
RECOMMENDATIONS
TABLE OF CONTENTS
CHAPTER-XV
RECOMMENDATIONS
15.1 GENERAL
Acquisition of land;
Completion of main infrastructure facilities such as roads and buildings,
bridge across various Gads and falls;
Completion of detailed design and specifications;
Financial Closure and
Tender and Award of main Civil, Hydro Mechanical and Electro-Mechanical
works.
A total time period of 48 months has been considered for main Civil and Hydro-
mechanical works. Adequate construction equipment planning has been done to
achieve the desired progress rates. Timely completion of construction works also
depends on the timely supply of construction material to all the civil structures. Sufficient
storage shall be ensured at proper locations to ensure continuous construction without
stoppage due to shortage of materials.
Nine numbers of turbine machines have been proposed to generate 1350 MW of power.
The generated power will be transmitted through 220 kV transmission line upto the
substation nearest to the project site.
15.8 RECOMMENDATIONS
The Upper Sileru Pumped Storage Project utilises a design head of 92.48 m and rated
discharge of 1652 cumecs to generate 3780 MU of energy annually at 8 hrs/day
operations and the total estimated cost of the project including IDC with escalation is
Rs.11054.10 Crores.
The Project with installed capacity of 1350 MW proposed in this PFR is techno-
economically viable and the project is recommended for implementation.