Professional Documents
Culture Documents
Earned Value: Earned Value Provides A Means of Detecting The Nature and Extent of
Earned Value: Earned Value Provides A Means of Detecting The Nature and Extent of
‘Value’ does not mean cost – it represents the worth to the client
sponsor, and
the Earned Value (EV) of any item can never exceed the Planned Value
(PV).
If our Earned Value is not consistent with our actual expenditure to date
(AC), then we have a Cost Variance (CV). This could be positive (under
budget) or negative (over budget).
If our Earned Value is not consistent with the original allocated budget for
works scheduled to be completed by that date (PV), then we have a
schedule variance (SV). This could be positive (ahead of schedule) or
negative (behind schedule).
From this data, other calculations can also be carried out as suggested in the
glossary of terms in table3, including the budgeted cost at completion,
estimate at completion, forecasted cost at completion, as well as forecasted
date of completion. Different texts will use different terms, so don’t be
concerned with the detail. Focus on the principles of Earned Value analysis
and how it can be of assistance to you and your management of projects.
Term Meaning
AC Actual Costs (of the works performed)
BAC Budget at Completion (total budgeted cost of baseline scope of
works)
Baseline Original approved plan plus or minus approved scope
Budget Cost target for a given scope of works
CPI Cost Performance Index (cost efficiency ratio of EV to AC –
CPI=EV/AC)
CV Cost Variance (EV-AC)
EAC Estimate at Completion (costs to date plus estimate to complete
activity)
ETC Estimate to Complete ( additional costs to complete an activity)
EV Earned Value
LOE Level of Effort (unmeasured effort of a general or supportive nature
with no deliverable end product e.g. supervision)
PV Planned Value
SPI Schedule Performance Index (schedule efficiency ratio of EV against
PV – SPI=EV/PV)
SV Schedule Variance (EV-BAC)
VAC Variance at Completion (BAC-EAC)